July 10, 2024 |
2024 |
P00800043MN |
SR2024-01-000108 |
January 24, 2024 |
Region X |
Bukidnon 1st District Engineering Office |
P00800043MN
310202101599000
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Roads
FROM:
Kalapong- Talaingod- Valencia (Bukidnon) Rd - K1543+000 - K1545+000
Type of Work:
CW1 - Road Widening
Physical Target:
CW1 - 4.00 Lane Km
Allocation
CW1: Php 75,986,030.00
EAO: Php 2,755,970.00
TO:
Kapalong-Talaingod-Valencia (Bukidnon) Rd - K1543 + 000 - K1544 + 506
Type of Work:
CW1 - Road Widening
Physical Target:
CW1 - 3.012 Lane Km
Allocation:
CW1: Php 75,986,030.00
EAO: Php 2,755,970.00
|
July 10, 2024 |
2024 |
P00800438MN |
GAA FY 2024 |
January 1, 2024 |
Region X |
Lanao del Norte 1st District Engineering Office |
P00800438MN
310107100696000
OO1 - Asset Preservation Program - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads
FROM:
Linamon-Zamboanga Rd - K1557 + 250 - K1557 + 315
Type of Work:
CW1 - Construction of Road Slope Protection Structure
Physical Target:
CW1 - 780.00 Square Meter
Allocation:
CW1 - Php 19,600,000.00
EAO - Php 400,000.00
TO:
Linamon-Zamboanga Rd - K1557 + 230 - K1557 + 315
Type of Work:
CW1 - Construction of Road Slope Protection Structure
Physical Target:
CW1 - 1,020.00 Square Meter
Allocation:
CW1 - Php 19,600,000.00
EAO - Php 400,000.00
|
July 10, 2024 |
2024 |
300204101351000 |
GAA 2024 |
January 3, 2024 |
Region II |
Cagayan 1st District Engineering Office |
Construction/ Improvement of Access Roads leading to Trades, Industries and Economic Zones (Roads Leveraging Linkages for Industry and Trade Infrastructure Program - ROLL-IT) - Access Road leading to Fish Landing and Bagoong Processing, Sitio Namuyucan, San Jose, Gonzaga, Cagayan |
July 10, 2024 |
2024 |
P00800046MN |
GAA FY 2024 |
January 1, 2024 |
Region X |
Bukidnon 2nd District Engineering Office |
P00800046MN
310201101448000
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
FROM:
Bukidnon Davao City Rd - K1598 + 323 - K1598 + 646
Type of Work:
CW1 - Road Widening
Physical Target:
CW1 - 0.646 Lane Km
Allocation
CW1: Php 12,740,000.00
EAO: Php 260,000.00
TO:
Bukidnon Davao City Rd - K1598 + 297 - K1598 + 585
Type of Work:
CW1 - Road Widening
Physical Target:
CW1 - 0.576 Lane Km
Allocation
CW1: Php 12,740,000.00
EAO: Php 260,000.00
|
July 10, 2024 |
2024 |
P00830297MN |
GAA FY 2024 |
January 1, 2024 |
Region X |
Lanao del Norte 1st District Engineering Office |
P00830297MN
300214101301000
CSSP - Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239 - -
FROM:
Installation of Roadway Lighting Structures along Linamon-Zamboanga National Highway, Maigo, Lanao del Norte
Type of Work:
CW1 - Road Safety: Roadway Lighting
Physical Target:
CW1 – 50.00 Number of Units
Allocation:
CW1 - Php 9,800,000.00
EAO - Php 200,000.00
TO:
Installation of Roadway Lighting Structures along Linamon-Zamboanga National Highway, Maigo, Lanao del Norte
Type of Work:
CW1 - Road Safety: Roadway Lighting
Physical Target:
CW1 – 44.00 Number of Units
Allocation:
CW1 - Php 9,800,000.00
EAO - Php 200,000.00
|
July 10, 2024 |
2024 |
P00800336MN |
GAA FY 2024 |
January 1, 2024 |
Region X |
Bukidnon 2nd District Engineering Office |
P00800336MN
310110100539000
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Construction/ Upgrading/ Rehabilitation of Drainage along National Roads - Primary Roads
FROM:
Sayre Highway - K1547 + 750 - K1548 + 000, K1548 + 200 - K1548 + 300
Type of Work:
CW1- Construction of Drainage Structure along Road
Physical Target:
CW1- 818 Lineal Meters
Allocation:
CW1: Php 8,820,000.00
EAO: Php 180,000.00
TO:
Sayre Highway - K1547 + 711 - K1548 + 000, K1548 + 280 - K1548 + 350
Type of Work:
CW1- Construction of Drainage Structure along Road
CW2- Off-Carriageway Improvement: Shoulder Paving/ Construction
Physical Target:
CW1- 610 Lineal Meters
CW2- 590.50 Square Meters
Allocation:
CW1: Php 6,659,889.54
CW2: Php 2,160,110.46
EAO: Php 180,000.00 |
July 10, 2024 |
2024 |
P00800997MN |
GAA FY 2024 |
January 1, 2024 |
Region X |
Bukidnon 2nd District Engineering Office |
P00800997MN
310101101327000
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads
FROM:
Bukidnon-Davao City Rd - K1588 + 000 - K1589 + 588
Type of Work:
CW1- Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1- 6.260 Lane Km
Allocation:
CW1: Php 85,885,000.00
EAO: Php 3,115,000.00
TO:
Bukidnon-Davao City Rd - K1587 + 714 - K1588 + 000, K1589+443 - K1590 + 111, K1590 + 126 - K1590 + 380
Type of Work:
CW1- Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1- 4.244 Lane Km
Allocation:
CW1: Php 85,885,000.00
EAO: Php 3,115,000.00
|
July 10, 2024 |
2024 |
P00803757MN |
SR2024-03-013346 |
March 16, 2024 |
Region X |
Regional Office X |
P00803757MN
310101101333000
OO1:Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads
FROM:
Sayre Highway K1476 + 026 - K1479 + 000
Type of Work:
CW1-Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1-5.844 Lane Km
Allocation:
Total: Php 114,750,000.00
CW1: Php 110,733,750.00
EAO: Php 4,016,250.00
TO:
Sayre Highway K1482+432 - K1483+000, K1483 + 659 - K1487+000
Type of Work:
CW1-Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1-7.790 Lane Km
Allocation:
Total: Php 114,750,000.00
CW1: Php 110,733,750.00
EAO: Php 4,016,250.00 |
July 10, 2024 |
2024 |
310101101184000 |
GAA 2024 |
January 3, 2024 |
Region II |
Isabela 4th District Engineering Office |
FROM:
Asset Preservation - Preventive Maintenance - Primary Roads - Santiago-Tuguegarao Rd - K0329+164-K0331+000
TO:
Asset Preservation - Preventive Maintenance - Primary Roads - Santiago-Tuguegarao Rd - K0329+911-K0331+675
|
July 10, 2024 |
2024 |
P00800073MN |
SR2024-01-002830 |
January 27, 2024 |
Region X |
Lanao del Norte 1st District Engineering Office |
P00800073MN
310201101321000
OO1 - Network Development Program - Road Widening - Primary Roads
FROM:
Linamon-Zamboanga Rd - K1545 +
651 - K1545 + 660, K1547 + 543 -
K1547 + 547, K1547 + 569 - K1547
+ 584, K1550 + 000 - K1551 + 600,
K1551 + 601 - K1554 + 140, K1554
+ 142 - K1555 + 926, K1555 + 928 -
K1556 + 008, K1556 + 009 - K1558
+ 374, K1558 + 479.80 - K1558 +
618, K1558 + 619 - K1560 + 096,
K1560 + 134.15 - K1561 + 014,
K1561 + 030.30 - K1562 + 527,
K1562 + 528 - K1562 + 532, K1562
+ 610.20 - K1563 + 215, K1564 +
680 - K1566 + 257, K1566 + 258 -
K1566 + 261, K1566 + 299.70 -
K1566 + 590, K1566 + 646.65 -
K1566 + 752, K1568 + 346 - K1568
+ 919, K1568 + 921 - K1568 + 925,
K1569 + 000 - K1570 + 034, K1570
+ 035 - K1570 + 039, K1570 + 100 -
K1570 + 104, K1571 + 590 - K1573
+ 257
Type of Work:
CW1 - Road Widening
ROW – ROW Acquisition
Physical Target:
CW1 – 3.192 lane km
ROW – 33.497 lane km
Allocation:
CW1 - Php 83,711,820.00
ROW – Php 2,904,650.00
EAO - Php 3,141,530.00
TO:
Linamon-Zamboanga Rd K1547+516 - K1547+547, K1547+569 - K1547+580, K1550+000 - K1550+391, K1551+212 - 1551+277, K1553+647 - K1553+693, K1571+590 - K1572+235, K1572+944 - K1573+257
Type of Work:
CW1 - Road Widening
CW2 - Construction of Road Slope Protection Structure
ROW – ROW Acquisition
Physical Target:
CW1 – 2.823 lane km
CW2 – 2,307.95 Square meter
ROW – 1,970.00 Square meter
Allocation:
CW1 - Php 65,897,450.00
ROW – Php 17,814,370.00
EAO - Php 3,141,530.00
|
July 10, 2024 |
2024 |
P00800074MN |
SR2024-01-002832 |
January 27, 2024 |
Region X |
Lanao del Norte 1st District Engineering Office |
P00800074MN
310201101322000
OO1 - Network Development Program - Road Widening - Primary Roads
FROM:
Linamon-Zamboanga Rd - K1573 + 257 - K1573 + 860, K1573 + 885 - K1574 + 042, K1574 + 122 - K1574 + 250, K1575 + 641 - K1575 + 643
Type of Work:
CW1 - Road Widening
Physical Target:
CW1 – 1.780 lane km
Allocation:
CW1 - Php 49,015,245.00
EAO – Php 1,777,755.00
TO:
Linamon-Zamboanga Rd - K1573 + 257 - K1573 + 860, K1573 + 885 - K1574 + 042, K1574 + 122 - K1574 + 250
Type of Work:
CW1 - Road Widening
CW2 - Construction of Road Slope Protection Structure
Physical Target:
CW1 – 1.776 lane km
CW2 – 1,451.90 Square meter
Allocation:
CW1 - Php 42,073,440.00
CW2 – Php 6,941,800.00
EAO – Php 1,777,755.00
|
July 10, 2024 |
2024 |
P00800057MN |
SR2024-01-001817 |
January 27, 2024 |
Region X |
Bukidnon 3rd District Engineering Office |
P00800057MN
310201101326000
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
FROM:
Sayre Highway - K1445 + 075 - K1446 + 483
Type of Work:
CW1- Road Widening
Physical Target:
CW1- 2.91 Lane Km
Allocation:
CW1: Php 70,203,750.00
EAO: Php 2,546,250.00
TO:
Sayre Highway - K1445 + 075 - K1445 + 885
Type of Work:
CW1- Road Widening
CW2- Construction of Drainage Structure
Physical Target:
CW1- 1.62 Lane Km
CW2- 1,400.20 Lineal Meters
Allocation:
CW1: Php 52,619,750.00
CW2: Php 17,584,000.00
EAO: Php 2,546,250.00 |
July 10, 2024 |
2024 |
P00803759MN |
SR2024-03-013348 |
March 16, 2024 |
Region X |
Regional Office X |
P00803759MN
310101101335000
OO1:Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads
FROM:
Sayre Highway K1488 + 324 - K1490 + 106, K1490 + 122 - K1490 + 970, K1491 + 175 - K1492 + 000, K1493 + 805 - K1494 + 000
Type of Work:
CW1-Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1-2.420 Lane Km
Allocation:
Total: Php 144,885,000.00
CW1: Php 139,814,025.00
EAO: Php 5,070,975.00
TO:
Sayre Highway K1488 + 324 - K1490 + 088, K1490 + 122 - K1490 + 970, K1491 + 175 - K1492 + 000, K1493 + 805 - K1494 + 000
Type of Work:
CW1-Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1-10.680 Lane Km
Allocation:
Total: Php 144,885,000.00
CW1: Php 139,814,025.00
EAO: Php 5,070,975.00 |
July 10, 2024 |
2024 |
P00801163MN |
GAA FY 2024 |
January 1, 2024 |
Region X |
Lanao del Norte 1st District Engineering Office |
P00801163MN
310104100686000
OO1 - Asset Preservation Program - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Primary Roads
FROM:
Linamon-Zamboanga Rd - K1546 + 306 - K1546 + 401, K1546 + 958 - K1547 + 153, K1566 + 000 - K1566 + 261, K1566 + 728 - K1566 + 762, K1567 + 710 - K1567 + 738, K1567 + 750.82 - K1567 + 773, K1568 + 387 - K1568 + 404, K1569 + 000 - K1570 + 039, K1574 + 996 - K1575 + 379, K1585 + 871 - K1586 + 000
Type of Work:
CW1 - Reconstruction to Concrete Pavement
Physical Target:
CW1 – 4.738 lane km
Allocation:
CW1 - Php 59,958,345.00
EAO – Php 2,174,655.00
TO:
Linamon-Zamboanga Rd - K1546 + 000 - K1546 + 306, K1547 + 775 - K1548 + 000, K1566 + 000 - K1566 + 261, K1566 + 728 - K1566 + 759, K1567 + 710 - K1567 + 734, K1567 + 754.50 - K1567 + 769, K1569 + 000 - K1569 + 800, K1585 + 571 - K1585 + 728
Type of Work:
CW1 - Reconstruction to Concrete Pavement
Physical Target:
CW1 – 3.661 lane km
Allocation:
CW1 - Php 59,958,345.00
EAO – Php 2,174,655.00
|
July 10, 2024 |
2024 |
310103101375000 |
GAA 2024 |
January 3, 2024 |
Region II |
Isabela 4th District Engineering Office |
FROM:
Asset Preservation - Preventive Maintenance - Tertiary Roads - Santiago-Baluarte-Quirino Bdry - K0326 + 500 - K0335 + 640
TO:
Asset Preservation - Preventive Maintenance - Tertiary Roads - Santiago-Baluarte-Quirino Bdry - K0326 + 215 - K0333 + 761
|
July 10, 2024 |
2024 |
P00803758MN |
SR2024-03-013347 |
March 16, 2024 |
Region X |
Regional Office X |
P00803758MN
310101101334000
OO1:Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads
FROM:
Sayre Highway K1480 + 000 - K1480 + 881, K1480 + 917 - K1481 + 783, K1486 + 048 - K1486 + 319, K1486 + 740 - K1487 + 236
Type of Work:
CW1-Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1-5.160 Lane Km
Allocation:
Total: Php 101,145,000.00
CW1: Php 97,604,925.00
EAO: Php 3,540,075.00
TO:
Sayre Highway K1487 + 000 - K1488 + 324, K1492 + 000 - K1493 + 000, K1494 + 000 - K1496 + 000
Type of Work:
CW1-Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1-8.620 Lane Km
Allocation:
Total: Php 101,145,000.00
CW1: Php 97,604,925.00
EAO: Php 3,540,075.00 |
July 10, 2024 |
2024 |
P00800056MN |
GAA FY 2024 |
January 1, 2024 |
Region X |
Bukidnon 3rd District Engineering Office |
P00800056MN
310201101450000
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
FROM:
Sayre Highway - K1441 + 812 - K1442 + 100
Type of Work:
CW1- Road Widening
Physical Target:
CW1- 0.430 Lane Km
Allocation:
CW1: Php 22,050,980.00
EAO: Php 450,020.00
TO:
Sayre Highway - K1441 + 1063 - K1442 + 100
Type of Work:
CW1- Road Widening
CW2- Construction of Slope Protection Structure
Physical Target:
CW1- 0.358 Lane Km
CW2- 1,255.76 Lineal Meters
Allocation:
CW1: Php 14,944,980.00
CW2: Php 7,106,000.00
EAO: Php 450,020.00 |
July 10, 2024 |
2024 |
P00801164MN |
SR2024-01-002827 |
January 27, 2024 |
Region X |
Lanao del Norte 1st District Engineering Office |
P00801164MN
310104100685000
OO1 - Asset Preservation Program - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Primary Roads
FROM:
Iligan City-Marawi City Rd - K1536 + (-082) - K1536 + 000, K1536 + (-116) - K1536 + (-082),
K1536 + (-129) - K1536 + (-116), K1536 + (-162) - K1536 + (-129), K1536 + (-175) - K1536 +
(-162), K1536 + (-181) - K1536 + (-175), K1536 + (-188) - K1536 + (-181), K1536 + (-206) - K1536
+ (-188), K1536 + (-218) - K1536 + (-206), K1536 + (-228) - K1536 + (-218), K1536 + (-238) -
K1536 + (-228), K1536 + (-308) - K1536 + (-238), K1536 + (-332) - K1536 + (-308), K1536 + (-342)
- K1536 + (-332), K1536 + (-344) - K1536 + (-342), K1536 + (-384) - K1536 + (-344), K1536 +
(-389) - K1536 + (-384), K1536 + (-432) - K1536 + (-389), K1536 + (-527) - K1536 + (-432), K1536
+ (-542) - K1536 + (-527), K1536 + (-635) - K1536 + (-542), K1536 + (-682) - K1536 + (-635),
K1536 + 000 - K1539 + 840
Type of Work:
CW1 - Reconstruction to Concrete Pavement
Physical Target:
CW1 – 8.90 lane km
Allocation:
CW1 - Php 71,681,165.00
EAO – Php 2,599,835.0
TO:
Iligan City-Marawi City Rd - K1536+(-635) - K1536+500, K1545+312 - K1546+000 , K1553+665 - K1554+207, K1554+281 - K1554+331
Type of Work:
CW1 - Reconstruction to Concrete Pavement
CW2 - Construction of Drainage Structure along Road
Physical Target:
CW1 – 4.086 lane km
CW2 – 688 lineal meters
Allocation:
CW1 - Php 58,873,548.18
CW2 – 12,807,616.82
EAO – Php 2,599,835.0
|
July 10, 2024 |
2024 |
P00803770MN |
SR2024-03-013391 |
March 16, 2024 |
Region X |
Regional Office X |
P00803770MN
310101101356000
OO1:Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads
FROM:
Sayre Highway K1521+862-K1523
Type of Work:
CW1-Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1-5.102 Lane Km
Allocation:
Total: Php 100,000,000.00
CW1: Php 96,500,000.00
EAO: Php 3,500,000.00
TO:
Sayre Highway K1512 + 366 - K1514 + 000, K1518 + 000 - K1519 + 285
Type of Work:
CW1-Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1-8.390 Lane Km
Allocation:
Total: Php 100,000,000.00
CW1: Php 96,500,000.00
EAO: Php 3,500,000.00 |
July 10, 2024 |
2024 |
P00833111MN |
GAA FY 2024 |
January 1, 2024 |
Region X |
Bukidnon 3rd District Engineering Office |
P00833111MN
300214101277000
CSSP - Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239
FROM:
Installation/Application of Signage and Pavement Markings along Jct. SH- Manolo Fortich-Libona-Indahag Road - K1481 + 000 - K1482 + 000, Barangay Agusan Canyon, Manolo Fortich Bukidnon and Barangay Crossing, Libona, Bukidnon
Type of Work:
CW1- Road Safety- Pavement Markings
Physical Target:
CW1- 990.00 Lineal Meters
Allocation:
CW1: Php 1,641,500.00
EAO: Php 33,500.00
TO:
Installation/Application of Signage and Pavement Markings along Jct. SH- Manolo Fortich-Libona-Indahag Road - K1460 + 366 - K1460 + 736, K1460 + 787.50 - K1461 + 450.50 Barangay Agusan Canyon, Manolo Fortich Bukidnon and Barangay Crossing, Libona, Bukidnon
Type of Work:
CW1- Road Safety- Pavement Markings
Physical Target:
CW1- 990.00 Lineal Meters
Allocation:
CW1: Php 1,641,500.00
EAO: Php 33,500.00 |
July 10, 2024 |
2024 |
P00800536MN |
GAA FY 2024 |
January 1, 2024 |
Region X |
Misamis Occidental 2nd District Engineering Office |
P00800536MN
310107100702000
OO1 - Asset Preservation Program - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads
FROM:
Ozamis-Pagadian Rd - K1668 + 100 - K1668 + 150
Type of Work:
CW1 - Construction of Road Slope Protection Structure
Physical Target:
CW1 – 2,149.610 Square meter
Allocation:
CW1 - Php 24,500,000.00
EAO – Php 500,000.00
TO:
Ozamis-Pagadian Rd - K1668 + 020 - K1668 + 170
Type of Work:
CW1 - Construction of Road Slope Protection Structure
Physical Target:
CW1 – 6,448.830 Square meter
Allocation:
CW1 - Php 24,500,000.00
EAO – Php 500,000.00
|
July 10, 2024 |
2024 |
P00800390MN |
GAA FY 2024 |
January 1, 2024 |
Region X |
Iligan City District Engineering Office |
P00800390MN
310110100543000
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Construction/ Upgrading/ Rehabilitation of Drainage - Primary Roads
FROM:
Overton-Buru-un Bdry Rd - K1535 + 073 - K1535 + 330, K1535 + 575 - K1535 + 877
Type of Work:
CW1- Construction of Drainage Structure along Road
Physical Target:
CW1- 559.00 Lineal Meters
Allocation:
CW1: Php 19,600,000.00
EAO: Php 400,000.00
TO:
Overton-Buru-un Bdry Rd - K1535 + 073 - K1535 + 370, K1535 + 534 - K1535 + 877
Type of Work:
CW1- Construction of Drainage Structure along Road
Physical Target:
CW1- 640.00 Lineal Meters
Allocation:
CW1: Php 19,600,000.00
EAO: Php 400,000.00 |
July 10, 2024 |
2024 |
P00801236MN |
SR2024-01-002893 |
January 27, 2024 |
Region X |
Misamis Occidental 2nd District Engineering Office |
P00801236MN
310104100688000
OO1 - Asset Preservation Program - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Primary Roads
FROM:
Ozamis-Oroquieta Rd - K1702 + 835 - K1703 + 000, K1709 + 960 - K1711 + 000, K1717 + 589 - K1718 + 398
Type of Work:
CW1 - Reconstruction to Concrete Pavement
Physical Target:
CW1 – 4.026 lane km
Allocation:
CW1 - Php 57,900,000.00
EAO – Php 2,100,000.00
TO:
Ozamis-Oroquieta Rd - K1709 + 000 - K1711 + 000, K1717 + 589 - K1718 + 398
Type of Work:
CW1 - Reconstruction to Concrete Pavement
Physical Target:
CW1 – 5.620 lane km
Allocation:
CW1 - Php 57,900,000.00
EAO – Php 2,100,000.00
|
July 10, 2024 |
2024 |
P00803771MN |
SR2024-01-002891 |
January 27, 2024 |
Region X |
Misamis Occidental 2nd District Engineering Office |
P00803771MN
310101101357000
OO1 - Asset Preservation Program - Preventive Maintenance - Primary Roads
FROM:
Asphalt Overlay Ozamis - Pagadian Road (Ozamiz Section) , K1695 + 409 K1696 + 687, Misamis Occidental
Type of Work:
CW1 - Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1 – 2.556 lane km
Allocation:
CW1 - Php 144,750,000.00
EAO - Php 5,250,000.00
TO:
Asphalt Overlay Ozamis - Pagadian Road (Ozamiz Section), K1695 + 000 - K1695 + 391, K1695 + 421 - K1699 + 831.70, Misamis Occidental
Type of Work:
CW1 - Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1 – 13.033 lane km
Allocation:
CW1 - Php 144,750,000.00
EAO - Php 5,250,000.00
|
July 10, 2024 |
2024 |
P00800543MN |
GAA FY 2024 |
January 1, 2024 |
Region X |
Iligan City District Engineering Office |
P00800543MN
310107100695000
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads
FROM:
Overton-Buru-un Bdry Rd - K1534 + 846 - K1534 + 939
Type of Work:
CW1- Construction of Road Slope Protection/ Structure
Physical Target:
CW1- 2,369.67 Square Meters
Allocation:
CW1: Php 49,000,000.00
EAO: Php 1,000,000.00
TO:
Overton-Buru-un Bdry Rd - K1533 + 313 - K1533 + 380 - K1534 + 840 - K1535 + 000
Type of Work:
CW1- Construction of Road Slope Protection/ Structure
Physical Target:
CW1- 2,060.00 Square Meters
Allocation:
CW1: Php 49,000,000.00
EAO: Php 1,000,000.00
|
July 10, 2024 |
2024 |
P00803773MN |
SR2024-01-002890 |
January 27, 2024 |
Region X |
Misamis Occidental 2nd District Engineering Office |
P00803773MN
310101101359000
OO1 - Asset Preservation Program - Preventive Maintenance - Primary Roads
FROM:
Asphalt Overlay Ozamis - Oroquieta Road (Ozamiz - Clarin Section), K1703 + 000 - K1704 + 252, Misamis Occidental
Type of Work:
CW1 - Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1 – 2.50 lane km
Allocation:
CW1 - Php 135,100,000.00
EAO - Php 4,900,000.00
TO:
Asphalt Overlay Ozamis - Oroquieta Road (Ozamiz - Clarin Section), K1701 + 526.000 - K1705 + 022.00, Misamis Occidental
Type of Work:
CW1 - Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1 – 12.850 lane km
Allocation:
CW1 - Php 135,100,000.00
EAO - Php 4,900,000.00
|
July 10, 2024 |
2024 |
P00803816MN |
GAA FY 2024 |
January 1, 2024 |
Region X |
Misamis Occidental 2nd District Engineering Office |
P00803816MN
310102101923000
OO1 - Asset Preservation Program - Preventive Maintenance - Secondary Roads
FROM:
Asphalt Overlay Ozamis Port Road, 0 - 105, 117 - 556, Misamis Occidental
Type of Work:
CW1 - Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1 – 1.088 lane km
Allocation:
CW1 - Php 9,800,000.00
EAO - Php 200,000.00
TO:
Asphalt Overlay Ozamis Port Road, 10.40 - 105, 117 - 428, Misamis Occidental
Type of Work:
CW1 - Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1 – 0.811 lane km
Allocation:
CW1 - Php 9,800,000.00
EAO - Php 200,000.00
|
July 10, 2024 |
2024 |
P00803817MN |
GAA FY 2024 |
January 1, 2024 |
Region X |
Misamis Occidental 2nd District Engineering Office |
P00803817MN
310102101924000
OO1 - Asset Preservation Program - Preventive Maintenance - Secondary Roads
FROM:
Asphalt Overlay Ozamis Port Road Dual, 0 - 439, 451 - 556, Misamis Occidental
Type of Work:
CW1 - Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1 – 1.088 lane km
Allocation:
CW1 - Php 9,800,000.00
EAO - Php 200,000.00
TO:
Asphalt Overlay Ozamis Port Road Dual, 130 - 439, 451 - 545.60, Misamis Occidental
Type of Work:
CW1 - Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1 – 0.807 lane km
Allocation:
CW1 - Php 9,800,000.00
EAO - Php 200,000.00
|
July 10, 2024 |
2024 |
P00801244MN |
GAA FY 2024 |
January 1, 2024 |
Region X |
Iligan City District Engineering Office |
P00801244MN
310104100777000
OO1: Ensure Safe and Reliable National Road System - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Primary Roads
FROM:
Misamis Oriental-Ma Cristina Bdry Rd - K1512+(-140) - K1512+040
Type of Work:
CW1- Rehabilitation of Paved Road
Physical Target:
CW1- 0.360 Lane Km
Allocation:
CW1: Php 7,288,260.00
EAO: Php 148,740.00
TO:
Misamis Oriental-Ma Cristina Bdry Rd - K1512+(-140) - K1512+135
Type of Work:
CW1- Reconstruction to Concrete Pavement
Physical Target:
CW1- 0.550 Lane Km
Allocation:
CW1: Php 7,288,260.00
EAO: Php 148,740.00 |
July 10, 2024 |
2024 |
P00803828MN |
GAA FY 2024 |
January 1, 2024 |
Region X |
Misamis Occidental 2nd District Engineering Office |
P00803828MN
310103101705000
OO1 - Asset Preservation Program - Preventive Maintenance - Tertiary Roads
FROM:
Asphalt Overlay Tan Avenue Road, K1686 + 669 - K1687 + 1071, Misamis Occidental
Type of Work:
CW1 - Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1 – 2.824 lane km
Allocation:
CW1 - Php 39,200,000.00
EAO - Php 800,000.00
TO:
Asphalt Overlay Tan Avenue Road, K1686 + 669 - K1687 + 610, Misamis Occidental
Type of Work:
CW1 - Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1 – 3.804 lane km
Allocation:
CW1 - Php 39,200,000.00
EAO - Php 800,000.00
|
July 10, 2024 |
2024 |
P00803874MN |
GAA FY 2024 |
January 1, 2024 |
Region X |
Iligan City District Engineering Office |
P00803874MN
310204102863000
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of By-Pass and Diversion Roads
FROM:
Construction of Bypass and Diversion Roads Iligan City-Cagayan de Oro City Alternate Route (Digidaan – Bulua Section) Package II, Iligan City, Lanao del Norte
Type of Work:
CW1- Construction of Concrete Road
Physical Target:
CW1- 1.64 Lane Km
Allocation:
CW1: Php 49,000,000.00
EAO: Php 1,000,000.00
TO:
Construction of Bypass and Diversion Roads Iligan City-Cagayan de Oro City Alternate Route (Digkilaan – Bulua Section) Package II, Iligan City, Lanao del Norte
Type of Work:
CW1- Construction of Concrete Road
Physical Target:
CW1- 1.64 Lane Km
Allocation:
CW1: Php 49,000,000.00
EAO: Php 1,000,000.00
|
July 10, 2024 |
2024 |
P00803844MN |
SR2024-01-002894 |
January 27, 2024 |
Region X |
Misamis Occidental 2nd District Engineering Office |
P00803844MN
310201101320000
OO1 - Network Development Program - Road Widening - Primary Roads
FROM:
Ozamis - Oroquieta Rd - K1707 + 535 - K1708 +200, K1715 + 968 - K1717 + 407, K1717 + 425 - K1717 + 589, K1720 + 184 - K1720 + 665, K1720 + 692 - K1721 + 184
Type of Work:
CW1 - Road Widening
Physical Target:
CW1 – 6.478 lane km
Allocation:
CW1 - Php 57,900,000.00
EAO - Php 2,100,000.00
TO:
Ozamis - Oroquieta Rd - K1707 + 535 - K1708 +200, K1715 + 968 - K1717 + 402.5
Type of Work:
CW1 – Road Widening
CW2 – Construction of Drainage Structure along Road
CW3 – Construction of Road Slope Protection Structure
Physical Target:
CW1 – 4.195 lane km
CW2 – 892.359 lm
CW3 – 2,781.930 Square meter
Allocation:
CW1 – Php 36,267,939.180
CW2 – Php 9,808,678.187
CW3 – Php 11,823,382.633
EAO – Php 2,100,000.00
|
July 10, 2024 |
2024 |
P00803792MN |
SR2024-01-002930 |
January 27, 2024 |
Region X |
Misamis Oriental 1st District Engineering Office |
P00803792MN
310102101629000
OO1 - Asset Preservation Program - Preventive Maintenance - Secondary Roads
FROM:
Gingoog-Claveria-Villanueva Rd - K1316 + 040 - K1317 + 269, K1329 + 775 - K1329 + 850
Type of Work:
CW1 - Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1 – 2.614 lane km
Allocation:
CW1 - Php 96,500,000.00
EAO - Php 3,500,000.00
TO:
Gingoog-Claveria-Villanueva Rd - K1316 + (-320) - K1317 + 886
Type of Work:
CW1 - Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1 – 8.836 lane km
Allocation:
CW1 - Php 96,500,000.00
EAO - Php 3,500,000.00
|
July 10, 2024 |
2024 |
P00803796MN |
SR2024-01-002932 |
January 27, 2024 |
Region X |
Misamis Oriental 1st District Engineering Office |
P00803796MN
310102101633000
OO1 - Asset Preservation Program - Preventive Maintenance - Secondary Roads
FROM:
Gingoog-Claveria-Villanueva Road-K1316+040-K1317+839, K1318+011-K1318+705
Type of Work:
CW1 - Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1 – 4.992 lane km
Allocation:
CW1 - Php 96,500,000.00
EAO - Php 3,500,000.00
TO:
Gingoog-Claveria-Villanueva Road - K1318 + 011 - K1318 + 705, K1325 + 500 – K1327 + 000
Type of Work:
CW1 - Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1 – 8.692 lane km
Allocation:
CW1 - Php 96,500,000.00
EAO - Php 3,500,000.00
|
July 10, 2024 |
2024 |
P00820035MN |
SR2024-01-004798 |
January 27, 2024 |
Region X |
Iligan City District Engineering Office |
P00820035MN
320101111349000
OO2: Protect Lives and Properties Against Major Floods - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
FROM:
Construction of Flood Mitigation Structure along Mandulong River, Barangay Mandulog, Iligan City
Type of Work:
CW1- Construction of Flood Mitigation Structure
Physical Target:
CW1- 320.0 Linear Meters
Allocation:
CW1: Php 96,500,000.00
EAO: Php 3,500,000.00
TO:
Construction of Flood Mitigation Structure along Mandulog River, Barangay Mandulog, Iligan City
Type of Work:
CW1- Construction of Flood Mitigation Structure
Physical Target:
CW1- 320.0 Linear Meters
Allocation:
CW1: Php 96,500,000.00
EAO: Php 3,500,000.00 |
July 10, 2024 |
2024 |
P00836526MN |
GAA FY 2024 |
January 1, 2024 |
Region X |
Misamis Oriental 1st District Engineering Office |
P00836526MN
300226115528000
CSSP - Basic Infrastructure Program (BIP) - Multi-Purpose Buildings/ Facilities to support Social Services
FROM:
Construction (Completion) of Multi-Purpose Building, (Mahayhay Elementary School), Magsaysay, Misamis Oriental
Type of Work:
CW1 - Construction of Multi Purpose Building
Physical Target:
CW1 – 2.00 Number of Building
Allocation:
CW1 - Php 19,800,000.00
EAO - Php 200,000.00
TO:
Construction (Completion) of Multi-Purpose Building, (Mahayahay Elementary School), Magsaysay, Misamis Oriental
Type of Work:
CW1 - Construction of Multi Purpose Building
Physical Target:
CW1 – 2.00 Number of Building
Allocation:
CW1 - Php 19,800,000.00
EAO - Php 200,000.00
|
July 10, 2024 |
2024 |
P00803653MN |
GAA FY 2024 |
January 1, 2024 |
Region X |
Misamis Oriental 2nd District Engineering Office |
P00803653MN
310201101462000
OO1 - Network Development Program - Road Widening - Primary Roads
FROM:
Butuan City-Cagayan de Oro City-Iligan City Rd - K1419 + 532 - K1419 + 645
Type of Work:
CW1 - Road Widening
Physical Target:
CW1 – 0.226 lane km
Allocation:
CW1 - Php 4,488,400.00
EAO - Php 91,600.00
TO:
Butuan City-Cagayan de Oro City-Iligan City Rd - K1418 + 801 - K1419 + 018
Type of Work:
CW1 - Road Widening
Physical Target:
CW1 – 0.226 lane km
Allocation:
CW1 - Php 4,488,400.00
EAO - Php 91,600.00
|
July 10, 2024 |
2024 |
P00833120MN |
GAA FY 2024 |
January 1, 2024 |
Region X |
Iligan City District Engineering Office |
P00833120MN
300214101298000
CSSP - Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239
FROM:
Installation of Road Safety Devices and Facilities along Misamis Oriental-Ma. Cristina Bdry Rd - K1521 + 757 - K1522 + 753, Iligan City, Lanao del Norte
Type of Work:
CW1- Road Safety: Pavement Markings
Physical Target:
CW1- 1,000.00 Linear Meters
Allocation:
CW1: Php 17,150,000.00
EAO: Php 350,000.00
TO:
Installation of Road Safety Devices and Facilities along Misamis Oriental-Ma. Cristina Bdry Rd - K1521 + 757 - K1522 + 753, Iligan City, Lanao del Norte
Type of Work:
CW1- Road Safety: Roadway Lighting
CW2- Off- Carriageway: Construction of Traffic Island
CW3- Road Safety: Traffic Signals
Physical Target:
CW1-25 Units
CW2- 447.44 Square Meters
CW3- 4 Number of Traffic Signals
Allocation:
CW1: Php 8,901,544.01
CW2- Php 5,189,774.49
CW3- Php 3,058,681.50
EAO: Php 350,000.00
|
July 10, 2024 |
2024 |
P00837175MN |
GAA FY 2024 |
January 1, 2024 |
Region X |
Iligan City District Engineering Office |
P00837175MN
300221106802000
CSSP - Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
FROM:
Construction of Road along Sitio Sinicabog, Brgy. Rongongon, Iligan City
Type of Work:
CW1- Construction of Concrete Road
Physical Target:
CW1- 1.20 Lane Km
Allocation:
CW1: Php 49,500,000.00
EAO: Php 500,000.00
TO:
Construction of Road along Sitio Sinicabog, Brgy. Rogongon, Iligan City
Type of Work:
CW1- Construction of Concrete Road
Physical Target:
CW1- 1.20 Lane Km
Allocation:
CW1: Php 49,500,000.00
EAO: Php 500,000.00
|
July 10, 2024 |
2024 |
P00837176MN |
GAA FY 2024 |
January 1, 2024 |
Region X |
Iligan City District Engineering Office |
P00837176MN
300221106803000
CSSP - Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
FROM:
Construction of Road with Box Culvert along Purok Poblacion, Brgy. Rongongon, Iligan City
Type of Work:
CW1- Construction of Concrete Road
Physical Target:
CW1- 1.30 Lane Km
Allocation:
CW1: Php 49,500,000.00
EAO: Php 500,000.00
TO:
Construction of Road with Box Culvert along Purok Poblacion, Brgy. Rogongon, Iligan City
Type of Work:
CW1- Construction of Concrete Road
Physical Target:
CW1- 1.30 Lane Km
Allocation:
CW1: Php 49,500,000.00
EAO: Php 500,000.00 |
July 10, 2024 |
2024 |
P00800346MN |
GAA FY 2024 |
January 1, 2024 |
Region X |
Lanao del Norte 2nd District Engineering Office |
P00800346MN
310110100544000
OO1: Ensure Safe and Reliable National Road System - Asset Preservation Program - Construction/ Upgrading/ Rehabilitation of Drainage along National Roads - Primary Roads
FROM:
Linamon-Zamboanga Rd – K1600 + 970 - K1600 + 993, K1600 + 994 - K1601 + 155, K1601 + 156 - K1601 + 744
Type of Work:
CW1- Construction of Drainage Structure along Road
Physical Target:
CW1- 824.00 Linear Meters
Allocation:
CW1: Php 10,497,760.00
EAO: Php 214,240.00
TO:
Linamon-Zamboanga Rd – K1600 + 970 - K1601 + 674
Type of Work:
CW1- Construction of Drainage Structure along Road
Physical Target:
CW1- 756.00 Linear Meters
Allocation:
CW1: Php 10,497,760.00
EAO: Php 214,240.00 |
July 10, 2024 |
2024 |
P00803617MN |
GAA FY 2024 |
January 1, 2024 |
Region X |
Lanao del Sur 2nd District Engineering Office |
P00803617MN
310109101639000
OO1: Ensure Safe and Reliable National Road System - Asset Preservation Program - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
FROM:
Dobleston-Butadon Rd - K1996 + 273 - K1996 + 358
Type of Work:
CW1- Rehabilitation/ Major Repair of Road Slope Protection Structure
Physical Target:
CW1- 595.00 Square Meters
Allocation:
CW1: Php 11,237,660.00
EAO: Php 229,340.00
TO:
Dobleston-Butadon Rd - K1996 + 160 - K1996 + 220, K1996 + 245 - K1996 + 272
Type of Work:
CW1- Rehabilitation/ Major Repair of Road Slope Protection Structure
CW2- Rehabilitation of Paved Road
Physical Target:
CW1- 1,015.68 Square Meters
CW2- 0.141 Lane Km
Allocation:
CW1: Php 7,046,629.12
CW2: Php 4,191,030.88
EAO: Php 229,340.00 |
July 5, 2024 |
2024 |
WIN4XY00250 |
GAA 2024 |
January 19, 2024 |
Region V |
Regional Office V |
Project ID : P00838587LZ
UACS : 300221104732000
FROM :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - BIP - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Road, Barangay Morocborocan to Barangay Poblacion, Rapu-Rapu, Albay
Physical Target :
CW1 - Construction of Gravel Road - 2.922 Lane Km
CW2 - Construction of Concrete Road - 2.96 Lane Km
CW3 - Construction of Drainage Structure along Road - 2780 Lineal meters
TO :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - BIP - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Road, Barangay Morocborocan to Barangay Poblacion, Rapu-Rapu, Albay
Physical Target :
CW1 - Construction of Gravel Road - 2.922 Lane Km
CW2 - Construction of Concrete Road - 2.96 Lane Km |
July 5, 2024 |
2024 |
WIN4XY00256 |
GAA 2024 |
January 19, 2024 |
Region V |
Regional Office V |
Project ID : P00842598LZ
UACS : 300215103828000
FROM :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - SIPAG - Access Roads and/ or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Namantao - Mapulang Daga Road, Bacacay, Albay
Physical Target :
CW1 - Construction of Gravel Road - 4.682 Lane Km
TO :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - SIPAG - Access Roads and/ or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Namantao - Mapulang Daga Road, Bacacay, Albay
Physical Target :
CW1 - Construction of Gravel Road - 3.6 Lane Km |
July 5, 2024 |
2024 |
WIN4E03501 |
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Agusan del Sur 1st District Engineering Office |
UACS No. : 310106101214000
Project ID: P00801219MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Asset Preservation Program - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads
- Tertiary Roads
FROM:
NRJ Bayugan-Calaitan-Tandag Rd - K1273 + 451 - K1273 + 529, K1275 + 145 - K1275 + 370, K1291 + 000 - K1291 + 200, K1291 + 714 - K1291 + 777, K1292 + 050- K1292 + 324, K1292 + 850 - K1292 + 886, K1293 + 153 - K1293 + 292
Type of Work:
CW1- Rehabilitation of Paved Road
Physical Target:
CW1- 3.548 Lane Km
Allocation:
TOTAL: P 41,611,000
CW1: P 40,778,780
EAO: P 832,220
Unit Cost:
CW1: P 11,493,455.47/Lane Km
TO:
NRJ Bayugan-Calaitan-Tandag Rd – K1291+714 – K1291+776.92, K1292+166 – K1292+409.50, K1293+753 – K1293+780.10
Type of Work:
CW1- Rehabilitation of Paved Road
Physical Target:
CW1- 0.67 Lane Km
CW2- 455 Square meters
Allocation:
TOTAL: P 41,611,000
CW1: P 20,944,649.97
CW2: P 19,834,130.03
EAO: P 832,220
Unit Cost:
CW1: P 31,260,671.60/Lane Km
CW2: P 43,591.49/Square meters
|
July 4, 2024 |
2024 |
WIN4XY00308 |
FY 2024 GAA |
December 20, 2023 |
Region III |
Bulacan 2nd District Engineering Office |
Asset Preservation Program - Preventive Maintenance - Tertiary Roads
NCR/Bulacan Brdy-Bigte-Ipo Dam Rd K0031+422 - K0031+635 |
July 4, 2024 |
2024 |
WIN4XY00314 |
FY 2024 GAA |
December 20, 2023 |
Region III |
Bulacan 2nd District Engineering Office |
Asset Preservation Program - Preventive Maintenance - Tertiary Roads
NCR/Bulacan Brdy - Bigte -Ipo Dam Rd - K0036+239 - K0036+600 |
July 4, 2024 |
2024 |
WIN4E03472 |
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Regional Office XIII |
UACS No. : 310201101372000
Project ID: P00800152MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Primary Roads
FROM:
Daang Maharlika (Surigao-Agusan Sect) - K1176 + 680 - K1176 + 960
Type of Work:
CW1- Road Widening
Physical Target:
CW1- 0.56 Lane Km
Allocation:
TOTAL: P 11,200,000
CW1: P 10,808,000
EAO: P 392,000
Unit Cost:
CW1: P 19,300,000/Lane Km
TO:
Daang Maharlika (Surigao-Agusan Sect) - K1176 + 750 - K1176 + 960
Type of Work:
CW1- Road Widening
CW2- Construction of Road Slope Protection Structure
Physical Target:
CW1- 0.42 Lane Km
CW1- 283.800 Square meters
Allocation:
TOTAL: P 11,200,000
CW1: P 8,769,920
CW1: P 2,038,080
EAO: P 392,000
Unit Cost:
CW1: P 20,880,761.90/Lane Km
CW2: P 7,181.39/Square meters
|
July 4, 2024 |
2024 |
WIN4E03472 |
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Regional Office XIII |
UACS No. : 310201101372000
Project ID: P00800152MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Primary Roads
FROM:
Daang Maharlika (Surigao-Agusan Sect) - K1176 + 680 - K1176 + 960
Type of Work:
CW1- Road Widening
Physical Target:
CW1- 0.56 Lane Km
Allocation:
TOTAL: P 11,200,000
CW1: P 10,808,000
EAO: P 392,000
Unit Cost:
CW1: P 19,300,000/Lane Km
TO:
Daang Maharlika (Surigao-Agusan Sect) - K1176 + 750 - K1176 + 960
Type of Work:
CW1- Road Widening
CW2- Construction of Road Slope Protection Structure
Physical Target:
CW1- 0.42 Lane Km
CW1- 283.800 Square meters
Allocation:
TOTAL: P 11,200,000
CW1: P 8,769,920
CW1: P 2,038,080
EAO: P 392,000
Unit Cost:
CW1: P 20,880,761.90/Lane Km
CW2: P 7,181.39/Square meters
|
July 4, 2024 |
2024 |
WIN4E03504 |
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Regional Office XIII |
UACS No. : 310101101424000
Project ID: P00801065MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Asset Preservation Program - Preventive Maintenance - Primary Roads
FROM:
Daang Maharlika (Agusan-Davao Sect) - K1258 + 292 - K1258 + 938
Type of Work:
CW1- Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1- 1.292 Lane Km
Allocation:
TOTAL: P 11,145,000
CW1: P 10,754,925
EAO: P 390,075
Unit Cost:
CW1: P 8,324,245.36/Lane Km
TO:
Daang Maharlika (Agusan-Davao Sect) - K1258 + 292 - K1258 + 787.5
Type of Work:
CW1- Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1- 0.991 Lane Km
Allocation:
TOTAL: P 11,145,000
CW1: P 10,754,925
EAO: P 390,075
Unit Cost:
CW1: P 10,852,598.39/Lane Km
|
July 4, 2024 |
2024 |
WIN4E03504 |
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Regional Office XIII |
UACS No. : 310101101424000
Project ID: P00801065MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Asset Preservation Program - Preventive Maintenance - Primary Roads
FROM:
Daang Maharlika (Agusan-Davao Sect) - K1258 + 292 - K1258 + 938
Type of Work:
CW1- Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1- 1.292 Lane Km
Allocation:
TOTAL: P 11,145,000
CW1: P 10,754,925
EAO: P 390,075
Unit Cost:
CW1: P 8,324,245.36/Lane Km
TO:
Daang Maharlika (Agusan-Davao Sect) - K1258 + 292 - K1258 + 787.5
Type of Work:
CW1- Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1- 0.991 Lane Km
Allocation:
TOTAL: P 11,145,000
CW1: P 10,754,925
EAO: P 390,075
Unit Cost:
CW1: P 10,852,598.39/Lane Km
|
July 4, 2024 |
2024 |
WIN4E03504 |
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Regional Office XIII |
UACS No. : 310101101424000
Project ID: P00801065MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Asset Preservation Program - Preventive Maintenance - Primary Roads
FROM:
Daang Maharlika (Agusan-Davao Sect) - K1258 + 292 - K1258 + 938
Type of Work:
CW1- Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1- 1.292 Lane Km
Allocation:
TOTAL: P 11,145,000
CW1: P 10,754,925
EAO: P 390,075
Unit Cost:
CW1: P 8,324,245.36/Lane Km
TO:
Daang Maharlika (Agusan-Davao Sect) - K1258 + 292 - K1258 + 787.5
Type of Work:
CW1- Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1- 0.991 Lane Km
Allocation:
TOTAL: P 11,145,000
CW1: P 10,754,925
EAO: P 390,075
Unit Cost:
CW1: P 10,852,598.39/Lane Km
|
July 4, 2024 |
2024 |
WIN4XY00307 |
FY 2024 GAA |
December 20, 2023 |
Region III |
Tarlac 2nd District Engineering Office |
Flood Management Program - Construction / Maintenance of Flood Mitigation Structures and Drainage Systems –
Rehabilitation of Existing Dike along Bangut River Upstream of Bangot Bridge, Right Side, Package B, Capas, Tarlac, Sta. 0+382.80 to Sta. 0+736.80 |
July 4, 2024 |
2024 |
WIN4XY00206 |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Aklan District Engineering Office |
UACS No. 310202101713000
Project ID: P00800196VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Secondary Roads
Jaime Cardinal Sin Ave - K0293+600 - K00294+682.5
CW1- Road Widening: 2.156 lane km. – 27,672.26
EAO – 564.74
TO:
OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Secondary Roads
Jaime Cardinal Sin Ave - K0293+600 - K00294+332.45
CW1- Road Widening: 1.4549 lane km. – 22,366.9565
ROW Acquisition: 3,662.25 sq. m. – 5,305.3035
EAO – 564.74 |
July 4, 2024 |
2024 |
WIN4XY00185 |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Aklan District Engineering Office |
UACS No. 310105101173000
Project ID: P00801050VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Secondary Roads
Aklan West Rd (Kalibo-Nabas) - K0261+560 - K0263+030, K0264+290 - K0265+317
CW1- Rehabilitation of Paved Road: 4.696 lane km. – 48,110.16
EAO – 981.84
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Secondary Roads
Aklan West Rd (Kalibo-Nabas) - K0261+560 - K0262+490, K0264+290 - K0265+311
CW1- Rehabilitation of Paved Road: 4.696 lane km. – 48,110.16
EAO – 981.84 |
July 4, 2024 |
2024 |
WIN4X700237 |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Aklan District Engineering Office |
UACS No. 310102101593000
Project ID: P00801028VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Secondary Roads
Jaime Cardinal Sin Ave (S00335PN) - K0278 + (-150) - K0280+000
CW1- Preventive Maintenance of Road - Asphalt Overlay: 8.22 lane km. – 45,240.165
EAO – 1,640.835
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Secondary Roads
Jaime Cardinal Sin Ave (S00536PN) - K0278 + (-391) - K0278+839
CW1- Preventive Maintenance of Road - Asphalt Overlay: 4.92 lane km. – 45,240.165
EAO – 1,640.835 |
July 4, 2024 |
2024 |
WIN4XY00226 |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Aklan District Engineering Office |
UACS No. 310102101586000
Project ID: P00801192VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Secondary Roads
Aklan West Rd - (S00324PN) - K0260 + 781 - K0271 + 000
CW1- Preventive Maintenance of Road - Asphalt Overlay: 19.96 lane km. – 142,337.50
EAO – 5,162.50
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Secondary Roads
Aklan West Rd - (S00324PN) - K0205+811 - K0257+368, K0258+145 - K0260+335
CW1- Preventive Maintenance of Road - Asphalt Overlay: 14.84 lane km. – 142,337.50
EAO – 5,162.50
|
July 4, 2024 |
2024 |
|
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Regional Office XIII |
UACS No. : 310101101385000
Project ID: P00803783MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Asset Preservation Program - Preventive Maintenance - Primary Roads
FROM:
Surigao-Davao Coastal Rd, Lianga, Surigao del Sur
Type of Work:
CW1- Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1- 12.524 Lane Km
Allocation:
TOTAL: P 250,000,000
CW1: P 241,250,000
EAO: P 8,750,000
Unit Cost:
CW1: P 19,263,015.01/Lane Km
TO:
Surigao-Davao Coastal Rd, Lianga, Surigao del Sur
Type of Work:
CW1- Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1- 20.952 Lane Km
Allocation:
TOTAL: P 250,000,000
CW1: P 241,250,000
EAO: P 8,750,000
Unit Cost:
CW1: P 11,514,413.90/Lane Km
|
July 4, 2024 |
2024 |
WIN4XY00186 |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Aklan District Engineering Office |
UACS No. 310102101587000
Project ID: P00801193VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Secondary Roads
Aklan West Rd - (S00324PN) - K0250 + 800 - K0260 + 781
CW1- Preventive Maintenance of Road - Asphalt Overlay: 20.006 lane km. – 142,337.50
EAO – 5,162.50
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Secondary Roads
Aklan West Rd - (S00324PN) - K0247+664 - K0250+012, K0252+020 - K0252+412, K0252+957 - K0255+838
CW1- Preventive Maintenance of Road - Asphalt Overlay: 15.116 lane km. – 142,337.50
EAO – 5,162.50
|
July 4, 2024 |
2024 |
WIN4XY00200 |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Aklan District Engineering Office |
UACS No. 310202101538000
Project ID: P00802922VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Secondary Roads
Aklan East Rd - K0294+144 - K0296+559, K0296+884 - K0296+952, K0296+1017 - K0297+031
CW1- Road Widening: 5.034 lane km. – 113,387.50
ROW Acquisition: 24,110 sq. m
EAO – 5,162.50
TO:
OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Secondary Roads
Aklan East Rd - K0294+144 - K0296+559, K0296+884 - K0296+952, K0296+1017 - K0297+031, K0301+000 - K0302+476
CW1- Road Widening: 5.034 lane km. – 101,388.578
CW2- Off Carriageway Improvement: Shoulder Paving: 4,428.00 sq. m. - 11,998.922
ROW Acquisition: 24,110 sq. m
EAO – 5,162.50
|
July 4, 2024 |
2024 |
|
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Aklan District Engineering Office |
UACS No. 310105101172000
Project ID: P00802926VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Secondary Roads
Aklan East Rd - K0321+115 - K0322+766
CW1- Reconstruction to Concrete Pavement: 3.418 lane km. – 31,375.68
EAO – 640.32
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Secondary Roads
Aklan East Rd - K0321+344 - K0322+748
CW1- Reconstruction to Concrete Pavement: 2.924 lane km. – 30,895.44
EAO – 640.32
Excess - 480.24 |
July 4, 2024 |
2024 |
WIN4X700237 |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Aklan District Engineering Office |
UACS No. 310102101592000
Project ID: P00803395VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Secondary Roads
Aklan West Rd - (S00324PN) - K0271+000 - K0275+499
CW1- Preventive Maintenance of Road - Asphalt Overlay: 17.188 lane km. – 96,500.00
EAO – 3,500.00
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Secondary Roads
Aklan West Rd - (S00324PN) - K0271+000 - K0275+499
CW1- Preventive Maintenance of Road - Asphalt Overlay: 17.188 lane km. – 96,500.00
EAO – 3,500.00
|
July 4, 2024 |
2024 |
|
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Aklan District Engineering Office |
UACS No. 310214100770000
Project ID: P00830325VS
FROM:
Convergence and Special Support Program
Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239
Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads along Aklan East Rd - K0286+349 - K0287+430, K0287+600 - K0287+890, K0288+174 - K0288+840, K0290+000 - K0290+174, K0290+223 - K0290+671, K0291+387 - K0293+649, K0294+112 - K0296+559
CW1-Rehabilitation of Paved Road: 17.734 lane km. – 133,364.93
EAO – 4,837.07
TO:
Convergence and Special Support Program
Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239
Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads along Aklan East Rd - K0286+349 - K0287+430, K0287+600 - K0287+890, K0288+174 - K0288+840, K0290+000 - K0290+174, K0290+223 - K0290+671, K0291+387 - K0293+649, K0294+112 - K0296+559, K0296+800 - K0296+952, K0297+000 - K0297+340, K0298+000 - K0298+332, K0298+370 - K0299+146, K0299+223 - K0299+472, K0299+740 - K0300+000, K0300+600 - K0300+882, K0301+160 - K0301+585
CW1-Rehabilitation of Paved Road: 12.636 lane km. – 133,364.93
EAO – 4,837.07
Excess - 3,000
|
July 4, 2024 |
2024 |
|
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Aklan District Engineering Office |
UACS No. 310214100772000
Project ID: P00832006VS
FROM:
Convergence and Special Support Program
Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239
Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads along Aklan West Rd (Kalibo-Nabas) - K0252 + 900 - K0254 + 590, K0258 + 730 - K0259 + 000, K0259 + 920 - K0260 + 890, K0261 + 230 - K0261 + 650, K0265 + 954 - K0266 + 227, K0267 + 750 - K0269 + 575
CW1-Rehabilitation of Paved Road: 12.228 lane km. – 110,899.73
EAO – 4,022.27
TO:
Convergence and Special Support Program
Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239
Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads along Aklan West Rd (Kalibo-Nabas) - K0234 + (-920) - K0234 + 426, K0235 + 300 - K0238 + 078, K0254 + 450 - K0255 + 340
CW1-Rehabilitation of Paved Road: 10.262 lane km. – 110,899.73
EAO – 4,022.27
|
July 4, 2024 |
2024 |
|
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Aklan District Engineering Office |
UACS No. 310214100771000
Project ID: P00830326VS
FROM:
Convergence and Special Support Program
Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239
Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads along Aklan East Rd - K0296 + 800 - K0296 + 952, K0297 + 000 - K0297 + 340, K0298 + 000 - K0298 + 332, K0298 + 370 - K0299 + 146, K0299 + 223 - K0299 + 472, K0299 + 740 - K0300 + 000, K0300 + 600 - K0300 + 882, K0301 + 160 - K0302 + 733, K0303 + 380 - K0304 + 270, K0304 + 450 - K0304 + 788, K0305 + 800 - K0306 + 000, K0306 + 400 - K0306 + 517, K0307 + 070 - K0307 + 189, K0307 + 500 - K0308 + 238, K0308 + 419 - K0309 + 654, K0309 + 654 - K0309 + 760
CW1-Rehabilitation of Paved Road: 15.184 lane km. – 137,441.09
EAO – 4,984.91
TO:
Convergence and Special Support Program
Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239
Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads along Aklan East Rd - K0286 + 349 - K0287 + 430, K0287 + 600 - K0287 + 890, K0288 + 174 - K0288 + 840, K0290 + 000 - K0290 + 174, K0301 + 585 - K0302 + 733, K0303 + 380 - K0304 + 270, K0304 + 450 - K0304 + 788, K0305 + 800 - K0306 + 000, K0306 + 400 - K0306 + 517, K0307 + 070 - K0307 + 189, K0307 + 500 - K0308 + 238, K0315 + 919 - K0316 + 660
CW1-Rehabilitation of Paved Road: 13.206 lane km. – 137,441.09
EAO – 4,984.91
|
July 4, 2024 |
2024 |
WIN4XY00240 |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Antique District Engineering Office |
UACS No. 310103101422000
Project ID: P00801493VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Tertiary Roads
Odiong-Sibalom-Sn Remigio-Leon Rd - K0104 + 072 - K0109 + 147, K0111 + 645 - K0117 + 000
CW1-Preventive Maintenance: Asphalt Overlay : 21.236 lane km. – 96,500.00
EAO – 3,500.00
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Tertiary Roads
Odiong-Sibalom-Sn Remigio-Leon Rd - K0104 + 079 – K0108 + 840
CW1-Preventive Maintenance: Asphalt Overlay : 9.754 lane km. – 96,500.00
EAO – 3,500.00 |
July 4, 2024 |
2024 |
|
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Capiz 1st District Engineering Office |
UACS No. 310110100516000
Project ID: P00802945VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Construction/ Upgrading/ Rehabilitation of Drainage along National Roads – Primary Roads
Iloilo Capiz Rd (New Route) – K0108+177.50 – K0108+535, K0110+791.50 – K0110+876.50
CW1-Construction of Drainage Structure along Road: 442.50 l.m.– 5,292.00
EAO – 108.00
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Construction/ Upgrading/ Rehabilitation of Drainage along National Roads – Primary Roads
Iloilo-Capiz Rd (New Route) - K0108 + 177.50 – K0108 + 490, K0110 + 791.50 –KO110 + 876.50
CW1-Construction of Drainage Structure along Road: 397.50 l.m.– 5,292.00
EAO – 108.00 |
July 4, 2024 |
2024 |
|
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Capiz 1st District Engineering Office |
UACS No. 310104100739000
Project ID: P00802953VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads – Primary Roads
Iloilo Capiz Rd (New Route) – K0106+612 – K0107+461
CW1-Rehabilitation of Paved Road: 1.710 Lane Km– 18,032.00
EAO – 368.00
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads – Primary Roads
Iloilo Capiz Rd (New Route) – K0106+190 – K0106+995.50
CW1-Rehabilitation of Paved Road: 1.610 Lane Km – 15,079.16
CW2- Construction of Drainage Structure along Road:
169.740 Lineal Meters - 2,952.84
EAO – 368.00 |
July 4, 2024 |
2024 |
WIN4F07935 |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Capiz 1st District Engineering Office |
UACS No. 300221106238000
Project ID: P00832266VS
FROM:
Convergence and Special Support Program
BIP – Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Construction of Road, Barangay Manoling, Pilar, Capiz
CW1-Construction of Concrete Road: 0.580 lane km– 4,950.00
EAO – 50.00
TO:
Convergence and Special Support Program
BIP – Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Construction of Road, Barangay Manoling, President Roxas, Capiz
CW1-Construction of Concrete Road: 0.441 lane km– 4,950.00
EAO – 50.00 |
July 4, 2024 |
2024 |
WIN4XY00222 |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Capiz 1st District Engineering Office |
UACS No. 310108101882000
Project ID: P00800380VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Rehabilitation/ Reconstruction of National Roads with Slis, Slope Collapse, and Landslide - Secondary Roads
Maayon-Jct Bailan Rd – K0122+185 – K0122+225, K0123+612 – K0123+654, K0127+255.70 - K0127+289.85
CW1-Construction of Road Slope Protection Structure: 349.80 sq. m.– 2,589.16
CW2-Off-Carriageway Improvement: Paving of Shoulders: 328.00 sq. m. - 644.84
EAO – 66.00
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Rehabilitation/ Reconstruction of National Roads with Slis, Slope Collapse, and Landslide - Secondary Roads
Maayon-Jct Bailan Rd – K0122+200 – K0122+225, K0123+600 – K0123+717, K0127+304 - K0127+319
CW1-Construction of Road Slope Protection Structure: 381.02 sq. m.– 3,234.00
EAO – 66.00 |
July 4, 2024 |
2024 |
WIN4XY00187 |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Capiz 1st District Engineering Office |
UACS No. 310105101176000
Project ID: P00801051VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads – Secondary Roads
Iloilo East Coast – Capiz Rd – K0119 +157 – K0120 + 300
CW1-Rehabilitation of Paved Road: 2.196 Lane Km– 19,600.00
EAO – 400.00
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads – Secondary Roads
Iloilo East Coast – Capiz Rd – K0119 +413.5 – K0120 + 300
CW1-Rehabilitation of Paved Road: 1.680 Lane Km– 19,600.00
EAO – 400.00 |
July 4, 2024 |
2024 |
|
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Capiz 1st District Engineering Office |
UACS No. 310105101175000
Project ID: P00801052VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads – Secondary Roads
Iloilo East Coast–Capiz Rd– K0117+113 – K0118+090
CW1-Rehabilitation of Paved Road: 1.846 Lane Km– 16,660.00
EAO – 340.00
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads – Secondary Roads
Iloilo East Coast – Capiz Rd – K0117+113–K0117+908.5
CW1-Rehabilitation of Paved Road: 1.560 Lane Km– 16,660.00
EAO – 340.00 |
July 4, 2024 |
2024 |
|
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Capiz 1st District Engineering Office |
UACS No. 310105101178000
Project ID: P00801053VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads – Secondary Roads
Iloilo East Coast–Capiz Rd – K0127+837.38 – K0128+360
CW1-Rehabilitation of Paved Road: 1.107 Lane Km– 9,800.00
EAO – 200.00
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads – Secondary Roads
Iloilo East Coast–Capiz Rd– K0127+837.38 – K0128+309
CW1-Rehabilitation of Paved Road: 1.01 Lane Km– 9,800.00
EAO – 200.00 |
July 4, 2024 |
2024 |
WIN4XY00188 |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Capiz 2nd District Engineering Office |
UACS No. 310203100773000
Project ID: P00802955VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Tertiary Roads
Iloilo-Capiz Road (Old Route) K0084+450 - K0084 + 572, K0084+603 - K0086 + 678
CW1-Road Widening: 4.134 lane km. – 48,250.00
EAO – 1,750.00
TO:
OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Tertiary Roads
Iloilo-Capiz Road (Old Route) K0087+820 - K0088 + 176, K0088+214 - K0088 + 474
CW1-Road Widening: 1.134 lane km – 25,593.33
CW2 – Construction of Road Slope Protection Structure: 2,754.46 sq. m - 17,206.67
ROW Acquisition: 1,593.71 sq. m. - 5,450.00
EAO – 1,750.00 |
July 4, 2024 |
2024 |
|
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Guimaras District Engineering Office |
UACS No. 310201101287000
Project ID: P00801508VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Primary Roads
Guimaras Circumferential Rd (S000028GR) - K0023+654 - K0024+537, K0029+848 - K0030+000
CW1-Road Widening: 1.778 lane km. – 91,675.00
EAO – 3,325.00
TO:
OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Primary Roads
Guimaras Circumferential Rd (S000028GR) - K0020+490 - K0020+740, K0023+654 - K0024+000, K0029+859 - K0029+1000, K0039+214 - K0040+280
CW1-Road Widening: 3.051 lane km. – 81,675.00
ROW Acquisition: 7,628 sq. m. - 10,000.00
EAO – 3,325.00 |
July 4, 2024 |
2024 |
WIN4XY00230 |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Guimaras District Engineering Office |
UACS No. 310102101847000
Project ID: P00802958VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asst Preservation - Preventive Maintenance - Secondary Roads
Guimaras Circumferential Rd - K0045+207 - K0046+492
CW1-Preventive Maintenance of Road: Asphalt Overlay: 2.58 lane km. – 14,700.00
EAO – 300.00
TO:
OO1: Ensure Safe and Reliable National Road System
Asst Preservation - Preventive Maintenance - Secondary Roads
Guimaras Circumferential Rd - K0001+000 - K0001+217, K0005+732 - K0005+795
CW1-Preventive Maintenance of Road: Asphalt Overlay: 1.12 lane km. – 14,700.00
EAO – 300.00 |
July 4, 2024 |
2024 |
|
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Guimaras District Engineering Office |
UACS No. 310202101540000
Project ID: P00802959VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Secondary Roads
Guimaras Circumferential Rd - K0082+942 - K0084+278
CW1-Road Widening: 2.72 lane km. – 53,075.00
EAO – 1,925.00
TO:
OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Secondary Roads
Guimaras Circumferential Rd - K0083+660 - K0084+460
CW1-Road Widening: 1.538 lane km. – 38,062.175
CW2 - Construction of Drainage Structure along Road: 605 Lineal meters- 12,512.825
ROW Acquisition: 3,845 sq. m. - 2,500.00
EAO – 1,925.00 |
July 4, 2024 |
2024 |
|
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Guimaras District Engineering Office |
UACS No. 310202101720000
Project ID: P00802960VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Secondary Roads
Guimaras Circumferential Rd - K0025+358 - K0025+525
CW1-Road Widening: 0.540 lane km. – 14,896.00
ROW Acquisition: 840 sq. m. - 3,920.00
EAO – 304.00
TO:
OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Secondary Roads
Guimaras Circumferential Rd - K0025+363 - K0025+547
CW1-Road Widening: 0.575 lane km. – 14,582.03275
ROW Acquisition: 920 sq. m. - 313.96725
EAO – 304.00 |
July 4, 2024 |
2024 |
WIN4F07936 |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Guimaras District Engineering Office |
UACS No. 310102101588000
Project ID: P00802963VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Secondary Roads
Guimaras Circumferential Rd - (S00028GR) K0000+ (-114) - K0000+451, K0001+100 - K0002+268, K0005+732 - K0005+795, K0005+944 - K0006+018, K0006+296 - K0006+354, (S00029GR) K0000+(-449) - K0000+370
CW1-Preventive Maintenance of Road: Asphalt Overlay: 4.988 lane km. – 58,512.775
EAO – 2,122.225
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Secondary Roads
Guimaras Circumferential Rd - (S00028GR) K0001+250 - K0001+795, K0006+944 - K0006+018, K0006+290 - K0006+410, K0006+508 - K0006+593
CW1-Preventive Maintenance of Road: Asphalt Overlay: 3.296 lane km. – 58,512.775
EAO – 2,122.225 |
July 4, 2024 |
2024 |
WIN4XY00215 |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Iloilo 1st District Engineering Office |
UACS No. 310202101543000
Project ID: P00800018VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Secondary Roads
Iloilo-Antique Rd - K0032 + 083 - K0032 + 724, K0035 + 000 - K0035 + 056, K0035 + 205 - K0035 + 828
CW1-Road Widening: 2.64 lane km – 48,593.54
EAO – 1,762.46
TO:
OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Secondary Roads
Iloilo-Antique Rd – K0032+083 - K0032+724, K0039+000 - K0039+094, K0039+658 - K0039+696, K0039+852 - K0040+105
CW1-Road Widening: 2.024 lane km – 48,593.54
EAO – 1,762.46 |
July 4, 2024 |
2024 |
|
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Iloilo 2nd District Engineering Office |
UACS No. 310101101514000
Project ID: P00800780VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Primary Roads
Iloilo-Capiz (New Route) - K0035 + 849 - K0036 + 063, K0043 + 675 - K0044 + 400
CW1-Preventive Maintenance of Road: Asphalt Overlay -3.724 lane km – 33,611.06
EAO – 685.94
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Primary Roads
Iloilo-Capiz (New Route) - K0035 + 849 - K0036 + 063, K0047 + 000 - K0047 + 199, K0047 + 606 - K0048 + 006, K0048 + 283 - K0048 + 404
CW1-Preventive Maintenance of Road: Asphalt Overlay - 3.20 lane km – 33,611.06
EAO – 685.94 |
July 4, 2024 |
2024 |
WIN4XY00184 |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Iloilo 2nd District Engineering Office |
UACS No. 310203100844000
Project ID: P00802989VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Network Development Program - Road Widening - Tertiary Roads
Pototan-Tina-Lambunao Rd - K0036 + 500 - K0038 + 500
CW1-Construction of Drainage Structure along Road - 3,704 linear meter – 12,677.28
ROW Acquisition: 10,000.00 sq.m. - 9,800.00
EAO – 458.72
TO:
OO1: Ensure Safe and Reliable National Road System
Network Development Program - Road Widening - Tertiary Roads
Pototan-Tina-Lambunao Rd - K0037 + 530 - K0038 + 500
CW1-Road Widening: 0.894 lane km – 7,502.68
CW2-Construction of Drainage Structure along Road : 681.00 linear meter - 7,134.60
ROW Acquisition: 8,000.00 sq.m. - 7,840.00
EAO – 458.72 |
July 4, 2024 |
2024 |
|
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Iloilo 3rd District Engineering Office |
UACS No. 310112100517000
Project ID: P00800314VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Construction / Upgrading / Rehabilitation of Drainage along National Roads – Tertiary Roads
Sara-Sn Dionisio Rd – K0207+396 – K0207+598
CW1-Construction of Drainage Structure along Road: 202 lineal meters – 3,857.28
EAO – 78.72
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Construction / Upgrading / Rehabilitation of Drainage along National Roads – Tertiary Roads
Sara-Sn Dionisio Rd – K0207+360 – K0207+598
CW1-Construction of Drainage Structure along Road: 238 lineal meters – 3,857.28
EAO – 78.72 |
July 4, 2024 |
2024 |
WIN4XY00246 |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Iloilo 3rd District Engineering Office |
UACS No. 310109101605000
Project ID: P00800421VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide – Tertiary Roads
Concepcion-Sn Dionisio Rd – K0222+781 – K0222+855
CW1-Construction of Road Slope Protection Structure: 1480 Square Meters – 24,656.80
EAO – 503.20
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide – Tertiary Roads
Concepcion- Sn Dionisio Rd – K0223 +046 –K0223+116
CW1-Construction of Road Slope Protection Structure: 630.00 Square Meters – 24,656.80
EAO – 503.20 |
July 4, 2024 |
2024 |
WIN4XY00247 |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Iloilo 3rd District Engineering Office |
UACS No. 310109101606000
Project ID: P00800423VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide – Tertiary Roads
Concepcion-Sn Dionisio Rd – K0222+884 – K0222+928
CW1-Construction of Road Slope Protection Structure: 440 Square Meters – 1,293.60
EAO – 26.40
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide – Tertiary Roads
Concepcion-Sn Dionisio Rd–K0223+138–K0223+182
CW1-Construction of Road Slope Protection Structure: 156.64 Square Meters – 1,293.60
EAO – 26.40 |
July 4, 2024 |
2024 |
|
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Iloilo 3rd District Engineering Office |
UACS No. 310102101585000
Project ID: P00801031VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance- Secondary Roads
Passi-Sn Rafael-Lemery-Sara Rd – K0074+511 – K0078+369
CW1-Preventive Maintenance of Road: Asphalt Overlay: 15.56 lane km – 120,625.00
EAO –4,375.00
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance- Secondary Roads
Passi-Sn Rafael-Lemery-Sara Rd – K0074+511 – K0077+807
CW1-Preventive Maintenance of Road: Asphalt Overlay: 13.312 lane km – 120,625.00
EAO – 4,375.00 |
July 4, 2024 |
2024 |
WIN4XY00276 |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Iloilo 3rd District Engineering Office |
UACS No. 310105101184000
Project ID: P008003024VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads – Secondary Roads
Iloilo East Coast – Capiz Rd – K0215+906
CW1-Reconstruction to Concrete Pavement: 0.78 lane km: – 7,840.00
EAO –160.00
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads – Secondary Roads
Iloilo East Coast – Capiz Rd – K0215+887–K0215+1118
CW1-
Reconstruction to Concrete Pavement: 0.462 lane km – 7,840.00
EAO –160.00 |
July 4, 2024 |
2024 |
|
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Iloilo 4th District Engineering Office |
UACS No. 310102101857000
Project ID: P00803025VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation- Preventive Maintenance – Secondary Roads
Asphalt Overlay - Cabatuan - New Lucena - Banga Bante Rd, K0041+(-200) - K0042+209, K0042+223-K0046+200
CW1-Preventive Maintenance of Road: Asphalt Overlay: 10.77 lane km– 90,650.00
EAO – 1,850.00
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation- Preventive Maintenance – Secondary Roads
Asphalt Overlay - Cabatuan - New Lucena - Banga Bante Rd, K0041+(-677) - K0042+309, K0042+326-K0045+620
CW1-Preventive Maintenance of Road: Asphalt Overlay: 10.556 lane km - 90,650.00
EAO – 1,850.00 |
July 4, 2024 |
2024 |
|
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Surigao del Sur 1st District Engineering Office |
UACS No. : 300215104141000
Project ID: P00834949MN
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - SIPAG - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
FROM:
Construction of Road from Sitio Lomayaon - Sitio Haguimitan, Barangay Bolhoon, San Miguel, Surigao del Sur
Type of Work:
CW1- Construction of Concrete Road
Physical Target:
CW1- 2.641 Lane Km
Allocation:
TOTAL: P 30,000,000
CW1: P 28,950,000
EAO: P 1,050,000
Unit Cost:
CW1: P 10,961,756.91/Lane Km
TO:
Construction of Road from Sitio Lomayaon - Sitio Haguimitan, Barangay Bolhoon, San Miguel, Surigao del Sur
Type of Work:
CW1- Construction of Concrete Road
CW2- Construction of Road Slope Protection Structure
Physical Target:
CW1- 1.671 Lane Km
CW2- 5,183.87 Square meters
Allocation:
TOTAL: P 30,000,000
CW1: P 21,102,200
CW2: P 7,847,800
EAO: P 1,050,000
Unit Cost:
CW1: P 12,628,485.93/Lane Km
CW2: P 1,513.89/Square meters
|
July 4, 2024 |
2024 |
|
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Iloilo 4th District Engineering Office |
UACS No. 310102101858000
Project ID: P00803026VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation- Preventive Maintenance – Secondary Roads
Asphalt Overlay - Leganes - Sta. Barbara Rd., K0017+490-K0022+470
CW1-Preventive Maintenance of Road: Asphalt Overlay: 9.96 lane km– 83,790.00
EAO – 1,710.00
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation- Preventive Maintenance – Secondary Roads
Asphalt Overlay - Leganes - Sta. Barbara Rd., K0017 + 490 - K0022 + 297
CW1-Preventive Maintenance of Road: Asphalt Overlay: 9.614 lane km– 83,790.00
EAO – 1,710.00 |
July 4, 2024 |
2024 |
|
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Iloilo 4th District Engineering Office |
UACS No. 310102101859000
Project ID: P00803027VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Secondary Roads
Asphalt Overlay - Iloilo City - Leganes - Dumangas Coastal Rd., K0010+700 - K0013+568, K0013+664 - K0014+321
CW1-Preventive Maintenance of Road: Asphalt Overlay: 7.05 lane km– 96,530.00
EAO – 1,970.00
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Secondary Roads
Iloilo City - Leganes - Dumangas Coastal Rd., K0010+710 - K0013+530, K0013+644 - K0014+121
CW1-Preventive Maintenance of Road: Asphalt Overlay: 10.659 lane km– 96,530.00
EAO – 1,970.00 |
July 4, 2024 |
2024 |
WIN4XY00235 |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Iloilo 4th District Engineering Office |
UACS No. 310102101860000
Project ID: P00803028VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation- Preventive Maintenance – Secondary Roads
Asphalt Overlay – Iloilo East Coast – Capiz Rd., K0283 + 775 – K0284 + 777 – K0288 + 124
CW1-Preventive Maintenance of Road: Asphalt Overlay:
10.016 lane km– 130,830.00
EAO – 2,670.00
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation- Preventive Maintenance – Secondary Roads
Asphalt Overlay - Iloilo East Coast – Capiz Rd., K0286 + 280 – K0288 + 124
CW1-Preventive Maintenance of Road: Asphalt Overlay:
7.404 lane km– 76,981.94
CW2 – Off-Carriageway Improvement: Shoulder Paving: 2,778.10 sq. m. - 53,848.06
EAO – 2,670.00 |
July 4, 2024 |
2024 |
|
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Iloilo 4th District Engineering Office |
UACS No. 310103101630000
Project ID: P00803029VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation- Preventive Maintenance – Tertiary Roads
Asphalt Overlay Mandurriao-Sn Miguel-Alimodian-Maasin-Cabatuan Rd., K0014+491 - K0015+930 (with exception)
CW1-Preventive Maintenance of Road: Asphalt Overlay:
7.195 lane km– 61,250.00
EAO – 1,250.00
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation- Preventive Maintenance – Tertiary Roads
Mandurriao-Sn Miguel-Alimodian-Maasin-Cabatuan Rd., K0014 + 457 - K0016 + 166
CW1-Preventive Maintenance of Road: Asphalt Overlay:
6.346 lane km– 61,250.00
EAO – 1,250.00 |
July 4, 2024 |
2024 |
WIN4XY00199 |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Iloilo 4th District Engineering Office |
UACS No. 310103101631000
Project ID: P00803030VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation- Preventive Maintenance – Tertiary Roads
Asphalt Overlay Mandurriao-Sn Miguel-Alimodian-Maasin-Cabatuan Rd., K0018+300+1003, K0019+405 - K0021+460
CW1-Preventive Maintenance of Road: Asphalt Overlay:
11.335 lane km– 90,650.00
EAO – 1,850.00
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation- Preventive Maintenance – Tertiary Roads
Asphalt Overlay Mandurriao-Sn Miguel-Alimodian-Maasin-Cabatuan Rd., K0017+650 - K0018+400, K0021+054 - K0021+460, K0024+166 - K0024+305, K0025+988 - K0028+250
CW1-Preventive Maintenance of Road: Asphalt Overlay:
9.386 lane km– 90,650.00
EAO – 1,850.00 |
July 4, 2024 |
2024 |
|
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Iloilo 4th District Engineering Office |
UACS No. 310103101632000
Project ID: P00803031VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation- Preventive Maintenance – Tertiary Roads
Asphalt Overlay Mandurriao-Sn Miguel-Alimodian-Maasin-Cabatuan Rd., K0021+600 - K0024+565 (with exception)
CW1-Preventive Maintenance of Road: Asphalt Overlay:
5.878 lane km– 53,900.00
EAO – 1,100.00
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation- Preventive Maintenance – Tertiary Roads
Asphalt Overlay Mandurriao-Sn Miguel-Alimodian-Maasin-Cabatuan Rd., K0021+460 - K0024+166
CW1-Preventive Maintenance of Road: Asphalt Overlay:
5.36 lane km– 53,900.00
EAO – 1,100.00 |
July 4, 2024 |
2024 |
WIN4XY00202 |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Iloilo 4th District Engineering Office |
UACS No. 310202101728000
Project ID: P00800170VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Network Development – Road Widening – Secondary Roads
New Lucena-Sta. Barabara Rd – K0016+560 – K0017+048
CW1-Road Widening: 0.976 lane km – 26,446.28
EAO – 539.72
TO:
OO1: Ensure Safe and Reliable National Road System
Network Development – Road Widening – Secondary Roads
New Lucena-Sta. Barabara Rd – K0017+048 – K0017+454
CW1-Road Widening: 0.812 lane km – 26,446.28
EAO – 539.72 |
July 4, 2024 |
2024 |
WIN4XY00208 |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Iloilo 4th District Engineering Office |
UACS No. 310209100523000
Project ID: P00800255VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Network Development – Off-Carriageway Improvement – Tertiary Roads
Mandurriao- Sn Miguel- Alimodian- Maasin- Cabatuan Rd- K0023+316 – K0023+716
CW1-Off-Carriageway Improvement: Paving of Shoulders: 1,600 square meters – 14,700.00
EAO – 300.00
TO:
OO1: Ensure Safe and Reliable National Road System
Network Development – Off-Carriageway Improvement – Tertiary Roads
Mandurriao- Sn Miguel- Alimodian- Maasin- Cabatuan Rd- K0022+783 – K0023+089
CW1-Off-Carriageway Improvement: Paving of Shoulders: 1,172 square meters – 14,700.00
EAO – 300.00 |
July 4, 2024 |
2024 |
WIN4F07971 |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Iloilo 4th District Engineering Office |
UACS No. 310209100522000
Project ID: P00800256VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Network Development – Off-Carriageway Improvement – Tertiary Roads
Cabatuan-New Lucena-Banga-Bante Rd – K0036+000 – K0036+494
CW1-Off-Carriageway Improvement: Paving of Shoulders: 1,976 square meters – 14,700.00
EAO – 300.00
TO:
OO1: Ensure Safe and Reliable National Road System
Network Development – Off-Carriageway Improvement – Tertiary Roads
Cabatuan - New Lucena - Banga - Bante Rd – K0037+624 – K0038+000
CW1-Off-Carriageway Improvement: Paving of Shoulders: 1,452 square meters – 14,700.00
EAO – 300.00 |
July 4, 2024 |
2024 |
|
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Iloilo 4th District Engineering Office |
UACS No. 310109101608000
Project ID: P00800497VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide – Tertiary Roads
Jct Bancal-Leon-Antique Bdry Rd – K0046+893 – K0046+938
CW1-Construction of Road Slope Protection Structure: 333.33 Square Meters – 4,900.00
EAO – 100.00
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide – Tertiary Roads
Jct Bancal-Leon-Antique Bdry Rd – K0039+970 – K0040+107
CW1-Construction of Road Slope Protection Structure: 393.60 Square Meters – 4,900.00
EAO – 100.00 |
July 4, 2024 |
2024 |
|
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region VI |
Iloilo 4th District Engineering Office |
UACS No. 310102101594000
Project ID: P00801029VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Secondary Roads
Iloilo East Coast – Capiz Rd – K0283+(-120) – K0284+000
CW1-Preventive Maintenance of Road - Asphalt Overlay:
4.48 lane km– 53,075.00
EAO – 1,925.00
TO:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Secondary Roads
Iloilo East Coast-Capiz Rd - K0283 + (-120) - K0284 + 100, K0284 + 467 - K0284 + 700
CW1-Preventive Maintenance of Road - Asphalt Overlay: 5.812 lane km– 53,075.00
EAO – 1,925.00 |