Civil Works - Awarded Contracts
A) Date Entered in Civil Works Registry B) Contract ID C) Contract Name D) Implementing Office | 1) Awarded Contractor 2) Awarded Amount 3) Extent Of Participation % 4) Notice to Proceed Date |
---|---|
A) April 8, 2024 B) 24KK0062 C) CONSTRUCTION OF ROAD, PUROK 4, BARANGAY KALAGONOY, GINGOOG CITY, MISAMIS ORIENTAL D) Misamis Oriental 1st District Engineering Office |
1) D.O.T. CONSTRUCTION 2) 4,876,076.25 3) 100 4) 5/1/2024 |
A) April 8, 2024 B) 24F00214 C) CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP )-ACCESS ROADS AND/ D) Region V |
1) 888RV CONSTRUCTION AND SUPPLIES 2) 4,793,283.39 3) 100 4) 5/31/2024 |
A) April 8, 2024 B) 24F00239 C) CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM(BIP)-FLOOD MITIGATION ST D) Region V |
1) ARIK CONSTRUCTION 2) 95,945,657.97 3) 49 4) 6/24/2024 |
A) April 8, 2024 B) 24C00467 C) FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM D) Region III |
1) GLOBALCRETE BUILDERS INC. 2) 128,228,619.85 3) 100 4) 5/20/2024 |
A) April 8, 2024 B) 24CA0077 C) BASIC INFRASTRUCTURE PROGRAM - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITI D) Bataan 1st District Engineering Office |
1) 88 BUILDERS CONSTRUCTION 2) 9,701,900.00 3) 100 4) -/-/- |
A) April 8, 2024 B) 24N00095 C) TAGO-GAMUT BR. (B00701MN) ALONG SURIGAO-DAVAO COASTAL RD D) Region XIII |
1) TRIPARCO DEVELOPMENT CORPORATION 2) 137,381,684.38 3) 51 4) 5/17/2024 |
A) April 8, 2024 B) 24C00488 C) SUSTAINABLE INFRAS. PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING P D) Region III |
1) 722 CONSTRUCTION, INC. (FORMERLY 722 CONST.) 2) 90,298,550.37 3) 100 4) 5/20/2024 |
A) April 8, 2024 B) 24C00487 C) SUSTAINABLE INFRAS. PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING P D) Region III |
1) 722 CONSTRUCTION, INC. (FORMERLY 722 CONST.) 2) 90,298,969.95 3) 100 4) 5/20/2024 |
A) April 8, 2024 B) 24C00486 C) SUSTAINABLE INFRAS. PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING P D) Region III |
1) M3 KONSTRACT CORPORATION (FORMERLY:MARGARITA CONST 2) 90,298,438.88 3) 100 4) 5/20/2024 |
A) April 8, 2024 B) 24C00466 C) FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM D) Region III |
1) GLOBALCRETE BUILDERS INC. 2) 133,005,542.12 3) 100 4) 5/20/2024 |
A) April 8, 2024 B) 24LD0147 C) CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE- BANSALAN- MT. APO NAT'L PARK RD- K1602+754- K1602+7 D) Davao del Sur District Engineering Office |
1) ALFREGO BUILDERS AND SUPPLY 2) 33,269,973.47 3) 100 4) 6/24/2024 |
A) April 8, 2024 B) 24FD0047 C) CLUSTER 2: CONCRETING OF FMR AT RAGAY, CAMARINES SUR (1) BRGY. F. SIMEON (PUGOD), RAGAY, CAM. SUR (2 D) Camarines Sur 1st District Engineering Office |
1) BRENTMIN ROOFING ENTERPRISE 2) 29,336,289.68 3) 100 4) 4/29/2024 |
A) April 8, 2024 B) 24FD0046 C) CLUSTER 1: CONCRETING OF FMR AT DEL GALLEGO, CAM. SUR, (1) BRGY. DOMAGONDONG, DEL GALLEGO, CAM. SUR D) Camarines Sur 1st District Engineering Office |
1) 6G-R CONSTRUCTION SERVICES 2) 29,312,981.00 3) 100 4) 4/29/2024 |
A) April 8, 2024 B) 24C00550 C) BRIDGE PROGRAM-WIDENING OF PERMANENT BRIDGES-SAN FRANCISCO BRIDGE (BO3295LZ) ALONG CONCEPCION-CAPAS D) Region III |
1) ALPHATEC CHEMICAL CORPORATION 2) 28,649,114.70 3) 100 4) 8/8/2024 |
A) April 8, 2024 B) 24LD0069 C) CONSTRUCTION OF FLOOD CONTROL STRUCTURE (BRIDGE SECTION) AT BARANGAY NEW CLARIN-PULANG LUPA, BANSALA D) Davao del Sur District Engineering Office |
1) K AND C BUILDERS 2) 65,523,500.00 3) 20 4) 4/24/2024 |
A) April 8, 2024 B) 24LD0069 C) CONSTRUCTION OF FLOOD CONTROL STRUCTURE (BRIDGE SECTION) AT BARANGAY NEW CLARIN-PULANG LUPA, BANSALA D) Davao del Sur District Engineering Office |
1) RCDG CONSTRUCTION CORPORATION 2) 65,523,500.00 3) 80 4) 4/24/2024 |
A) April 6, 2024 B) 24AA0388 C) BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES: CONSTRUCTION OF MULTI PURPOSE B D) Ilocos Norte 1st District Engineering Office |
1) MEGAPOLITAN BUILDERS AND CONSTRUCTION SUPPLY 2) 4,837,345.36 3) 100 4) 5/2/2024 |
A) April 6, 2024 B) 24AA0426 C) CONCRETING OF BRGY. CARUSIKIS FMR, BRGY. CARUSIKIS, PASUQUIN, ILOCOS NORTE D) Ilocos Norte 1st District Engineering Office |
1) BJMJB CONSTRUCTION AND SUPPLY 2) 38,338,648.59 3) 51 4) 5/6/2024 |
A) April 6, 2024 B) 24AA0400 C) BIP - PUBLIC WATER SUPPLY SYSTEM - CONSTRUCTION (COMPLETION) OF WATER SYSTEM, BOYBOY ELEMENTARY SCHO D) Ilocos Norte 1st District Engineering Office |
1) BJMJB CONSTRUCTION AND SUPPLY 2) 1,900,740.18 3) 100 4) 5/2/2024 |
A) April 6, 2024 B) 24AA0426 C) CONCRETING OF BRGY. CARUSIKIS FMR, BRGY. CARUSIKIS, PASUQUIN, ILOCOS NORTE D) Ilocos Norte 1st District Engineering Office |
1) NORTHLANDER CONSTRUCTION 2) 38,338,648.59 3) 49 4) 5/6/2024 |
A) April 6, 2024 B) 24AA0385 C) BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES: CONSTRUCTION OF MULTI PURPOSE B D) Ilocos Norte 1st District Engineering Office |
1) BJMJB CONSTRUCTION AND SUPPLY 2) 7,761,458.19 3) 100 4) 5/2/2024 |
A) April 6, 2024 B) 24AA0444 C) CONCRETING OF BRGY. NAGSUROT, BRGY. NAGSUROT FMR, BURGOS, ILOCOS NORTE D) Ilocos Norte 1st District Engineering Office |
1) NUEDA BUILDERS CONSTRUCTION AND SUPPLY INC. 2) 47,947,345.66 3) 100 4) 5/2/2024 |
A) April 6, 2024 B) 24AA0381 C) BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES: CONSTRUCTION (COMPLETION) OF MU D) Ilocos Norte 1st District Engineering Office |
1) TMT CONSTRUCTION 2) 2,910,505.17 3) 100 4) 5/2/2024 |
A) April 6, 2024 B) 24AA0360 C) SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR / STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONS D) Ilocos Norte 1st District Engineering Office |
1) BJMJB CONSTRUCTION AND SUPPLY 2) 4,806,473.71 3) 100 4) 5/2/2024 |
A) April 5, 2024 B) 24J00091 C) REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED - SECONDARY ROADS - ROMANDIER - CAMP ANDRES D) Region IX |
1) ZHEREB CONSTRUCTION 2) 96,415,219.44 3) 100 4) 4/22/2024 |
A) April 5, 2024 B) 24HI0091 C) CONCRETING OF BRGY. CADARUHAN FMR, BRGY. CADARUHAN, BORBON, CEBU D) Cebu 5th District Engineering Office |
1) M.C. BUYSER CONSTRUCTION AND SUPPLY 2) 14,915,232.85 3) 100 4) 4/29/2024 |
A) April 5, 2024 B) 24HI0092 C) CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING, MOHON, SOGOD, CEBU D) Cebu 5th District Engineering Office |
1) LA PRUEBA CONSTRUCTION 2) 2,954,688.21 3) 100 4) 4/29/2024 |
A) April 5, 2024 B) 23HI0139 C) REPAIR OF 3 CLASSROOMS, MOABOG ES, PILAR, CEBU D) Cebu 5th District Engineering Office |
1) CYJE FIRST BUILDERS CONSTRUCTION CORP. (FORMERLY: 2) 1,771,288.83 3) 100 4) -/-/- |
A) April 5, 2024 B) 24AD0085 C) CONSTRUCTION OF REINFORCED CONSTRUCTION BRIDGE ALONG STA. LUCIA-SALCEDO ROAD, STA. LUCIA, ILOCOS SUR D) Ilocos Sur 2nd District Engineering Office |
1) M.V. SABALBURO CONSTRUCTION AND SUPPLY 2) 19,005,144.79 3) 100 4) 5/3/2024 |
A) April 5, 2024 B) 24GH0146 C) CONSTRUCTION OF MULTIPURPOSE BUILDING, BRGY. ALIPATA, CARLES, ILOILO D) Iloilo 3rd District Engineering Office |
1) BLOCK 15 CONSTRUCTION SERVICES 2) 4,900,001.99 3) 100 4) 5/16/2024 |
A) April 5, 2024 B) 24AD0072 C) CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SAN N D) Ilocos Sur 2nd District Engineering Office |
1) FIRST NORTHWAY DEVELOPMENT AND CONSTRUCTION CORP. 2) 38,023,884.18 3) 100 4) 5/3/2024 |
A) April 5, 2024 B) 24J00089 C) REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - ROMANDIER - CAMP D) Region IX |
1) ZHEREB CONSTRUCTION 2) 96,404,515.20 3) 100 4) 5/3/2024 |
A) April 5, 2024 B) 24MC0019 C) CONSTRUCTION OF DRAINAGE STRUCTURE ALONG ROAD - MAKILALA-ALLAH VALLEY RD - K1618+103 - K1618+117, MA D) Cotabato 2nd District Engineering Office |
1) REEM CONSTRUCTION AND SUPPLY 2) 5,821,199.95 3) 100 4) 8/8/2024 |
A) April 5, 2024 B) 24J00188 C) REHABILITATION OF PAGSALIPANGAN-MAIMBUNG ROAD, STA. 14+ 455.00 - STA. 16 + 400.00, MAIMBUNG, SULU D) Region IX |
1) ZHEREB CONSTRUCTION 2) 49,224,201.60 3) 100 4) 4/22/2024 |
A) April 5, 2024 B) 24J00232 C) CONSTRUCTION OF ACCESS ROAD LEADING TO VETERANS-LUMBIA-TIMALANG, IPIL, ZAMBOANGA SIBUGAY (PHASE II) D) Zamboanga Sibugay 2nd District Engineering Office |
1) BARILLO CONSTRUCTION AND ENTERPRISES 2) 49,000,104.80 3) 100 4) 5/9/2024 |
A) April 5, 2024 B) 24GH0147 C) CONSTRUCTION (COMPLETION) OF MULTIPURPOSE BUILDING, BRGY. PANTALAN, CARLES, ILOILO D) Iloilo 3rd District Engineering Office |
1) BRPRIME CONSTRUCTION SUPPLIES 2) 1,960,017.47 3) 100 4) 5/16/2024 |
A) April 5, 2024 B) 24J00233 C) CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT MAGSAYSAY RIVER PHASE I RT LIM, ZAMBOANGA SIBUGAY D) Zamboanga Sibugay 2nd District Engineering Office |
1) BARILLO CONSTRUCTION AND ENTERPRISES 2) 95,529,501.40 3) 100 4) 5/8/2024 |
A) April 5, 2024 B) 24GH0148 C) COMPLETION OF MULTIPURPOSE BUILDING, TINIGBAN INTEGRATED SCHOOL, CARLES, ILOILO D) Iloilo 3rd District Engineering Office |
1) R. IBA�EZ CONSTRUCTION 2) 2,939,999.99 3) 100 4) 5/16/2024 |
A) April 5, 2024 B) 24L00032 C) RECONSTRUCTION TO CONCRETE PAVEMENT - JCT. DAVAO - COTABATO OLD ROAD - TAGLUNO - TAGURANO - KILATE - D) Region XI |
1) ALZAM ENTERPRISES INCORPORATED (FORMERLY: ALZAM EN 2) 91,233,706.92 3) 100 4) 5/28/2024 |
A) April 5, 2024 B) 24AD0089 C) CONSTRUCTION OF RIVER WALL AT TILEK, SUAGAYAN, QUIRINO, ILOCOS SUR D) Ilocos Sur 2nd District Engineering Office |
1) EJIEV CONSTRUCTION SERVICES 2) 5,688,855.80 3) 100 4) 5/3/2024 |
A) April 5, 2024 B) 24GH0159 C) CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY PUERTO PRINCESA, BAROTAC VIEJO, ILOILO D) Iloilo 3rd District Engineering Office |
1) JHALL MARKETING AND SERVICES 2) 1,970,526.58 3) 100 4) -/-/- |
A) April 5, 2024 B) 24HI0090 C) CONCRETING OF SITIO LIANG, BRGY. BINGAY FMR, BRGY. BINGAY, BORBON, CEBU D) Cebu 5th District Engineering Office |
1) NOGNOG ENTERPRISES 2) 14,916,114.74 3) 100 4) 4/29/2024 |
A) April 5, 2024 B) 23HI0140 C) REPAIR OF 3 CLASSROOMS, DAAN SECANTE ES, TUDELA, CEBU D) Cebu 5th District Engineering Office |
1) CYJE FIRST BUILDERS CONSTRUCTION CORP. (FORMERLY: 2) 1,496,542.62 3) 100 4) -/-/- |
A) April 5, 2024 B) 24AI0204 C) CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE 1 UMINGAN, PANGASINAN D) Pangasinan 3rd District Engineering Office |
1) R.F. FLORES CONSTRUCTION (FORMERLY PATRIOT CONSTRU 2) 4,890,797.73 3) 100 4) 5/3/2024 |
A) April 5, 2024 B) 23NA0038 C) READ - CONSTRUCTION OF SOLAR WATER SYSTEM, TUBAY, AGUSAN DEL NORTE D) Agusan del Norte District Engineering Office |
1) JD-RG CONSTRUCTION AND SUPPLIES CORP. (FORMERLY: J 2) 9,779,848.45 3) 100 4) 4/11/2024 |
A) April 5, 2024 B) 24HB0113 C) ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGR D) Bohol 3rd District Engineering Office |
1) MUANA CONSTRUCTION AND DEVELOPMENT CORP. (FORMERLY 2) 144,590,168.00 3) 100 4) 5/6/2024 |
A) April 5, 2024 B) 24LC0074 C) CONSTRUCTION OF MULTI-PURPOSE BUILDING (PDEA PROVINCIAL OFFICE), EPARK, APOKON, TAGUM CITY, DAVAO DE D) Davao del Norte District Engineering Office |
1) TRIPLE S BUILDERS INC. 2) 21,574,602.00 3) 100 4) 6/6/2024 |
A) April 5, 2024 B) 24L00043 C) ROAD WIDENING - DAANG MAHARLIKA (MN) - K1444+988 - K1445+1058, DAVAO DE ORO D) Region XI |
1) TAGUM BUILDERS CONTRACTORS CORP. (FORMERLY: TAGUM 2) 80,721,897.29 3) 100 4) 6/13/2024 |
A) April 5, 2024 B) 24OH0090 C) ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGR D) South Manila District Engineering Office |
1) AMETHYST HORIZON BUILDERS AND GEN. CONTRACTOR AND 2) 47,343,640.32 3) 100 4) 5/6/2024 |
A) April 5, 2024 B) 23HB0179 C) RECONSTRUCTION OF THE TIGBAO BRIDGE IN BAGUMBAYAN, LOBOC, PROVINCE OF BOHOL INTO A REINFORCED CONCRE D) Bohol 3rd District Engineering Office |
1) KMCM BUILDERS AND DEVELOPMENT CORPORATION 2) 240,028,918.50 3) 49 4) 4/30/2024 |