Modification and Realignment



Date Posted GAA Year Reference No SARO Number SARO Date Region Implementing Office Description
August 7, 2024 2024 GAA 2024 January 19, 2024 Region V Masbate 2nd District Engineering Office
Project ID : P00802553LZ
UACS No : 310106101181000

FROM :
OO1 - Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstructure/ Upgrading of Damaged Paved Roads - Tertiary Roads - Masbate Circumferential Rd - K0004 + 000 - K0004 + 175

Physical Target :
CW1 - Rehabilitation of Paved Road - 0.7 Lane Km


TO :
OO1 - Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstructure/ Upgrading of Damaged Paved Roads - Tertiary Roads - Masbate Circumferential Rd - K0004 + 444 - K0004 + 884

Physical Target :
CW1 - Rehabilitation of Paved Road - 0.88 Lane Km
CW2 - Road Safety - Street Lighting - 32 Number of Units
August 7, 2024 2024 WIN4XY00339 GAA 2024 January 19, 2024 Region V Catanduanes District Engineering Office
Project ID : P00824785LZ
UACS No : 320101112028000

FROM :
ORGANIZATIONAL OUTCOME 2 - Protect Lives and Properties Against Major Floods - Construction/ Maintenance of Flood Mitigation Structures and Drainage System - Construction of Flood Control Structure at Brgy. Benticayan, Baras, Catanduanes

Physical Target :
CW1 - Construction of Flood Mitigation Structure - 186 Lineal meters


TO :
ORGANIZATIONAL OUTCOME 2 - Protect Lives and Properties Against Major Floods - Construction/ Maintenance of Flood Mitigation Structures and Drainage System - Construction of Flood Control Structure at Brgy. Benticayan, Baras, Catanduanes

Physical Target :
CW1 - Construction of Flood Mitigation Structure - 149 Lineal meters
August 7, 2024 2024 WIN4XY00337 GAA 2024 January 19, 2024 Region V Regional Office V
Project ID : P00839453LZ
UACS ID : 3000224100036000

FROM :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - BIP - Coastal Roads/ Causeway for environmental protection/ conservation - Construction of Coastal Road, Barangay Población, Rapu-Rapu, Albay

Physical Target :
CW1 - Construction of Concrete Road - 1.968 Lane Km
CW2 - Construction of Road Slope Protection - 2,601.40


TO :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - BIP - Coastal Roads/ Causeway for environmental protection/ conservation - Construction of Coastal Road, Barangay Población, Rapu-Rapu, Albay

Physical Target :
CW1 - Construction of Concrete Road - 1.38 Lane Km
CW2 - Construction of Road Slope Protection - 2,033.20 Square meters
August 7, 2024 2024 WIN4XY00338 WIN4XY00338 January 19, 2024 Region V Camarines Norte Sub-District Engineering Office
Project ID : P00848239LZ
UACS No : 300226113504000

FROM :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - BIP - Multi-Purpose Buildings/ Facilities to support Social Services - Construction of Multipurpose Buildings, Brgy. Mambungalon, Basud, Camarines Norte

Physical Target :
CW1 - Construction of Multi Purpose Building - 1 Number of Buildings


TO :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - BIP - Multi-Purpose Buildings/ Facilities to support Social Services - Construction of Multipurpose Buildings, Brgy. Mambungalon, Mercedes, Camarines Norte

Physical Target :
CW1 - Construction of Multi Purpose Building - 1 Number of Buildings
August 7, 2024 2024 SR2024-01-008076 January 31, 2024 Region VIII Regional Office VIII
OO1: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Primary Roads

AS PER GAA/ORIGINAL:

Daang Maharlika (LT) – K0906 + 569 – K0906 + 915

Physical Target: Allocation:
CW1- Preventive Maintenance of Road: P 14.94206 M
Asphalt Overlay: 1.384 Lane Km

EAO P 0.54194 M

Total P 15.484 M

AS MODIFIED:

Daang Maharlika (LT) – K0906 + 520 – K0906 + 915

Physical Target: Allocation:

CW1- Preventive Maintenance of Road: P 14.94206 M
Asphalt Overlay: 1.58 Lane Km

EAO P 0.54194 M

Total P 15.484 M
August 7, 2024 2024 SR2024-04-014756 April 12, 2024 Region VIII Regional Office VIII
Convergence and Special Support Program

Special Road Fund – Motor Vehicle Users Charge (MVUC) as per R.A. 11239

AS PER GAA/ORIGINAL:

Installation of Solar LED Street Lights, and Signages along Tacloban City Bypass Road Extension, Phase 1, Barangay Tigbao, Tacloban City

Physical Target: Allocation:

CW1- Road Safety: P 46.575435 M
Road Lighting: 268.00 Number of Units

CW2- Road Safety:
Guardrails: 1,760.00 Lineal Meters P 49.924565 M

EAO P 3.5 M

Total P 100.00 M

AS MODIFIED:

Installation of Solar LED Street Lights, and Signages along Tacloban City Bypass Road Extension, Phase 1, Barangay Tigbao, Tacloban City

Physical Target: Allocation:

CW1- Road Safety: P 73.16921039 M
Road Lighting: 442.00 Number of Units

CW2- Road Safety:
Guardrails: 3,100.00 Lineal Meters P 23.33078961 M

EAO P 3.5 M

Total P 100.00 M
August 7, 2024 2024 WIN4E03584 SR2024-01-003732 January 29, 2024 Cordillera Administrative Region Benguet 1st District Engineering Office
"From:
Installation of Road Safety Devices along Shilan-Beckel Road, K0261+(-392) - K0266+403, La Trinidad, Benguet;
Type of Work:
Road Safety: Pavement Markings;
Physical Target:
5514 Lineal Meter;
Allocation:
Php 125,000,000"

"To:
Installation of Road Safety Devices along Shilan-Beckel Road, K0261+(-392) - K0266+403, La Trinidad, Benguet;
Type of Work:
Road Safety: Roadway Lighting;
Physical Target:
535 Number of units;
Allocation:
Php 125,000,000"
August 7, 2024 2024 WIN4E03507 GAA 2024 January 1, 2024 Cordillera Administrative Region CAR - Regional Office
"From:
Construction of Bultot, Balawag Flood Control along Chico River Balawag, Tabuk City, Kalinga;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
802 Lineal meters;
Allocation:
Php 100,000,000"

"To:
Construction of Bultot, Balawag Flood Control along Chico River Balawag, Tabuk City, Kalinga;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
386 Lineal meters;
Allocation:
Php 100,000,000"
August 7, 2024 2024 WIN4E03515 GAA 2024 January 1, 2024 Cordillera Administrative Region CAR - Regional Office
"From:
Construction of Apayao-Abulog River Basin River Flood Control Structure (Bagutong Section), Apayao Sta 28 + 310 - Sta 31 + 250 (R/S);
Type of Work:
Construction of Revetment;
Physical Target:
518 Lineal meters;
Allocation:
Php 50,000,000"

"To:
Construction of Apayao-Abulog River Basin River Flood Control Structure (Bagutong Section), Apayao Sta. 29 + 760 - Sta 30 + 110 (R/S);
Type of Work:
Construction of Revetment;
Physical Target:
218 Lineal meters;
Allocation:
Php 50,000,000"
August 7, 2024 2024 GAA FY 2024 January 1, 2024 Region VIII Leyte 1st District Engineering Office
Convergence and Special Support Program

SIPAG - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities

AS PER GAA/ORIGINAL:

Construction of Road, Barangay Binolo, Tanauan Leyte

Physical Target: Allocation:

CW1- Construction of Concrete Road: P 12.250 M
0.246 Lane Km

EAO P .250 M

Total P 12.50 M

AS MODIFIED:

Construction of Road, Barangay Binolo, Tanauan Leyte

Physical Target: Allocation:

CW1- Construction of Concrete Road: P 12.250 M
1.20 Lane Km

EAO P .250 M

Total P 12.250 M
August 7, 2024 2024 GAA FY 2024 January 1, 2024 Region VIII Leyte 1st District Engineering Office
Convergence and Special Support Program

SIPAG - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities

AS PER GAA/ORIGINAL:

Construction of Road, San Antonio to Camire, Tanauan Leyte

Physical Target: Allocation:

CW1- Construction of Concrete Road: P 12.250 M
0.246 Lane Km

EAO P .250 M

Total P 12.50 M

AS MODIFIED:

Construction of Road, San Antonio to Camire, Tanauan Leyte

Physical Target: Allocation:

CW1- Construction of Concrete Road: P 12.250 M
1.50 Lane Km

EAO P .250 M

Total P 12.250 M
August 7, 2024 2024 WIN4XY00325 GAA FY 2024 January 1, 2024 Region VIII Leyte 1st District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Network Development – Road Widening – Tertiary Roads

AS PER GAA/ORIGINAL:

Tacloban-Baybay South Rd (Tanauan Sect) - K0921 + (-108.87) - K0921 + 356.69, K0921 + (-697) - K0921 + (-132)

Physical Target: Allocation:

CW1- Road Widening: P 23.69248 M
2.061 Lane Km

EAO P 0.48352 M

Total P 24.176 M

AS MODIFIED:

Tacloban-Baybay South Rd (Tanauan Sect) - K0921 + (-697) - K0921 + (-132)

Physical Target: Allocation:

CW1- Road Widening: P 13.20771917 M
1.130 Lane Km

CW2 – Construction of Drainage Structure: P 10.48476082 M
Along Road: 174 Lineal Meters

EAO P 0.48352 M

Total P 24.176 M
August 6, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Benguet 2nd District Engineering Office
"From:
Baguio-Bontoc Rd - K0317 + 468 - K0317 + 566;
Type of Work:
Rehabilitation /Major Repair of Road Slope Protection Structure;
Physical Target:
392.17 Square meters;
Allocation:
Php 4,310,000"

"To:
Baguio-Bontoc Rd - K0322+860 - K0323+037;
Type of Work:
Construction of Road Slope Protection Structure;
Physical Target:
716 Square meters;
Allocation:
Php 4,310,000"
August 6, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Benguet 2nd District Engineering Office
"From:
Baguio-Bontoc Rd - K0317 + 468 - K0317 + 566;
Type of Work:
Rehabilitation /Major Repair of Road Slope Protection Structure;
Physical Target:
392.17 Square meters;
Allocation:
Php 4,310,000"

"To:
Baguio-Bontoc Rd - K0322+860 - K0323+037;
Type of Work:
Construction of Road Slope Protection Structure;
Physical Target:
716 Square meters;
Allocation:
Php 4,310,000"
August 6, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Benguet 2nd District Engineering Office
"From:
Baguio-Bontoc Rd - K0317 + 468 - K0317 + 566;
Type of Work:
Rehabilitation /Major Repair of Road Slope Protection Structure;
Physical Target:
392.17 Square meters;
Allocation:
Php 4,310,000"

"To:
Baguio-Bontoc Rd - K0322+860 - K0323+037;
Type of Work:
Construction of Road Slope Protection Structure;
Physical Target:
716 Square meters;
Allocation:
Php 4,310,000"
August 6, 2024 2024 WIN4E03556 SR2024-03-012873 March 5, 2024 Cordillera Administrative Region Benguet 2nd District Engineering Office
"From:
Construction of Sagpat, Kibungan, Benguet to Santol, La Union Road (Phase II), Kibungan, Benguet;
Type of Work:
Construction of Gravel Road;
Physical Target:
16.938 Lane Km;
Allocation:
Php 153,000,000"

"To:
Construction of Sagpat, Kibungan, Benguet to Santol, La Union Road (Phase II), Kibungan, Benguet;
Type of Work:
Construction of Gravel Road;
Physical Target:
6.858 Lane Km;
Allocation:
Php 153,000,000"
August 6, 2024 2024 WIN4E03557 SR2024-03-012871 March 5, 2024 Cordillera Administrative Region Benguet 2nd District Engineering Office
"From:
Construction of Poblacion Dalingoan - Sinacbat Road (Phase II), Bakun, Benguet;
Type of Work:
Construction of Gravel Road;
Physical Target:
16.938 Lane Km;
Allocation:
Php 153,000,000"

"To:
Construction of Poblacion Dalingoan - Sinacbat Road (Phase II), Bakun, Benguet;
Type of Work:
Construction of Gravel Road;
Physical Target:
6.30 Lane Km;
Allocation:
Php 153,000,000"
August 6, 2024 2024 WIN4E03559 SR2024-02-008368 February 2, 2024 Cordillera Administrative Region Benguet 2nd District Engineering Office
"From:
Construction of Flood Mitigation Structure along Agno River, Loo Section, Sta. 0+432 - Sta. 1+836 (R.S), Buguias, Benguet;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
1404 Lineal meters;
Allocation:
Php 65,000,000"

"To:
Construction of Flood Mitigation Structure along Agno River, Loo Section, Sta. 0+432 - Sta. 1+043 (LS), Sta. 0+767 - Sta. 1+021 (RS), Buguias, Benguet;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
865 Lineal meters;
Allocation:
Php 65,000,000"
August 6, 2024 2024 SR2024-05-016179 May 20, 2024 Cordillera Administrative Region Benguet 1st District Engineering Office
"From:
Rehabilitation of Road, Bayabas Central - Calamay Road, Barangay Bayabas, Sablan, Benguet;
Type of Work:
CW1: Construction of Concrete Road
CW2: Construction of Road Slope Protection Structure;
Physical Target:
CW1: 0.240 Lane Km
CW2: 341.8 Square meter;
Allocation:
Php 5,000,000"

"To:
Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National
Road/s leading to Major/ Strategic Public Buildings/ Facilities;
Type of Work:
CW1: Construction of Concrete Road
CW2: Construction of Road Slope Protection Structure;
Physical Target:
CW1: 0.240 Lane Km
CW2: 416.14 Square meters;
Allocation:
Php 5,000,000"
August 6, 2024 2024 WIN4E03541 GAA 2024 January 1, 2024 Cordillera Administrative Region Mountain Province 2nd District Engineering Office
"From:
Jct Talubin-Barlig-Natonin-Paracelis-Calaccad Rd - K0426 + 280 - K0426 + 580;
Type of Work:
Reconstruction to Concrete Pavement;
Physical Target:
0.6 Lane Km;
Allocation:
Php 6,008,000"

"To:
Jct Talubin-Barlig-Natonin-Paracelis-Calaccad Rd - K0426 + 280 - K0426 + 400;
Type of Work:
CW1: Reconstruction of Concrete Pavement
CW2: Construction of Road Slope Protection Structures;
Physical Target:
CW1: 0.240 Lane Km
CW2: 360 Square meters;
Allocation:
Php 6,008,000"
August 6, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Lower Kalinga District Engineering Office
"From:
Tabuk-Banawe via Tanudan-Barlig Rd, Kalinga;
Type of Work:
Construction of Concrete Road;
Physical Target:
3.552 Lane Km;
Allocation:
Php 80,000,000"

"To:
Tabuk-Banawe via Tanudan-Barlig Rd, Kalinga;
Type of Work:
CW1: Construction of Gravel Road
CW2: Construction of Road Slope Protection Structure;
Physical Target:
CW1: 5.2 Lane Km
CW2: 4566 Square meters;
Allocation:
Php 80,000,000"
August 6, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Lower Kalinga District Engineering Office
"From:
Mt Province Bdry-Calanan-Pinukpuk-Abbut Rd (Calanan-Pinukpuk Sect) - K0505 + 722 - K0505 + 899, K0514 + 521 - K0514 + 621;
Type of Work:
Construction of Drainage Structure along Road;
Physical Target:
277 Lineal meters;
Allocation:
Php 10501000"

"To:
Mt Province Bdry-Calanan-Pinukpuk-Abbut Rd (Calanan-Pinukpuk Sect) - K0505 + 722 - K0506 + 044 & K0506 + 080 - K0506 + 280, K0514 + 521 - K0514 + 621;
Type of Work:
Construction of Drainage Structure along Road;
Physical Target:
652 Lineal meters;
Allocation:
Php 10,501,000"
August 6, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Lower Kalinga District Engineering Office
"From:
Rizal Natl Rd (Liwan West-Babalag-Macutay Sect) - K0522 + 321 - K0523 + 100;
Type of Work:
Construction of Drainage Structure along Road;
Physical Target:
760 Lineal meters;
Allocation:
Php 38,257,000"

"To:
Rizal Natl Rd (Liwan West-Babalag-Macutay Sect) - K0522 + 321 - K0523 + 640, K0522 + 121 - K0523 + 220;
Type of Work:
Construction of Drainage Structure along Road;
Physical Target:
2418 Lineal Meters;
Allocation:
Php 38,257,000"
August 6, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Lower Kalinga District Engineering Office
"From:
Construction of Flood Control Structure at Liwan East-Calaocan along Pangol Creek, Sta. 11+060-Sta. 11+160, Barangay Liwan East, Calaocan, Arsenio, Rizal, Kalinga;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
82.05 Lineal meter;
Allocation:
Php 10,000,000"

"To:
Construction of Flood Control Structure at Liwan East-Calaocan along Pangol Creek, Sta. 11+060-Sta. 11+320, Barangay Liwan East, Calaocan, Arsenio, Rizal, Kalinga;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
260 Lineal meters;
Allocation:
Php 10,000,000"
August 6, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Lower Kalinga District Engineering Office
"From:
Rehabilitation of Flood Control Structure, Purok Riverside, Poblacion Taga, Pinukpuk, Kalinga;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
205.124 Lineal meters;
Allocation:
Php 25,000,000"

"To:
Rehabilitation of Flood Control Structure, Purok Riverside, Poblacion Taga, Pinukpuk, Kalinga;
Type of Work:
Rehabilitation/ Major Repair of Flood Control Structure;
Physical Target:
322 Lineal Meters;
Allocation:
Php 25,000,000"
August 6, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Lower Kalinga District Engineering Office
"From:
Construction of Bulo-Makilo Road (Bulo Section), Barangay Bulo, Tabuk City, Kalinga;
Type of Work:
Construction of Concrete Road;
Physical Target:
0.871 Lane Km;
Allocation:
Php 50,000,000"

"To:
Construction of Bulo-Makilo Road (Bulo Section), Barangay Bulo, Tabuk City, Kalinga;
Type of Work:
Construction of Concrete Road;
Physical Target:
6.032 Lane Km;
Allocation:
Php 50,000,000"
August 6, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Lower Kalinga District Engineering Office
"From:
Construction of Seet-Mabaca-Taloctoc-Mangali Road, Tanudan, Kalinga;
Type of Work:
Construction of Concrete Road;
Physical Target:
0.644 Lane Km;
Allocation:
Php 37,000,000"

"To:
Construction of Seet-Mabaca-Taloctoc-Mangali Road, Tanudan, Kalinga;
Type of Work:
CW1: Construction of Concrete Road
CW2: Construction of Road Slope Protection Structure;
Physical Target:
CW1: 2.124 Lane Km
CW2: 1112 Square meters;
Allocation:
Php 37,000,000"
August 6, 2024 2024 WIN4E03544 GAA 2024 January 1, 2024 Cordillera Administrative Region Lower Kalinga District Engineering Office
"From:
Construction of Banagao-Mangali Road, Tanudan, Kalinga;
Type of Work:
Construction of Concrete Road;
Physical Target:
0.348 Lane Km;
Allocation:
Php 20,000,000"

"To:
Construction of Banagao-Mangali Road, Tanudan, Kalinga;
Type of Work:
CW1: Construction of Concrete Road
CW2: Construction of Road Slope Protection Structure;
Physical Target:
CW1: .2 Lane Km
CW2: 9.858 Square meters;
Allocation:
Php 20,000,000"
August 6, 2024 2024 WIN4E03578 SR2024-01-005186 January 30, 2024 Cordillera Administrative Region CAR - Regional Office
"From:
Banaue-Mayoyao-A Lista-Isabela Bdry Rd - K0345 + 240 - K0345 + 445;
Type of Work:
Construction of Road Slope Protection Structure;
Physical Target:
5882.353 Square meters;
Allocation:
Php 100,000,000"

"To:
Banaue-Mayoyao-A Lista-Isabela Bdry Rd - K0345 + 240 - K0345 + 340;
Type of Work:
Construction of Road Slope Protection Structure;
Physical Target:
3850 Square meters;
Allocation:
Php 100,000,000"
August 6, 2024 2024 WIN4E03596 SR2024-01-003715 January 29, 2024 Cordillera Administrative Region Benguet 1st District Engineering Office
"From:
Installation of Road Safety Devices along Pico-Lamtang Road, K0256 + 000 - K0261 + 000 - K0261 + 1965, La Trinidad, Benguet;
Type of Work:
Road Safety: Pavement Markings;
Physical Target:
6928 Lineal Meter;
Allocation:
Php 125,000,000"

"To:
Installation of Road Safety Devices along Pico-Lamtang Road, K0255+(-555) - K0261 + 000 - K0261 + 1965, La Trinidad, Benguet;
Type of Work:
Road Safety: Roadway Lighting;
Physical Target:
525 Number of units;
Allocation:
Php 125,000,000"
August 5, 2024 2024 WIN4XY00332 FY 2024 GAA December 20, 2023 Region III Bulacan 2nd District Engineering Office
Asset Preservation Program - Preventive Maintenance - Primary Roads

Manila North Road - K0018+541 - K0018+1059, K0019+000 - K0019+329
August 5, 2024 2024 WIN4XY00336 FY 2024 GAA December 20, 2023 Region III Bulacan 2nd District Engineering Office
Asset Preservation Program - Preventive Maintenance - Primary Roads

Manila North Road - K0021+587 - K0021+877, K0022+000- K0022+060, K0022+125 - K0022+492, K0023+801 - K0023+931
August 5, 2024 2024 WIN4F08059 FY 2024 GAA December 20, 2023 Region III Bulacan 2nd District Engineering Office
Asset Preservation Program - Preventive Maintenance - Tertiary Roads

Bocaue - Sn Jose Rd - K0037+825 - K0038+173
August 5, 2024 2024 WIN4F08081 FY 2024 GAA December 20, 2023 Region III Pampanga 2nd District Engineering Office
Network Development Program - Road Widening - Tertiary Roads

Sn Fernando-Lubao Rd - K0075+254 - K0075+538.64, K0081+531 - K0081+562, K0082+911 - K0083+106.51, K0085+029 - K0085+098.60, K0085+351.60 -K0085+458.75
August 5, 2024 2024 FY 2024 GAA December 20, 2023 Region III Regional Office III
Asset Preservation Program – Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Primary Roads

Jose Abad Santos Ave (JASA) - K0084+391 - K0084+540, K0084+540 - K0085+000, K0085+000 - K0085+088.50
August 5, 2024 2024 WIN4F08070 GAA FY 2024 January 1, 2024 Region VIII Leyte 1st District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Secondary Roads

AS PER GAA/ORIGINAL:

Govt Ctr Rd Network - K0913 + (-029.36) - K0913 + 000, K0913 + (-157) - K0913 + (-029.36), K0913 + 000 - K0913 + 730

Physical Target: Allocation:

CW1- Preventive Maintenance of Road: P 22.09312 M
Asphalt Overlay: 3.548 Lane Km

EAO P 0.45088 M

Total P 22.544 M

AS MODIFIED:

Govt Ctr Rd Network - K0913 + (-157) - K0913 + 395

Physical Target: Allocation:

CW1- Preventive Maintenance of Road: P 22.09312 M
Asphalt Overlay: 2.208 Lane Km

EAO P 0.45088 M

Total P 22.544 M
August 2, 2024 CY 2024 WIN4XY00341 UACS No. 300226110827000 June 11, 2024 National Capital Region NCR - Regional Office
As per GAA/Original
UACS No. 300226110827000
Project ID.: P00846706LZ

Convergence and Special Support Program

Basic Infrastructure Program (BIP) – Multi-Purpose Buildings/ Facilities to support Social Services

Rehabilitation of Multi-Purpose Buildingm (College of Economics) at U.P. Diliman, Quezon City
Physical Target: CW1 = Rehabilitation/ Major Repair of Multi-Purpose Building – 1 bldg.
Unit Cost (P’000) = P 29,700.00/no. of bldgs..
Allocation (P’000)= P 29,700.00
EAO (P’000) = P 300.00
Total (P’000)= P 30,000.00

As Modified
Convergence and Special Support Program

Basic Infrastructure Program (BIP) – Multi-Purpose Buildings/ Facilities to support Social Services

Rehabilitation of Multi-Purpose Buildingm (School of Economics) at U.P. Diliman, Quezon City
Physical Target: CW1 = Rehabilitation/ Major Repair of Multi-Purpose Building – 1 bldg.
Unit Cost (P’000) = P 29,700.00/no. of bldgs..
Allocation (P’000)= P 29,700.00
EAO (P’000) = P 300.00
Total (P’000)= P 30,000.00
Bar Code #WIN4XY00341
August 2, 2024 FY 2024 P00820198MN GAA 2024 January 1, 2024 Region XII Saranggani District Engineering Office
Construction of Bagacay Flood Mitigation Structure, Alabel, Sarangani
Construction of Flood Mitigation Structure
Amount: ₱ 47,254,000.00
August 2, 2024 FY 2024 P00800499MN SR2024-01-002300 January 27, 2024 Region XII Saranggani District Engineering Office
From: Sarangani-Davao Del Sur Coastal Rd - K1749 + 100 - K1749 + 300
To: Rehabilitatio/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide along Sarangani- Davao del Sur Coastal Rd- K1696+915- K1697+012, K1697+135- K1697+290, K1749+110-K1749+300
Amount: ₱ 75,000,000.00
August 2, 2024 2024 P00803766MN SR2024-01-001925 January 27, 2024 Region X Regional Office X
P00803766MN
310101101342000
OO1:Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads

FROM:
Sayre Highway K1525 + 274 - K1527 + 520, K1538 + 1014 - K1539 + 683
Type of Work:
CW1-Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1-6.218 Lane Km
Allocation:
Total: Php 122,720,000.00
CW1: Php 118,424,800.00
EAO: Php 4,925,200.00

TO:
Sayre Highway K1526 + (-726) - K1527 + 000, K1539 + 000 - K1539 + 681
Type of Work:
CW1-Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1-9.748 Lane Km
Allocation:
Total: Php 122,720,000.00
CW1: Php 118,424,800.00
EAO: Php 4,925,200.00
August 2, 2024 2024 P00800006MN SR2024-01-003092 January 27, 2024 Region X Regional Office X
P00800006MN
310203100788000
OO1:Ensure Safe and Reliable National Road System - Network Development- Road Widening - Tertiary Roads

FROM:
Mulondo-Wao Rd - (S01604MN) Chainage 9300 - Chainage 11300
Type of Work:
CW1- Road Widening
Physical Target:
CW1-4.000 Lane Km
Allocation:
Total: Php 50,000,000.00
CW1: Php 48,250,000.00
EAO: Php 1,750,000.00

TO:
Mulondo-Wao Rd - (S01604MN) Chainage 40 - Chainage 2040
Type of Work:
CW1-Road Widening
Physical Target:
CW1-4.000 Lane Km
Allocation:
Total: Php 50,000,000.00
CW1: Php 48,250,000.00
EAO: Php 1,750,000.00
August 2, 2024 2024 P00834899MN SR2024-07-01803 July 22, 2024 Region X Regional Office X
P00834899MN
300215104074000
CSSP:Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities

FROM:
Construction of Road, Jct. Bukidnon Davao City Road-Palacapao-East Dalurong-West Dalurong-Sinaysayan Road (East Dalurong Section and West Dalurong Section), Kitaotao,Bukidnon (Package 1)
Type of Work:
CW1- Construction of Concrete Road
Physical Target:
CW1-9.200 Lane Km
Allocation:
Total: Php 140,000,000.00
CW1: Php 135,100,000.00
EAO: Php 4,900,000.00

TO:
Construction of Road, Jct. Bukidnon Davao City Road-Palacapao-East Dalurong-West Dalurong-Sinaysayan Road (East Dalurong Section and West Dalurong Section), Kitaotao,Bukidnon (Package 1)
Type of Work:
CW1- Construction of Concrete Road
CW2- Construction of Road Slope Protection Structure
Physical Target:
CW1-5.200 Lane Km
CW2-4,940.00 Square meters
Allocation:
Total: Php 140,000,000.00
CW1: Php 108,376,592.01
CW2: Php 26,723,407.99
EAO: Php 4,900,000.00
August 2, 2024 2024 P00834902MN SR2024-07-018042 July 22, 2024 Region X Regional Office X
P00834902MN
300215104077000
CSSP:Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities

FROM:
Construction of Road (Jct. Bukidnon-Davao City Road, Brgy. Tawas- Sitio Balakbakan-Sitio Sumalil Road, Kitaotao, Bukidnon
Type of Work:
CW1- Construction of Concrete Road
Physical Target:
CW1-6.000 Lane Km
Allocation:
Total: Php 100,000,000.00
CW1: Php 96,500,000.00
EAO: Php 3,500,000.00

TO:
Construction of Road (Jct. Bukidnon-Davao City Road, Brgy. Tawas- Sitio Balakbakan-Sitio Sumalil Road, Kitaotao, Bukidnon
Type of Work:
CW1- Construction of Concrete Road
Physical Target:
CW1-4.040 Lane Km
Allocation:
Total: Php 100,000,000.00
CW1: Php 96,500,000.00
EAO: Php 3,500,000.00
July 31, 2024 2024 310109101450000 GAA 2024 January 3, 2024 Region II Cagayan 3rd District Engineering Office
Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads - Peñablanca- Callao Cave Rd- K0477+(-158)- K0477+(-258)

July 31, 2024 2024 310201101389000 GAA 2024 January 3, 2024 Region II Isabela 2nd District Engineering Office
FROM:

Network Development - Road Widening - Primary Roads - Santiago-Tuguegarao Rd - K0388 + 1075.62 - K0390 + 000

TO:

Network Development - Road Widening - Primary Roads - Santiago-Tuguegarao Rd - K0389 + 240 - K0389 + 776
July 31, 2024 2024 310103101374000 GAA 2024 January 3, 2024 Region II Isabela 4th District Engineering Office
FROM:

Asset Preservation - Preventive Maintenance - Tertiary Roads - Jct Ipil-Quirino Bdry Rd - K0365 + 500 - K0376 + 500 - K0376 + 211

TO:

Asset Preservation - Preventive Maintenance - Tertiary Roads - Jct Ipil-Quirino Bdry Rd - K0365 + 974 - K0373 + 763
July 31, 2024 2024 310105101009000 GAA 2024 January 3, 2024 Region II Nueva Vizcaya District Engineering Office
FROM:

Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Secondary Roads - Nueva Vizcaya-Ifugao Rd - K0283 + (-463) - K0289 + 010

TO:

Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Secondary Roads - Nueva Vizcaya-Ifugao Rd - K0283 + (-463) - K0283 + 073, K0284 + 365 - K0289 + 010
July 31, 2024 2024 310204102443000 GAA 2024 January 3, 2024 Region II Regional Office II
Network Development - Construction of By-Pass and Diversion Roads - Tuguegarao West Diversion Road (Jct. Carig-Linao-Atuluyan-Bagay-Buntun), Package 1, Cagayan
July 31, 2024 2024 300215104461000 GAA 2024 January 3, 2024 Region II Cagayan 3rd District Engineering Office
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Road , Brgy. Maddarulug Sur, Enrile, Cagayan
July 31, 2024 2024 300215104464000 GAA 2024 January 3, 2024 Region II Cagayan 3rd District Engineering Office
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Bridge and Approaches, Brgy. Dassun, Solana, Cagayan
July 31, 2024 2024 300216100032000 GAA 2024 January 3, 2024 Region II Cagayan 3rd District Engineering Office
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Roads connecting to Indigenous People (IP) Communities - Construction of Access Road, Leading to Indigenous People of Peñablanca, Cagayan
July 31, 2024 2024 300215104480000 GAA 2024 January 3, 2024 Region II Cagayan 3rd District Engineering Office
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or ridges from the National Road/s leading to Major/ Strategic Public Buildings/Facilities - Construction of Nattallag Bridges & Approaches, Brgy. Mangga, Peñablanca, Cagayan, Phase II
July 31, 2024 2024 310201101247000 GAA 2024 January 3, 2024 Region II Regional Office II
FROM:

Network Development - Road Widening - Primary Roads - Daang Maharlika (LZ) - K0271 + 000 - K0272 + 379, K0273 + 392 - K0276 + 000, K0277 + 580 - K0279 + 000

TO:

Network Development - Road Widening - Primary Roads - Daang Maharlika (LZ) - K0271 + 940 - K0272 + 376.30, K0273 + 408.70 - K0275 + 158.10
July 30, 2024 2024 WIN4F08073 GAA 2024 January 19, 2024 Region V Regional Office V
Project ID : P00800214LZ
UACS No: 310108101265000

FROM :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Primary Roads - Daang Maharlika (LZ) - K0414 + 385 - K0416 + 000, K0416 + 760 - K0416 + 836, K0423 + 970 - K0424 + 757, K0425 + 131 - K0426 + 722, K0429 + 597 - K0429 + 893, K0432 + 527 - K0432 + 528

Physical Target :
CW1 - Road Widening - 8.738 Lane Km

TO :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Primary Roads - Daang Maharlika (LZ) - K0414 + 385 - K0415 + 360, K0423 + 970 - K0424 + 757, K0425 + 131 - K0426 + 722, K0429 + 632 - K0429 + 893

Physical Target :
CW1 - Road Widening - 7.21 Lane Km
ROW - ROW Acquisition - 18025 Square meter
July 30, 2024 2024 GAA 2024 January 19, 2024 Region V Regional Office V
Project ID : P00800901LZ
UACS No: 310108101873000

FROM :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Asset Preservation Program - Rehabilitation/ Reconstruction of Road with Slips, Slope Collapse, and Landslide - Secondary Roads - Catanduanes Cir Rd - K0168 + 650 - K0168 + 675

Physical Target :
CW1 - Construction of Road Slope Protection Structure - 575 Square meters


TO :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Asset Preservation Program - Rehabilitation/ Reconstruction of Road with Slips, Slope Collapse, and Landslide - Secondary Roads - Catanduanes Cir Rd - K0168 + 620 - K0168 + 705

Physical Target :
CW1 - Construction of Road Slope Protection Structure - 681 Square meters
July 30, 2024 2024 WIN4X700328 GAA 2024 January 19, 2024 Region V Regional Office V
Project ID : P00800218LZ
UACS No: 310201101279000

FROM :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Primary Roads - Daang Maharlika (LZ) - Daang Maharlika (LZ) - K0580 + 939 - K0580 + 968, K0580 + 994 - K0581 + 000, K0581 + 024 - K0581 + 269, K0581 + 269 - K0581 + 279, K0581 + 279 - K0581 + 375, K0581 + 432 - K0581 + 444, K0581 + 528 - K0581 + 571, K0581 + 707 - K0581 + 761

Physical Target :
CW1 - Road Widening - 0.381 Lane Km
CW2 - Construction of Drainage Structure along Road - 386 Lineal meters
ROW - ROW Acquisition - 24.27 Square meters


TO :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Primary Roads - Daang Maharlika (LZ) - K0585 + 757 - K0586 + 322

Physical Target :
CW1 - Road Widening - 0.852 Lane Km
CW2 - Construction of Slope Protection Structure - 2191.34 Square meters
July 30, 2024 2024 WIN4F08047 GAA 2024 January 19, 2024 Region V Regional Office V
Project ID : P00800225LZ
UACS No: 310201101259000

FROM :
Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Primary Roads - Daang Maharlika (LZ) - K0267 + 145 - K0270 + 089

Physical Target :
CW1 - Road Widening - 5.912 Lane Km
ROW - ROW Acquisition - 59,120 Square meters

TO :
Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Primary Roads - Daang Maharlika (LZ) - K0267 + 145 - K0270 + 089

Physical Target :
CW1 - Road Widening - 5.077 Lane Km
CW2 - Construction of Road Slope Protection Structure - 4,199.92 Square Meters
July 30, 2024 2024 WIN4F08045 GAA 2024 January 19, 2024 Region V Regional Office V
Project ID : P00802127LZ
UACS No: 310101101263000

FROM :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Asset Preservation Program - Preventive Maintenance - Primary Roads - Daang Maharlika (LZ) - K0443 + (-420) - K0448 + 565 Phase II

Physical Target :
CW1 - Preventive Maintenance of Road Asphalt Overlay - 22.812 Lane Km


TO :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Asset Preservation Program - Preventive Maintenance - Primary Roads - Daang Maharlika (LZ) - K0444 + 159 - K0447 + 152.50

Physical Target :
CW1 - Preventive Maintenance of Road Asphalt Overlay - 11.822 Lane Km
July 30, 2024 2024 WIN4XY00327 2024 January 19, 2024 Region V Regional Office V
Project ID : P00800890LZ
UACS No: 310107100614000

FROM :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Asset Preservation Program - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Daang Maharlika (LZ) - K0526 + 041 - K0526 + 057

Physical Target :
CW1 - Construction of Road Slope Protection Structure

TO :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Asset Preservation Program - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Daang Maharlika (LZ) - K0520 + 744.16 - K0520 + 767.80, K0526 + 041.00 - K0526 + 057.00

Physical Target :
CW1 - Construction of Road Slope Protection Structure - 210.980 Square meters
July 30, 2024 2024 WIN4XY00318 GAA 2024 January 19, 2024 Region V Regional Office V
Project ID : P00800913LZ
UACS No: 310107100612000

FROM :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Asset Preservation Program - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Daang Maharlika (LZ) - K0367 + 825 - K0367 + 875

Physical Target :
CW1 - Construction of Road Slope Protection Structure - 1108 Square meters


TO :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Asset Preservation Program - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Daang Maharlika (LZ) - K0338 + 475 - K0338 + 560

Physical Target :
CW1 - Construction of Road Slope Protection Structure - 570.18 Square meters
July 30, 2024 2024 WIN4XY00319 GAA 2024 January 19, 2024 Region V Regional Office V
Project ID : P00800911LZ
UACS No: 310107100610000

FROM :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Asset Preservation Program - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Daang Maharlika (LZ) K0354 + 878 - K0355 + 000

Physical Target :
CW1 - Construction of Road Slope Protection Structure - 4000 Square meters

TO :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Asset Preservation Program - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Daang Maharlika (LZ) - K0358 + 860 - K0358 + 950, K0359 + 915 - K0359 + 975

Physical Target :
CW1 - Construction of Road Slope Protection Structure - 1866.06 Square meters
July 30, 2024 2024 WIN4XY00317 GAA 2024 January 19, 2024 Region V Regional Office V
Project ID : P00800912LZ
UACS No: 310107100611000

FROM :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Asset Preservation Program - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Daang Maharlika (LZ) - K0365 + 100 - K0365 + 130

Physical Target :
CW1 - Construction of Road Slope Protection Structure - 1560 Square meter

TO :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Asset Preservation Program - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Daang Maharlika (LZ) - K0365 + 100 - K0365 + 130, K0367 + 825 - K0367 + 875

Physical Target :
CW1 - Construction of Road Slope Protection Structure - 676.39 Square meters
July 30, 2024 2024 WIN4XY00289 GAA 2024 December 19, 2024 Region V Regional Office V
Project ID : P00800542LZ
UACS No: 310205101228000

FROM :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Network Development Program - Construction of Missing Links/ New Roads - Pasacao - Balatan Tourism Coastal Highway (Pasacao - Minalabac Section), Camarines Sur

Physical Target :
CW1 - Construction of Concrete Road - 10.477 Lane Km


TO :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Network Development Program - Construction of Missing Links/ New Roads - Pasacao - Balatan Tourism Coastal Highway (Pasacao - Minalabac Section), Camarines Sur

Physical Target :
CW1 - Construction of Concrete Road - 4.769 Lane Km
CW2 - Construction of Road Slope Protection Structure - 3651.7 Square
July 30, 2024 2024 WIN4F08046 GAA 2024 January 19, 2024 Region V Regional Office V
Project ID : P00837427LZ
UACS No: 300214100758000

FROM :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A 11239 - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads along Daang Maharlika (LZ) - K0515 + 659 -K0516 + 005, K0516 + 596 - K0518 + 706, K0521 + 128 - 522 + 434, K0522 + 800 - K0522 + 922, K0524 + 046 - K0524 + 480, K0527 + 627 - K0528 + 432

Physical Target :
CW1 - Rehabilitation of Paved Road - 9.418 Lane Km
CW2 - Preventive Maintenance of Road Asphalt Overlay


TO :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A 11239 - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads along Daang Maharlika (LZ) - K0516 + 596 - K0518 + 809, K0521 + 128 - 522 + 434
July 30, 2024 2024 WIN4XY00292 GAA 2024 January 19, 2024 Region V Sorsogon 2nd District Engineering Office
Project ID : P00848321LZ
UACS No: 300226113671000

FROM :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - Multipurpose Buildings/ Facilities to support Social Services - Construction of Multi-Purpose Building, Brgy. Bulawan, Sta. Magdalena, Sorsogon

Physical Target :
CW1 - Construction of Multi-Purpose Building - 1 No. of Building

TO :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - Multipurpose Buildings/ Facilities to support Social Services - Construction of Multi-Purpose Building, Brgy. Bulawan, Prieto Diaz, Sorsogon

Physical Target :
CW1 - Construction of Multi-Purpose Building - 1 No. of Building
July 30, 2024 2024 WIN4XY00283 GAA 2024 January 19, 2024 Region V Camarines Norte Sub-District Engineering Office
Project ID : P00846365LZ
UACS No: 300226109838000

FROM :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program(BIP) - BIP - Multi-Purpose Buildings/ Facilities to support Social Services - Completion of Multi-Purpose Buildings Mangamagong Elementary School Barangay Mangamagong Phase 2 Daet, Camarines Norte

Physical Target :
CW1 - Construction of Multi Purpose Building - 1 Number of Buildings


TO :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program(BIP) - BIP - Multi-Purpose Buildings/ Facilities to support Social Services - Completion of Multi-Purpose Buildings Mangcamagong Elementary School (Phase 2), Barangay Mangcamagong, Basud, Camarines Norte

Physical Target :
CW1 - Construction of Multi Purpose Building - 1 Number of Buildings
July 30, 2024 2024 WIN4XY00251 GAA 2024 January 19, 2024 Region V Regional Office V
Project ID : P00844598LZ
UACS : 300219102533000

FROM :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps(SIPAG) - SIPAG - Flood Mitigation Structure protecting Major/ Strategic Public Buildings/ Facilities - Construction of Sagñay River Flood Mitigation Structure along Barangay Tarague and Barangay Minangdongjol Sagñay, Camarines Sur

Physical Target :
CW1 - Construction of Flood Mitigation Structure - 551 lineal meters


TO :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps(SIPAG) - SIPAG - Flood Mitigation Structure protecting Major/ Strategic Public Buildings/ Facilities - Construction of Sagñay River Flood Mitigation Structure along Barangay Tarague and Barangay Minadongjol Sagñay, Camarines Sur

Physical Target :
CW1 - Construction of Flood Mitigation Structure - 551 lineal meters
July 30, 2024 2024 GAA 2024 January 19, 2024 Region V Regional Office V
Project ID : P00805178LZ
UACS : 310104100661000

FROM :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Asset Preservation Program - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Primary Roads - Daang Maharlika (LZ) - K0554 + 630 - K0555 + 074

Physical Target :
CW1 - Rehabilitation of Paved Roads - 0.888 Lane Km


TO :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Asset Preservation Program - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Primary Roads - Daang Maharlika (LZ) - K0554 + 630 - K0554 + 900, K0557 + 625 - K0557 + 940, K0562 + 143 - K0562 + 465

Physical Target :
Rehabilitation of Paved Road - 1.177 Lane Km
July 30, 2024 2024 GAA 2024 January 19, 2024 Region V Regional Office V
Project ID : P00837978LZ
UACS : 300215103870000

FROM :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - SIPAG - Access Roads and/ or Bridges from National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Ridge Road, Tinocawan - Maninila - Caracan, Rapu-Rapui, Albay

Physical Target :
CW1 - Construction of Gravel Road - 4.498 Lane km


TO :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - SIPAG - Access Roads and/ or Bridges from National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Ridge Road, Tinocawan - Manila - Caracan, Rapu-Rapui, Albay

Physical Target :
CW1 - Construction of Gravel Road - 4.241 Lane Km
Cw2 - Construction of Road Slope Protection Structure - 5,788 Square meters
July 29, 2024 2024 SR2024-01-008087 January 31, 2024 Region VIII Regional Office VIII
OO1: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Primary Roads

AS PER GAA/ORIGINAL:

Daang Maharlika (LT) – K0939 + 000 - K0941 + 000

Physical Target: Allocation:

CW1- Preventive Maintenance of Road: P 132.74926 M
Asphalt Overlay: 8.092 Lane Km

EAO P 4.81474 M

Total P 137.564 M

AS MODIFIED:

Daang Maharlika (LT) – K0939 + 770 – K0941 + 000, K0946 + 000 – K0947 + 000

Physical Target: Allocation:

CW1- Preventive Maintenance of Road: P 132.74926 M
Asphalt Overlay: 9.088 Lane Km

EAO P 4.81474 M

Total P 137.564 M
July 26, 2024 FY 2024 P00833593MN GAA 2024 January 1, 2024 Region XII Cotabato 1st District Engineering Office
Basic
Infrastructure Program (BIP) - Flood Mitigation Structures
protecting Public Infrastructures/Facilities
Construction of Drainage Canal along Kitao Creek, Central
Katingawan, Midsayap, Cotabato
Basic
₱ 5,000,000.00
July 26, 2024 FY 2024 P00800498MN GAA 2024 January 1, 2024 Region XII Cotabato 2nd District Engineering Office
From:Paco-Roxas-Arakan Valley - Jct Davao - Bukidnon Rd –
K1683 + 808 - K1683 + 929
To: Paco-Roxas-Arakan Valley - Jct Davao - Bukidnon Rd –
K1684 + 820 - K1684 + 892
Amount: ₱100,000,000.00
July 25, 2024 2024 WIN4E03573 FY 2024 GAA, R.A 11975 December 25, 2023 Region XIII Regional Office XIII
UACS No. : 310201101368000
Project ID: P00800223MN

ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Primary Roads

FROM:

Daang Maharlika (Surigao-Agusan Sect) - K1168 + (-823) - K1168 + 009, K1168 + 368 - K1169 + 000, K1171 + 000 - K1174 + 701, K1175 + 133 - K1175 + 240, K1175 + 270 - K1175 + 642

Type of Work:
CW1- Road Widening

Physical Target:
CW1- 11.284 Lane Km

Allocation:
TOTAL: P 216,616,000
CW1: P 209,034,440
EAO: P 7,581,560

Unit Cost:
CW1: P 18,524,852.89/Lane Km

TO:

Daang Maharlika (Surigao-Agusan Sect) - K1168 + (-823) - K1168 + (-036.09), K1168 + 380 - K1169 + 006.33, K1171 + 000 - K1171 + 640, K1171 + 860 - K1172 + 120, K1172 + 480 - K1172 + 625

Type of Work:
CW1- Road Widening
CW2- ROW Acquisition

Physical Target:
CW1- 4.916 Lane Km
CW2- 45,000 Square meters

Allocation:
TOTAL: P 216,616,000
CW1: P 199,384,440
CW2: P 9,650,000
EAO: P 7,581,560

Unit Cost:
CW1: P 40,558,266.88/Lane Km
CW2: P 214,.44/Square meters


July 25, 2024 2024 WIN4E03572 FY 2024 GAA, R.A 11975 December 25, 2023 Region XIII Regional Office XIII
UACS No. : 300215104139000
Project ID: P00834947MN

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - SIPAG - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities

FROM:

Construction of Road, Salaysayon - Jagimitan Road, (Sta K1+570 - K6+070) Package 2, Nasipit, Agusan Del Nore

Type of Work:
CW1- Construction of Concrete Road

Physical Target:
CW1- 17.604 Lane Km

Allocation:
TOTAL: P 200,000,000
CW1: P 193,000,000
EAO: P 7,000,000

Unit Cost:
CW1: P 52,445,652.17/Lane Km

TO:

Construction of Road, Salaysayon - Jaguimitan Road, (Sta K1+570 - K3+410) Package 2, Nasipit, Agusan Del Norte

Type of Work:
CW1- Construction of Gravel Road

Physical Target:
CW1- 3.68 Lane Km

Allocation:
TOTAL: P 200,000,000
CW1: P 193,000,000
EAO: P 7,000,000

Unit Cost:
CW1: P 52,445,652.17/Lane Km



July 25, 2024 2024 FY 2024 GAA, R.A 11975 December 25, 2023 Region XIII Regional Office XIII
UACS No. : 300219102729000
Project ID: P00835851MN

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - SIPAG - Flood Mitigation Structures protecting Major/ Strategic Public Buildings/ Facilities

FROM:

Construction of Jiabong-San Isidro River Control Project, Kitcharao, Agusan del Norte

Type of Work:
CW1- Construction of Flood Mitigation Structure

Physical Target:
CW1- 900.00 Lineal meters

Allocation:
TOTAL: P 250,000,000
CW1: P 241,250,000
EAO: P 8,750,000

Unit Cost:
CW1: P 268,055.55/Lineal meters

TO:

Construction of Jaliobong-San Isidro River Control Project, Kitcharao, Agusan del Norte

Type of Work:
CW1- Construction of Flood Mitigation Structure

Physical Target:
CW1- 900.00 Lineal meters

Allocation:
TOTAL: P 250,000,000
CW1: P 241,250,000
EAO: P 8,750,000

Unit Cost:
CW1: P 268,055.55/Lineal meters

July 25, 2024 2024 WIN4E03571 FY 2024 GAA, R.A 11975 December 25, 2023 Region XIII Regional Office XIII
UACS No. : 310101101426000
Project ID: P00801114MN

ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Asset Preservation Program - Preventive Maintenance - Primary Roads

FROM:

Daang Maharlika (Bayugan Rotunda) - Chainage 0 - Chainage 220

Type of Work:
CW1- Preventive Maintenance of Road: Asphalt Overlay

Physical Target:
CW1- 0.66 Lane Km

Allocation:
TOTAL: P 5,665,000
CW1: P 5,466,725
EAO: P 198,275

Unit Cost:
CW1: P 8,282,920/Lane Km

TO:

Daang Maharlika (Bayugan Rotunda) - Chainage 0 - Chainage 99

Type of Work:
CW1- Preventive Maintenance of Road: Asphalt Overlay

Physical Target:
CW1- 0.297 Lane Km

Allocation:
TOTAL: P 5,665,000
CW1: P 5,466,725
EAO: P 198,275

Unit Cost:
CW1: P 18,406,481/Lane Km

July 25, 2024 2024 FY 2024 GAA, R.A 11975 December 25, 2023 Region XIII Regional Office XIII
UACS No. : 310205101288000
Project ID: P00803885MN

ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Construction of Missing Links/ New Roads

FROM:

East-West Lateral Road connecting Agusan del Sur/Bukidnon Agusan-Malaybalay Road, Package 8, Agusan Del Sur

Type of Work:
CW1- Construction of Gravel Road

Physical Target:
CW1- 6.6 Lane Km

Allocation:
TOTAL: P 200,000,000
CW1: P 193,000,000
EAO: P 7,000,000

Unit Cost:
CW1: P 29,242,424.24/Lane Km

TO:

East-West Lateral Road connecting Agusan del Sur/Bukidnon Agusan-Malaybalay Road, Package 10, Agusan Del Sur

Type of Work:
CW1- Construction of Gravel Road

Physical Target:
CW1- 6.6 Lane Km

Allocation:
TOTAL: P 200,000,000
CW1: P 193,000,000
EAO: P 7,000,000

Unit Cost:
CW1: P 29,242,424.24/Lane Km
July 25, 2024 2024 WIN4E03570 FY 2024 GAA, R.A 11975 December 25, 2023 Region XIII Regional Office XIII
UACS No. : 310101101428000
Project ID: P00801130MN

ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Asset Preservation Program - Preventive Maintenance - Primary Roads

FROM:

Daang Maharlika (Agusan-Davao Sect) - K1336 + 234 - K1336 + 700

Type of Work:
CW1- Preventive Maintenance of Road: Asphalt Overlay

Physical Target:
CW1- 1.864 Lane Km

Allocation:
TOTAL: P 16,000,000
CW1: P 15,440,000
EAO: P 560,000

Unit Cost:
CW1: P 8,283,261.8/Lane Km

TO:

Daang Maharlika (Agusan-Davao Sect) - K1336 + 200 - K1336 + 455

Type of Work:
CW1- Preventive Maintenance of Road: Asphalt Overlay

Physical Target:
CW1- 1.02 Lane Km

Allocation:
TOTAL: P 16,000,000
CW1: P 15,440,000
EAO: P 560,000

Unit Cost:
CW1: P 15,137,254.9/Lane Km
July 25, 2024 2024 FY 2024 GAA, R.A 11975 December 25, 2023 Region XIII Regional Office XIII
UACS No. : 310104100707000
Project ID: P00801252MN

ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Asset Preservation Program - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads
- Primary Roads

FROM:

Daang Maharlika (Agusan-Davao Sect) - K1320 + 666 - K1321 + 522, K1326 + 000 - K1326 + 300, K1328 + 400 - K1329 + 000, K1330 + 669 - K1330 + 802, K1330 + 989 - K1331 + 075, K1334 + 058 - K1334 + 135, K1335 + 000 - K1335 + 102, K1335 + 300 - K1336 + 200, K1337 + 218 - K1337 + 785, K1351 + 900 - K1351 + 961

Type of Work:
CW1- Rehabilitation of Paved Road

Physical Target:
CW1- 7.364 Lane Km

Allocation:
TOTAL: P 220,920,000
CW1: P 213,187,800
EAO: P 7,732,200

Unit Cost:
CW1: P 28,950,000/Lane Km

TO:

Daang Maharlika (Agusan-Davao Sect) - K1320 + 666 - K1320 +932, K1321 + 015.946 - K1321 + 522, K1326 + 000 - K1326 + 300, K1328 + 400 - K1329 + 000, K1335 + 000 - K1335 + 102, K1335 + 300 - K1336 + 200, K1337 + 218 - K1337 + 785, K1351 + 900 - K1351 + 961

Type of Work:
CW1- Rehabilitation of Paved Road

Physical Target:
CW1- 7.032 Lane Km

Allocation:
TOTAL: P 220,920,000
CW1: P 213,187,800
EAO: P 7,732,200

Unit Cost:
CW1: P 30,316,808.87/Lane Km
July 25, 2024 2024 FY 2024 GAA, R.A 11975 December 25, 2023 Region XIII Regional Office XIII
UACS No. : 310204102791000
Project ID: P00803871MN

ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Construction of By-Pass and Diversion Roads

FROM:

Construction of Lake Mainit Circumferential Road Bypass Road to Wind Power Butuan City Surigao Norte

Type of Work:
CW1- Construction of Gravel Road
CW2- Construction of Road Slope Protection Structure

Physical Target:
CW1- 0.374 Lane Km
CW2- 3,692.4 Square meters

Allocation:
TOTAL: P 50,000,000
CW1: P 19,669,595
CW2: P 28,580,405
EAO: P 1,750,000

Unit Cost:
CW1: P 52,592,500/Lane Km
CW2: P 7,740.33/Square meters

TO:

Construction of Lake Mainit Circumferential Road Bypass Road to Wind Power, Surigao del Norte

Type of Work:
CW1- Construction of Gravel Road
CW2- Construction of Road Slope Protection Structure

Physical Target:
CW1- 0.374 Lane Km
CW2- 3,692.4 Square meters

Allocation:
TOTAL: P 50,000,000
CW1: P 19,669,595
CW2: P 28,580,405
EAO: P 1,750,000


Unit Cost:
CW1: P 52,592,500/Lane Km
CW2: P 7,740.33/Square meters


July 25, 2024 FY 2024 WIN4E03589 320101111308000 May 23, 2024 Region IX Regional Office IX
UACS No. 320101111308000
Project ID: P00820889MN

OO2: Protect Lives and Properties Against Major Floods – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems

Construction of Flood Control Structure along Puliran River, Puliran Br. Section Package 2, Sibuco, Zamboanga del Norte

CW1- Construction of Flood Mitigation Structure: 520 Lineal meters
Unit Cost: ₱ 315,369.11/ Lineal meters
EAO: ₱ 5,950,000.00 Excess: ₱ 58,059.63
Allocation: ₱ 170,000,000.00
July 25, 2024 FY 2024 WIN4E03594 310204102625000 May 23, 2024 Region IX Regional Office IX
UACS No. 310204102625000
Project ID: P00800804MN

OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Bypass and Diversion Roads

Airport-Turno-Sinaman Bypass Road, Zamboanga del Norte
CW1- Road Widening: 1.76 Lane Km
Unit Cost: ₱ 15,785,191.55/ Lane Km CW2- Construction of Road Slope Protection Structure: 5,123.79 sq.m. Unit Cost: ₱ 3,018.87/ sq.m. ROW Acquisition: 4,145.07 sq.m. Unit Cost: ₱ 1,206.25/ sq.m.
EAO: ₱ 1,750,000.00
Allocation: ₱ 50,000,000.00
July 25, 2024 FY 2024 WIN4E03591 310204102640000 June 13, 2024 Region IX Regional Office IX
UACS No. 310204102640000
Project ID: P00800792MN

OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Bypass and Diversion Roads

Sumagdang-Menzi Bypass Road, Zamboanga del Norte
CW1- Road Widening: 0.706 Lane Km
Unit Cost: ₱ 18,161,122.03/ Lane Km CW2- Construction of Concrete Road: 0.726 Lane Km Unit Cost: ₱ 21,203,812.19/ Lane Km CW3- Construction of Road Slope Protection Structure: 1,960.20 sq.m. Unit Cost: ₱ 10,301.15/ sq.m. CW4- Off-Carriageway Improvement/Construction of Bike Lanes: 9,700.00 sq. m. Unit Cost: ₱ 2,452.78/ sq.m. ROW Acquisition: 62,204.00 sq.m. Unit Cost: ₱ 80.38/ sq.m.
EAO: ₱ 2,800,000.00
Allocation: ₱ 80,000,000.00
July 25, 2024 FY 2024 WIN4E03555 310201101314000 May 23, 2024 Region IX Regional Office IX
UACS No. 310201101314000
Project ID: P00800213MN

OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads

Pagadian City-Zamboanga City Rd - K1935+900 - K1935+984.31, K1935+900 - K1935+930, K1935+520 - K1935+594.32
CW1- Road Widening: 0.263 Lane Km
Unit Cost: ₱ 17,407,510.30/ Lane Km CW2- Construction of Drainage Structure along Road: 166.0 Lineal meters Unit Cost: ₱10,758.59/ sq.m. ROW Acquisition: 330.55 sq.m. Unit Cost: ₱ 16,655.26/ sq.m.
EAO: ₱ 430,500.00
Allocation: ₱ 12,300,000.00
July 25, 2024 FY 2024 WIN4E03554 310201101311000 May 23, 2024 Region IX Regional Office IX
UACS No. 310201101311000
Project ID: P00800021MN

OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads

Lanao-Pagadian-Zamboanga City Rd - K1784+900 - k1785+256
CW1- Road Widening: 0.712 Lane Km
Unit Cost: ₱ 18,455,955.52/ Lane Km ROW Acquisition: 2,000.00 sq.m. Unit Cost: ₱ 500.0/ sq.m.
EAO: ₱ 514,150.00 Excess: ₱ 42,329.67
Allocation: ₱ 14,690,000.00
July 25, 2024 FY 2024 WIN4E03551 320101111321000 May 23, 2024 Region IX Regional Office IX
UACS No. 320101111321000
Project ID: P00820895MN

OO2: Protect Lives and Properties Against Major Floods – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems

Construction of Flood Control Structure along Tumaga River (Guiwan Section), Zamboanga City Package 1

CW1- Construction of Flood Mitigation Structure: 283.00 Lineal meters
Unit Cost: ₱ 340,897.41/ Lineal meters
EAO: ₱ 3,500,000.00 Excess: ₱ 26,032.91
Allocation: ₱ 100,000,000.00
July 25, 2024 FY 2024 300214100814000 June 18, 2024 Region IX Regional Office IX
UACS No. 300214100814000 Project ID: P00833110MN Convergence and Special Support Program - Special Road Fund - Motor Vehicle Users Charge (MVUC) as per R.A. 11239

Installation of Signage-Warning, Advisory and Regulatory Signs, Pavement Markings, and Pedestrian Fencing along Pagadian City-Zamboanga City Rd- K1676+800 - K1677+800, Camanga, Dumalinao, Zamboanga del Sur

CW1 - Road Safety/Pavement Markings: 926.00 Lineal Meters
Unit Cost: ₱ 884.28/ Lineal Meters
Allocation: ₱ 810,000.00
July 25, 2024 FY 2024 WIN4E03563 310201101313000 May 23, 2024 Region IX Regional Office IX
UACS No. 310201101313000
Project ID: P00802689MN

OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads

Lanao-Pagadian-Zamboanga City Rd - K1648+(-273) - K1649+260
CW1- Road Widening: 3.044 Lane Km
Unit Cost: ₱ 36,298,153.48/ Lane Km ROW Acquisition: 1,425.00 sq.m. Unit Cost: ₱ 7,017.54/ sq.m.
EAO: ₱ 4,375,000.00 Excess: ₱ 133,420.81
Allocation: ₱ 125,000,000.00
July 25, 2024 FY 2024 WIN4E03597 310107100642000 May 23, 2024 Region IX Regional Office IX
UACS No. 310107100642000
Project ID: P00800404MN

OO1: Ensure Safe and Reliable National Road System – Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads

Pagadian City-Zamboanga City Rd - K1703+790 - K1703+990, K1704+060 - K1704+161, K1721+200 - K1721+596.69
CW1- Construction of Road Slope Protection Structure: 5,390.00 sq.m.
Unit Cost: ₱ 20,307.014/sq.m. ROW Acquisition: 68.5788 sq.m.
EAO: ₱ 3,982,300.00
Allocation: ₱ 113,780,000.00
July 23, 2024 FY 2024 P00833081MN SR2024-01-000917 January 26, 2024 Region XII Regional Office XII
Contract ID: 24M00027
Project Cost: P58,677,000

From:
Project Name: Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads along Marbel-Allah Valley-Cotabato Rd - K1810 + 1500 - K1812 + 900
Physical Target: 2.818 lane-km

To:
Project Name: Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads along Marbel-Allah Valley-Cotabato Rd - K1809 + 972 - K1813 + 423.50
Physical Target: 6.903 lane-km
July 22, 2024 CY 2024 WIN4F08064 UACS No. 310101101446000 April 23, 2024 National Capital Region Metro Manila 3rd District Engineering Office
As per GAA/Original
UACS No. 310101101446000
Project ID.: P00802172LZ
OO1: Ensure Safe and Reliable National Road System

Asset Preservation Program – Preventive Maintenance – Primary Roads

MacArthur H-way – K0017+216 – K0017+388
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay – 1.032 lane km
Unit Cost (P’000) = P 15,098.84/lane km
Allocation = P 15,582,000.00
EAO = P 318,000.00
Total = P 15,900,000.00

As Modified
As per GAA/Original
UACS No. 310101101446000
Project ID.: P00802172LZ
OO1: Ensure Safe and Reliable National Road System

Asset Preservation Program – Preventive Maintenance – Primary Roads

MacArthur H-way – K0017+249 – K0017+388
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay – 0.556 lane km
Unit Cost (P’000) = P 26,502.71/lane km
Allocation = P 14,735,500.00
EAO = P 318,000.00
Excess = P 846,500.00
Total = P 15,900,000.00
Bar Code #WIN4F08064
July 22, 2024 2024 WIN4E03543 FY 2024 GAA, R.A 11975 December 25, 2023 Region XIII Agusan del Sur 1st District Engineering Office
UACS No. : 300221106980000
Project ID: P00837269MN

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - BIP - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities

FROM:

Construction of Road along Don Pedro, San Luis, Agusan del Sur

Type of Work:
CW1- Construction of Concrete Road

Physical Target:
CW1- 1.320 Lane Km

Allocation:
TOTAL: P 15,000,000
CW1: P 14,850,000
EAO: P 150,000,000

Unit Cost:
CW1: P 11,250,000/Lane Km

TO:

Construction of Road along Don Pedro, San Luis, Agusan del Sur

Type of Work:
CW1- Construction of Concrete Road
CW1- Construction of Road Slope Protection Structure

Physical Target:
CW1- 0.95 Lane Km
CW2- 462.5 Square meters

Allocation:
TOTAL: P 15,000,000
CW1: P 11,680,457
CW2: P 3,169,543
EAO: P 150,000,000

Unit Cost:
CW1: P 12,295,218/Lane Km
CW2: P 6,853/Square meters

July 22, 2024 2024 WIN4F08072 GAA FY 2024 January 1, 2024 Region VIII Leyte 1st District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Secondary Roads

AS PER GAA/ORIGINAL:

Tacloban-Baybay South Rd - K0917 + (-088.50) - K0917 + 000, K0917 + (-247) - K0917 + (-088.50), K0917 + (-263) - K0917 + (-247), K0917 + 000 - K0917 + 430

Physical Target: Allocation:

CW1- Preventive Maintenance of Road: P 17.26074 M
Asphalt Overlay: 2.772 Lane Km

EAO P 0.35226 M

Total P 17.613 M

AS MODIFIED:

Tacloban-Baybay South Rd - K0917 + (-263) - K0917 + 165

Physical Target: Allocation:

CW1- Preventive Maintenance of Road: P 17.26074 M
Asphalt Overlay: 1.712 Lane Km

EAO P 0.35226 M


Total P 17.613 M
July 22, 2024 2024 GAA FY 2024 January 1, 2024 Region VIII Tacloban City District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation – Construction/ Upgrading/ Rehabilitation of Drainage along National Roads – Tertiary Roads

AS PER GAA/ORIGINAL:

Sn Jose-Manlurip-MacArthur Park Rd - K0913 + 726 - K0914 + 761

Physical Target: Allocation:

CW1- Construction of Drainage Structure P 52.772955 M
along Road: 2,056.00 Lineal Meters

EAO P 1.914045 M

Total P 54.687 M

AS MODIFIED:

Sn Jose-Manlurip-MacArthur Park Rd - K0913 + 726 - K0914 + 074, K0914+149 - K0914+761

Physical Target: Allocation:

CW1- Construction of Drainage Structure P 52.772955 M
along Road: 1,906.00 Lineal Meters

EAO P 1.914045 M


Total P 54.687 M
July 22, 2024 2024 GAA FY 2024 March 21, 2024 Region VIII Eastern Samar District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation – Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads – Secondary Roads

AS PER GAA/ORIGINAL:

Jct Taft-Oras-Sn Policarpo-Arteche Rd - K0943 + 542 - K0943 + 893

Physical Target: Allocation:

CW1- Reconstruction to Concrete Pavement: P 7.69202 M
0.702 Lane Km

EAO P 0.15698 M

Total P 7.849 M

AS MODIFIED:

Jct Taft-Oras-Sn Policarpo-Arteche Rd - K0943+542 - K0943+634, K0943+799 - K0943+808, K0943+825 - K0943+880, K0944+144 - K0944+153, K0944+348 - K0944+371, K0944+748 - K0944+781, K0945+909 - K0946+029, K0946+177 - K0946+187, K0946+221 - K0946+261, K0953+923 - K0953+946, K0954+012 - K0954+039, K0954+302 - K0954+344, K0955+400 - K0955+424, K0955+632 - K0955+660, K0957+344 - K0957+353, K0957+466 - K0957+484

Physical Target: Allocation:

CW1- Reconstruction to Concrete Pavement: P 7.69202 M
0.680 Lane Km

EAO P 0.15698 M


Total P 7.849 M
July 22, 2024 2024 GAA FY 2024 March 21, 2024 Region VIII Eastern Samar District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation – Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads – Secondary Roads

AS PER GAA/ORIGINAL:

Wright-Taft-Borongan Rd - K0908 + 852 - K0909 + 000, K0909 + 759 - K0909 + 862, K0912 + 728 - K0912 + 828, K0916 + 320 - K0916 + 370, K0916 + 416 - K0916 + 466

Physical Target: Allocation:

CW1- Reconstruction to Concrete Pavement: P 9.92642 M
0.906 Lane Km

EAO P 0.20258 M

Total P 10.129 M

AS MODIFIED:

Wright-Taft-Borongan Rd – K0898 + 266 - K0898 + 338, K0901 + 475 - K0901 + 497, K0901 + 515 - K0901 + 529, K0905 + 525 - K0905 + 695, K0908 + 857 - K0908 + 875, K0908 + 884 - K0908 + 898, K0908 + 937 - K0908 + 944, K0908 + 957 - K0908 + 980, K0908 + 985 - K0908 + 998, K0909 + 805 - K0909 + 861, K0912 + 746 - K0912 + 798, K0916 + 320 - K0916 + 370, K0916 + 416 - K0916 + 466

Physical Target: Allocation:

CW1- Reconstruction to Concrete Pavement: P 9.92642 M
0.793 Lane Km

EAO P 0.20258 M

Total P 10.129 M

July 22, 2024 2024 GAA FY 2024 January 31, 2024 Region VIII Samar 1st District Engineering Office
OO2: Protect Lives and Properties Against Major Floods

Flood Management – Construction/ Rehabilitation of Flood Mitigation Facilities along Major River Basins and Principal Rivers

AS PER GAA/ORIGINAL:

Construction of Flood Control Structure along Gandara River, Barangay Mabuligon, Matuguinao, Samar

Physical Target: Allocation:

CW1- Construction of Food Mitigation Structure: P 49.00 M
175.00 Lineal Meters

EAO P 1.00 M

Total P 50.00 M

AS MODIFIED:

Construction of Flood Control Structure along Gandara River, Barangay Mabuligon, Matuguinao, Samar

Physical Target: Allocation:

CW1- Construction of Food Mitigation Structure: P 49.00 M
159.00 Lineal Meters
EAO P 1.00 M


Total P 50.00 M
July 22, 2024 2024 GAA FY 2024 January 31, 2024 Region VIII Samar 1st District Engineering Office
OO2: Protect Lives and Properties Against Major Floods

Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems

AS PER GAA/ORIGINAL:

Construction of Danao CIS Protection Works along the Dam, Calbayog City, Samar

Physical Target: Allocation:

CW1- Construction of Food Mitigation Structure: P 9.8 M
40.00 Lineal Meters

EAO P 0.20 M

Total P 10.00 M

AS MODIFIED:

Construction of Danao CIS Protection Works along the Dam, Calbayog City, Samar

Physical Target: Allocation:

CW1- Construction of Food Mitigation Structure: P 9.8 M
37.40 Lineal Meters
EAO P 0.20 M


Total P 10.00 M
July 22, 2024 2024 WIN4F08083 GAA FY 2024 January 1, 2024 Region VIII Leyte 1st District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation – Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads – Tertiary Roads

AS PER GAA/ORIGINAL:

Kiling-Tanauan-Tabontabon-Julita Rd – K0931 + 317 – K0931 + 363

Physical Target: Allocation:

CW1- Reconstruction to Concrete Pavement: P 4.9 M
0.230 Lane Km

EAO P 0.10 M

Total P 5.00 M

AS MODIFIED:

Kiling-Tanauan-Tabontabon-Julita Rd – K0931 + 304 – K0931 + 363

Physical Target: Allocation:

CW1- Reconstruction to Concrete Pavement: P 4.9 M
0.118 Lane Km
EAO P 0.10 M


Total P 5.00 M
July 22, 2024 2024 WIN4XY00323 GAA FY 2024 January 1, 2024 Region VIII Tacloban City District Engineering Office
Convergence and Special Support Program

Basic Infrastructure Program (BIP) – Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities

AS PER GAA/ORIGINAL:

Rehabilitation of Road with Drainage, Tacloban North Resettlement, Salvacion Heights, Tacloban City, Leyte

Physical Target: Allocation:

CW1- Rehabilitation of Paved Road: P 49.50 M
3.75 Lane Km

EAO P 0.50 M

Total P 50.00 M

AS MODIFIED:

Rehabilitation of Road with Drainage, Tacloban North Resettlement, Salvacion Heights, Tacloban City, Leyte

Physical Target: Allocation:

CW1- Rehabilitation of Paved Road : P 12.5832082 M
1.638 Lane Km

CW2 – Construction of Drainage Structure: P 36.9167918 M
2,212.00 Lineal Meters

EAO P 0.50 M


Total P 50.00 M