August 1, 2019 |
FY - 2019 |
WIN9F05761 |
FY - 2019 GAA DPWH Infra Program |
April 15, 2019 |
Region IV-B |
Palawan 2nd District Engineering Office |
UACS No. 300107200470000
Project ID: P00353445LZ
Local Program
Local - Flood Control and Drainage -
Flood Control Structures/Facilities - Local Infrastructure Program
FROM:
Construction of Danadio Flood Control, Barangay Danadio,
Brooke's Point, Palawan
CW1 - Construction of Flood Mitigation Structure - 0 lineal meter
Unit Cost - php 0/lineal meter
Allocation - Php 5.00 Million
TO:
Construction of Danadio Flood Control, Barangay Danadio,
Brooke's Point, Palawan
CW1 - Construction of Flood Mitigation Structure:
220 lineal meters
Unit Cost - Php 22.50/lineal meters
Allocation - Php 5.00 Million
|
August 1, 2019 |
FY - 2019 |
WIN9F05768 |
FY - 2019 GAA DPWH Infra Program |
April 15, 2019 |
Region IV-B |
Palawan 2nd District Engineering Office |
UACS No. 300107200472000
Project ID: P00353446LZ
Local Program
Local - flood Control and Drainage -
Flood Control Structures/Facilities - Local Infrastructure Program
FROM:
Construction of Lamikan River Flood Control, Sitio Tina Tagusao,
Barangay Tagusao, Quezon, Palawan
CW1 - Construction of Flood Mitigation Structure: 0 lineal meter
Unit Cost - Php 0/lineal meter
Allocation - Php 5.00 Million
TO:
Construction of Lamikan River Flood Control, Sitio Tina Tagusao,
Barangay Tagusao, Quezon, Palawan
CW1 - Construction of Flood Mitigation Structure -
80 lineal meters
Unit Cost - Php 61.8750/lineal meters
Allocation - Php 5.00 Million
|
August 1, 2019 |
FY - 2019 |
WIN9F05765 |
FY - 2019 GAA DPWH Infra Program |
April 15, 2019 |
Region IV-B |
Palawan 2nd District Engineering Office |
UACS No. 300107200473000
Project ID: P00353447LZ
Local Program
Local - Flood Control and Drainage -
Flood Control Structures/Facilities - Local Infrastructure Program
FROM:
Construction of Panacan II Flood Control,
Barangay Panacan II, Narra, Plawan
CW1 - Construction of Flood Mitigation Structure: 0 lineal meter
Unit Cost Php 0/lineal meter
Allocation - Php 5.00 Million
TO:
Construction of Panacan II Flood Control,
Barangay Panacan II, Narra, Palawan
CW1 - Construction of Flood Mitigation Structure:
118 lineal maters
Unit Cost - Php 41.9492/lineal meters
Allocation - Php 5.00 Million
|
August 1, 2019 |
FY - 2019 |
WIN9F05766 |
FY - 2019 GAA DPWH Infra Program |
April 15, 2019 |
Region IV-B |
Palawan 2nd District Engineering Office |
UACS No 300107200468000
Project ID: P00353443LZ
Local Program
Local - Flood Control and Drainage -
Flood Control Structures/Facilities - Local Infrastructure Program
FROM:
Construction of Bunog Flood Control, Barangay Bunog,
Rizal, Palawan
CW1 - Construction of Flood Mitigation Structure: 0 lineal meter
Unit Cost - Php 0/lineal meter
Allocation - Php 5.00 Million
TO:
Construction of Bunog Flood Control, Barangay Bunog,
Rizal, Palawan
CW1 - Construction of Flood Mitigation Structure:
50.35 lineal meters
Unit Cost - Php 98.3118/lineal meters
Allocation - Php 5.00 Million
|
August 1, 2019 |
FY - 2019 |
WIN9F05763 |
FY - 2019 GAA DPWH Infra Program |
April 15, 2019 |
Region IV-B |
Palawan 2nd District Engineering Office |
UACS No. 300107200469000
Project ID: P00353444LZ
Local Program
Local - Flood Control and Drainage -
Flood Control Structures/Facilities - Local Infrastructure Program
FROM:
Construction of Culasian Flood Control, Barangay Culasian,
Rizal, Palawan
CW1 - Construction of Flood Mitigation Structure: 0 lineal meter
Unit Cost - Php 0/lineal meter
Allocation - php 5.00 million
TO:
Construction of Culasian Flood Control, Barangay Culasian,
Rizal, Palawan
CW1 - Construction of Flood Mitigation Structure:
50.35 lineal meters
Unit Cost - Php 98.3118/lineal meters
Allocation - Php 5.00 million |
August 1, 2019 |
FY - 2019 |
WIN9F05764 |
FY - 2019 GAA DPWH Infra Program |
April 15, 2019 |
Region IV-B |
Palawan 2nd District Engineering Office |
UACS No. 300107200474000
Project ID: P00353448LZ
Local Program
Local - Flood Control and Drainage -
Flood Control Structures/Facilities - Local Infrastructure Program
FROM:
Construction of Panitian Flood Contol, Barangay Panitian,
Quezon, Palawan
CW1 - Construction of Flood Mitigation Structure: 0 lineal meter
Unit Cost - Php 0/lineal meter
Allocation - php 5.00 million
TO:
Construction of Panitian Flood Control, Barangay Panitian
Quezon, Palawan
CW1 - Construction of Flood Mitigation Structure:
50.35 lineal meters
Unit Cost - Php 98.3118/lineal meters
Allocation - Php 5.00 Million |
August 1, 2019 |
FY - 2019 |
WIN9F05767 |
FY - 2019 GAA DPWH Infra Program |
April 15, 2019 |
Region IV-B |
Palawan 2nd District Engineering Office |
UACS No. 300111200073000
Project ID: P00345370LZ
Local Program
Local - National Roads and Bridges - Local Roads
Construction/Repair/Rehabilitation/Improvement of Various infrastructure including Local Projects
FROM:
Rehabilitation/Improvement (Asphalt Overlay) along Quezon -
Punta Baja & PCR ( Rizal-Panalingan Section ),
K0196+976 - K0197+352,
K0201+377 - K0202+500,
K0204+770 - K0208+100,
Palawan
CW1 - Preventive maintenance of Road: Asphalt Overlay:
0 lane km
Unit Cost - Php 0/lane km
Allocation - Php 100.00 Million
TO:
Rehabilitation/Improvement (Asphalt Overlay) along Quezon -
Punta Baja & PCR ( Rizal - Panalingaan Section ),
K0196+976 - K0197+352,
K0201+377 - K0202+500,
K0204+770 - K0208+100,
Palawan
CW1 - Preventive maintenance of Road: Asphalt Overlay :
9.254 lane km
Unit Cost - Php 10,427.9231/lane km
Allocation - Php 100.00 Million
|
August 1, 2019 |
FY - 2019 |
WIN9F05779 |
FY - 2019 GAA DPWH Infra Program |
April 15, 2019 |
Region IV-B |
Palawan 2nd District Engineering Office |
UACS No. 300203100050000
Project ID: P00330312LZ
Convergence and Special Support program
Convergence and Special Support - Construction/Improvement of Access Roads leading to Declared Tourism Destinations
FROM:
Balabac Circumferential Road, Balabac, Palawan
CW1 - Construction of Concrete Road: 3 lane km
Unit Cost - Php 16,333.333/lane km
Allocation - Php 50.00 Million
TO:
Balabac, Circumferential Road, Balabac, Palawan
CW1 - Construction of Concrete Road : 2.24 lane km
Unit Cost - Php 21,875.00/lane km
Allocation - Php 50.00 million |
July 31, 2019 |
FY - 2019 |
WIN9F05775 |
FY - 2019 GAA DPWH Infra Program |
May 1, 2019 |
Region IV-B |
Regional Office IV-B |
UACS No. 310203100155000
Project ID: P00303422LZ
Organizational Outcome 1:
Ensure Safe and Reliable National Road System
Network Development - Road Widening - Tertiary Roads
FROM:
F.B. Reyes (Busuanga - Coron) Rd
K0015+550 - K0017+550
CW1 - Road Widening: 4 Lane Km
Allocation: Php 150.00Million
TO:
F.B.Reyes (Busuanga - Coron) Rd
K0014+951.50 - K0015+200.00,
K0015+300.00 - K0016+029.00,
K0017+843.00 - K0020+855.00
CW1 - Road Widening: 7.0015 Lane Km
Allocation: Php 150.00 Million
|
July 31, 2019 |
FY - 2019 |
WIN9F05778 |
FY - 2019 GAA DPWH Infra Program |
April 15, 2019 |
Region IV-B |
Regional Office IV-B |
UACS No. 310205100246000
Project ID: P00304063LZ
Organizational Outcome 1:
Ensure Safe and Reliable National Road System
Network Development - Construction Of Missing Links/New Roads
FROM:
Odiongan East - West Road, Romblom
CW1 - Construction of Concrete Roads: 2.942 Lane Km
Unit Cost: Php 36,654.91/Lane Km
Allocation: Php 122.526 Million
TO:
Odiongan East - West Road, Romblon
CW1 - Construction of Concrete Roads: 1.460 Lane Km
Unit Cost: Php 73,862.16/Lane Km
Allocation; Php 122.526.00 million |
July 31, 2019 |
FY - 2019 |
WIN9F05776 |
FY - 2019 GAA DPWH Infra Program |
April 15, 2019 |
Region IV-B |
Regional Office IV-B |
UACS No. 310108100191000
Project ID: P00300365LZ
Organizational Outcome 1:
Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide -
Secondary Roads
FROM:
Tablas Circumferential Road
K0034+488 - K0034+760
CW1 - Construction of Road Slope Protection Structure: 9,520 sq.m
Unit Cost - Php 15.712/sq.m.
Allocation - Php 150.00 Million
TO:
Tablas Circumferential Road
K0034+185 - K0034+568
CW1 - Construction of Road Slope Protection Structure: 6,762 sq.m
Unit Cost - Php 22.120/sq.m.
Allocation - Php 150.00 Million |
July 31, 2019 |
FY - 2019 |
WIN9F05775 |
FY - 2019 GAA DPWH Infra Program |
April 15, 2019 |
Region IV-B |
Palawan 2nd District Engineering Office |
UACS No. 310306100111000
Project ID: P00301379LZ
Organizational Outcome 001:
Ensure Safe and Reliable National Road System
Bridge - Construction of New Bridges
FROM:
Punang Br. along Puerto Princesa South Rd.
CW1 - Construction of Concrete Bridge - 301 sq.m.
Unit Cost - Php 101.3737/sq.m.
Allocation - Php 30.00 Million
TO:
Punang Br. along Puerto Princesa South Rd.
CW1 - Construction of Concrete Bridge - 304.50 sq.m.
Unit Cost - Php 96.5517/sq.m.
Allocation - Php 30.00 Million
|
July 31, 2019 |
FY - 2019 |
WIN9F05754 |
FY - 2019 GAA DPWH Infra Program |
April 15, 2019 |
Region IV-B |
Palawan 2nd District Engineering Office |
UACS No. 300107200476000
Project ID: O00353450LZ
Local Program
Local - Flood Control and Drainage -
Flood Control Control Structures/Facilities -
Local infrastructure Program
FROM:
Construction of Salungsong Flood Control, Rizal, Palawan
CW1 - Construction of Flood Mitigation Structure: 0 lineal meter
Unit Cost - Php 0/lineal meter
Allocation - Php 5.00 Million
TO:
Construction of Salungsong Flood Control, Rizal, Palawan
CW1 - Construction of Flood Mitigation Structure: 222 lineal meters
Unit Cost - Php 22.2973/lineal meters
Allocation - Php 5.00 Million |
July 31, 2019 |
FY - 2019 |
WIN9F05756 |
FY - 2019 GAA DPWH Infra Program |
April 15, 2019 |
Region IV-B |
Palawan 2nd District Engineering Office |
UACS No. 300107200475000
Project ID: P00353449 LZ
Local Program
Local - Flood Control and Drainage -
Flood Control Structures/Facilities -
Local Infrastructure Program
FROM:
Construction of Panitian Flood Control, Barangay Panitian, Sofronio Espanola, Palawan
CW1 - Construction of Flood Mitigation Structure: 0 lineal meter
Unit Coat - Php 0/lineal meter
Allocation - 5.00 Million
TO:
Construction of Panitian Flood Control, Barangay Panitian, Sofronio Espanola, Palawan
CW1 - Construction of Flood Mitigation Structure: 120 lineal meters\
Unit Cost - Php 41.25/lineal meters
Allocation - Php 5.00 Million |
July 31, 2019 |
2019 |
WIN9F05759 |
UACS No. 310111100084000 |
May 5, 2019 |
National Capital Region |
Las Piñas - Muntinlupa District Engineering Office |
As per GAA/Original
UACS No. 310111100084000
Project ID.: P00300001LZ
001: Ensure Safe and Reliable National Road System
Assets Preservation – Construction/ Upgrading/ Rehabilitation of Drainage along National Roads-
Secondary Roads
Zapote-Alabang Road (S03497LZ), K0021+-565 – K0022+386
Physical Target: CW1 = Upgrading of Drainage Structure along Road = 1,403 Lineal Meter
Unit Cost (P’000) = P12,024.73 /Lineal meter
Allocation = P 16,870,700.00
EAO = P 344,300.00
Total = P 17,215,000.00
As Modified
001: Ensure Safe and Reliable National Road System
Assets Preservation – Construction/ Upgrading/ Rehabilitation of Drainage along National Roads-
Secondary Roads
Zapote-Alabang Road (S03497LZ), K0021+335 – K0022+190
Physical Target: CW1 = Upgrading of Drainage Structure along Road = 1,078 Lineal Meter
Unit Cost (P’000) = P15,650.00 /Lineal meter
Allocation = P 16,870,700.00
EAO = P 344,300.00
Total = P 17,215,000.00
WIN9F05759
|
July 31, 2019 |
2019 |
WIN9F05769 |
UACS No. 310103100224000 |
May 5, 2019 |
National Capital Region |
Las Piñas - Muntinlupa District Engineering Office |
As per GAA/Original
UACS No. 310103100224000
Project ID.: P00302554LZ
001: Ensure Safe and Reliable National Road System
Assets Preservation – Construction/ Upgrading/ Rehabilitation of Drainage along National Roads-
Tertiary Road
International Receiver Road – K0019+330 = K0020+776
Physical Target: CW-Asphalt Overlay =8.456 Km
Unit Cost (P’000) = P6,145.83 /Lane km
EAO = P1,967,700.00
Total = P56,220,000.00
As Modified
001: Ensure Safe and Reliable National Road System
Assets Preservation – Construction/ Upgrading/ Rehabilitation of Drainage along National Roads-
Tertiary Road
International Receiver Road – K0019+(-)330 = K0019+982
Physical Target: CW-Asphalt Overlay = 5.22 Km
Unit Cost (P’000) = P10,393.16 /Lane km
EAO = P1,967,700.00
Total = P56,220,000.00
WIN9F05769
|
July 25, 2019 |
2019 |
320101103144000 |
GAA FY2019 |
May 2, 2019 |
Region II |
Isabela 2nd District Engineering Office |
OO2: Protect Lives and Properties - Flood Management - Construction/Maintenance of Flood Mitigation Structures and Drainage Systems: Construction of Mallig River Flood Control Project (Rang Ayan Section), Mallig, Isabela |
October 17, 2018 |
FY 2018 |
WIN8C03350 |
310107100015000 |
May 14, 2018 |
Region IX |
Regional Office IX |
UACS No. 310107100015000
Project ID: P002000185MN
OO1: Ensure Safe and Reliable National Road System
Asset Preservation/Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse and Landslide - Primary Roads
Lanao - Pagadian - Zamboanga City Road
Physical Target:
CW 1 - Const. of Road Slope Protection: 6,959.80 sq.m
Unit Cost: P 15,857.70/sq.m
ROW: 2,028.61 sq.m
Unit Cost: P 300/sq.m
EAO: P 4,025,000.00
Allocation: P 115,000,000 |
October 17, 2018 |
FY 2018 |
WIN8C03350 |
310107100015000 |
May 14, 2018 |
Region IX |
Regional Office IX |
UACS No. 310107100015000
Project ID: P002000185MN
OO1: Ensure Safe and Reliable National Road System
Asset Preservation/Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse and Landslide - Primary Roads
Lanao - Pagadian - Zamboanga City Road
Physical Target:
CW 1 - Const. of Road Slope Protection: 6,959.80 sq.m
Unit Cost: P 15,857.70/sq.m
ROW: 2,028.61 sq.m
Unit Cost: P 300/sq.m
EAO: P 4,025,000.00
Allocation: P 115,000,000 |
October 17, 2018 |
FY 2018 |
WIN8C03350 |
310107100015000 |
May 14, 2018 |
Region IX |
Regional Office IX |
UACS No. 310107100015000
Project ID: P002000185MN
OO1: Ensure Safe and Reliable National Road System
Asset Preservation/Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse and Landslide - Primary Roads
Lanao - Pagadian - Zamboanga City Road
Physical Target:
CW 1 - Const. of Road Slope Protection: 6,959.80 sq.m
Unit Cost: P 15,857.70/sq.m
ROW: 2,028.61 sq.m
Unit Cost: P 300/sq.m
EAO: P 4,025,000.00
Allocation: P 115,000,000 |
August 23, 2018 |
FY 2018 |
REG8XL00910 |
UACS No. 310204100161000 |
May 10, 2018 |
Region IX |
Regional Office IX |
UACS No. 310204100161000
Project ID: P00200301MN
OO1: Ensure Safe and Reliable National Road System
Network Development - Construction of Bypass and Diversion Roads
Labangan-Pagadian City-Dumalinao ZDS Bypass Road, incl. ROW, Zamboanga del Sur
Physical Target:
CW1- Construction of Concrete Road: 12.80 lane km
Unit Cost: P 18,879,025.60/lane km
ROW: 159,494.91sq.m
Unit Cost: P 300/sq.m.
EAO: P 10,500,000.00
Allocation: P 300,000,000.00 |
August 4, 2018 |
2018 |
WIN8F05595 |
R.A. 10964 |
December 19, 2017 |
Region VII |
Regional Office VII |
Organizational Outcome 1: Ensure Safe and Reliable National Road System, Network Development - Construction of Flyovers/ Interchanges/ Underpasses/ Long Span Bridges, Panglao-Tagbilaran City Offshore Connector, Bohol |
August 4, 2018 |
2018 |
WIN8F05559 |
R.A. 10964 |
December 19, 2017 |
Region VII |
Cebu 4th District Engineering Office |
Organizational Outcome 1: Ensure safe and Reliable National Road System, Network Development-Road Widening of Primary Roads, N. Bacalso Ave. (Cebu South Road) incl. ROW - K0131+000 - K0131+776 |
August 4, 2018 |
2018 |
WIN8F05611 |
R.A. 10964 |
December 19, 2017 |
Region VII |
Cebu 4th District Engineering Office |
Organizational Outcome 1: Ensure safe and Reliable National Road System, Network Development-Road Widening of Secondary Roads, Santander-Barili-Toledo Rd. - K0214+884 - K0216+100 |
August 4, 2018 |
2018 |
WIN8F05683 |
R.A. 10964 |
December 19, 2017 |
Region VII |
Negros Oriental 1st District Engineering Office |
LOCAL PROGRAM: Local Infrastructure Program- Local Roads and Bridges- Local Roads -Construction of Foot Bridge, Brgy. Solonggon-Mandapaton-Cangabo, La Libertad, Negros Oriental |
August 4, 2018 |
2018 |
WIN8F05575 |
R.A. 10964 |
December 19, 2017 |
Region VII |
Bohol 1st District Engineering Office |
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/Improvement of Access Roads leading to Declared Tourism Destinations - Jct. TCSR Abucay Norte - Can-agong leading to Lake Linaw, Sikatuna Tree Park & Tarsier Conservation Area, Brgy.Can-agong, Sikatuna, Bohol |
August 4, 2018 |
2018 |
WIN8F05584 |
R.A. 10964 |
December 19, 2017 |
Region VII |
Bohol 1st District Engineering Office |
LOCAL PROGRAM - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects - Local Roads and Bridges - Local Roads - Road Concreting Brgy. Dipatlong (1 KM), Maribojoc, Bohol |
August 4, 2018 |
2018 |
WIN8F05577 |
R.A. 10964 |
December 19, 2017 |
Region VII |
Bohol 1st District Engineering Office |
LOCAL PROGRAM - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects - Water Management Facilities - Water Supply - Construction of Water Supply System Level III, Barangay Poblacion - Alegria - Candumayao - Baang - Liboron - Triple Union, Catigbian, Bohol |
August 4, 2018 |
2018 |
WIN8F05579 |
R.A. 10964 |
December 19, 2017 |
Region VII |
Bohol 1st District Engineering Office |
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads - Jct.(TNR) Cortes-Balilihan-Catigbian Macaas Rd. K0009+(-090) - K0009+020, K0017+250 - K0017+330, K0027+550 - K0027+600, K0044+506.580 - K0044+521.900, K0045+600 - K0045+847 |
August 4, 2018 |
2018 |
WIN8F05582 |
R.A. 10964 |
December 19, 2017 |
Region VII |
Bohol 1st District Engineering Office |
LOCAL PROGRAM - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects - Road Concreting Brgy. Jandig (1KM), Maribojoc, Bohol |
August 4, 2018 |
2018 |
WIN8F05583 |
R.A. 10964 |
December 19, 2017 |
Region VII |
Bohol 1st District Engineering Office |
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Secondary Roads - Tagbilaran North Rd (Tagbilaran-Jetafe Sect) - K0006+060 -K0006+237 |
August 4, 2018 |
2018 |
WIN8F05580 |
R.A. 10964 |
December 19, 2017 |
Region VII |
Bohol 1st District Engineering Office |
LOCAL PROGRAM - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects - Concreting of Jct. San Isidro - Binayran - Dampas Road, Sta. 00+000 - Sta. 00+315.37, Sta. 00+435 - Sta. 01+225, Tagbiliaran City |
August 4, 2018 |
2018 |
WIN8F05581 |
R.A. 10964 |
December 19, 2017 |
Region VII |
Bohol 1st District Engineering Office |
LOCAL PROGRAM - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects - Road Concreting, Tagbilaran City |
August 4, 2018 |
2018 |
WIN8F05576 |
R.A. 10964 |
December 19, 2017 |
Region VII |
Bohol 1st District Engineering Office |
LOCAL PROGRAM - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects - Concreting of Road Bicahan-Bantolinao, Antequera, Bohol |
August 4, 2018 |
2018 |
WIN8F05597 |
R.A. 10964 |
December 19, 2017 |
Region VII |
Bohol 1st District Engineering Office |
ORGANIZATIONAL OUTCOME 2: Protect Lives and Properties - Construction / Maintenance of Flood Mitigation Structures and Drainage Systems - Construction of Sal-ing River Control, Balilihan, Bohol |
August 4, 2018 |
2018 |
WIN8F05688 |
R.A. 10964 |
December 19, 2017 |
Region VII |
Bohol 1st District Engineering Office |
LOCAL PROGRAM - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects - Widening and Concreting of Hangos Road, Tagbilaran City (Road leading to new Provincial Capitol |
August 4, 2018 |
2018 |
WIN8F05687 |
R.A. 10964 |
December 19, 2017 |
Region VII |
Bohol 1st District Engineering Office |
ORGANIZATIONAL OUTCOME 2: Protect Lives and Properties Flood Management Program -Construction /Maintenance of Flood Control Mitigation Structure and Drainage Systems - Construction of Cantomimbo River Control, Balilihan, Bohol |
August 4, 2018 |
2018 |
WIN8F05686 |
R.A. 10964 |
December 19, 2017 |
Region VII |
Bohol 1st District Engineering Office |
ORGANIZATIONAL OUTCOME 2: Protect Lives and Properties Flood Management Program -Construction /Maintenance of Flood Control Mitigation Structure and Drainage Systems - Construction of Antequera River Control, Antequera, Bohol |
July 27, 2018 |
FY 2018 |
WIN8G02508 |
FY 2018 GAA |
January 4, 2018 |
Region III |
Nueva Ecija 1st District Engineering Office |
Asset Preservation Program – Preventive Maintenance – Primary Roads – San Jose – Lupao Rd, K0160+000 – K0160+778, K0172+299.40 – K0172+565, K0172+592.20 – K0173+716.40 |
July 26, 2018 |
FY 2018 |
WIN8G02509 |
FY 2018 GAA |
January 4, 2018 |
Region III |
Tarlac District Engineering Office |
Asset Preservation Program - Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Anao - Ramos Rd - K0159 + (-504.40) - K0160 + 624.60, K0162 + 303 - K0163 + 206.50, K0163 + 206.50 - K0163 + 374 , K0164 + 942 - K0166+800 |
July 24, 2018 |
2018 |
WIN8C02894 |
GAA FY 2018 |
January 1, 2018 |
Region VIII |
Tacloban City District Engineering Office |
Organizational Outcome 1: Ensure Safe and Reliable National Road System
Asset Preservation - Construction / Upgrading / Rehabilitation of Drainage along National Roads - Primary Roads
FROM:
Daang Maharlika (LT) - K0901 + 1026 - K0902 + 929
Physical Target: Allocation:
CW1- Upgrading of Drainage Structure P 47.726 M
along Road -944 lineal meters
EAO P 0.974 M
Total Allocation: P 48.700 M
AS MODIFIED:
Daang Maharlika (LT) - K0901 + 1026 - K0902 + 933
Physical Target: Allocation:
CW1- Upgrading of Drainage Structure P 47.726 M
along Road -2,690 lineal meters
EAO P 0.974 M
Total Allocation: P 48.700 M |
July 24, 2018 |
2018 |
WIN8C02415 |
GAA FY 2018 |
January 1, 2018 |
Region VIII |
Tacloban City District Engineering Office |
Organizational Outcome 1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Secondary Roads
FROM:
Rizal Avenida Ext Rd - K0905 + -909 - K0905+-736, K0905+-485 - K0905+-440
Physical Target: Allocation:
CW1-Road Widening-0.436 Lane Km P 8.526 M
EAO- P 0.174 M
Total Allocation: P 8.700 M
AS MODIFIED:
Rizal Avenida Ext Rd - K0905 + -909 - K0905+-733, K0905+-733 - K0905+-705, K0905+-480-K0905+-471, K0905+-471-K0905+-440
Physical Target: Allocation:
CW1-Road Widening-0.451 Lane Km P 8.526 M
EAO- P 0.174 M
Total Allocation: P 8.700 M |
July 24, 2018 |
2018 |
WIN8F05225 |
GAA FY 2018 |
January 1, 2018 |
Region VIII |
Tacloban City District Engineering Office |
Organizational Outcome 1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
FROM:
Rizal Avenida Ext Rd - K0905+-836 - K0905+-736
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 2.254 M
Structure-321 Sq.m
EAO- P 0.046 M
Total Allocation: P 2.300 M
AS MODIFIED:
Rizal Avenida Ext Rd - K0905+-805 - K0905+-705
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 2.254 M
Structure-321.31 Sq.m
EAO- P 0.046 M
Total Allocation: P 2.300 M |
July 24, 2018 |
2018 |
WIN8C02384 |
GAA FY 2018 |
January 1, 2018 |
Region VIII |
Tacloban City District Engineering Office |
Local Program
Local Infrastructure Program-National Roads and Bridges-National Roads
FROM:
Improvement/Widening of San Jose-Manlurip-McArthur Park Road, K0913+000-K0914+056, Tacloban City
Physical Target: Allocation:
CW1-Improvement/Widening of P 36.630 M
Road-2.093 Lane Km
EAO- P 0.370 M
Total Allocation: P 37.00 M
AS MODIFIED:
Improvement/Widening of San Jose-Manlurip-McArthur Park Road, K0913+000-K0914+756, Tacloban City
Physical Target: Allocation:
CW1-Improvement/Widening of P 36.630 M
Road-3.498 Lane Km
EAO- P 0.370 M
Total Allocation: P 37.00 M |
July 24, 2018 |
2018 |
WIN8C02893 |
GAA FY 2018 |
January 30, 2018 |
Region VIII |
Tacloban City District Engineering Office |
Organizational Outcome 2: Protect lives and Properties Against Major Floods
Flood Management Program: Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
FROM:
Construction/Rehabilitation of Flood Control Structure at Tanghas-Lirang Creek, Mahayahay creek, Baruguan River, Kawayan River and Suhi River, Tacloban City
Physical Target: Allocation:
CW1- Construction of Flood Mitigation P 93.875 M
Structure- 850 lineal meters
EAO- P 3.405 M
Total Allocation: P 97.280 M
AS MODIFIED:
Construction/Rehabilitation of Flood Control Structure at Tanghas-Lirang Creek, Mahayahay Creek, Baruguan River, Kawayan River and Suhi River, Tacloban City
Physical Target: Allocation:
CW1- Construction of Flood Mitigation P 93.875 M
Structure- 2,180 lineal meters
EAO- P 3.405 M
Total Allocation: P 97.280 M
|
July 24, 2018 |
2018 |
WIN8C02382 |
GAA FY 2018 |
January 1, 2018 |
Region VIII |
Tacloban City District Engineering Office |
Organizational Outcome1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
FROM:
Tigbao-Sta Fe-Sn Miguel Rd - K0912 + (-180) - K0912 + (-144), K0914 + 023 - K0914 + 080, K0914 + 056 - K0914 + 071, K0914 + 118 - K0914 + 163, K0914 + 153 - K0914 + 431, K0914 + 247 - K0914 + 431
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 49.00 M
Structure-3,891 Sq.m
EAO- P 1.00 M
Total Allocation: P 50.00 M
AS MODIFIED:
Tigbao-Sta Fe-Sn Miguel Rd - K0912 + (-180) - K0912 + (-080), K0914 + (-300) - K0914 + (- 080), K0914 + 023 - K0914 + 080, K0914 + 056 - K0914 + 071, K0914 + 118 - K0914 + 163, K0914 + 153 - K0914 + 431, K0914 + 247 - K0914 + 431
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 49.00 M
Structure-3,578.25 Sq.m
EAO- P 1.00 M
Total Allocation: P 50.00 M |
July 24, 2018 |
2018 |
WIN8C02830 |
GAA FY 2018 |
January 1, 2018 |
Region VIII |
Tacloban City District Engineering Office |
Organizational Outcome1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
FROM:
Tigbao-Sta Fe-Sn Miguel Rd - K0904 +194 - K0904 + 360, K0905 + (-215) - K0905 + (-131), K0905 + 450 - K0905 + 586, K0905 + 561 - K0905 + 586, K0908 + (-382) - K0908 + (-365), K0908 + (-484) - K0908 + (-370), K0908 + (-690) - K0908 + (-640)
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 49.00 M
Structure-3,196 Sq.m
EAO- P 1.00 M
Total Allocation: P 50.00 M
AS MODIFIED:
Tigbao-Sta Fe-Sn Miguel Rd - K0904 +194 - K0904 + 360, K0905 + (-215) - K0905 + (-131), K0905 + 400 - K0905 + 586, K0905 + 561 - K0905 + 586, K0908 + (-549) - K0908 + (-476), K0908 + (-421) - K0908 + (-275), K0908 + (-382) - K0908 + (-365)
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 49.00 M
Structure-3,694 Sq.m
EAO- P 1.00 M
Total Allocation: P 50.00 M |
July 24, 2018 |
2018 |
WIN8C02878 |
GAA FY 2018 |
January 31, 2018 |
Region VIII |
Leyte 4th District Engineering Office |
OO2: Protect Lives and Properties
Flood Management-Construction/Rehabilitation of Flood Mitigation Facilities along Major River Basins and Principal Rivers
FROM:
Improvement/Rehabilitation/Rechanneling of Pagsanga-an River including Dredging at Pagsanga-an River Mouth A, Brgy. San Juan, Ormoc City, Leyte
Physical Target: Allocation:
CW1-Construction of Flood Mitigation P 96.500 M
Structure-600.00 Lineal Meter
EAO- P 3.500 M
Total Allocation: P 100.00 M
AS MODIFIED:
Improvement/Rehabilitation/Rechanneling of Pagsanga-an River including Dredging at Pagsanga-an River Mouth A, Brgy. San Juan, Ormoc City, Leyte
Physical Target: Allocation:
CW1-Construction of Flood Mitigation P 96.500 M
Structure-500.00 Lineal Meter
EAO- P 3.500 M
Total Allocation: P 100.00 M
|
July 24, 2018 |
2018 |
WIN8C02418 |
GAA FY 2018 |
March 20, 2018 |
Region VIII |
Leyte 4th District Engineering Office |
Organizational Outcome1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Primary Roads
FROM:
Asphalt Overlay with Thermoplastic Pavement Markings along Palo-Carigara-Ormoc Road K0994+850 - K0999+000
Physical Target: Allocation:
CW1-Preventive Maintenance of Road: P 96.500 M
Asphalt Overlay-8.342 Lane Km
EAO- P 3.500 M
Total Allocation: P 100.00 M
AS MODIFIED:
Asphalt Overlay with Thermoplastic Pavement Markings along Palo-Carigara-Ormoc Road K0996+335 - K0998+916
Physical Target: Allocation:
CW1-Preventive Maintenance of Road: P 96.500 M
Asphalt Overlay-10.556 Lane Km
EAO- P 3.500 M
Total Allocation: P 100.00 M |
July 23, 2018 |
2018 |
WIN8F05693 |
GAA FY 2018 |
January 27, 2018 |
Region VIII |
Regional Office VIII |
Organizational Outcome 1: Ensure Safe and Reliable National Road System
Network Development - Construction of By-Pass and Diversion Roads
FROM:
Ormoc City Diversion Road (Brgy. San Juan-Lao-Naungan) incl. ROW, Package C, Leyte
Physical Target: Allocation:
CW1-Construction of Concrete Road- P 386.00 M
20.00 Lane Km
EAO P 14.00 M
Total Allocation: P 400.00 M
AS MODIFIED:
Ormoc City Diversion Road (Brgy. San Juan-Lao-Naungan) incl. ROW, Package C, Leyte
Physical Target: Allocation:
CW1-Construction of Concrete Road- P 17.093 M
2.16 Lane Km
CW2-Construction of Gravel Road- P 113.059 M
6.504 Lane Km
CW3- Construction of Road Slope Protection P 240.848 M
Structure-5,400 Sq.m
ROW- ROW Acquisition-21,600 Sq.m P 15.00 M
EAO P 14.00 M
Total Allocation: P 400.00 M |
July 23, 2018 |
2018 |
WIN8F05694 |
GAA FY 2018 |
January 29, 2018 |
Region VIII |
Regional Office VIII |
Organizational Outcome 1: Ensure Safe and Reliable National Road System
Network Development - Construction of By-Pass and Diversion Roads
FROM:
Construction of Concrete Road-Ormoc City Diversion Road (Brgy. San Juan-Lao-Naungan) Package C, Leyte
Physical Target: Allocation:
CW1-Construction of Concrete Road- P 193.00 M
10.00 Lane Km
EAO- P 7.00 M
Total Allocation: P 200.00 M
AS MODIFIED:
Construction of Concrete Road-Ormoc City Diversion Road (Brgy. San Juan-Lao-Naungan) Package C1, Leyte
Physical Target: Allocation:
CW1-Construction of Concrete Road- P 12.176 M
1.32 Lane Km
CW2-Construction of Gravel Road- P 35.695 M
1.98 Lane Km
CW3-Construction of Road Slope Protection P 145.129 M
Structure-3,300 Sq.m
EAO- P 7.00 M
Total Allocation: P 200.00 M |
July 23, 2018 |
2018 |
WIN8C02421 |
GAA FY 2018 |
January 1, 2018 |
Region VIII |
Tacloban City District Engineering Office |
Organizational Outcome1: Ensure Safe and Reliable National Road System
Asset Preservation - Construction / Upgrading / Rehabilitation of Drainage along National Roads - Tertiary Roads
FROM:
Avenida Veteranos St - Chainage 197 - Chainage 535, Chainage 347 - Chainage 529
Physical Target: Allocation:
CW1-Construction of Drainage Structure- P 10.780 M
510 linear meters
EAO- P 0.220 M
Total Allocation: P 11.00 M
AS MODIFIED:
Avenida Veteranos St - Chainage 110 - Chainage 430
Physical Target: Allocation:
CW1-Construction of Drainage Structure- P 10.780 M
630 linear meters
EAO- P 0.220 M
Total Allocation: P 11.00 M |
July 23, 2018 |
2018 |
WIN8C02877 |
GAA FY 2018 |
January 1, 2018 |
Region VIII |
Tacloban City District Engineering Office |
Local-Flood Control and Drainage-Drainage/Protection Works
Construction/Repair/Rehabilitation/Improvement of various Infrastructure Including Local Projects
FROM:
Construction of Drainage System, along Main Road of Brgy. 110 Utap, Tacloban City
Physical Target: Allocation:
CW1-Construction of Drainage Structure- P 9.90 M
850 lineal meters
EAO- P 0.10 M
Total Allocation: P 10.00 M
AS MODIFIED:
Construction of Drainage System, along Main Road of Brgy. 110 Utap, Tacloban City
Physical Target: Allocation:
CW1-Construction of Drainage Structure- P 9.90 M
600 lineal meters
EAO- P 0.10 M
Total Allocation: P 10.00 M |
July 20, 2018 |
FY 2018 |
WIN8G02514 |
FY 2018 GAA |
January 4, 2018 |
Region III |
Pampanga 2nd District Engineering Office |
Local Roads and Bridges - Local Roads – Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects - Improvement / Concreting of Sapang Uwak Road leading to Miyamit Falls, Porac Pampanga |
July 20, 2018 |
FY 2018 |
WIN8G02513 |
FY 2018 GAA |
January 4, 2018 |
Region III |
Pampanga 2nd District Engineering Office |
Local Roads and Bridges - Local Roads – Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects - Reconstruction (Completion) of Sta. Ursula Bridge, Betis, Guagua, Pampanga |
July 17, 2018 |
FY 2018 |
WIN8G02339 |
FY 2018 GAA R.A. 10964 |
December 29, 2017 |
Region V |
Albay 2nd Engineering Office |
UACS No.: 300106200017000
Project ID: P00257546LZ
LOCAL PROGRAM – Local - Flood Control and Drainage - Flood Control Structures / Facilities - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects - Construction of Flood Mitigation along Taysan River, Legazpi City
Physical Target: CW1 – Construction of Flood Mitigation Structure/ 802.00 lm
Unit Cost: CW1 – Php 60.16T/lm.
Estimated Cost: Php 50.0 M
(As Modified)
|
July 17, 2018 |
FY 2018 |
WIN8G02348 |
FY 2018 GAA R.A. 10964 |
December 29, 2017 |
Region V |
Albay 2nd Engineering Office |
UACS No.: 300106200008000
Project ID: P00257537LZ
LOCAL PROGRAM – Flood Control and Drainage - Flood Control Structures/ Facilities - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects - Construction of Flood Control Structures along Matanag River (Upstream) - Sta. 0+460 - Sta. 0+910 (B/S), Legazpi City
Physical Target: CW1 – Construction of Flood Mitigation Structure/ 900 lm
Unit Cost: CW1 – Php 107.22T/lm.
Estimated Cost: Php 100.0 M
(As Modified)
|
July 17, 2018 |
FY 2018 |
WIN8G02332 |
FY 2018 GAA R.A. 10964 |
December 29, 2017 |
Region V |
Albay 2nd Engineering Office |
UACS No.: 320102100424000
Project ID: P00221296LZ
OO2: Protect Lives and Properties Against Major Floods – Flood Management Program – Construction/Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers – Construction/Improvement of Quirangay River Course (Poblacion Section), Sta. 0+000 - Sta. 0+125.30, Sta. 0+005 - Sta. 0+063, Sta. 0+025 - Sta. 0+125.30, Sta. 0+005 - Sta. 0+063, Albay
Physical Target: CW1 – Construction of Flood Mitigation Structure/ 341.60 lm
Unit Cost: CW1 – Php 71.721T/lm.
Estimated Cost: Php 25.00 M
(As Modified)
|
July 16, 2018 |
FY - 2018 |
WIN8F05662 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Regional Office IV-B |
Local Program
Local Roads and Bridges - Local Roads
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects
FROM:
Widening of Puerto Princesa South Road
from two (2) to six (6) lanes including drainage
and other ancillary works,
K0111+300 - K0113+800,
Narra
CW1: 9.812 lane km
Allocation: 150,000,000 Php
TO:
Widening of Puerto Princesa Road
from to (2) to six (6) lanes including drainage
and other ancillary works,
K0110+440 - K0110+740,
K0111+300 - K0111+439,
K0111+455 - K0111+677,
K0111+693 - K0113+714,
K0111+736 - K0113+770,
Narra
CW1: 10.892 lane km
Allocation: 150,000,000 Php
|
July 16, 2018 |
FY - 2018 |
WIN8F05663 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Regional Office IV-B |
Local Program
Local roads and Bridges - Local Roads
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects
FROM:
Widening of Puerto Princesa South Road
from two (2) to six (6) lanes including
drainage and other ancillary works,
K0232+100 - K0234+300,
Bataraza
CW1: 9.248 lane km
Allocation: 135,000,000 Php
TO:
Widening of Puerto Princesa South Road
from two (2) to six (6) lanes including
drainage and other ancillary works,
K0232+171 - K0234+460,
Bataraza
CW1: 9.604 lane km
Allocation: 135,000,000 Php |
July 16, 2018 |
FY - 2018 |
Win8F05654 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Regional Office IV-B |
Local program
Local Roads and Bridges - Local Roads
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects
FROM:
Widening of Puerto Princesa Road
from two (2) to six (6) lanes including
drainage and other ancillary works,
K0226+400 - K228+900,
CW1: 9.784 lane km
Allocation: 150,000,000 Php
TO:
Widening of Puerto Princesa South Road
from two (2) to six (6) lanes including
drainage and other ancillary works,
K0226+400 - K0226+5378,
K0226+562 - K0228+954,
Bataraza
CW1: 10.00 lane km
Allocation: 150,000,000 Php
|
July 16, 2018 |
FY 2018 |
WIN8G02338 |
FY 2018 GAA R.A. 10964 |
December 29, 2017 |
Region V |
Masbate 1st District Engineering Office |
UACS No.: 300106200114000
Project ID: P00257615LZ
Local Infrastructure Program – Flood Control and Drainage - Flood control Structures / facilities - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects - Construction of Seawall along the coast of Barangay Poblacion East to Brgy. Poblacion West, Milagros, Masbate
Physical Target: CW1 – Construction of Flood Mitigation Structure/ 358.75 lm
Unit Cost: CW1 – Php 55.19 T/lm
Estimated Cost: Php 20.0 M
(As Modified)
|
July 16, 2018 |
FY 2018 |
WIN8G02502 |
FY 2018 GAA R.A. 10964 |
December 29, 2017 |
Region V |
Regional Office V |
UACS No.: 300201100014000
Project ID: P00230380LZ
Convergence and Special Support Program –
Construction/Improvement of Access Roads leading to Airports – Jct. DM (Tabon-tabon)-Mariawa-Homapon-Maslog-Lamba-Puro Road leading to Bicol International Airport, Albay
Physical Target: CW1 – Road Widening/ 5.998 lane-km
CW2 - Construction of Drainage Structure along Road/ 4,340 lm.
CW3 - Construction of Road Slope Protection Structure/ 6,687.65 sq.m
Unit Cost: CW1 – Php 16.85 M/lane-km
CW2 – Php 11,042.74/lm.
CW3 – Php 2,248.12/sq.m.
Estimated Cost: Php 170.0 M
(As Modified)
|
July 16, 2018 |
FY 2018 |
WIN8G02503 |
FY 2018 GAA R.A. 10964 |
December 29, 2017 |
Region V |
Regional Office V |
UACS No.: 310204100075000
Project ID: P00201069LZ
OO1: Ensure Safe and Reliable National Road System - Network Development Program – Construction of By-Pass and Diversion Roads - Camarines Sur-Albay Diversion Road (Camarines Sur Section), Camarines Sur
Physical Target: CW1 – Reconstruction of Concrete Road/ 4.8524 lane-km
CW2 - Construction of Road Slope Protection Structure/ 4,217.62 sq.m.
Right-of-Way Acquisition (ROW)/ 72,786 sq.m.
Unit Cost: CW1 – Php 30.10 M/lane-km
CW2 – Php 8,813.40/sq.m.
ROW Acquisition – Php 134.23/sq.m.
Estimated Cost: Php 200.0 M
(As Modified)
|
July 16, 2018 |
FY 2018 |
WIN8G02503 |
FY 2018 GAA R.A. 10964 |
December 29, 2017 |
Region V |
Regional Office V |
UACS No.: 310204100075000
Project ID: P00201069LZ
OO1: Ensure Safe and Reliable National Road System - Network Development Program – Construction of By-Pass and Diversion Roads - Camarines Sur-Albay Diversion Road (Camarines Sur Section), Camarines Sur
Physical Target: CW1 – Reconstruction of Concrete Road/ 4.8524 lane-km
CW2 - Construction of Road Slope Protection Structure/ 4,217.62 sq.m.
Right-of-Way Acquisition (ROW)/ 72,786 sq.m.
Unit Cost: CW1 – Php 30.10 M/lane-km
CW2 – Php 8,813.40/sq.m.
ROW Acquisition – Php 134.23/sq.m.
Estimated Cost: Php 200.0 M
(As Modified)
|
July 13, 2018 |
2018 |
WIN8F05501 |
GAA FY 2018 |
January 29, 2018 |
Region VIII |
Leyte 3rd District Engineering Office |
Organizational Outcome1: Ensure Safe and Reliable National Road System
Network Development - Off-Carriageway Improvement - Tertiary Roads
FROM:
Tabango-Catmon-La Fortuna-Manlawaan-Gimarco Rd - K1036 + 800 - K1038 + 445
Physical Target: Allocation:
CW1-Off-Carriageway Improvement: P 96.50 M
Shoulder Paving / Construction-
10,004.00 sq.m.
EAO P 3.50 M
Total Allocation: P 100.00 M
AS MODIFIED:
Tabango-Catmon-La Fortuna-Manlawaan-Gimarco Rd - K1036 + 800 - K1038 + 000
Physical Target: Allocation:
CW1-Off-Carriageway Improvement: P 25.483 M
Shoulder Paving / Construction-
7,959.50 sq.m.
CW2-Construction of Slope Protection P 71.017 M
Structure-4,605.00 sq.m.
EAO P 3.50 M
Total Allocation: P 100.00 M |
July 13, 2018 |
2018 |
WIN8F05635 |
GAA FY 2018 |
January 30, 2018 |
Region VIII |
Samar 2nd District Engineering Office |
Organizational Outcome1: Ensure Safe and Reliable National Road System
Bridge - Widening of Permanent Bridges
FROM:
Silaga Br. (B00397SM) along Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br)
Physical Target: Allocation:
CW1-Widening of Bridge- 539.00 Square Meter P 38.208210 M
EAO P 1.385790 M
Total Allocation: P 39.594 M
AS MODIFIED:
Silaga Br. (B00397SM) along Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br)
Physical Target: Allocation:
CW1-Widening of Bridge- 269.50 Square Meter P 38.208210 M
EAO P 1.385790 M
Total Allocation: P 39.594 M |
July 13, 2018 |
2018 |
WIN8F05625 |
GAA FY 2018 |
January 27, 2018 |
Region VIII |
Samar 2nd District Engineering Office |
Organizational Outcome 1: Ensure Safe and Reliable National Road
System
Network Development - Construction of By-Pass and Diversion Roads
FROM:
Basey-Maydolong Road, Including ROW and Bridge, Samar
Physical Target: Allocation:
ROW Acquisition-80,000 square meters P 4.825 M
CW1-Construction of Gravel Road- P 24.125 M
8.00 Lane Km
CW2-Construction of Concrete Bridge- P 9.650 M
334.00 square meter
CW3-Construction of Concrete Road- P 9.650 M
4.00 Lane Km
EAO P 1.750 M
Total Allocation: P 50.00 M
AS MODIFIED:
Basey-Maydolong Road, Samar
Physical Target: Allocation:
CW1-Construction of Concrete Road- - P 49.00 M
5.050 Lane Km
EAO P 1.00 M
Total Allocation: P 50.00 M |
July 12, 2018 |
2018 |
WIN8G02500 |
SR2018-02-003215 |
February 1, 2018 |
Region III |
Regional Office III |
Local Program - Local Roads and Bridges
LocaL Roads
Construction/Improvement/Upgrading of Lubao-Guagua-Minlain-Sto. Tomas Road, Pampanga
Allotment: PHP 1 BILLION
CW-1: Construction of Gravel Road / 55.000ln-km
CW-2: Construction of Drainage Structure along Road / 380 lm
ROW: ROW Acquisition / 466,666.67 sq.m. |
July 12, 2018 |
2018 |
WIN8G02507 |
SR2018-02-003447 |
February 1, 2018 |
Region III |
Regional Office III |
Local Program - Local Roads and Bridges
Local Bridges
Construction of Ciudad de Victoria Interchange Overpass Bridge, Bocaue, Bulacan
Allotment: PHP 300 MILLION
CW-1: Construction of Concrete Road / 6.399ln-km
CW-2: Construction of Concrete Bridge / 1,526.40sq.m.
ROW: ROW Acquisition / 51,152sq.m. |
July 12, 2018 |
2018 |
WIN8F05215 |
GAA FY 2018 |
January 1, 2018 |
Region VIII |
Eastern Samar District Engineering Office |
Local Projects
Local Roads and Bridges-Local Roads-Local Infrastructure Program
FROM:
Construction/Repair/Rehabilitation of Road, Barangay Nato to Barangay Bongdo, Borongan, Eastern Samar
Physical Target: Allocation:
CW1-Construction of Concrete Road- P 9.900 M
0.967 Lane Km
EAO P 0.100 M
Total Allocation: P 10.00 M
AS MODIFIED:
Construction/Repair/Rehabilitation of Road, Barangay Nato to Barangay Bongdo, Taft, Eastern Samar
Physical Target: Allocation:
CW1-Construction of Concrete Road- P 9.900 M
1.620 Lane Km
EAO P 0.100 M
Total Allocation: P 10.00 M
|
July 12, 2018 |
2018 |
WIN8F05502 |
GAA FY 2018 |
March 20, 2018 |
Region VIII |
Biliran District Engineering Office |
Local Program
Local- National Roads and Bridges- Local Roads- Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
FROM:
Road Opening and Concreting of Access Road going to Germohenes Waterfalls, Biliran
Physical Target: Allocation:
CW1-Construction of Concrete Road- P 96.500 M
7.00 Lane Km
EAO P 3.500 M
Total Allocation: P 100.00 M
AS MODIFIED:
Road Opening and Concreting of Access Road going to Germohenes Waterfalls, Biliran
Physical Target: Allocation:
CW1-Construction of Concrete Road- P 96.500 M
5.80 Lane Km
EAO P 3.500 M
Total Allocation: P 100.00 M
|
July 12, 2018 |
2018 |
WIN8F05542 |
GAA FY 2018 |
January 1, 2018 |
Region VIII |
Biliran District Engineering Office |
Organizational Outcome 1: Ensure Safe and Reliable National Road System
Asset Preservation - Construction / Upgrading / Rehabilitation of Drainage along National Roads - Secondary Roads
FROM:
Naval-Caibiran Cross Country Rd - K1027+361 - K1027+660, K1027+788 - K1027+890, K1028 + 770 - K1029 + 740, K1030 + 150 - K1030 + 750, K1030 + 311 - K1030 + 920, K1030+930 - K1031+630, K1031+1000 - K1032+500
Physical Target: Allocation:
CW1-Construction of Drainage Structure P 48.6864 M
along Road-3,794.0 Lineal meters
EAO P 0.9936 M
Total Allocation: P 49.680 M
AS MODIFIED:
Naval-Caibiran Cross Country Rd - K1027+361 - K1027+660, K1027+788 - K1027+890, K1028 + 770 - K1029 + 740, K1030 + 150 - K1030 + 750, K1030 + 311 - K1030 + 920, K1030+930 - K1031+630
Physical Target: Allocation:
CW1-Construction of Drainage Structure P 46.9412 M
along Road-3,794.0 Lineal meters
ROW-ROW Acquisition- P 1.000 M
EAO P 0.9936 M
EXCESS P 0.7452 M
Total Allocation: P 49.680 M |
July 12, 2018 |
2018 |
WIN8F05541 |
GAA FY 2018 |
January 1, 2018 |
Region VIII |
Biliran District Engineering Office |
Convergence and Special Support Program
Convergence and Special Support-Construction/Improvement of Access Roads leading to Declared Tourism Destination
FROM:
Access Road leading to Tomalistis Falls, Brgy. Asug, Caibiran, Biliran
Physical Target: Allocation:
CW1-Reconstruction from Paved to Concrete- P 4.90 M
0.4 Lane Km
EAO P 0.10 M
Total Allocation: P 5.00 M
AS MODIFIED:
Access Road leading to Tomalistis Falls, Brgy. Asug, Caibiran, Biliran
Physical Target: Allocation:
CW1-Reconstruction from Paved to Concrete- P 2.86966 M
0.28 Lane Km
CW2- Construction of Slope Protection P 1.95534 M
Structure- 190 Square meters
EAO P 0.10 M
EXCESS P 0.075 M
Total Allocation: P 5.00 M
|
July 12, 2018 |
2018 |
WIN8F05073 |
GAA FY 2018 |
January 1, 2018 |
Region VIII |
Leyte 5th District Engineering Office |
Organizational Outcome 1: Ensure Safe and Reliable National Road System
Network Development - Off Carriageway Improvement - Secondary Roads
FROM:
Bato-Bontoc Rd - K1116+700 - K1117+851, K1118+030 - K1120+335
Physical Target: Allocation:
CW1 - Off Carriageway Improvement: P 42.614320 M
Shoulder Paving/ Construction-
13,876.00 Square meter
EAO P 0.869680 M
Total Allocation: P 43.484 M
AS MODIFIED:
Bato - Bontoc Rd - K1110 + 848 - K1111 + 000, K1111 + 000 - K1111 + 211, K1111 + 211 - K1111 + 441, K1111 + 441 - K1111 + 484, K1111 + 484 - K1111 + 726, K1111 + 726 - K1111 + 872, K1111 + 872 - K1112 + 000, K1112 + 000 - K1112 + 022, K1112 + 022 - K1112 + 130, K1112 + 130 - K1112 + 227, K1112 + 588 - K1112 + 615, K1112 + 615 - K1112 + 770, K1118 + 030 - K1120 + 335
Physical Target: Allocation:
CW1 - Off Carriageway Improvement: P 42.614320 M
Shoulder Paving/ Construction-
13,876.00 Square meter
EAO P 0.869680 M
Total Allocation: P 43.484 M |
July 12, 2018 |
2018 |
WIN8F05503 |
GAA FY 2018 |
January 29, 2018 |
Region VIII |
Leyte 3rd District Engineering Office |
Organizational Outcome1: Ensure Safe and Reliable National Road System
Network Development - Off-Carriageway Improvement - Secondary Roads
FROM:
Calubian Jct-Sn Isidro-Tabango-Villaba-Palompon Rd - K1011 + 947 - K1014 + 639
Physical Target: Allocation:
CW1-Off-Carriageway Improvement: P 96.50 M
Shoulder Paving / Construction-
16,665.00 sq.m.
EAO- P 3.50 M
Total Allocation: P 100.00 M
AS MODIFIED:
Calubian Jct-Sn Isidro-Tabango-Villaba-Palompon Rd - K1011 + 952 - K1013 + 700
Physical Target: Allocation:
CW1-Off-Carriageway Improvement: P 39.574 M
Shoulder Paving / Construction-
10,821.40 sq.m.
CW2-Construction of Slope Protection P 56.926 M
Structure-4,275.65 sq.m.
EAO- P 3.50 M
Total Allocation: P 100.00 M |
July 12, 2018 |
2018 |
WIN8F05592 |
GAA FY 2018 |
January 31, 2018 |
Region VIII |
Leyte 3rd District Engineering Office |
Local Program
Local-National Roads and Bridges-Local Roads-Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
FROM:
Construction of Calubian-Jubay-Daja Road including Bridges, Calubian and San Isidro, Leyte
Physical Target: Allocation:
CW1-Construction of Concrete Road- P 168.875 M
6.0 Lane Km
EAO P 6.125 M
Total Allocation: P 175.00 M
AS MODIFIED:
Construction of Calubian-Jubay-Daja Road including Bridges, Calubian and San Isidro, Leyte
Physical Target: Allocation:
CW1-Construction of Concrete Road- P 61.438 M
6.566 Lane Km
CW2-Construction of Concrete Bridge- P 105.687 M
1,004.41 sq.m
ROW-ROW Acquisition-20,000 sq.m P 1.750 M
EAO P 6.125 M
Total Allocation: P 175.00 M |
July 12, 2018 |
2018 |
WIN8F05543 |
GAA FY 2018 |
January 29, 2018 |
Region VIII |
Leyte 3rd District Engineering Office |
Organizational Outcome1: Ensure Safe and Reliable National Road System
Network Development - Off-Carriageway Improvement - Secondary Roads
FROM:
Sambulawan Jct-Calaguise-Calubian Rd - K0984 + (-300) - K0984 + 771, K0984 + 833 - K0986 + 596
Physical Target: Allocation:
CW1-Off-Carriageway Improvement: P 96.50 M
Shoulder Paving / Construction-
16,671.00 sq.m.
EAO P 3.50 M
Total Allocation: P 100.00 M
AS MODIFIED:
Sambulawan Jct-Calaguise-Calubian Rd - K0984 + (-300) - K0984 + 766, K0984 + 838 - K0985 + 505
Physical Target: Allocation:
CW1-Off-Carriageway Improvement: P 30.544 M
Shoulder Paving / Construction-
9,869.80 sq.m.
CW2-Construction of Slope Protection P 65.956 M
Structure-5,790.60 sq.m.
EAO P 3.50 M
Total Allocation: P 100.00 M |
July 11, 2018 |
FY - 2018 |
WIN8F05648 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Regional Office IV-B |
Local Program
Local Roads and Bridges - Local Roads
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects
FROM:
Widening of Puerto Princesa Road
from two (2)to six (6) lanes including
drainage structures and other ancillary works,
K0200+100 - K0202+300,
Bataraza
CW1: 8.024 lane km ( Road Widening )
Allocation: 135,000,000 Php
TO:
Widening of Puerto Princesa South Road
from two (2) to six (6) lanes including drainage
structures and other ancillary works,
K0200+100 - K0201+147,
K0201+173 - K0202+200,
K0202+275 - K0202+435,
Bataraza
CW1: 8.576 lane km ( Road Widening )
Allocation: 135,000,000 Php |
July 11, 2018 |
FY - 2018 |
WIN8F05652 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Regional Office IV-B |
Local Program
Local Roads and Bridges - Local Roads
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects
FROM:
Widening of Puerto Princesa Road
from two (2) to six (6) lanes including drainage
structures and other ancillary works,
K0175+290 - K0177+600,
Brooke's Point
CW1: 9.176 lane km ( Road Widening )
Allocation: 140,000,000 Php
TO:
Widening of Puerto Princesa South Road
from two (2) to six (6) lanes including drainage
structures and other ancillary works,
K0175+627 - K0176+185,
K0176+194 - K0177+880,
Brooke's Point
CW1: 9.024 lane km ( Road Widening )
Allocation: 140,000,000 Php
|
July 11, 2018 |
2018 |
WIN8F05112 |
GAA FY 2018 |
January 26, 2018 |
Region VIII |
Regional Office VIII |
Organizational Outcome 1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Primary Roads
FROM:
Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) incl. ROW - K0870 + 000 - K0870 + 250, K0870 + 850 - K0871 + 445, K0879 + 680 - K0880 + 370, K0881 + 000 - K0881 + 880, K0882 + 100 - K0883 + 000, K0883 + 600 - K0885 + 177, K0885 + 209 - K0885 + 521
Physical Target: Allocation
CW1-Road Widening-10.434 Lane Km P 63.764 M
CW2- ROW Acquisition-53,665.00 Sq.m P 32.736 M
EAO P 3.500 M
Total Allocation: P 100.00 M
AS MODIFIED:
Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) - K0870 + 000 - K0870 + 250, K0870 + 850 - K0871 + 445, K0881 + 000 - K0881 + 880, K0883 + 600 - K0884 + 862
Physical Target: Allocation
CW1-Road Widening-6.00 Lane Km P 96.500 M
EAO P 3.500 M
Total Allocation: P 100.00 M
|
July 11, 2018 |
2018 |
WIN8F05113 |
GAA FY 2018 |
January 26, 2018 |
Region VIII |
Regional Office VIII |
Organizational Outcome 1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Primary Roads
FROM:
Daang Maharlika (LT) - K0935 + 585.30 - K0936 + 000, K0935 + -634 - K0935 + 540, K0943 + 277 - K0944 + 225, K0945 + 222 - K0946 + 500
Physical Target: Allocation:
CW1-Road Widening-7.679 Lane Km P 193.00 M
EAO P 7.00 M
Total Allocation: P 200.00 M
AS MODIFIED:
Daang Maharlika (LT) - K0935 + 585.30 - K0936 + 000, K0935 + -634 - K0935 + 540, K0943 + 277 - K0944 + 225, K0945 + 222 - K0946 + 448
Physical Target: Allocation:
CW1-Road Widening-7.5754 Lane Km P 183.00 M
ROW Acquisition- 5,000.00 Sq.m P 10.00 M
EAO P 7.00 M
Total Allocation: P 200.00 M
|
July 11, 2018 |
2018 |
WIN8F05114 |
GAA FY 2018 |
January 26, 2018 |
Region VIII |
Regional Office VIII |
Organizational Outcome 1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Primary Roads
FROM:
Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) incl. ROW - K0786 + 432 - K0787 + 000, K0789 + 000 - K0790 + 000, K0834 + 000 - K0835 + 000, K0841 + 300 - K0841 + 400, K0842 + 860 - K0844 + 000, K0845 + 000 - K0845 + 440, K0845 + 670 - K0846 + 814
Physical Target: Allocation:
CW1-Road Widening-10.786 Lane Km P 69.108 M
CW2-ROW Acquisition-55,449.00 Sq.m P 27.392 M
EAO P 3.500 M
Total Allocation: P 100.00 M
AS MODIFIED:
Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) - K0834 + 000 - K0835 + 000, K0842 + 860 - K0844 + 000, K0845 + 000 - K0845 + 440, K0845 + 670 - K0846 + 081
Physical Target: Allocation:
CW1-Road Widening-6.00 Lane Km P 96.500 M
EAO P 3.500 M
Total Allocation: P 100.00 M
|
July 11, 2018 |
2018 |
OUT8$85139 |
GAA FY 2018 |
January 26, 2018 |
Region VIII |
Regional Office VIII |
Organizational Outcome 1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Primary Roads
FROM:
Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) - K0680 + 790 - K0680 + 800, K0684 + 840 - K0685 + 020, K0687 + 550 - K0687 + 975, K0688 + 250 - K0688 + 350, K0691 + 800 - K0691 + 900
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 77.200 M
Structure-3,215 Sq.m
EAO P 2.800 M
Total Allocation: P 80.00 M
AS MODIFIED:
Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) - , K0688 + 250 - K0688 + 350, K0691 + 800 - K0691 + 920
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 77.200 M
Structure-3,534.95 Sq.m
EAO P 2.800 M
Total Allocation: P 80.00 M |
July 11, 2018 |
2018 |
WIN8F05085 |
GAA FY 2018 |
January 26, 2018 |
Region VIII |
Regional Office VIII |
Organizational Outcome 1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Primary Roads
FROM:
Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) incl. ROW - K0885 + 553 - K0886 + 036, K0886 + 058 - K0886 + 210, K0887 + 200 - K0887 + 550, K0887 + 800 - K0888 + 950, K0889 + 480 - K0890 + 460, K0890 + 600 - K0890 + 710, K0891 + 410 - K0891 + 800, K0892 + 000 - K0892 + 470, K0893 + 190 - K0894 + 000, K0894 + 100 - K0894 + 300
Physical Target: Allocation:
CW1-Road Widening-10.250 Lane Km P 66.900 M
CW2- ROW Acquisition-5,103.00 Sq.m P 29.600 M
EAO P 3.500 M
Total Allocation: P 100.00 M
AS MODIFIED:
Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) - K0888 + 000 - K0888 + 200, K0889 + 480 - K0890 + 000, K0890 + 000 - K0890 + 460, K0890 + 600 - K0890 + 710, K0891 + 410 - K0891 + 800, K0892 + 000 - K0892 + 470, K0893 + 190 - K0893 + 230, K0893 + 230 - K0894 + 000, K0894 + 100 - K0894 + 300
Physical Target: Allocation:
CW1-Road Widening-6.350 Lane Km P 96.500 M
EAO P 3.500 M
Total Allocation: P 100.00 M |
July 11, 2018 |
2018 |
WIN8F05088 |
GAA FY 2018 |
January 26, 2018 |
Region VIII |
Regional Office VIII |
OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Primary Roads
FROM:
Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) - K0679 + -056 - K0680 + 133, K0680 + 163.60 - K0680 + 572, K0680 + 596 - K0680 + 879, K0680 + 901.60 - K0682 + 330, K0682 + 345 - K0684 + 389, K0684 + 423 - K0685 + 000, K0690 + 000 - K0690 + 565
Physical Target: Allocation:
CW1-Road Widening-12.562 Lane Km P 193.00 M
EAO P 7.00 M
Total Allocation P 200.00 M
AS MODIFIED:
Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) - K0690 + 000 - K0690 + 565, K0679 + (-056) - K0680 + 133, K0680 + 163.60 - K0680 + 572, K0680 + 596 - K0680 + 879, K0680 + 909 - K0682 + 330, K0682 + 345 - K0684 + 389, K0684 + 423 - K0685 + 000,
Physical Target: Allocation:
CW1-Road Widening-12.5468 Lane Km P 193.00 M
EAO P 7.00 M
Total Allocation P 200.00 M |
July 11, 2018 |
2018 |
WIN8F05087 |
GAA FY 2018 |
January 26, 2018 |
Region VIII |
Regional Office VIII |
Organizational Outcome 1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Tertiary Roads
FROM:
Arteche-Jipapad-Las Navas-Rawis Rd - K0805 + -237 - K0806 + 748, K0806 + 778 - K0811 + 000
Physical Target: Allocation:
CW1-Asphalt Overlay-12.426 Lane Km P 59.151605 M
EAO P 2.145395 M
Total Allocation: P 61.297 M
AS MODIFIED:
Arteche-Jipapad-Las Navas-Rawis Rd - K0805 + -237 - K0806 + 748, K0806 + 778 - K0810 + 293
Physical Target: Allocation:
CW1-Asphalt Overlay-11.00 Lane Km P 59.151605 M
EAO P 2.145395 M
Total Allocation: P 61.297 M |
July 11, 2018 |
FY 2018 |
WIN8G02477 |
FY 2018 GAA R.A. 10964 |
December 29, 2017 |
Region V |
Camarines Sur 1st District Engineering Office |
UACS No.: 300117201356000
Project ID: P00254194LZ
Local Infrastructure Program – Local Roads and Bridges – Local Roads – Local Infrastructure Program – Construction of Patong-Cagbibi Road, Brgy. Patong, Pamplona, Camarines Sur
Physical Target - CW1 - Construction of Concrete Road / 0.252 lane-km
Unit Cost: Php 7.86M / lane km
Estimated Cost: Php 2.00M
(As Modified)
|
July 11, 2018 |
FY 2018 |
WIN8G02472 |
FY 2018 GAA R.A. 10964 |
December 29, 2017 |
Region V |
Camarines Sur 1st District Engineering Office |
UACS No.: 300117201357000
Project ID: P00255759LZ
Local Infrastructure Program – Local Roads and Bridges – Local Roads – Local Infrastructure Program – Reconstruction of Tambo-Calawat Road, Brgy. Calawat, Pamplona, Camarines Sur
Physical Target - CW1 – reconstruction of Concrete Road / 0.24 lane km
Unit Cost: CW1 - Php 8.25 M/lane km
Estimated Cost: Php 2.00 M
(As Modified)
|
July 11, 2018 |
2018 |
WIN8F05587 |
GAA FY 2018 |
May 10, 2018 |
Region VIII |
Regional Office VIII |
Organizational Outcome 2: Protect Lives and Properties Against Major Floods
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
FROM:
Construction of Flood Control along Poblacion Kananga-Kanawagan River flood control and Protection Work, Kananga, Leyte
Physical Target: Allocation:
CW1-Construction of Flood Mitigation Structure- P 48.250 M
870.00 Lineal Meters
EAO P 1.750 M
Total Allocation: P 50.00 M
AS MODIFIED:
Construction of Flood Control along Poblacion Kananga-Kanawagan River flood control and Protection Work, Kananga, Leyte
Physical Target: Allocation:
CW1-Construction of Revetment- P 48.250 M
350.00 Lineal Meters
EAO P 1.750 M
Total Allocation: P 50.00 M |
July 11, 2018 |
FY 2018 |
WIN8G02486 |
FY 2018 GAA R.A. 10964 |
December 29, 2017 |
Region V |
Catanduanes District Engineering Office |
UACS No.: 320101101718000
Project ID: P00223409LZ
OO2: Protect Lives and Properties Against Major Floods – Flood Management Program – Construction/Maintenance of Flood Mitigation Structures and Drainage Systems – Construction of Bocon Seawall/Causeway, Caramoran, Catanduanes
Physical Target: CW1 – Construction of Flood Mitigation Structure/ 88 lm
Unit Cost: CW1 – Php 556,818.18/lm.
Estimated Cost: Php 50.0 M
(As Modified)
|
July 11, 2018 |
FY 2018 |
WIN8G02491 |
FY 2018 GAA R.A. 10964 |
December 29, 2017 |
Region V |
Catanduanes District Engineering Office |
UACS No.: 320101101700000
Project ID: P00220236LZ
OO2: Protect Lives and Properties Against Major Floods – Flood Management Program –
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems – Construction of Breakwater Rock Causeway, Brgy. Rawis, Sta. 0+000 - Sta. 0+091, Virac, Catanduanes
Physical Target: CW1 – Construction of Flood Mitigation Structure/ 91 lm
Unit Cost: CW1 – Php 323.077 T/lm.
Estimated Cost: Php 30.0 M
(As Modified)
|
July 11, 2018 |
FY 2018 |
WIN8G02492 |
FY 2018 GAA R.A. 10964 |
December 29, 2017 |
Region V |
Catanduanes District Engineering Office |
UACS No.: 320101101701000
Project ID: P00220237LZ
OO2: Protect Lives and Properties Against Major Floods – Flood Management Program –
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems – Construction of Breakwater Rock Causeway, Brgy. Rawis, Sta. 0+091 - Sta. 0+167, Virac, Catanduanes
Physical Target: CW1 – Construction of Flood Mitigation Structure/ 76 lm
Unit Cost: CW1 – Php 386.842 T/lm.
Estimated Cost: Php 30.0 M
(As Modified)
|
July 11, 2018 |
FY 2018 |
WIN8G02476 |
FY 2018 GAA R.A. 10964 |
December 29, 2017 |
Region V |
Regional Office V |
UACS No.: 300203100144000
Project ID: P00230392LZ
Convergence and Special Support Program – Construction/Improvement of Access Roads leading to Declared Tourism Destinations – Pasacao-Balatan Tourism Coastal Highway leading to Pasacao Port to White San Beaches, Brgy. Odicon, Pasacao, Camarines Sur
Physical Target: CW1 – Construction of Gravel Road/ 8.5288 lane-km
CW2 - Construction of Drainage Structure along Road/ 6,272 lm.
CW3 - Construction of Road Slope Protection Structure/ 8,556.23 sq.m.
Unit Cost: CW1 Php 10.046 M/lane km
CW2 - Php 5,505.08/lm
CW3 - Php 2,868.55/sq.m.
Estimated Cost: Php 150.0 M
(As Modified)
|
July 11, 2018 |
FY 2018 |
WIN8G02483 |
FY 2018 GAA R.A. 10964 |
December 28, 2017 |
Region V |
Regional Office V |
UACS No.: 300204100075000
Project ID: P00230404LZ
Convergence and Special Support Program – Construction/Improvement of Access Roads leading to Declared Tourism Destinations – Sta. Cruz-Pandan-Upland Central Economic Zone in Busac-Oma oma-Paulba Road connecting to Ligao-Pioduran Road, incl. bridge in support to Agribusiness (Food Resource Based Processing) Ligao City, Albay
Physical Target: CW1 – Reconstruction from Paved to Concrete/ 3.68 lane-km
CW2 – Construction of Gravel Road/1.029 lane-km
CW3 – Construction of Concrete Bridge/122.11 sq.m.
Unit Cost: CW1 – Php 13.28 M/lane-km
CW2 – Php 13.93 M/lane-km
CW3 – Php 35,671.61 T/sq.m.
Estimated Cost: Php 70.0 M
(As Modified)
|
July 11, 2018 |
FY 2018 |
WIN8G02495 |
FY 2018 GAA R.A. 10964 |
December 29, 2017 |
Region V |
Regional Office V |
UACS No.: 300116200121000
Project ID: P00257842LZ
LOCAL PROGRAM – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects - Construction of Ariman - Panganiban Coastal Road and Shore Protection, Gubat, Sorsogon
Physical Target: CW1 – Construction of Concrete Road/ 0.7332 lane-km
CW2 - Construction of Road Slope Protection Structure/ 1,887.99 sq.m.
Unit Cost: CW1 – Php 41.66 M/lane-km
CW2 – Php 34,932.92/sq.m.
Estimated Cost: Php 100.0 M
(As Modified)
|
July 11, 2018 |
FY 2018 |
WIN8G02494 |
FY 2018 GAA R.A. 10964 |
December 29, 2017 |
Region V |
Regional Office V |
UACS No.: 300116200144000
Project ID: P00257865LZ
LOCAL PROGRAM – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects – Construction of Paghuliran – Poropandan Coastal Road and Shore Protection, Matnog, Sorsogon
Physical Target:CW1 – Construction of Concrete Road/ 0.6168 lane-km
CW2 - Construction of Road Slope Protection Structure/ 1,588.26 sq.m.
Unit Cost: CW1 – Php 48.16 M/lane-km
CW2 – Php 42,054.20/sq.m.
Estimated Cost: Php 100.0 M
(As Modified)
|
July 11, 2018 |
FY 2018 |
WIN8G02496 |
FY 2018 GAA R.A. 10964 |
December 29, 2017 |
Region V |
Regional Office V |
UACS No.: 300116200146000
Project ID: P00257867LZ
LOCAL PROGRAM – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects – Construction of Poropandan – Culasi Coastal Road with Shore Protection, Matnog, Sorsogon
Physical Target: CW1 – Construction of Concrete Road/ 0.6067 lane-km
CW2 - Construction of Road Slope Protection Structure/ 1,562.25 sq.m.
Unit Cost: CW1 – Php 49.44 M/lane-km
CW2 – Php 42,571.29/sq.m.
Estimated Cost: Php 100.0 M
(As Modified)
|
July 11, 2018 |
FY 2018 |
WIN8G02474 |
FY 2018 GAA R.A. 10964 |
December 29, 2017 |
Region V |
Regional Office V |
UACS No.: 310201100070000
Project ID: P00201255LZ
OO1: Ensure Safe and Reliable National Road System - Network Development Program – Road Widening – Primary Roads – Daang Maharlika (LZ) – K0376+006 – K0377+540
Physical Target: CW1 - Road Widening/ 3.078 lane-km
CW2 - Construction of Drainage Structure along Road/ 2,654 lm.
Unit Cost: CW1 – Php 20.10 M/lane-km
CW1 – Php 12.00 T/lm.
Estimated Cost: Php 97.122 M
(As Modified)
|
July 11, 2018 |
FY 2018 |
WIN8G02468 |
FY 2018 GAA R.A. 10964 |
December 29, 2017 |
Region V |
Regional Office V |
UACS No.: 310102100040000
Project ID: P00202708LZ
OO1: Ensure Safe and Reliable National Road System - Asset Preservation Program – Preventive Maintenance – Secondary Roads –
Repair/Rehabilitation (Asphalt Overlay) Masbate-Uson-Placer Road (Buenavista-Cawayan Section), Masbate
Physical Target: CW1 - Preventive Maintenance of Road: Asphalt Overlay/ 9.054 lane-km
Unit Cost: CW1 – Php 10.66 M/lane-km
Estimated Cost: Php 100.0 M
(As Modified)
|