Modification and Realignment



Date Posted GAA Year Reference No SARO Number SARO Date Region Implementing Office Description
March 28, 2018 FY 2018 GAA WIN8C02236 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Network Development Program
Construction of Missing Links/New Roads
Davao-Bukidnon Highway (Calinan Poblacion Portion) to Dalagdag-Fatima National Road to Panabo, incl. ROW, Davao del Norte, Davao City
Physical Target:
CW1: 6.820 Lane Km (Construction of Concrete Road)
ROW: 34,099.50 sq.m.
Allocation:
TOTAL: P 136,898,00,.00
CW1: P 131,624,070.00 (Construction of Concrete Road)
ROW: P 482,500.00
EAO: P 4,791,430.00

TO: OO1: Ensure Safe and Reliable National Road System - Network Development Program
Construction of Missing Links/New Roads
Davao-Bukidnon Highway (Calinan Poblacion Portion) to Dalagdag-Fatima National Road to Panabo, incl. ROW, Davao del Norte, Davao City
Physical Target:
CW1: 10.895 Lane Km (Construction of Concrete Road)
ROW: 34,099.50 sq.m.
Allocation:
TOTAL: P 136,898,000.00
CW1: P 131,624,070.00 (Construction of Concrete Road)
ROW: P 482,500.00
EAO: P 4,791,430.00
March 28, 2018 FY 2018 GAA WIN8C02249 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones
New Corella-Guadalupe-Del Monte Connecting New Corella Overland Transport Terminal In Support of Cacao, Coconut, Banana and Rubber Industry, New Corella, Davao del Norte
Physical Target:
CW1: 9.142 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 200,000,000.00
CW1: P 193,000,000.00 (Construction of Concrete Road)
EAO: P 7,000,000.00

TO: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones
New Corella-Guadalupe-Del Monte Connecting New Corella Overland Transport Terminal In Support of Cacao, Coconut, Banana and Rubber Industry, New Corella, Davao del Norte
Physical Target:
CW1: 12.1206 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 200,000,000.00
CW1: P 193,000,000.00 (Construction of Concrete Road)
EAO: P 7,000,000.00
March 28, 2018 FY 2018 GAA WIN8C02248 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones
NRJ Surigao Davao Coastal Road to Hijo Cadastral Connecting Tagum City Overland Terminal in Support of Business Processing Outsourcing, Coconut Farm and Renewable Energy Industries, Tagum City, Davao del Norte
Physical Target:
CW1: 6.400 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 140,000,000.00
CW1: P 135,100,000.00 (Construction of Concrete Road)
EAO: P 4,900,000.00

TO: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones
NRJ Surigao Davao Coastal Road to Hijo Cadastral Connecting Tagum City Overland Terminal in Support of Business Processing Outsourcing, Coconut Farm and Renewable Energy Industries, Tagum City, Davao del Norte
Physical Target:
CW1: 7.916 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 140,000,000.00
CW1: P 135,100,000.00 (Construction of Concrete Road)
EAO: P 4,900,000.00
March 28, 2018 FY 2018 GAA WIN8C02242 FY 2018 GAA RA 10964 January 2, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones
Brgy. Poblacion-Brgy. Dalawinon Connecting to Brgy. Kasuga in Support of Meat Processing, Magsaysay, Davao del Sur
Physical Target:
CW1: 7.140 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 121,370,000.00
CW1: P 117,122,050.00 (Construction of Concrete Road)
EAO: P 4,247,950.00

TO: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones
Brgy. Poblacion-Brgy. Dalawinon Connecting to Brgy. Kasuga in Support of Meat Processing, Magsaysay, Davao del Sur
Physical Target:
CW1: 9.756 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 121,370,000.00
CW1: P 117,122,050.00 (Construction of Concrete Road)
EAO: P 4,247,950.00

March 27, 2018 2018 WIN8C02184 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Agusan del Norte District Engineering Office
Network Development – Road Widening - Primary Road

FROM:
Daang Maharlika (Surigao-Agusan Sect.) incl. ROW –
K1197+472-K1197+533,
K1199+322-K1200+700,
K1200+950-K1201+000,
K1201+050-K1202+000,
K1203+238-K1203+576
Physical Target: - 4.562 lane km.(Road)
- 16,232.40 square meter (ROW)
Allocation - Php 79.968M (Total)
- Php 72.53M (Road)
- Php 4.64M (ROW)
- Php 2.798 (EAO)

TO:
Daang Maharlika (Surigao-Agusan Sect.) incl. ROW –
K1199+422-K1200+700, K1201+370-K1202+000,
K1203+238-K1203+577
Physical Target: - 4.500 lane km.(Road)
- 52,425 square meter (ROW)
Allocation - Php 79.968M (Total)
- Php 67.17M (Road)
- Php 10.0M (ROW)
- Php 2.798 (EAO)
March 27, 2018 2018 WIN8C02183 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Agusan del Norte District Engineering Office
Network Development – Road Widening - Primary Road

FROM:
Daang Maharlika (Surigao-Agusan Sect.) Incl. ROW – K1194+092-K1196+733, K1196+751-K1197+472
Physical Target: - 6.796 lane km.(Road)
- 20,388 square meter (ROW)
Allocation - Php 100.0M(Total)
- Php 91.5M (Road)
- Php 5.0M (ROW)
- Php 3.50M (EAO)

TO:
Daang Maharlika (Surigao-Agusan Sect.) Incl. ROW – K1192+530 – K1193+573, K1194+120 – K1194+624
Physical Target: - 3.068 lane km.(Road)
- 32,365.40 square meter (ROW)
Allocation - Php 100.0M(Total)
- Php 76.50M (Road)
- Php 20.0M (ROW)
- Php 3.50M (EAO)
March 27, 2018 2018 WIN8C02187 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Agusan del Norte District Engineering Office
Network Development – Road Widening - Tertiary Road

FROM:
Agusan-Malaybalay Rd. Incl. ROW – K1271+834 - K1272+535, K1272+775 – K1274+104
Physical Target: - 4.006 lane km.(Road)
- 28,042 square meter (ROW)
Allocation - Php 60.09M (Total)
- Php 53.49M (Road)
- Php 4.50M (ROW)
- Php 2.10M (EAO)

TO:
Agusan-Malaybalay Rd. Incl. ROW - K1271+984 - K1272+445.60, K1273+000 – K1274+031.96
Physical Target: - 2.933 lane km.(Road)
- 62.10 square meter (ROW)
Allocation - Php 60.09M (Total)
- Php 57.98M (Road)
- Php 0.01M (ROW)
- Php 2.10M (EAO)
March 27, 2018 2018 WIN8C02192 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Agusan del Norte District Engineering Office
Asset Preservation Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Primary Road

FROM:
Butuan City-Cagayan de Oro City-Iligan City Road (Agusan-Misamis Or. Road) - K1266+222-K1266+543, K1272+914-K1273+000, K1273+000-K1273+287, K1273+411-K1274+000, K1275+157-K1275+446
Physical Target: - 2.867 Lane Km
Allocation - Php 32.835M (Total)
- Php 32.178M
- Php 0.657M (EAO)

TO:
Butuan City-Cagayan de Oro City-Iligan City Road (Agusan-Misamis Or. Road) - K1266+222-K1266+562, K1272+914-K1274+000
Physical Target: - 2.862 Lane Km
Allocation - Php 32.835M (Total)
- Php 32.178M
- Php 0.657M (EAO)
March 27, 2018 2018 WIN8C02182 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Agusan del Norte District Engineering Office
Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Primary Road

FROM:
Butuan-Cagayan de Oro-Iligan Road (Agusan-Misamis Or. Rd.) Incl. ROW-K1265+527-K1265+642, K1279+400-K1279+500
Physical Target: - 6,150 square meter (Slope Protection)
- 2,020 square meter (ROW)
Allocation - Php 39.0M (Total)
- Php 37.82M (Slope Protection)
- Php 0.40M (ROW)
- Php 0.78M (EAO)

TO:
Butuan-Cagayan de Oro-Iligan Road (Agusan-Misamis Or. Rd.) Incl. ROW-K1265+527 – K1265+652, K1279+440 – K1279+451.60
Physical Target: - 2,925.87 square meter (Slope)
- 50.51 square meter (ROW)
Allocation - Php 39.0M (Total)
- Php 38.21M (Slope Protection)
- Php 0.01M (ROW)
- Php 0.78M (EAO)
March 27, 2018 2018 WIN8C02191 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Agusan del Norte District Engineering Office
Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Primary Road

FROM:
Daang Maharlika (Surigao-Agusan Sect.) Incl. ROW – K1179+600-K1180+000
Physical Target: - 1,880 square meter (Slope Protection)
- 4,090 square meter (ROW)
Allocation - Php 15.0M (Total)
- Php 13.0M (Slope Protection)
- Php 1.70M (ROW)
- Php 0.30M (EAO)

TO:
Daang Maharlika (Surigao-Agusan Sect.) Incl. ROW – K1179+600-K1179+651
Physical Target: - 1,161.27 square meter (Slope)
- 4,090 square meter (ROW)
Allocation - Php 15.0M (Total)
- Php 13.0M (Slope Protection)
- Php 1.70M (ROW)
- Php 0.30M (EAO)
March 27, 2018 2018 WIN8C02206 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Agusan del Norte District Engineering Office
Network Development - Paving of Unpaved Roads - Tertiary Roads

FROM:
Buenavista-Bunaguit Rd. incl. ROW - (S00396MN) K1271+145 – K1271+919, (S00475MN) K1273+463 – K1273+675, (S00390MN) CHAINAGE 000-CHAINAGE 120
Physical Target: - 2.212 lane km.(Road)
- 7,410.20 square meter (ROW)
Allocation - Php 33.0M (Total)
- Php 31.54M (Road)
- Php 0.80M (ROW)
- Php 0.66M (EAO)


TO:
Buenavista-Bunaguit Rd. incl. ROW - (S00396MN) K1271+178 – K1271+919, (S00475MN) K1273+463 – K1273+675, (S00390MN) CHAINAGE 0 - CHAINAGE 120
Physical Target: - 2.146 lane km.(Road)
- 92.59 square meter (ROW)
Allocation - Php 33.0M (Total)
- Php 32.33M (Road)
- Php 0.01M (ROW)
- Php 0.66M (EAO)
March 27, 2018 2018 WIN8C02186 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Agusan del Norte District Engineering Office
Construction/Improvement of Access Roads leading to Declared Tourism Destinations

FROM:
Banza to Magallanes Road leading to Centennial Tree and Beaches, Magallanes, Agusan del Norte
Physical Target: - 3.60 Lane Km. (Concrete Road)
Allocation - Php 81.0M (Total)
- Php 78.17M (Conc. Road)
- Php 2.83M (EAO)

TO:
Banza to Magallanes Road leading to Centennial Tree and Beaches, Magallanes, Agusan del Norte
Physical Target: - 1.60 Lane Km. (Concrete Road)
Allocation - Php 81.0M (Total)
- Php 78.17M (Conc. Road)
- Php 2.83M (EAO)
March 27, 2018 2018 WIN8C02190 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Surigao del Sur 2nd District Engineering Office
Construction/Improvement of Access Roads leading to Declared Tourism Destinations

FROM:
Access Road leading to Libuacan Cold Spring, Brgy. Carpenita, Tagbina, Surigao del Sur
Physical Target: - 1.181 Lane Km. (Concrete Road)
Allocation - Php 20.0M (Total)
- Php 19.60M (Conc. Road)
- Php 0.40M (EAO)

TO:
Access Road leading to Libuacan Cold Spring, Brgy. Carpenito, Tagbina, Surigao del Sur
Physical Target: - 1.60 Lane Km. (Concrete Road)
Allocation - Php 20.0M (Total)
- Php 19.60M (Conc. Road)
- Php 0.40M (EAO)
March 27, 2018 2018 WIN8C02185 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Surigao del Sur 2nd District Engineering Office
Construction/Improvement of Access Roads leading to Declared Tourism Destinations

FROM:
Access Road leading to Caguyao Mangrove Site, Brgy. Caguyao, Bislig City, Surigao del Sur
Physical Target: - 1.60 Lane Km. (Gravel Road)
Allocation - Php 20.0M (Total)
- Php 19.60M (Gravel Road)
- Php 0.40M (EAO)

TO:
Access Road leading to Caguyao Mangrove Site, Brgy. Caguyao, Bislig City, Surigao del Sur
Physical Target: - 1.60 Lane Km. (Concrete Road)
Allocation - Php 20.0M (Total)
- Php 19.60M (Concrete Road)
- Php 0.40M (EAO)
March 27, 2018 2018 WIN8C02189 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Surigao del Sur 2nd District Engineering Office
Construction/Improvement of Access Roads leading to Declared Tourism Destinations

FROM:
Access Road leading to Panaraga White Beach Resort, Brgy. Gamut, Barobo, Surigao del Sur
Physical Target: - 1.48 Lane Km. (Reconstruction from Paved to Concrete)
Allocation - Php 20.0M (Total)
- Php 19.60M (Road)
- Php 0.40M (EAO)

TO:
Access Road leading to Panaraga White Beach Resort, Brgy. Gamut, Barobo, Surigao del Sur
Physical Target: - 1.48 Lane Km. (Construction of Concrete Road)
Allocation - Php 20.0M (Total)
- Php 19.60M (Road)
- Php 0.40M (EAO)
August 25, 2017 DA CY 2017 S-06-17-0441 SR2017-03-006885 March 18, 2017 Region VII Cebu 3rd District Engineering Office
REALIGNMENT:

From: Concreting of Sitio Bangkal Brgy. Sibago - Sitio Laka Guimbawian FMR, Pinamungajan, Cebu

To: Concreting of Sitio Danawan, Sibago to Alpaco FMR, Pinamungajan, Cebu.
August 25, 2017 DA CY 2017 S-06-17-0441 SR2017-03-006886 March 18, 2017 Region VII Cebu 3rd District Engineering Office
REALIGNMENT:

From: Concreting of Sitio Tagaytay, Brgy. Binabag, Pinamungajan, Cebu.


To: Concreting of Sitio Pundol to Sitio Sangil FMR, Brgy. Binabag, Pinamungajan, Cebu.
August 17, 2017 2017 No Reference Number FY 2017 GAA RA 10924 December 29, 2016 Region V Masbate 2nd District Engineering Office
As per GAA:
Locally Funded Project: Local Infrastructure Program,
Buildings and Other Structures, Multipurpose Facilities, Construction of Activity Center/Covered Court, Pio V. Corpuz Municipality, Masbate
(Construction of Other Building)
Physical Target: 1 Bldg.
Unit Cost: P5,000/bldg.
Allocation: PhP 5.0M

As MODIFIED:
Locally Funded Project: Local Infrastructure Program,
Buildings and Other Structures, Multipurpose Facilities, Construction of Two (2) Storey Multipurpose Building of Municipality of Pio V. Corpuz Municipality, Masbate
(Construction of Other Building)
Physical Target: 1 Bldg.
Unit Cost: P5,000/bldg.
Estimated Cost: PhP 5.0M
August 17, 2017 2017 WIN7E01073 FY 2017 GAA RA 10924 December 29, 2016 Region V Masbate 2nd District Engineering Office
As per GAA:
Locally Funded Project: Local Infrastructure Program,
Buildings and Other Structures, Multipurpose Facilities, Construction of Multi-Purpose Building (Covered Court), Tunga, Esperanza, Masbate
(Construction of Multipurpose Building)
Physical Target: 1 Bldg.
Unit Cost: P2,000/bldg.
Allocation: PhP 2.0M

As MODIFIED:
Locally Funded Project: Local Infrastructure Program,
Buildings and Other Structures, Multipurpose Facilities, Construction of Multi-Purpose Building (Covered Court), Putingbato, Esperanza, Masbate
(Construction of Multipurpose Building)
Physical Target: 1 Bldg.
Unit Cost: P2,000/bldg.
Estimated Cost: PhP 2.0M
August 17, 2017 2017 WIN7E01096 FY 2017 GAA RA 10924 December 29, 2016 Region V Masbate 2nd District Engineering Office
As per GAA:
Locally Funded Project: Local Infrastructure Program,
Buildings and Other Structures, Multipurpose Facilities, Construction of Multi-Purpose Covered Court (MPB), Brgy. Naboctot, Placer, Masbate
(Construction of Multi- Purpose Building)
Physical Target: 1 Bldg.
Unit Cost: P2,000/bldg.
Allocation: PhP 2.0M

As MODIFIED:
Locally Funded Project: Local Infrastructure Program,
Buildings and Other Structures, Multipurpose Facilities, Construction of Multi-Purpose Covered Court (MPB), Brgy. Calabad, Dimasalang, Masbate
(Construction of Multipurpose Building)
Physical Target: 1 Bldg.
Unit Cost: P2,000/bldg.
Estimated Cost: PhP 2.0M
August 17, 2017 2017 WIN7E01037 FY 2017 GAA RA 10924 December 29, 2016 Region V Masbate 2nd District Engineering Office
As per GAA:
Locally-Funded Projects: Local Infrastructure Program,
Buildings and Other Structure - Multipurpose Facilities, Construction of Mufti-purpose Covered Court
Brgy. Sto. Niño, Cataingan, Masbate
(Construction of Multi-Purpose Building)
Physical Target: 1 bldg.
Unit Cost: P2,000/bldg.
Allocation: PhP 2.0M

As MODIFIED:
Locally-Funded Projects: Local Infrastructure Program,
Buildings and Other Structure - Multipurpose Facilities, Construction of Mufti-purpose Covered Court
Brgy. G. Aliño, Dimasalang, Masbate
(Construction of Multi-Purpose Building)
Physical Target: 1 bldg.
Unit Cost: P2,000/bldg.
Estimated Cost: PhP 2.0M
August 17, 2017 2017 No Reference Number FY 2017 GAA RA 10924 December 29, 2016 Region V Masbate 2nd District Engineering Office
As per GAA:
MFO 2: Flood Management Services - Construction/
Maintenance of Flood Mitigation Structures and
Drainage Systems, Construction of Buenavista River Flood Control, Brgy. Buenavista, Uson, Masbate
(Construction of Flood Mitigation Structure)
Physical Target: -
Unit Cost: P20,000/Lm.
Allocation: PhP 20.0M

As MODIFIED:
MFO 2: Flood Management Services - Construction/
Maintenance of Flood Mitigation Structures and
Drainage Systems, Construction of Buenavista River Flood Control, Brgy. Magsaysay Uson, Masbate Sta.0+587 - Sta.1+037
(Construction of Flood Mitigation Structure)
Physical Target: 450 Lm.
Unit Cost: P20,000/Lm
Estimated Cost: PhP 20.0M
August 17, 2017 2017 No Reference Number FY 2017 GAA RA 10924 December 29, 2016 Region V Masbate 2nd District Engineering Office
As per GAA:
MFO 2: Flood Management Services - Construction/
Maintenance of Flood Mitigation Structures and
Drainage Systems, Construction of Buenavista River Flood Control, Brgy. Buenavista, Uson, Masbate
(Construction of Flood Mitigation Structure)
Physical Target: -
Unit Cost: P20,000/Lm.
Allocation: PhP 20.0M

As MODIFIED:
MFO 2: Flood Management Services - Construction/
Maintenance of Flood Mitigation Structures and
Drainage Systems, Construction of Buenavista River Flood Control, Brgy. Magsaysay Uson, Masbate Sta.0+587 - Sta.1+037
(Construction of Flood Mitigation Structure)
Physical Target: 450 Lm.
Unit Cost: P20,000/Lm
Estimated Cost: PhP 20.0M
August 9, 2017 2017 165003014600182 FY 2017 GAA January 1, 2017 Region III Nueva Ecija 1st District Engineering Office
Asset Preservation of National Roads - Rehabilitation / Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary - Rehabilitation / Major Repair of Road Slope Protection Structure - Jct. Pinagpanaan - Rizal - Pantabangan Rd -
K0160+357.40 - K0160+371.80, K0160+379.10 - K0160+418.10, K0160+496.00 - K0160+523.30, K0160+529.20 - K0160+547.00, K0160+900.00 - K0160+951.50

(Rehabilitation / Major Repair of Slope Protection Structure)
August 9, 2017 2017 292003020402662 FY 2017 GAA January 1, 2017 Region III Zambales 1st District Engineering Office
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems - Construction of Slope Protection / Flood Control at San Vicente River (Upstream), Sta. 0+240 - Sta. 0+377, Candelaria, Zambales

(Construction of Slope Protection Structure)
August 9, 2017 2017 103004010311211 FY 2017 GAA January 1, 2017 Region III Zambales 1st District Engineering Office
Local Infrastructure Program - Buildings and Other Structures - Multipurpose/Facilities - Construction of Tourism Information Center Building, Pundaquit, San Antonio, Zambales
August 8, 2017 2017 WIN7F05060 FY 2017 GAA January 1, 2017 Region III Bataan 2nd District Engineering Office
Network Development - Improvement/Widening of National Roads - Tertiary - Balanga Poblacion Rd including RROW (S01336LZ) Chainage 0 - Chainage 500
(CW-1 Road Widening)
(ROW Acquisition)
August 2, 2017 2017 WIN7E01616 FY 2017 GAA RA 10924 December 29, 2016 Region V Camarines Norte District Engineering Office
As per GAA:
Locally-Funded Projects: Local Infrastructure Program: Roads and Bridges: Local Roads: Concreting / Construction of Iberica Road in Brgy. Iberica, Labo, Camarines Norte (Construction of Concrete Road)
Physical Target: 0.40 lane.km
Unit Cost: P5.0M/lane-km
Allocation: P2.0M

As MODIFIED:
Locally-Funded Projects: Local Infrastructure Program: Roads and Bridges: Local Roads: Concreting / Construction of Iberica Road in Brgy. Iberica, Labo, Camarines Norte (Construction of Concrete Road)
Physical Target: 0.742 lane.km
Unit Cost: P2,695.42M/lane-km
Estimated Cost: P2.0M

August 2, 2017 2017 WIN7E01576 FY 2017 GAA RA 10924 December 29, 2016 Region V Camarines Norte District Engineering Office
As per GAA:
Locally Funded Projects - Roads and Bridges - Local Roads : Construction of road, Barangay Il, Daet, Camarines Norte
(Construction of Concrete Road)
Physical Target: -
Unit Cost (P'000): -
Allocation Cost (P'000): P2,000

As MODIFIED:
Locally Funded Projects - Roads and Bridges - Local Roads : Construction of road, Barangay Il,
Daet, Camarines Norte
(Construction of Concrete Road)
Physical Target: 0.57
Unit Cost (P'000): P3,509/lane-km
Estimated Cost (P'000): P2,000
July 26, 2017 2017 WIN7E01032 FY 2017 GAA RA 10924 December 29, 2016 Region V Sorsogon District Engineering Office
As per GAA:
MFO 2 - Flood Management Services: Construction/Maintenance of Flood Mitigation Structures and Drainage Systems, Construction of Milagrosa River Control, Sorsogon City, Sorsogon
(Construction of Flood Mitigation Structure)
Physical Target: 780 Lm
Unit Cost: P44.87/Lm
Allocation: PhP35.0M

As MODIFIED:
MFO 2 - Flood Management Services: Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems, Construction of Milagrosa River Control, Castilla, Sorsogon
(Construction of Flood Mitigation Structure)
Physical Target: 780 Lm
Unit Cost: P44.87/Lm
Estimated Cost: PhP35.0M
July 26, 2017 2017 WIN7E01058 FY 2017 GAA RA 10924 December 29, 2016 Region V Sorsogon District Engineering Office
As per GAA:
MFO 1: National Road Network Services - Asset
Preservation of National Roads, Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads including drainage based on Pavement Management System/Highway Development and Management - 4 (HDM-4) Tertiary, Reconstruction from Concrete to Concrete, Jct Donsol-Banuang Gurang Rd - (S04433LZ)
K0578+800 - K0579+732, K0580+604 - K0580+906, K0583+540 - K0584+423,
K0585+046 - K0585+333 (Rehabilitation of Concrete Road)
Physical Target: 4.6 Lm
Unit Cost: P10,434.78/Lm
Allocation: PhP 48.0M

As MODIFIED:
MFO 1: National Road Network Services - Asset
Preservation of National Roads, Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads including drainage based on Pavement Management System/Highway Development and Management - 4 (HDM-4) Tertiary, Reconstruction from Concrete to Concrete, Jct Donsol-Banuang Gurang Rd - (S04433LZ) - K0578+800 - K0579+732, K0580+604 - K0580+906, K0583+540 - K0584+832 (Rehabilitation of Concrete Road)
Physical Target: 2,844 Lm
Unit Cost: P16,877.64/Lm
Estimated Cost: PhP 48.0M
July 25, 2017 CY 2017 WIN7F05033 GAA CY 2017 RA 10924 December 29, 2016 Region IV-B Palawan 3rd District Engineering Office
as MODIFIED:
Locally-Funded Projects
- Local Infrastructure Program
- Buildings and Other Structures
- Multipurpose/Facilities:
Construction of Multi-Purpose Building,
Barangay Bancao-Bancao, Puerto Princesa City
1 Bldg.
Php 3.00 Million
July 25, 2017 CY 2017 WIN7F05047 GAA CY 2017 RA 10924 December 29, 2016 Region IV-B Marinduque District Engineering Office
as MODIFIED:
Locally-Funded Projects
- Local Infrastructure Program
- Roads and Bridges :
National Roads:
- Road Opening of the Missing Gaps at
Dr. Damian Reyes Road ( Boac Side )
K0027+645 - K0028+056.5
L = 0.823 lane km
Php = 100.00 Million
( Road Opening )
July 25, 2017 CY 2017 UACS: 165003015700149 GAA CY 2017 RA 10924 December 29, 2016 Region IV-B Palawan 2nd District Engineering Office
as MODIFIED:
MF01 - National Road Network Services
- Road Upgrading ( Unpaved to Paved )
based on Gravel Road Strategies,
Traffic benchmark for Upgrading to
Paved Road Standards (HDM-4 Project Analysis)
- Secondary Road:
Road Upgrading
Gravel to Paved
Aramaywan - Berong - Pto. Princesa Road
L = 4.211 lane km
Php = 100.00 Million
July 25, 2017 2017 WIN7F04906 FY 2017 GAA RA 10924 December 29, 2016 Region V Albay 2nd Engineering Office
As per GAA:
Locally Funded Projects, Local Infrastructure Program - Buildings and Other Structures - School Buildings - Construction of Two Classroom Building, Victory Village Elementary School, Victory Village, Legazpi City, Albay
Physical Target: 2 Classroom
Unit Cost: P1.875M/Classroom
Allocation: PhP 3.750M

As MODIFIED:
Locally Funded Projects, Local Infrastructure Program - Buildings and Other Structures - School Buildings - Construction of Three Classroom Building, Victory Village Elementary School, Victory Village, Legazpi City, Albay
(Construction of Classrooms)
Physical Target: 3 Classroom
Unit Cost: P1.250M/Classroom
Estimated Cost: PhP 3.750M
July 25, 2017 2017 WIN7F05003 FY 2017 GAA RA 10924 December 29, 2016 Region V Albay 2nd Engineering Office
As per GAA:
Locally Funded Projects, Local Infrastructure Program - Buildings and Other Structures - Multipurpose/Facilities - Construction of Multi-Purpose Building, Brgy. Peñafrancia, Daraga, Albay
Physical Target: 1 Bldg.
Unit Cost: P5.0M/Bldg.
Allocation: PhP 5.0M

As MODIFIED:
Locally Funded Projects, Local Infrastructure Program - Buildings and Other Structures - Multipurpose/Facilities - Construction of Multi-Purpose Building, Brgy. Villahermosa, Daraga, Albay
(Construction of Multi-Purpose Building)
Physical Target: 1 Bldg.
Unit Cost: P5.0M/Bldg.
Estimated Cost: PhP 5.0M
July 25, 2017 2017 WIN7F04957 FY 2017 GAA 10924 December 29, 2016 Region V Albay 2nd Engineering Office
As per GAA:
Locally Funded Projects, Local Infrastructure Program - Buildings and Other Structures - Multipurpose/Facilities - Construction of Multi-Purpose Building, Brgy. Bonot, Legazpi City (Albay)
Physical Target:
Unit Cost:
Allocation: PhP 5.0M

As MODIFIED:
Locally Funded Projects, Local Infrastructure Program - Buildings and Other Structures - Multipurpose/Facilities - Construction of Multi-Purpose Building, School Division Office (SDO), Rawis, Legazpi City (Construction of Multi-Purpose Building)
Physical Target: 1 Bldg.
Unit Cost: P5.0M/Bldg.
Estimated Cost: PhP 5.0M
July 25, 2017 2017 WIN7F04930 FY 2017 GAA RA 10924 December 29, 2016 Region V Albay 2nd Engineering Office
As per GAA:
MFO-1 National Road Network Services, Network Development-Improvement/Widening of National Roads - Secondary - Road Widening - Daang Maharlika Jct - Legazpi - Sto Doming - Tabaco - Camarines Sur Bdry Rd including RROW - K0534+000 - K0534+300
Physical Target:
CW1 - Road Widening - 0.60 Lane Km
ROW - ROW Acquisition - 2,070 Sq.m.
Unit Cost:
CW1 - Road Widening - P12.458M/Lane Km
ROW - ROW Acquisition - P13.30T/Sq.m.
Allocation: PhP 35.0M

As MODIFIED:
MFO-1 National Road Network Services, Network Development-Improvement/Widening of National Roads - Secondary - Road Widening - Daang Maharlika Jct - Legazpi - Sto Doming - Tabaco - Camarines Sur Bdry Rd including RROW - K0534+000 - K0534+360
Physical Target:
CW1 - Road Widening - 0.720 Lane Km
ROW - ROW Acquisition - 1,444 Sq.m.
Unit Cost:
CW1 - Road Widening - P22.199M/Lane Km
ROW - ROW Acquisition - P13.17T/Sq.m.
Estimated Cost: PhP 35.0M
July 25, 2017 FY 2017 WIN7F04991 FY 2017 APPROVED MODIFICATION June 19, 2017 Cordillera Administrative Region Benguet 1st District Engineering Office
From: MFO 1: National Road Network Services- Network Development - Off- Carriageway Improvement including drainage- Tertiary Roads- Benguet-Nueva Vizcaya Rd - K0298 + 853 - K0304 + 000 ; Physical Target = 4,854 Sq.m.

To: MFO 1: National Road Network Services- Network Development - Off- Carriageway Improvement including drainage- Tertiary Roads- Benguet-Nueva Vizcaya Rd - K0298 + 853 - K0304 + 000 ; Physical Target = 8,000 Sq.m.
July 25, 2017 FY 2017 WIN7F04978 FY 2017 APPROVED MODIFICATION June 19, 2017 Cordillera Administrative Region Benguet 1st District Engineering Office
From: MFO 1: National Road Network Services- Construction and Maintenance of Bridges along National Roads - Replacement of Bridges (Temporary to Permanent)- Batuan Br. (B04275LZ) along Asin (Km 8)-Nangalisan-San Pascual, Tuba, Benguet-La Union Bdry Rd ; Physical Target = 286.20 Sq.m.

To: MFO 1: National Road Network Services- Construction and Maintenance of Bridges along National Roads - Replacement of Bridges (Temporary to Permanent)- Batuan Br. (B04275LZ) along Asin (Km 8)-Nangalisan-San Pascual, Tuba, Benguet-La Union Bdry Rd ; Physical Target =211.788 Sq.m.
July 25, 2017 FY 2017 WIN7F04992 FY 2017 APPROVED MODIFICATION June 19, 2017 Cordillera Administrative Region Benguet 1st District Engineering Office
From: MFO 2: Flood Management Services- Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems- Construction of Balili Flood Control, La Trinidad, Benguet ; Physical Target = 540 Lm

To: MFO 2: Flood Management Services- Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems- Construction of Balili Flood Control, La Trinidad, Benguet ; Physical Target = 250.40 Lm
July 25, 2017 FY 2017 WIN7F04976 FY 2017 APPROVED MODIFICATION June 19, 2017 Cordillera Administrative Region Benguet 1st District Engineering Office
From: MFO 2: Flood Management Services- Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems- Construction of Bangao Flood Control, Bokod, Benguet ; Physical Target = 1200 Lm

To:MFO 2: Flood Management Services- Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems- Construction of Bangao Flood Control, Bokod, Benguet ; Physical Target = 604 Lm
July 25, 2017 FY 2017 WIN7F04977 FY 2017 APPROVED MODIFICATION June 19, 2017 Cordillera Administrative Region Benguet 1st District Engineering Office
From: Locally Funded Projects- Local Infrastructure Program, Roads and Bridges- Local Roads- Improvement of Lusod Road, Lusod, Kabayan, Benguet

To:Locally Funded Projects- Local Infrastructure Program, Roads and Bridges- Local Roads- Improvement of Lusod Road, Lusod, Kabayan, Benguet ; Physical Target = 302.5 Lm
July 25, 2017 FY 2017 WIN7F04990 FY 2017 APPROVED MODIFICATION June 19, 2017 Cordillera Administrative Region Benguet 1st District Engineering Office
From: Locally Funded Projects- Local Infrastructure Program, Roads and Bridges- Local Roads- Improvement Camanga-an-Cacoduran Road, Tikey, Bokod, Benguet

To:Locally Funded Projects- Local Infrastructure Program, Roads and Bridges- Local Roads- Improvement Camanga-an-Cacoduran Road, Tikey, Bokod, Benguet ; Physical Target = 549 Lm
July 25, 2017 FY 2017 WIN7F04980 FY 2017 APPROVED MODIFICATION June 19, 2017 Cordillera Administrative Region Benguet 1st District Engineering Office
From: Locally Funded Projects- Local Infrastructure Program, Roads and Bridges- Local Roads- Improvement of Landing Road, Daclan, Bokod, Benguet

To:Locally Funded Projects- Local Infrastructure Program, Roads and Bridges- Local Roads- Improvement of Landing Road, Daclan, Bokod, Benguet ; Physical Target = 583.5 Lm
July 25, 2017 FY 2017 WIN7F04979 FY 2017 APPROVED MODIFICATION June 19, 2017 Cordillera Administrative Region Benguet 1st District Engineering Office
From: Locally Funded Projects- Local Infrastructure Program, Roads and Bridges- Local Roads- Improvement of Cobabeng Road, Cobabeng, Poblacion, Bokod, Benguet

To:Locally Funded Projects- Local Infrastructure Program, Roads and Bridges- Local Roads- Improvement of Cobabeng Road, Cobabeng, Poblacion, Bokod, Benguet ; Physical Target = 585 Lm
July 25, 2017 FY 2017 WIN7F04997 FY 2017 APPROVED MODIFICATION June 22, 2017 Cordillera Administrative Region Benguet 1st District Engineering Office
From: Locally Funded Projects- Local Infrastructure Program, Roads and Bridges- Local Roads- Construction/Rehabilitation of Local Road, Camp 3, Tuba, Benguet

To:Locally Funded Projects- Local Infrastructure Program, Roads and Bridges- Local Roads- Concreting of Local Road, Camp 3, Tuba, Benguet ; Physical Target = 307 Lm
July 25, 2017 FY 2017 WIN7E01160 FY 2017 APPROVED MODIFICATION March 27, 2017 Cordillera Administrative Region Lower Kalinga District Engineering Office
From: MFO 1 - National Road Network Services - Asset Preservation of National Roads - Rehabilitation/ Reconstruction/ Upgrading - Tertiary - Balbalan-Pinukpuk Road - Chainage 11070 - Chainage 11575, Chainage 27650 - Chainage 27687, Chainage 27705 - Chainage 27737 [Reconstruction from Concrete to Concrete] ; Physical Target = 1.148 ln-km

To:MFO 1 - National Road Network Services - Asset Preservation of National Roads - Rehabilitation/ Reconstruction/ Upgrading - Tertiary - Balbalan-Pinukpuk Road - Chainage 11070 - Chainage 11588, Chainage 27650 - Chainage 27684.25, Chainage 27702.33 - Chainage 27734.33 [Reconstruction from Concrete to Concrete] ; Physical Target =1.169 ln-km
July 25, 2017 FY 2017 WIN7F05028 FY 2017 APPROVED MODIFICATION June 23, 2017 Cordillera Administrative Region Upper Kalinga District Engineering Office
From: MFO-2 : Flood Management Services, Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems - Construction of Balbalasang 1 and 2 Flood Control along Saltan River, Kalinga (Construction of Revetment) ; Physical Target = 600 Lm

To:MFO-2 : Flood Management Services, Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems - Construction of Balbalasang 1 and 2 Flood Control along Saltan River, Kalinga (Construction of Revetment) ; Physical Target = 89 Lm
July 25, 2017 FY 2017 292003020402311 FY 2017 APPROVED MODIFICATION January 27, 2017 Cordillera Administrative Region Upper Kalinga District Engineering Office
From: MFO-2 : Flood Management Services, Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems : Construction of Revetment - Construction of Ambato Flood Control, Kalinga (Construction of Revetment) ; Physical Target = 800 Lm

To:MFO-2 : Flood Management Services, Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems : Construction of Revetment - Construction of Ambato Flood Control, Kalinga (Construction of Revetment) ; Physical Target = 196.50 Lm
July 25, 2017 2017 WIN7F04885 FY 2017 GAA RA 10924 December 29, 2016 Region V Catanduanes District Engineering Office
As per GAA:
MFO-1 National Road Network Services: Asset Preservation of National Roads - Rehabilitation/
Reconstruction of National Roads with Slips, Sope Collapse, and Landslide — Secondary:
(Construction of Road Slope Protection Structure - Jct Catanduanes Cir Rd-Panganiban-Sabloyon Rd - K0058+300-K0058+600, K0060+250-K0060+550, K0061+800-K0062+099
(Construction of Road Slope Protection Structure)
Physical Target: 6,800 sq.m .
Unit Cost: P4.11T/sq.m.
Allocation: P28M

As MODIFIED:
MFO-1 National Road Network Services: Asset Preservation of National Roads - Rehabilitation/
Reconstruction of National Roads with Slips, Sope Collapse, and Landslide — Secondary:
(Construction of Road Slope Protection Structure - Jct Catanduanes Cir Rd-Panganiban-Sabloyon Rd - K0058+300-K0058+600, K0060+250-K0060+550,
K0061+264, K0061+800-K0062+099
(Construction of Road Slope Protection Structure)
Physical Target: 4,815 sq.m .
Unit Cost: P5.82T/sq.m.
Estimated Cost: P28M
July 25, 2017 2017 WIN7F05019 FY 2017 GAA RA 10924 December 29, 2016 Region V Catanduanes District Engineering Office
As per GAA:
MFO-1 National Road Network Services: Asset Preservation of National Roads - Rehabilitation/
Reconstruction of National Roads with Slips, Sope Collapse, and Landslide - Tertiary: Construction of Road Slope Protection Structure - Baras-Gigmoto-Viga Rd - K0042+500-K0042+1000, K0046+450-K0046+950
(Construction of Road Slope Protection Structure)
Physical Target: 10,000 sq.m .
Unit Cost: P3.88T/sq.m.
Allocation: P38.815M

As MODIFIED:
MFO-1 National Road Network Services: Asset Preservation of National Roads - Rehabilitation/
Reconstruction of National Roads with Slips, Sope Collapse, and Landslide - Tertiary: Construction of Road Slope Protection Structure - Baras-Gigmoto-Viga Rd - K0031+580-K0032+000,
K0033+000-K0034+060,K0038+840-K0040+520, K0046+740-K0048+500
(Construction of Road Slope Protection Structure)
Physical Target: 4,600 sq.m .
Unit Cost: P8.44T/sq.m.
Estimated Cost: P38.815M
July 25, 2017 2017 WIN7F05017 FY 2017 GAA RA 10924 December 29, 2016 Region V Catanduanes District Engineering Office
As per GAA:
MFO-1 National Road Network Services: Asset Preservation of National Roads - Rehabilitation/
Reconstruction of National Roads with Slips, Sope Collapse, and Landslide - Tertiary: Construction of Road Slope Protection Structure - Jct Bato-Baras Rd - K0021+300-K0021+800, K0022+500-K0023+029 (Construction of Road Slope Protection Structure)
Physical Target: 4,000 sq.m .
Unit Cost: P6.0T/sq.m.
Allocation: P23.997M

As MODIFIED:
MFO-1 National Road Network Services: Asset Preservation of National Roads - Rehabilitation/
Reconstruction of National Roads with Slips, Sope Collapse, and Landslide - Tertiary: Construction of Road Slope Protection Structure - Jct Bato-Baras Rd - K0013+500-K0013+740, K0022+350-K0023+029 (Construction of Road Slope Protection Structure)
Physical Target: 2,104 sq.m .
Unit Cost: P11.41T/sq.m.
Estimated Cost: P23.997M
July 25, 2017 2017 WIN7F04836 FY 2017 GAA RA 109249 December 29, 2016 Region V Catanduanes District Engineering Office
As per GAA:
MFO-1 National Road Network Services: Construction and Maintenance of Bridges along National Roads - Widening of Permanent Bridges to more than 2 Lanes, including ROW,
Widening of Bridge - Gogon Br. (B00043CN) along Catanduanes Cir Rd (Widening of Bridge)
Physical Target:
CW-1 Widening of Bridge : 228.75 sq.m .
Unit Cost:
CW-1 Widening of Bridge : P218.14T/sq.m .
Allocation: P49.900M

As MODIFIED:
MFO-1 National Road Network Services: Construction and Maintenance of Bridges along National Roads - Widening of Permanent Bridges to more than 2 Lanes, including ROW,
Widening of Bridge - Gogon Br. (B00043CN) along Catanduanes Cir Rd (Widening of Bridge) (ROW Acquisition)
Physical Target:
CW-1 Widening of Bridge : 243.00 sq.m.
ROW Acquisition: 1,515.59sq.m.
Unit Cost:
CW-1 Widening of Bridge : P127.36T/sq.m.
ROW Acquisition: P12.50T/sq.m.
Estimated Cost: P49.900M
July 25, 2017 2017 WIN7F04837 FY 2017 GAA RA 10924 December 29, 2016 Region V Catanduanes District Engineering Office
As per GAA:
MFO-1 National Road Network Services: Construction and Maintenance of Bridges along National Roads - Widening of Permanent Bridges to more than 2 Lanes, including ROW,
Widening of Bridge - Sinibaan Br. (B00001CN) along Catanduanes Cir Rd (Widening of Bridge)
Physical Target:
CW-1 Widening of Bridge : 137.25 sq.m .
Unit Cost:
CW-1 Widening of Bridge : P327.86T/sq.m .
Allocation: P45.00M

As MODIFIED:
MFO-1 National Road Network Services: Construction and Maintenance of Bridges along National Roads - Widening of Permanent Bridges to more than 2 Lanes, including ROW,
Widening of Bridge - Sinibaan Br. (B00001CN) along Catanduanes Cir Rd (Widening of Bridge) (ROW Acquisition)
Physical Target:
CW-1 Widening of Bridge : 135.00 sq.m.
ROW Acquisition: 1,170.85 sq.m.
Unit Cost:
CW-1 Widening of Bridge : P255.46T/sq.m.
ROW Acquisition: P8.97T/sq.m.
Estimated Cost: P45.00M
July 25, 2017 2017 WIN7F04872 FY 2017 GAA RA 10924 December 29, 2016 Region V Catanduanes District Engineering Office
As per GAA:
MFO-1 National Road Network Services: Network Development - Off-Carriageway Improvement including drainage — Secondary: Off-carriageway Improvement: Shoulder Paving / Construction Catanduanes Cir Rd - K0181+000-K0182+000,
K0191+000-K0193+000
(Off-Carriageway Improvement: Shoulder Paving / Construction)
Physical Target: 17,982 sq.m.
Unit Cost: P1.67T/sq.m.
Allocation: P30M


As MODIFIED:
MFO-1 National Road Network Services: Network Development - Off-Carriageway Improvement including drainage — Secondary: Off-carriageway Improvement: Shoulder Paving / Construction Catanduanes Cir Rd - K0181+000-K0182+000,
K0191+000-K0193+000, K0193+000-K0193+607
(Off-Carriageway Improvement: Shoulder Paving / Construction)
Physical Target: 10,588.45 sq.m.
Unit Cost: P2.83T/sq.m.
Estimated Cost: P30M
July 24, 2017 CY 2017 WIN7F05038 GAA CY 2017 RA 10924 December 29, 2016 Region IV-B Southern Mindoro Engineering District Office
as MODIFIED:
MF03 - Construction and maintenance Services of
Other Infrastructure
- Construction/Improvement of Access Road
Leading to Seaports:
- Construction of By-Pass Road
Campaasan to Kabangkalan Roro Port Road
Bulalacao, Oriental Mindoro

Road Widening:
CW1 = 3.172 lane km

Construction of Road with Drainage Structure
CW2 = 2,820 lm

Php CW1 = Php 27.209 Million
Php CW2 = Php 22.290 Million
Total = Php 45.500 Million
July 21, 2017 2017 WIN7F05044 FY 2017 GAA January 1, 2017 Region III Bulacan 2nd District Engineering Office
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems - Construction of Flood Control Structures along Maasim River, San Rafael, Bulacan
July 21, 2017 2017 WIN7E01300 FY 2017 GAA January 1, 2017 Region III Bulacan 2nd District Engineering Office
Local Infrastructure Program - Buildings and Other Structures - Multipurpose/Facilities - Construction/Improvement of Multi-Purpose Building, San Jose Del Monte City, Bulacan
July 21, 2017 2017 WIN7E01201 FY 2017 GAA January 1, 2017 Region III Bulacan 2nd District Engineering Office
Local Infrastructure Program - Flood Control and Drainage - Flood Control Structures/Facilities - Slope Protection along Sta. Maria river, Bagbaguin, Sta. Maria, Bulacan
July 21, 2017 2017 WIN7F04632 FY 2017 GAA January 1, 2017 Region III Bulacan 2nd District Engineering Office
Local Infrastructure Program - Buildings and Other Structures - Multipurpose/Facilities - Construction of Multi-Purpose Building, Brgy. Loma de Gato, Marilao, Bulacan
July 21, 2017 2017 WIN7E01229 FY 2017 GAA January 1, 2017 Region III Bulacan 2nd District Engineering Office
Local Infrastructure Program - Buildings and Other Structures - Multipurpose/Facilities - Improvement/Rehabilitation of Minuyan Sports Complex, Sapang Palay, City of San Jose Del Monte, Bulacan
July 21, 2017 2017 WIN7E01230 FY 2017 GAA January 1, 2017 Region III Bulacan 2nd District Engineering Office
Local Infrastructure Program - Roads and Bridges - Local Roads – Construction of Tukod - Casalat Bridge, San Rafael & San Ildefonso, Bulacan
July 21, 2017 2017 WIN7E01232 FY 2017 GAA January 1, 2017 Region III Bulacan 2nd District Engineering Office
Local Infrastructure Program - Buildings and Other Structures - Multipurpose/Facilities - Construction of Multi-Purpose Building, Brgy. Malhacan, Meycauayan City, Bulacan
July 20, 2017 2017 WIN7F04750 FY 2017 GAA RA 10924 December 29, 2016 Region V Catanduanes District Engineering Office
As per GAA:
MFO-I National Road Network Services: Asset Preservation of National Roads - Rehabilitation/ Reconstruction / Upgrading of Damaged Paved National Roads including drainage based on Pavement Management System/ Highway Development Management-4 (HDM4) Secondary: Reconstruction from Concrete to Concrete Catanduanes Cir Rd - K0046+376 - K0046+450, K0051+121 - K0051+280 (Rehabilitation of Concrete Road)
Physical Target: 0.466 lane-km
Unit Cost (P'000): P6,437.77/Lane-km
Allocation: P3.0M

As MODIFIED:
MFO-I National Road Network Services: Asset Preservation of National Roads - Rehabilitation/ Reconstruction / Upgrading of Damaged Paved National Roads including drainage based on Pavement Management System/ Highway Development Management-4 (HDM4) Secondary: Reconstruction from Concrete to Concrete Catanduanes Cir Rd - K0052+263.60-K0052+416.60 (Rehabilitation of Concrete Road)
Physical Target: 0.306 lane-km
Unit Cost (P'000): P9,803.92/Lane-km
Estimated Cost: P3.0M
July 20, 2017 2017 WIN7F04743 FY 2017 GAA RA 10924 December 29, 2016 Region V Catanduanes District Engineering Office
As per GAA:
MFO-I National Road Network Services: Asset Preservation of National Roads - Rehabilitation/ Reconstruction / Upgrading of Damaged Paved National Roads including drainage based on Pavement Management System/ Highway Development Management-4 (HDM4) Secondary: Reconstruction from Concrete to Concrete - Baras-Gigmoto-Viga Rd - K0046+000 - K0046+066, K0046+084 - K0046+450,
K0051+121 - K0052+058, K0053+128 - K0053+166
(Reconstruction from Concrete to Concrete)
Physical Target: 2.768 lane-km
Unit Cost (P'000): P14,966.76/Lane-km
Allocation: P41.428M

As MODIFIED:
MFO-I National Road Network Services: Asset Preservation of National Roads - Rehabilitation/ Reconstruction / Upgrading of Damaged Paved National Roads including drainage based on Pavement Management System/ Highway Development Management-4 (HDM4) Secondary: Reconstruction from Concrete to Concrete - Baras-Gigmoto-Viga Rd - K0046+000 - K0046+066, K0046+084 - K0046+450, K0051+121 - K0052+058, K0053+128 - K0053+166, K0037+560-K0037+727, K0038+150-K0038+600
(Rehabilitation of Concrete Road)
Physical Target: 3.589 lane-km
Unit Cost (P'000): P11,543.05/Lane-km
Estimated Cost: P41.428M
July 18, 2017 GAA FY 2017 WIN7F05055 UACS No. 165004050306265 January 1, 2017 National Capital Region NCR - Regional Office
As per GAA
Locally Funded Projects – VIILP – Roads and Bridges – Local Roads: Construction of Bantayan Extension Road, Taguig City – (Construction of Concrete Road)
UACS No. 165004050306265
Physical Target/ Cost
Original: 4.12 lane-km
Unit Cost: P23.79M/lane-km
Allocation Cost: P98.0M
WIN7F05055

As Modified
Locally Funded Projects – VIILP – Roads and Bridges – Local Roads: Rehabilitation of Cayetano Blvd. and Roads leading to Laguna Lake Highway Taguig City – (Construction of Concrete Road)
UACS No. 165004050306265
Physical Target/ Cost
Modified: 3.263 lane-km
Unit Cost: P30.03M/lane-km
Estimated Cost: P98.0M
WIN7F05055
July 18, 2017 GAA FY 2017 WIN7F05052 UACS No. 292003020401743 January 1, 2017 National Capital Region Metro Manila 1st District Engineering Office
As per GAA
MFO-2 Flood Management System: Construction/ Maintenance of Flood Mitigation Structures and Drainage System: Construction of Drainage Structures – Construction of Shoe Avenue Drainage Outfall Via Aquilina & Exequiel Sts., Brgy. Sto. Niño, Marikina City
UACS No. 292003020401743
Physical Target/ Cost
Per GAA/ Original
Physical Target/ Original: Physical Target 1,072 lm
Unit Cost: P18.65T/lm
Allocation: P20M
WIN7F05052

As Modified
MFO-2 Flood Management System: Construction/ Maintenance of Flood Mitigation Structures and Drainage System: Construction of Box Culvert along Balanti Creek, Brgy. Sta. Elena, Marikina City
UACS No. 292003020401743
Physical Target/ Cost
Per GAA/ Original
Physical Target/ Original: Physical Target 102 lm
Unit Cost: P196.07T/lm
Allocation: P20M
WIN7F05052
July 18, 2017 GAA FY 2017 WIN7F05052 UACS No. 292003020401743 January 1, 2017 National Capital Region Metro Manila 1st District Engineering Office
As per GAA
MFO-2 Flood Management System: Construction/ Maintenance of Flood Mitigation Structures and Drainage System: Construction of Drainage Structures – Construction of Shoe Avenue Drainage Outfall Via Aquilina & Exequiel Sts., Brgy. Sto. Niño, Marikina City
UACS No. 292003020401743
Physical Target/ Cost
Per GAA/ Original
Physical Target/ Original: Physical Target 1,072 lm
Unit Cost: P18.65T/lm
Allocation: P20M
WIN7F05052

As Modified
MFO-2 Flood Management System: Construction/ Maintenance of Flood Mitigation Structures and Drainage System: Construction of Box Culvert along Balanti Creek, Brgy. Sta. Elena, Marikina City (Phase II)
UACS No. 292003020401743
Physical Target/ Cost
Per GAA/ Original
Physical Target/ Original: Physical Target 102 lm
Unit Cost: P196.07T/lm
Allocation: P20M
WIN7F05052
July 18, 2017 GAA FY 2017 WIN7F05049 UACS No. 103004010310122 January 1, 2017 National Capital Region Metro Manila 1st District Engineering Office
As per GAA
Locally Funded Projects: Local Infrastructure Program – Buildings and Other Structures – Multipurpose/ Facilities, Construction of Multi-Purpose Building, Brgy. Parang, Marikina City (Construction of Multi-Purpose Building)
UACS No. 103004010310122
Physical Target/ Cost
Per GAA/ Original: 1 Bldg.
Unit Cost: P3M/Bldg.
Allocation: Php3M
WIN7F05049

As Modified
Locally Funded Projects: Local Infrastructure Program – Buildings and Other Structures – Multipurpose/ Facilities, Construction of Multi-Purpose Building, Brgy. Marikina Heights, Marikina City (Phase I) (Construction of Multi-Purpose Building)
UACS No. 103004010310122
Physical Target/ Cost
As Modified: 1 Bldg.
Unit Cost: P3M/Bldg.
Estimated Cost: Php3M
WIN7F05049
July 18, 2017 GAA FY 2017 WIN7F05051 UACS No. 103004010310120 January 1, 2017 National Capital Region Metro Manila 1st District Engineering Office
As per GAA
Locally Funded Projects: Local Infrastructure Program – Buildings and Other Structures – Multipurpose/ Facilities, Construction of Multi-Purpose Building, Brgy. Fortune, Marikina City (Construction of Multi-Purpose Building)
UACS No. 103004010310120
Physical Target/ Cost
Per GAA/ Original: 1 Bldg.
Unit Cost: P3M/Bldg.
Allocation: Php3M
WIN7F05051

As Modified
Locally Funded Projects: Local Infrastructure Program – Buildings and Other Structures – Multipurpose/ Facilities, Construction/Completion of Multi-Purpose Building, Brgy. Marikina Heights, Marikina City (Phase II) (Construction of Multi-Purpose Building)
UACS No. 103004010310120
Physical Target/ Cost
As Modified: 1 Bldg.
Unit Cost: P3M/Bldg.
Estimated Cost: Php3M
WIN7F05051
July 18, 2017 GAA FY 2017 WIN7F05056 UACS No. 292003020401721 January 1, 2017 National Capital Region Metro Manila 1st District Engineering Office
As Per GAA
MFO-2 Flood Management Services: Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems: Construction of Flood Mitigation Structure – Construction of Box Culvert along Tañong Creek, Brgy. Tañong, Marikina City (Construction of Flood Mitigation Structure)
UACS No. 292003020401721
Physical Target/ Cost
Per GAA/ Original: Physical Target 150 lm
Unit Cost: P66.66T/lm
Allocation: P10M
WIN7F05056

As Modified
MFO-2 Flood Management Services: Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems: Construction of Flood Mitigation Structure – Construction of Box Culvert/Rehabilitation of Tañong Creek, Marikina City (Construction of Drainage Structure)
UACS No. 292003020401721
Physical Target/ Cost
As Modified: Physical Target 110 lm
Unit Cost: P90.90T/lm
Estimated Cost: P10M
WIN7F05056
July 18, 2017 GAA FY 2017 WIN7F05056 UACS No. 292003020401721 January 1, 2017 National Capital Region Metro Manila 1st District Engineering Office
As Per GAA
MFO-2 Flood Management Services: Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems: Construction of Flood Mitigation Structure – Construction of Box Culvert along Tañong Creek, Brgy. Tañong, Marikina City (Construction of Flood Mitigation Structure)
UACS No. 292003020401721
Physical Target/ Cost
Per GAA/ Original: Physical Target 150 lm
Unit Cost: P66.66T/lm
Allocation: P10M
WIN7F05056

As Modified
MFO-2 Flood Management Services: Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems: Construction of Flood Mitigation Structure – Construction of Box Culvert/Rehabilitation of Tañong Creek, Marikina City (Construction of Drainage Structure)
UACS No. 292003020401721
Physical Target/ Cost
As Modified: Physical Target 110 lm
Unit Cost: P90.90T/lm
Estimated Cost: P10M
WIN7F05056
July 18, 2017 GAA FY 2017 WIN7F05054 UACS No. 292003020401767 January 1, 2017 National Capital Region Metro Manila 1st District Engineering Office
As Per GAA
MFO – 2 Flood Management Services: Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems: Construction of Drainage Structure – Rehabilitation of Drainage System along J.P. Rizal St. Including Laterals, Brgy. Malanday, Marikina City (Construction of Drainage Structure)
UACS No. 292003020401767
Physical Target/ Cost
Per GAA/ Original: Physical Target 1,679 lm
Unit Cost: P8.93T/lm
Allocation: P15m
WIN7F05054

As Modified
MFO – 2 Flood Management Services: Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems: Construction of Box Culvert along Balanti Creek, Brgy. Sta. Elena, Marikina City (Phase IV) (Construction of Drainage Structure)
UACS No. 292003020401767
Physical Target/ Cost
Per GAA/ Original: Physical Target 1,679 lm
Unit Cost: P8.93T/lm
Allocation: P15m
WIN7F05054
July 18, 2017 GAA FY 2017 WIN7F05059 UACS No. 292003020401742 January 1, 2017 National Capital Region Metro Manila 1st District Engineering Office
Per GAA
MFO-2 Flood Management Services: Construction/ Maintenance of Flood Mitigation Structures and Drainage System: Construction of Drainage Structure – Construction of Shoe Avenue Drainage Outfall Via Guerilla St., Marikina City (Construction of Drainage Structure)
UACS No. 292003020401742
Physical Target/ Cost
Per GAA/ Original: Physical Target 620 lm
Unit Cost: P32.25T/lm
Allocation: P20M
WIN7F05059

As Modified
MFO-2 Flood Management Services: Construction/ Maintenance of Flood Mitigation Structures and Drainage System: Construction of Box Culvert along Balanti Creek, Brgy. Sta. Elena, Marikina City (Phase I) (Construction of Drainage Structure)
UACS No. 292003020401742
Physical Target/ Cost
Per GAA/ Original: Physical Target 102 lm
Unit Cost: P196.07T/lm
Estimated Cost: P20M
WIN7F05059
July 18, 2017 GAA FY 2017 WINF05053 UACS No. 292003020401731 January 1, 2017 National Capital Region Metro Manila 1st District Engineering Office
Per GAA
MFO-2 Flood Management Services: Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems: Construction of Drainage Structure – Construction of Marikina River Drainage Outfall including Laterals, Brgy. Sto. Niño, Marikina City (Construction of Drainage Structure)
UACS No. 292003020401731
Physical Target/ Cost
Per GAA/ Original: Physical Target 920 lm
Unit Cos: P16.30T/lm
Allocation: P15M
WINF05053

As Modified
MFO-2 Flood Management Services: Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems: Construction of Box Culvert along Balanti Creek, Brgy. Sta. Elena, Marikina City (Phase III) (Construction of Drainage Structure)
UACS No. 292003020401731
Physical Target/ Cost
Per GAA/ Original: Physical Target 76.50 lm
Unit Cos: P196.078T/lm
Estimated Cost: P15M
WINF05053
July 18, 2017 2017 WIN7F05026 FY 2017 GAA January 1, 2017 Region III Bataan 2nd District Engineering Office
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems - Construction of Flood Control Structure with channel excavation of Abo-abo River Manimas Dam Section, Balanga City
July 17, 2017 2017 WIN7C01994 R.A 10924 January 12, 2017 Region VII Cebu City District Engineering Office
Locally-Funded Projects

LIP-Buildings and Other Structures - Multipurpose/Facilities

Construction of Multi-Purpose Building (Covered Court), Carreta Elementary School Building, Brgy. Carreta, Cebu City

Allocation - ₱ 2 Million
Physical Target - 1 building
Unit Cost - ₱ 2 Million / building
July 17, 2017 2017 WIN7C01991 R.A 10924 January 12, 2017 Region VII Cebu City District Engineering Office
Locally-Funded Projects

LIP - Buildings and Other Structures - Multipurpose/Facilities

Construction of Multi-Purpose Building, Brgy. Cogon Ramos, Cebu City

Allocation - ₱ 2 Million
Physical Target - 1 building
Unit Cost - ₱ 2 Million / Building
July 17, 2017 2017 165003015200148 GAA FY 2017 January 1, 2017 Region II Cagayan 1st District Engineering Office
Network Development - Improvement / Widening of National Roads - Tertiary: Road Widening - Manila North Rd (Jct Bangag-Paruddun Sect) (S00637LZ) K0690+000 - K0692+909.40
July 17, 2017 2017 165003014100083 GAA FY 2017 January 1, 2017 Region II Cagayan 1st District Engineering Office
Asset Preservation of National Roads - Rehabilitation / Reconstruction/ Upgrading of Damaged Paved National Roads including drainage based on Pavement Management System/ Highway Development Management - 4 (HDM-4) - Primary: Reconstruction from Concrete to Concrete with Paving of Shoulders - Reblocking with Paving of Shoulders Cagayan Valley Road - K0517+100 - K0517+267 (BS), K0517+339 - K0517+383 (BS), K0517+396 - K0517+410 (BS), K0517+518 - K0517+560 (BS), K0518+022 - K0518+100 (BS), K0518+140 - K0518+172 (BS), K0518+400 - K0518+414 (LS), K0518+450 - K0518+504 (LS), K0518+581 - K0518+657 (RS), K0518+657 - K0518+719 (BS), K0526+945 - K0527+049 (BS), K0527+160 - K0527+174 (LS), K0527+174 - K0527+222 (BS), K0527+244 - K0527+302 (LS), K0527+302 - K0527+320 (BS), K0527+360 - K0527+401 (BS), K0527+420 - K0527+558 (BS), K0527+600 - K0527+622 (BS), K0527+680 - K0527+691 (RS), K0527+695 - K0527+699 (LS), K0527+722 - K0527+756 (LS), K0527+756 - K0527+802 (BS), K0527+816 - K0527+834 (BS). K0527+847 - K0527+896 (BS), K0528+003 - K0528+010 (BS), K0528+108 - K0528+117 (LS), K0528+147 - K0528+202 (BS), K0528+231 - K0528+252 (BS), K0528+275 - K0528+284 (BS), K0528+348 - K0528+380 (BS), K0528+389 - K0528+426 (RS), K0528+426 - K0528+555 (BS), K0528+650 - K0528+656 (LS), K0528+672 - K0528+675 (LS), K0528+724 - K0528+728 (RS), K0528+737 - K0528+777 (LS), K0528+785 - K0528+794 (RS), K0528+835 - K0528+858 (LS), K0529+181 - K0529+186 (LS), K0529+236 - K0529+240 (BS), K0529+293 - K0529+315 (BS), K0529+376 - K0529+417 (BS), K0529+429 - K0529+446 (LS), K0529+555 - K0529+600 (BS); Paving of Shoulders - K0517+267 - K0517+339 (BS), K0517+383 - K0517+396 (BS), K0517+410 - K0517+518 (BS), K0517+560 - K0518+022 (BS), K0518+100 - K0518+140 (BS), K0518+172 - K0518+400 (BS), K0518+414 - K0518+450 (LS), K0518+400 - K0518+500 (RS)
July 17, 2017 2017 165003030800304 GAA FY 2017 January 1, 2017 Region II Cagayan 1st District Engineering Office
Construction/Improvement of Access Roads Leading to Airports, Seaports, and Declared Tourism Destinations - to Declared Tourism Destinations: Construction of Concrete Road, Construction of Concrete Bridge and ROW Acquisition - Poblacion Sta. Ana - Marede - Sta. Clara - Patunungan - Sinago Road leading to Boacag Falls & Sinago Coves, including Bridge and ROW
July 17, 2017 2017 165003016700014 GAA FY 2017 January 1, 2017 Region II Cagayan 1st District Engineering Office
Network Development - Off-carriageway Improvement including drainage - Primary: Off-carriageway Improvement: Shoulder Paving/ Construction - Cagayan Valley Road (S00887LZ)
July 17, 2017 2017 165003014800116 GAA FY 2017 January 1, 2017 Region II Cagayan 1st District Engineering Office
Asset Preservation of National Roads - Construction/ Upgrading/ Rehabilitation of Drainage along National Roads - Secondary: Construction of Drainage along Road - Cagayan Valley Rd (Magapit - Jct Aparri Airport Sect) K0568+980 - K0570+203 (R/S), K0576+268.70 - K0577+368.70 (L/S), K0580+427.30 - K0580+439.23 (L/S), K0580+439.23 - K0580+920.50 (B/S), K0580+920.5 - K0580+991.45 (R/S), K0580+991.45 - K0581+233.30 (B/S), K0581+233.30 - K0581+409.30 (R/S), K0581+409.30 - K0581+460.49 (B/S), K0581+460.49 - K0581+743.90 (L/S)
July 14, 2017 2017 NO BAR CODE FY 2017 GAA RA 10924 December 29, 2016 Region V Sorsogon 2nd District Engineering Office
As per GAA:
Locally-Funded Projects - Flood Control and Drainage - Flood Control Structures/Facilities Repair/Rehab of Flood Control Structure along Cadac-an River, Carriedo, Irosin, Sorsogon
[Rehabilitation/Major Repair of Flood Control Structure]
Allocation (P'000): P20,000.00

As Modified:
Locally-Funded Projects - Flood Control and Drainage - Flood Control Structures/Facilities - Repair/Rehab of Flood Control Structure along Cadac-an River, Bacolod/San Agustin, Irosin, Sorsogon (Upstream, Left Side)
Sta. 0+936.10 - Sta. 0+968.90,
Sta. 0+968.90 - Sta. 0+997, Sta. 1+096 - Sta. 1+358 [Rehabilitation/Major Repair of
Flood Control Structure]
Physical Target: 322.90 lm
Unit Cost (P'000): P61.94/lm
Estimated Cost (P'000): P20,000.00
July 14, 2017 2017 WIN7E01571 FY 2017 GAA RA 10924 December 29, 2016 Region V Sorsogon 2nd District Engineering Office
As per GAA:
MFO 1 - National Road Network Services - Asset Preservation of National Roads - Rehabilitation/ Reconstruction of National Roads With Slips, Slope Collapse, and Landslide - Tertiary - Jct. Abuyog - Gubat - Ariman Road - K0593+610 - K0593+700
[Construction of Road Slope Protection Structure]
Physical Target: 200 sq.m.
Unit Cost (P'000): P50.00/sq.m.
Allocation (P'000): P10,000.00

As MODIFIED:
MFO 1 - National Road Network Services - Asset Preservation of National Roads - Rehabilitation/ Reconstruction of National Roads With Slips, Slope Collapse, and Landslide - Tertiary -Jct. Abuyog - Gubat - Ariman Road - K0593+524 - K0593+720
[Construction of Road Slope Protection Structure]
Physical Target: 619.68 sq.m.
Unit Cost (P'000): P16.14/sq.m.
Allocation (P'000): P10,000.00
July 14, 2017 2017 WIN7E01565 FY 2017 GAA January 1, 2017 Region III Pampanga 1st District Engineering Office
Asset Preservation of National Roads - Rehabilitation / Reconstruction / Upgrading of Damaged Paved National Roads including Drainage based on Pavement Management System / Highway Development Management - 4 (HDM-4) – Tertiary - Candaba - San Miguel Rd., K0082+726.50 - K0082+962.50
July 14, 2017 2017 WIN7E01585 FY 2017 GAA RA 10924 December 29, 2016 Region V Sorsogon 2nd District Engineering Office
As per GAA:
MFO 2 - Flood Management Services - Construction/Maintenance of Flood Mitigation
Structures and Drainage Systems - Construction of Flood Control Structure - Rangas River, Downstream, Both Side,
Sta. 0+191 - Sta. 0+440, Juban, Sorsogon
[Construction of Flood Mitigation Structure]
Physical Target: 498 lm.
Unit Cost (P'000): P100.40/lm.
Allocation (P'000): P50,000.00

As MODIFIED:
MFO 2 - Flood Management Services - Construction/Maintenance of Flood Mitigation
Structures and Drainage Systems - Construction of Flood Control Structure - Rangas River, Downstream, Both Side,
Sta. 0+220 - Sta. 0+460, Juban, Sorsogon
[Construction of Flood Mitigation Structure]
Physical Target: 480 lm.
Unit Cost (P'000): P104.17/lm.
Estimated Cost (P'000): P50,000.00
July 14, 2017 2017 WIN7F05045 FY 2017 GAA January 1, 2017 Region III Pampanga 1st District Engineering Office
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems - Rehabilitation / Improvement, San Antonio to Sapang Matulid River, Sta. 0+000 to Sta. 1+175, Mexico, Pampanga
July 14, 2017 2017 WIN7E01635 FY 2017 GAA RA 10924 December 29, 2016 Region V Sorsogon 2nd District Engineering Office
As per GAA:
MFO 2 - Flood Management Services - Construction/Maintenance of Flood Mitigation
Structures and Drainage Systems - Construction of Flood Control Structure along Cadac-an River, Right Side, Downstream Section, Brgy. Cariedo, Irosin, Sorsogon
[Construction of Flood Mitigation Structure]
Physical Target: 450 lm.
Unit Cost (P'000): P111.11/lm.
Allocation (P'000): P50,000.00

As MODIFIED:
MFO 2 - Flood Management Services - Construction/Maintenance of Flood Mitigation
Structures and Drainage Systems - Reconstruction of Flood Control Structure along Cadac-an River, Brgy. Cariedo, Irosin, Sorsogon (Upstream, Right Side)
Sta. 1+025.40 - Sta.1+170.60, Sta. 1+371.70 - Sta.1+578.70
[Construction of Flood Mitigation Structure]
Physical Target: 352.20 lm.
Unit Cost (P'000): P141.96/lm.
Estimated Cost (P'000): P50,000.00
July 14, 2017 2017 WIN7E01210 FY 2017 GAA RA 10924 December 29, 2016 Region V Sorsogon 2nd District Engineering Office
As per GAA:
MFO 2 - Flood Management Services - Construction/Maintenance of Flood Mitigation
Structures and Drainage Systems - Construction of Flood Control Structure along Cadac-an River, Barangay Cariedo, Irosin, Sorsogon
[Construction of Flood Mitigation Structure]
Physical Target: 250 sq.m.
Unit Cost (P'000): P200.00/sq.m.
Allocation (P'000): P50,000.00

As MODIFIED:
MFO 2 - Flood Management Services - Construction/Maintenance of Flood Mitigation
Structures and Drainage Systems - Reconstruction of Flood Control Structure along Cadac-an River, Barangay Cariedo, Irosin, Sorsogon (Upstream, Right Side)
Sta. 1+578.70- Sta.1+932.70 [Reconstruction of Flood Mitigation Structure]
Physical Target: 354.00 sq.m.
Unit Cost (P'000): P141.24/sq.m.
Estimated Cost (P'000): P50,000.00
July 14, 2017 2017 WIN7E01570 FY 2017 GAA RA 10924 December 29, 2016 Region V Sorsogon 2nd District Engineering Office
As per GAA:
MFO 2 - Flood Management Services - Construction/Maintenance of Flood Mitigation Structures and Drainage Systems - Construction of Flood
Mitigation Structure - Rehabilitation of Flood Control Structures, Downstream, Right Side (Sta. 0+364 - Sta. 0+532), Left Side (Sta. 0+401 - Sta. 0+533), Barangay San Vicente, Bulan, Sorsogon
[Construction of Flood Mitigation Structure]
Physical Target: 300 l.m.
Unit Cost (P'000): P150.00/sq.m.
Allocation (P'000): P45,000.00

As MODIFIED:
MFO 2 - Flood Management Services - Construction/Maintenance of Flood Mitigation Structures and Drainage Systems - Construction of Flood Mitigation Structure - Rehabilitation of Flood Control Structures along Sabang River, Barangay San Vicente, Bulan, Sorsogon,[Construction of Flood Mitigation Structure]
Physical Target: 489 l.m.
Unit Cost (P'000): P92.0/l.m.
Estimated Cost (P'000): P45,000.00
July 14, 2017 2017 WIN7F05005 FY 2017 GAA January 1, 2017 Region III Pampanga 2nd District Engineering Office
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems - Rehabilitation / Widening / Deepening with slope Protection along Remedios River, Sasmuan, Pampanga, Sta. 0+000 to sta. 0+295.58
July 14, 2017 2017 WIN7F05012 SR2017-01-000376 January 28, 2017 Region V Regional Office V
As per GAA:
MFO 1 — National Road Network Services - Construction and Maintenance of Bridges along National Roads - Construction of New Permanent Bridges: Construction of Concrete Bridge - Asgad Br. along Catanduanes Circumferential Rd (Construction of Concrete Bridge)
Physical Target: 366 sq.m.
Unit Cost: P109.29T/sq.m.
Allocation Cost: P40.00M

As Modified:
MFO 1 — National Road Network Services - Construction and Maintenance of Bridges along National Roads - Construction of New Permanent Bridges Construction of Concrete Bridge - Asgad Br. along Catanduanes Circumferential Rd (Construction of Concrete Bridge)
Physical Target: 578.12 sq.m.
Unit Cost: P69.19T/sq.m.
Estimated Cost: P40.00M

July 14, 2017 2017 WIN7F05034 SR2017-01-000388 January 28, 2017 Region V Regional Office V
As per GAA:
MFO 1 — National Road Network Services - Construction and Maintenance of Bridges along National Roads - Construction of New Permanent Bridges : Construction of Concrete Bridge - Cabungahan Br. along
Catanduanes Circumferential Rd
(Construction of Concrete Bridge)
Physical Target: 247.05 sq.m.
Unit Cost: P138.88T/sq.m.
Allocation Cost: P34.31M

As MODIFIED:
MFO 1 — National Road Network Services - Construction and Maintenance of Bridges along National Roads - Construction of New Permanent Bridges : Construction of Concrete Bridge - Cabungahan Br. along
Catanduanes Circumferential Rd
(Construction of Concrete Bridge)
Physical Target: 420.624 sq.m.
Unit Cost: P81.57T/sq.m.
Estimated Cost: P34.31M
July 13, 2017 2017 WIN7F04967 FY 2017 GAA January 1, 2017 Region III Nueva Ecija 1st District Engineering Office
Asset Preservation of National Roads - Rehabilitation / Reconstruction / Upgrading of Damaged Paved National Roads including Drainage based on Pavement Management System / Highway Development Management - 4 (HDM-4) – Primary - San Jose - Lupao Rd, K0168+000 - K0169+336, K0170+000 - K0170+615
July 12, 2017 FY 2017 WIN7F04948 UACS No. 165004050306778 January 1, 2017 National Capital Region Metro Manila 1st District Engineering Office
As per GAA
Locally Funded Projects – LIP, Road and Bridges – Local Roads: Construction/ Improvement of Drainage at Brgy. Nangka Twinville Subdivision Area, Marikina City
UACS No. 165004050306778
Physical Target/ Cost
Original: -
Unit Cost (P’000): -
Allocation Cost (P’000): P10,000
WIN7F04948

As Modified
Locally Funded Projects – LIP, Road and Bridges – Local Roads: Construction/ Rehabilitation of Road Network including Drainage System at Brgy. Tumana, Marikina City
UACS No. 165004050306778
Physical Target/ Cost
Modified: 2,105 lineal meter
Unit Cost (P’000): P4.751T/lineal meter
Estimated Cost (P’000): P10,000
WIN7F04948
July 12, 2017 FY 2017 WIN7F04922 UACS No. 292003020401755 January 1, 2017 National Capital Region Metro Manila 1st District Engineering Office
As per GAA
MFO-2 Flood Management Services: Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems: Construction of Flood Mitigation Structure – Improvement of Bangkaan Creek, Marikina City (Construction of Flood Mitigation Structure)
UACS No. 292003020401755
Physical Target/ Cost
Per GAA/ Original: Physical Target 937 lm
Unit Cost: P10.672T/lm
Allocation: P10M
WIN7F04922

As Modified
MFO-2 Flood Management Services: Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems: Improvement of Bangkaan Creek and Concepcion Creek, Marikina City (Construction of Flood Mitigation Structure)
UACS No. 292003020401755
Physical Target/ Cost
As Modified: Physical Target 962 lm
Unit Cost: P10.395T/lm
Estimated: P10M
WIN7F04922
July 12, 2017 FY 2017 WIN7F05007 UACS No. 103004010309907 January 1, 2016 National Capital Region Metro Manila 1st District Engineering Office
As per GAA
Locally Funded Projects: VIILP – Buildings and Other Structures – Multipurpose/Facilities, Construction of Multipurpose Building including Site Development. Brgy. Nangka, Marikina City (Construction of Multi-Purpose Building)
UACS No. 103004010309907
Physical Target/ Cost
Per GAA/ Original
CW-1 Const. of Multi Purpose Building: 1 Building
Unit Cost: CW-1 Const. of Multi Purpose Building: P15M/Bldg.
Allocation: Php15M
WIN7F05007

As Modified
Locally Funded Projects: VIILP – Buildings and Other Structures – Multipurpose/Facilities, Construction/Repair/Rehabilitation of Multipurpose Building including Site Development. Brgy. Concepcion Dos, Marikina City (Construction of Multi-Purpose Building) (Rehabilitation/Major Repair Multi Purpose Building)
UACS No. 103004010309907
Physical Target/ Cost
As Modified
CW-1 Const. of Multi Purpose Building: 2 Bldg.
CW-2 Rehab./Major Repair Multi Purpose Building: 1 Bldg.
Unit Cost: CW-1 Const. of Multi Purpose Building: P5.1M/Bldg.
CW-2 Rehab./Major Repair Multi Purpose Building: P4.8M/Bldg.
Estimated Cost: Php15M
WIN7F05007
July 12, 2017 FY 2017 WIN7F05040 UACS No. 292003020401739 January 1, 2017 National Capital Region Metro Manila 1st District Engineering Office
As per GAA
MFO-2 Flood Management Services: Construction/Maintenance of Flood Mitigation Structures and Drainage Systems, Construction of RCBC Drainage Outfall from Panorama to Lilac Bridge Approach (Balanti Creek), Brgy. Concepcion Dos, Marikina City (Construction of Drainage Structure)
UACS No. 292003020401739
Physical Target/ Cost
Per GAA/ Original: 260 Lm
Unit Cost: P192.307T/Lm
Allocation: Php 50M
WIN7F05040

As Modified
MFO-2 Flood Management Services: Construction/Maintenance of Flood Mitigation Structures and Drainage Systems, Construction of RCBC Drainage Outfall from Katipunan Street to Lilac Bridge Approach (Balanti Creek), Brgy. Concepcion Dos, Marikina City (Construction of Drainage Structure)
UACS No. 292003020401739
Physical Target/ Cost
As Modified: 698 Lm
Unit Cost: P71.633T/Lm
Estimated Cost: Php 50M
WIN7F05040

Pages