May 16, 2018 FY 2018 WIN8C02939 320101102168000 May 7, 2018 Region IX Zamboanga del Sur 1st District Engineering Office
UACS No: 320101102168000
Project ID: P00220994MN
OO2: Protect lives and Properties Against Major Floods
Flood Management Program Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control, Sto. Niño Tukuran, Zamboanga del Sur
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 202.00 l.m
Unit Cost: P 121,287.13/l.m.
EAO: P 0.5M
Allocation: P 25.0M
May 16, 2018 GAA FY 2018 WIN8F05508 UACS No. 310111100016000 January 1, 2018 National Capital Region Las Piñas - Muntinlupa District Engineering Office
As per GAA/Original
UACS No. 310111100016000
Project ID: P00202757LZ
WIN8F05508
Organizational Outcome 001: Ensure and Safe and Reliable National Road System
Asset Preservation – Construction/Upgrading/Rehabilitation of Drainage along National Road –
Secondary Roads
Quirino Avenue – K0013+316 – K0013+583
Physical Target: CW1-Construction of Drainage Structure along Road = 532.00 lineal meters
EAO – P 1,000,000.00
Unit Cost (P’000): P92,105.26/ linear meter
Allocation: P 49,000,000.00
Total: P 50,000,000.00

As Modified
As per GAA/Original
UACS No. 310111100016000
Project ID: P00202757LZ
WIN8F05508
Organizational Outcome 001: Ensure and Safe and Reliable National Road System
Asset Preservation – Construction/Upgrading/Rehabilitation of Drainage along National Road –
Secondary Roads
Quirino Avenue – K0013+316 – K0013+583
Physical Target: CW1-Construction of Drainage Structure along Road = 1,142.09 lineal meters
EAO – P 1,000,000.00
Unit Cost (P’000): P42,903.80/ linear meter
Allocation: P 49,000,000.00
Total: P 50,000,000.00
May 16, 2018 FY 2018 WIN8C02706 320102100516000 May 3, 2018 Region IX Zamboanga Sibugay 2nd District Engineering Office
UACS No. 320102100516000
Project ID: P00222747MN

OO2: Protect Lives and Properties Against Major Floods-Flood Management -
Construction/Rehabilitation of Flood Mitigation Facilities along Major River Basins and Principal Rivers

Construction of Flood Control Structure along Sibuguey River (Phase VII), Siay, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 680 lineal meters
Unit Cost: P 63,860.29/lineal meter
ROW Acquisition: 2,250 square meters
Unit Cost: P 300.00/square meter
EAO: P 0.9 M
Allocation: P 45 M
May 16, 2018 GAA FY 2018 WIN8F05506 UACS No. 320101100613000 January 1, 2018 National Capital Region North Manila District Engineering Office
As per GAA/Original
UACS No. 320101100613000
Project ID: P00223289LZ
WIN8F05506
002: Protect Lives and Properties
Flood Management – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Bank Improvement (Steel Sheet Pile) Estero de Binondo, Sta. 0+323.96 to Sta. 0+400.00, Sta. 0+420.00 to Sta. 0+484.81, Manila City
Physical Target: CW1 Construction of Revetment L=80.80 lm
Unit Cost (P’000): P363,861.39/ lm
Allocation: P 29,400,000.00 M
EAO P 600,000 M
Total: P 30,000,000.00

As Modified
UACS No. 320101100613000
Project ID: P00223289LZ
WIN8F05506
002: Protect Lives and Properties
Flood Management – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Bank Improvement (Steel Sheet Pile) Estero de Binondo, Sta. 0+323.96 to Sta. 0+403.16, Manila City
Physical Target: CW1 Construction of Revetment L=79.20 lm
Unit Cost (P’000): P371,212.12/ lm
Allocation: P 29,400,000.00 M
EAO P 600,000 M
Total: P 30,000,000.00
May 16, 2018 FY 2018 WIN8C02940 320101102173000 May 7, 2018 Region IX Zamboanga del Sur 1st District Engineering Office
UACS No: 320101102173000
Project ID: P00220991MN
OO2: Protect lives and Properties Against Major Floods
Flood Management Program Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Dipolog Flood Control, Tiparak, Tambulig, Zamboanga del Sur
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 335 l.m.
Unit Cost: P 87,761.19/l.m.
EAO: P 0.60M
Allocation: P 30.0M
May 16, 2018 GAA FY 2018 WIN8F05506 UACS No. 320101100613000 January 1, 2018 National Capital Region North Manila District Engineering Office
As per GAA/Original
UACS No. 320101100613000
Project ID: P00223289LZ
WIN8F05506
002: Protect Lives and Properties
Flood Management – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Bank Improvement (Steel Sheet Pile) Estero de Binondo, Sta. 0+323.96 to Sta. 0+400.00, Sta. 0+420.00 to Sta. 0+484.81, Manila City
Physical Target: CW1 Construction of Revetment L=80.80 lm
Unit Cost (P’000): P363,861.39/ lm
Allocation: P 29,400,000.00 M
EAO P 600,000 M
Total: P 30,000,000.00

As Modified
UACS No. 320101100613000
Project ID: P00223289LZ
WIN8F05506
002: Protect Lives and Properties
Flood Management – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Bank Improvement (Steel Sheet Pile) Estero de Binondo, Sta. 0+323.96 to Sta. 0+403.16, Manila City
Physical Target: CW1 Construction of Revetment L=79.20 lm
Unit Cost (P’000): P371,212.12/ lm
Allocation: P 29,400,000.00 M
EAO P 600,000 M
Total: P 30,000,000.00
May 16, 2018 FY 2018 WIN8C02690 300116201167000 May 3, 2018 Region IX Zamboanga Sibugay 2nd District Engineering Office
UACS No. 300116201167000
Project ID: P00240255MN

Local Program:

Local Roads and Bridges - Local Roads -
Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects

Construction of Poblacion Titay Dalangin-Dalangin Muslim-Achasol-San Antonio Tugop-Banco-Boundary Kalawit (Phase III), Zamboanga Sibugay Sta. 5+372.00 - Sta. 6+557.00
Physical Target:
CW-1 - Construction of Concrete Road:
2.370 lane km.
Unit Cost: P 12,405.063/lane km.
EAO: P 0.600 M
Allocation: P 30 M
May 16, 2018 GAA FY 2018 WIN8F05504 UACS No. 310102100053000 January 1, 2018 National Capital Region North Manila District Engineering Office
As per GAA/Original
UACS No. 310102100053000
Project ID: P00200070LZ
WIN8F05504
001: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Secondary Road
Legarda Flyover – (S02369LZ) Chainage 0 – Chainage 98, Chainage 303 – Chainage 417
Physical Target: CW1 Preventive Maintenance Asphalt Overlay L=0.42 lane km
Unit Cost (P’000): P6,723.63/ lane km
Allocation: P 2,850,820.00 M
EAO P 58,180.00 M
Total: P 2,909,000.00

As Modified
UACS No. 310102100053000
Project ID: P00200070LZ
WIN8F05504
001: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Secondary Road
Legarda Flyover – (S02369LZ) Chainage 44 – Chainage 302
Physical Target: CW1 Preventive Maintenance Asphalt Overlay L=0.516 lane km
Unit Cost (P’000): P5,524.84/ lane km
Allocation: P 2,850,820.00 M
EAO P 58,180.00 M
Total: P 2,909,000.00
May 16, 2018 GAA FY 2018 WIN8F05490 UACS No. 300116200393000 January 1, 2018 National Capital Region North Manila District Engineering Office
As per GAA/Original
UACS No. 300116200393000
Project ID: P00240688LZ
WIN8F05490
Local Program
Local Roads and Bridges – Local Roads – Construction/ Repair/ Rehabilitation/ Improvements of Various Infrastructure including Local Projects
Rehabilitation of Road with Drainage Improvement at Zone 64, Manila City
Physical Target: CW1 Rehabilitation of Paved Road L=4.00 lane km
Unit Cost (P’000): P4,900,000/ lane km
Allocation: P 19,600,000.00
EAO P 400,000.00
Total: P 20,000,000.00

As Modified
UACS No. 300116200393000
Project ID: P00240688LZ
WIN8F05490
Local Program
Local Roads and Bridges – Local Roads – Construction/ Repair/ Rehabilitation/ Improvements of Various Infrastructure including Local Projects
Rehabilitation of Road with Drainage Improvement at Zone 64, Manila City
Physical Target: CW1 Rehabilitation of Paved Road L=1.414 lane km
Unit Cost (P’000): P13,861,386.14/ lane km
Allocation: P 19,600,000.00
EAO P 400,000.00
Total: P 20,000,000.00
May 16, 2018 FY 2018 WIN8C02860 310211100034000 May 7, 2018 Region IX Zamboanga del Sur 1st District Engineering Office
UACS No: 310211100034000
Project ID: P00201353MN
Network Development - Paving of Unpaved Roads - Secondary Roads
Sindangan - Siayan - Dumingag - Mahayag Road (Mahayag - Dumingag) K1690+250 - K1690+428.42
Physical Target:
CW-1 - Paving of Unpaved Roads: 0.35684 lane km
Unit Cost: P 19.032M/lane km
EAO: P 0.1386M
Allocation: P 6.93M
May 16, 2018 FY 2018 WIN8C02689 320101102190000 May 3, 2018 Region IX Zamboanga Sibugay 2nd District Engineering Office
UACS No. 320101102190000
Project ID: P00220473MN

OO2: Protect Lives and Properties Against Major Floods-Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems

Construction of Flood Control project from Veterans Village to Don Andres, Ipil, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 595.84 lineal meters
Unit Cost: P 39,104.46/lineal meter
ROW Acquisition: 4,000.00 sq.m.
Unit Cost: P 300/sq.m.
EAO: P 0.5 M
Allocation: P 25 M
May 16, 2018 FY 2018 WIN8G02178 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Sorsogon District Engineering Office
OO1: Ensure Safe and Reliable National Road System –
Network Development Program - Construction of By-Pass and Diversion Roads - Castilla Bypass Road incl. ROW, Sorsogon
Physical Target - CW1- Construction of Concrete Road/ 6.08 lane-km.
ROW Acquisition/ 60,800 sq.m.
Unit Cost: CW1 - Php 14.23 M /lane-km
ROW - Php 164.47/sq.m.
Estimated Cost: Php 100.0M
(As Modified)
May 16, 2018 FY 2018 WIN8G01922 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Sorsogon District Engineering Office
UACS No.: 310208100029000
Project ID: P00201548LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program - Off-Carriageway Improvement - Secondary Roads - Jct. Putiao-Pilar-Donsol Rd - K0544+(-980) - K0547+074
Physical Target - CW1-Off-carriageway Improvement: Shoulder Paving/Construction/ 12,150 sq.m.
CW2- Construction of Slope Protection Structure/ 13,831.64 sq.m.
Unit Cost: CW1 - Php 5,486.55/sq.m.
CW2 - Php 2,157.26/sq.m.
Estimated Cost: Php 100.0M
(As Modified)
May 16, 2018 FY 2018 WIN8G02174 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Sorsogon District Engineering Office
UACS No.: 310103100027000
Project ID: P00202724LZ
OO1: Ensure Safe and Reliable National Road System – Asset Preservation Program - Preventive Maintenance -Tertiary Roads - Jct Donsol-Banuang-Gurang Rd - K0571+(-470) - K0571+138, K0572+170 - K0575+388
Physical Target - CW1- Preventive Maintenance of Road: Asphalt Overlay/6.776 lame-km
Unit Cost: Php 11.45M
Estimated Cost: Php 80.40M
(As Modified)


May 16, 2018 FY 2018 WIN8G01853 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Sorsogon District Engineering Office
UACS No.: 31020110024500
Project ID: P00201267LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program - Road Widening – Primary Roads - Daang Maharlika (LZ) -K0559+485 - K0559+573, K0544+786 - K0545+013, K0545+076 - K0545+267, K0564+203 - K0564+403, K0584+940 - K0585+125, K0585+157 - K0585+350, K0599+294 - K0599+751
Physical Target - CW1- Road Widening/0.09 lane-km
CW2- Off-Carriageway Improvement: Shoulder Paving/Construction/ 4,176.12 sq.m.
Unit Cost: Php113.067M/lane-km
Estimated Cost: Php 25.0M
(As Modified)
May 15, 2018 FY - 2018 WIN8F05344 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
Local Program

Construction/Repair/Rehabilitation/improvement of
Various Infrastructure including Local Projects

FROM:
Concreting of 2 km Malibago - Masilig road,
Barangay malibago, Torrijos, Marinduque

CW1: 1.759 Lanr km ( Construction of Concrete Road )
Allocation: 10,000,000 Php

TO:
Concreting of 2 lane km Malibago - Masilig road,
Barangay Malibago, Torrijos, Marinduque

CW1: 2.000 Lane km ( Construction of Concrete Road )
Allocation: 10,000,000 Php
May 15, 2018 FY - 2018 WIN8F05347 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
Local Program

Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects
- Buildings and Other Structures - Multipurpose/Facilities

FROM:
Construction of barangay Health Station
( 2nd Floor of Brgy. Hall ), Barangay Masaguisi,
Santa Cruz, Marinduque

CW1: 1 Bldg. ( Construction of Multi Purpose Building )
Allocation: 2,000,000 Php

TO:
Construction of Barangay Health Stattion
( 1st Floor of Brgy. Hall ), Brgy. Masaguisi,
Santa Cruz, Marinduque

CW1: 1 Bldg ( Construction of Multi Purpose Building )
Allocation: 2,000,000 Php
May 15, 2018 FY - 2018 WIN8F05340 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
Local program

Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects
- Buildings and Other Structures - Multipurpose/Facilities

FROM:
Construction of Brgy. Mataas na Bayan Covered Court,
Mogpog, Marinduque

CW1: 1 Bldg. ( Construction of Multi Purpose Building )
Allocation: 4,000,000 Php

TO:
Construction(Completion) of Brgy. Mataas na Bayan
Covered Court, Mogpog, Marinduque

CW1: 1 Bldg ( Construction of Multi Purpose Building)
Allocation: 4,000,000
May 15, 2018 FY - 2018 WIN8F05353 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
Local Program

Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects
-Buildings and Other Structures - Multipurpose/Facilities

FROM:
Construction of Multi-Purpose Building, Brgy. II,
Gasan, Marinduque

CW1: 1 Bldg. ( Construction of Multi-Purpose Building )
Allocation: 2,000,000 Php

TO:
Construction/Rehabilitation of Multi-Purpose Building,
Brgy. II, Gasan, Marinduque

CW1: 1 Bldg. ( Construction of Multi Purpose Building )
Allocation: 2,000,000 Php
May 15, 2018 FY - 2018 WIN8F05386 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
Local Program

Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including local Projects
- Flood Control Structures/Facilities

FROM:
Construction of Brgy. Poctoy Flood Control,
Boac, Marinduque

CW1: 179.00 lin.m ( Construction of Revetment )
Allocation: 6,000,000 Php

TO:
Construction of Brgy. Poctoy Flood Control,
Boac, Marinduque

CW1: 110.00 lin.m ( Construction of Revetment )
Allocation: 6,000,000 Php
May 15, 2018 FY - 2018 WIN8F05371 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
Local Program

Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM:
Concreting of Brgy. Danao - Mampaitan Road,
Mogpog, Marinduque

CW1: 1.055 Lane km ( Construction of Concrete Road )
Allocation: 6,000,000 Php

TO:
Concreting of Brgy. Danao - Mampaitan Road,
Mogpog, Marinduque

CW1: 1.404 Lane km ( Construction of Concrete Road )
Allocation: 6,000,000 Php
May 15, 2018 FY 2018 WIN8G02008 FY 2018 GAA R.A. 10964 November 29, 2017 Region V Regional Office V
UACS No.: 310201100077000
Project ID: P00201261LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program - Road Widening – Primary Roads - Daang Maharlika (LZ) - K0618+320 - K0619+522, K0619+742 - K0620+000, K0621+676 - K0621+987, K0622+680 - K0623+295, K0623+516 - K0624+320
Physical Target - CW1- Road Widening/ 6.382 lane-km
CW2- Construction of Drainage Structure along Road/
3,653 lm
Unit Cost: CW1 - Php 12.888M/lane-km
CW1 - Php 10,980/lm
Estimated Cost: Php 126.801M
(As Modified)

May 15, 2018 FY 2018 WIN8G02020 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
UACS No.: 310201100063000
Project ID: P00201252LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program - Road Widening – Primary Roads - Daang Maharlika (LZ) – K0247+883 – K0250+193, K0250+719 – K0250+832, K0251+180 – K0251+800
Physical Target - CW1 – Road Widening/5.6804 lane-km
CW2 - Construction of Drainage Structure along Road/ 4,446.00 lm.
Unit Cost: CW1 – Php 16.589M/lane-km
CW2 – Php 11.36T/lm
Estimated Cost: Php 150.0M
(As Modified)
May 15, 2018 2018 310109100019000 GAA FY 2018 January 1, 2018 Region II Quirino District Engineering Office
OO1: Ensure Safe and Reliable National Road System - Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads

Jct Abbag-Guingin Bdry Rd - K0392 + 900 - K0393 + 255
May 15, 2018 FY 2018 WIN8G02006 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
UACS No.: 300201100067000
Project ID: P00201253LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program - Road Widening - Primary Roads - Daang Maharlika (LZ) – K0335+971 – K0336+040, K0336+858 – K0337+245, K0337+255 – K0338+461, K0338+486 – K0339+092, K0339+186 – K0339+479, K0339+663 – K0339+803, K0339+817 – K0340+174, K0341+257 – K0341+445, K0342+600 – K0342+713, K0343+412 – K0343+416, K0343+493 – K0343+880, K0345+208 – K0345+500
Physical Target - CW1 – Road Widening/8.04250 lane-km
CW2 - Construction of Drainage Structure along Road/ 3,765.00 lm.
CW3 – Construction of Slope Protection Structure/ 27,467.97 sq.m.
Unit Cost: CW1 – Php 7.998M/lane-km
CW2 – Php 10.71T/lm
CW3 - Php 1.46T/sq.m.
Estimated Cost: Php 150.0M
(As Modified)

May 15, 2018 FY 2018 WIN8G02000 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
UACS No.: 300201100069000
Project ID: P00201254LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program - Road Widening – Primary Roads - Daang Maharlika (LZ) – K0371+-269 – K0371+160, K0371+167 – K0371+841, K0371+847.30 – K0373+660
Physical Target - CW1 – Road Widening/4.684 lane-km
CW2 - Construction of Drainage Structure along Road/ 3,310.20 lm.
Unit Cost: PhpCW1 – Php 22.42M/lane-km
CW2 – Php 12.01T/lm
Estimated Cost: Php 150.0M
(As Modified)

May 15, 2018 2018 WIN8C02910 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao Oriental 2nd District Engineering Office

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development
Construction of Bypass and Diversion Roads
Mapantad-Tagbobolo-Taguibo Road, incl. Slope Protection, Davao Oriental
Physical Target:
CW1: 8.000 Lane Km (Construction of Concrete Road)
CW2: 3,500.00 sq. m. (Construction of Slope Protection Structure)
Allocation:
TOTAL: P 55,000,000.00
CW1: P 46,320,000.00 (Construction of Concrete Road)
CW2: P 6,755,000.00 (Construction of Slope Protection Structure)
EAO: P 1,925,000.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development
Construction of Bypass and Diversion Roads
Mapantad-Tagbobolo-Taguibo Road, Davao Oriental
Physical Target:
CW1: 6.040 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 55,000,000.00
CW1: P 53,075,000.00 (Construction of Concrete Road)
EAO: P 1,925,000.00
May 15, 2018 FY 2018 GAA WIN8C02983 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao City District Engineering Office

MODIFICATION:

FROM: Local Program - Flood Control and Drainage
Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Improvement/ Construction of Drainage along Tulip Drive, Davao City
Physical Target:
CW1: 500 Lineal Meters (Construction of Drainage Structure)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 28,950,000.00 (Construction of Drainage Structure)
EAO: P 1,050,000.00

TO: Local Program- Flood Control and Drainage
Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Improvement/ Construction of Drainage along Tulip Drive, Davao City
Physical Target:
CW1: 1,272 Lineal Meters (Construction of Drainage Structure)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 28,950,000.00 (Construction of Drainage Structure)
EAO: P 1,050,000.00
May 15, 2018 FY 2018 GAA WIN8C02749 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Norte District Engineering Office

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development
Off-Carriageway Improvement- Secondary Roads
Tagum City Diversion Rd – K1459+605 – K1460+803.80
Physical Target:
CW1: 9,498.40 sq. m. (Off-Carriageway Improvement: Shoulder Paving/Construction)
Allocation:
TOTAL: P 57,780,000.00
CW1: P 55,757,700.00 (Off-Carriageway Improvement: Shoulder Paving/Construction)
EAO: P 2,022,300.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development
Off-Carriageway Improvement- Secondary Roads
Tagum City Diversion Rd – K1459+600 – K1460+793
Physical Target:
CW1: 7,808.79 sq. m. (Off-Carriageway Improvement: Shoulder Paving/Construction)
ROW: 4,150.00 sq. m.
Allocation:
TOTAL: P 57,780,000.00
CW1: P 54,900,700.00 (Off-Carriageway Improvement: Shoulder Paving/Construction)
ROW: P 857,000.00
EAO: P 2,022,300.00
May 15, 2018 FY 2018 GAA WIN8C02975 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao City District Engineering Office

MODIFICATION:

FROM: Convergence and Special Support Program
Construction/ Improvement of Access Roads leading to Declared Tourism Destinations
Coaco Road leading to Coaco Beach Resort, Brgy. Pampanga, Davao City
Physical Targets:
CW1: 0.240 Lane km (Construction of Concrete Road)
CW2: 0.600 Lane km (Reconstruction from Paved to Concrete)
Allocation:
TOTAL: P 5,110,000.00
CW1: P 2,116,800.00 (Construction of Concrete Road)
CW2: P 2,891,000.00 (Reconstruction from Paved to Concrete)
EAO: P 102,200.00

TO: Convergence and Special Support Program
Construction/ Improvement of Access Roads leading to Declared Tourism Destinations
Coaco Road leading to Coaco Beach Resort, Brgy. Pampanga, Davao City
Physical Targets:
CW1: 0.298 Lane km (Construction of Concrete Road)
CW2: 524 sq.m. (Additional Lane Width)
Allocation:
TOTAL: P 5,110,000.00
CW1: P 2,669,520.00 (Construction of Concrete Road)
CW2: P 2,338,280.00 (Additional Lane Width)
EAO: P 102,200.00
May 15, 2018 FY 2018 GAA WIN8C02977 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao City District Engineering Office

MODIFICATION:

FROM: Local Program - Flood Control and Drainage
Drainage/Protection Works - Construction/Repair/ Rehabilitation/Improvement of Various Infrastructure including Local Projects
Improvement/Rehabilitation of Drainage along Ecowest Drive, Davao City
Physical Targets:
CW1: 630 lineal meter (Construction of Drainage Structure)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 28,950,000.00 (Construction of Drainage Structure)
EAO: P 1,050,000.00

TO: Local Program - Flood Control and Drainage
Drainage/Protection Works - Construction/Repair/ Rehabilitation/Improvement of Various Infrastructure including Local Projects
Improvement/Rehabilitation of Drainage along Ecowest Drive, Davao City
Physical Targets:
CW1: 1,210 lineal meter (Construction of Drainage Structure)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 28,950,000.00 (Construction of Drainage Structure)
EAO: P 1,050,000.00
May 15, 2018 FY 2018 GAA WIN8C02976 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao City District Engineering Office

MODIFICATION:

FROM: Convergence and Special Support Program
Construction/ Improvement of Access Roads leading to Declared Tourism Destinations
Mamay Road Extension leading to D’Leonor Inland Resort and Adventure Park, Brgy. Cabantian, Davao City
Physical Targets:
CW1: 0.900 Lane Km (Reconstruction from Paved to Concrete)
Allocation:
TOTAL: P 6,750,000.00
CW1: P 6,615,000.00 (Reconstruction from Paved to Concrete)
EAO: P 135,000.00

TO: Convergence and Special Support Program
Construction/ Improvement of Access Roads leading to Declared Tourism Destinations
Mamay Road Extension leading to D’Leonor Inland Resort and Adventure Park, Brgy. Cabantian, Davao City
Physical Targets:
CW1: 0.880 Lane Km (Additional Lane Width)
Allocation:
TOTAL: P 6,750,000.00
CW1: P 6,615,000.00 (Additional Lane Width)
EAO: P 135,000.00
May 15, 2018 FY 2018 GAA WIN8C02738 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Norte District Engineering Office

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Asset Preservation
Preventive Maintenance – Secondary Roads
Tagum City Diversion Rd – K1455+000 – K1456+076, K1456+255 – K1456+635
Physical Target:
CW1: 6.120 Lane Km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 48,960,000.00
CW1: P 47,980,800.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 979,200.00

TO: OO1: Ensure Safe and Reliable National Road System – Asset Preservation
Preventive Maintenance – Secondary Roads
Tagum City Diversion Rd – K1456+(-1095) – K1456+076, K1456+255 – K1456+400
Physical Target:
CW1: 5.264 Lane Km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 48,960,000.00
CW1: P 47,980,800.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 979,200.00
May 15, 2018 FY 2018 WIN8G02181 FY 2018 GAA January 4, 2018 Region III Pampanga 2nd District Engineering Office
Local Roads and Bridges – Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects - Concreting of Road, Brgy. San Isidro, Santa Rita, Pampanga
May 15, 2018 FY 2018 WIN8G02196 FY 2018 GAA January 4, 2018 Region III Tarlac District Engineering Office
Network Development Program - Construction of By-Pass and Diversion Roads - Sta. Ignacia - Guimba Road via Gerona Pura (Sta. Ignacia Section) incl. Slope Protection, Tarlac
May 15, 2018 FY 2018 WIN8G02201 FY 2018 GAA January 4, 2018 Region III Tarlac District Engineering Office
Network Development Program - Construction of By-Pass and Diversion Roads - Romulo Highway to MNR via Fairlane Bypass/ Diversion Road, incl. Drainage, Tarlac

May 15, 2018 WIN8G02198 WIN8G02198 FY 2018 GAA January 4, 2018 Region III Tarlac District Engineering Office
Network Development Program - Construction of By-Pass and Diversion Roads - Sta. Ignacia-Guimba Road via Gerona Pura (Gerona Section 2), Tarlac
May 15, 2018 FY 2018 WIN8G02200 FY 2018 GAA January 4, 2018 Region III Tarlac District Engineering Office
Network Development Program - Construction of By-Pass and Diversion Roads - MNR to Tarlac - San Miguel via Macabulos Road, incl. Drainage, Tarlac

May 15, 2018 FY 2018 GAA WIN8C02716 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Norte District Engineering Office

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development
Road Widening – Secondary Roads
Kapalong-Talaingod-Valencia (Bukidnon) Rd incl. ROW –
K1488+382 – K1490+190, K1491+966 – K1492+418
Physical Target:
CW1: 4.520 Lane Km (Road Widening)
ROW: 3,299.60 sq. m.
Allocation:
TOTAL: P 90,740,000.00
CW1: P 77,293,605.00 (Road Widening)
ROW: P 10,270,495.00
EAO: P 3,175,900.00

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development
Road Widening – Secondary Roads
Kapalong-Talaingod-Valencia (Bukidnon) Rd incl. ROW –
K1489+039.15 – K1490+155, K1491+966 – K1492+418
Physical Target:
CW1: 3.136 Lane Km (Road Widening)
CW2: 3,136.00 Lineal Meters (Construction of Drainage Structure along Road)
ROW: 3,299.60 sq. m.
Allocation:
TOTAL: P 90,740,000.00
CW1: P 29,152,510.00 (Road Widening)
CW2: P 47,768,560.00 (Construction of Drainage Structure along Road)
ROW: P 10,643,000.00
EAO: P 3,175,900.00
May 15, 2018 FY 2018 WIN8G02023 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
UACS No.: 300201100073000
Project ID: P00201256LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program - Road Widening – Primary Roads - Daang Maharlika (LZ) – K0426+722 – K0428+361.50, K0428+383.47 – K0429+581, K0430+182.30 – K0431+150
Physical Target - CW1 – Road Widening/ 7.629 lane-km
Unit Cost: CW1 – Php 17.360M /lane-km
Estimated Cost: Php 137.244M
(As Modified)

May 15, 2018 FY 2018 WIN8G02195 FY 2018 GAA January 4, 2018 Region III Tarlac District Engineering Office
Network Development Program - Construction of By-Pass and Diversion Roads - Paniqui-Camiling-Wawa Road to Sta. Ignacia-Guimba Road via Gerona and Pura incl. Bridge, Tarlac
May 15, 2018 FY 2018 WIN8G02005 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
UACS No.: 300201100074000
Project ID: P00201257LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program - Road Widening – Primary Roads - Daang Maharlika (LZ) – K0437+258 - K0441+290
Physical Target - Road Widening/ 7.47 lane-km
Unit Cost: Php 16.148M /lane-km
Estimated Cost: Php 125.0M
(As Modified)
May 15, 2018 FY 2018 WIN8G02193 FY 2018 GAA January 4, 2018 Region III Tarlac District Engineering Office
Network Development Program – Road Widening – Tarlac – San Miguel via Macabulos Rd – K0122 + 400 – K0124 + 750
May 15, 2018 FY 2018 WIN8G02007 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
UACS No.: 300201100194000
Project ID: P00201262LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program - Road Widening – Primary Roads – Rolando A Andaya Highway – K0283+183 – K0285+888, K0285+916 – K0286+760
Physical Target - CW1 – Road Widening/ 7.117 lane-km
Unit Cost: CW1 – Php 20.338M /lane-km
Estimated Cost: Php 150.0M
(As Modified)
May 15, 2018 FY 2018 WIN8G02007 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
UACS No.: 300201100194000
Project ID: P00201262LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program - Road Widening – Primary Roads – Rolando A Andaya Highway – K0283+183 – K0285+888, K0285+916 – K0286+760
Physical Target - CW1 – Road Widening/ 7.117 lane-km
Unit Cost: CW1 – Php 20.338M /lane-km
Estimated Cost: Php 150.0M
(As Modified)
May 15, 2018 FY 2018 WIN8G02007 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
UACS No.: 300201100194000
Project ID: P00201262LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program - Road Widening – Primary Roads – Rolando A Andaya Highway – K0283+183 – K0285+888, K0285+916 – K0286+760
Physical Target - CW1 – Road Widening/ 7.117 lane-km
Unit Cost: CW1 – Php 20.338M /lane-km
Estimated Cost: Php 150.0M
(As Modified)
May 15, 2018 FY 2018 WIN8G02028 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
UACS No.: 300201100196000
Project ID: P00201264LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program - Road Widening – Primary Roads – Rolando A Andaya Highway – K0294+477 – K0295+980
Physical Target - CW1 – Road Widening/ 3.018 lane-km
CW2 - Construction of Drainage Structure along Road/ 2,312 lm.
Unit Cost: CW1 – Php 14.693M /lane-km
CW2 – Php 12.00T/lm
Estimated Cost: Php 74.701M
(As Modified)

May 15, 2018 FY 2018 WIN8G01991 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
OO1: Ensure Safe and Reliable National Road System –
Asset Preservation Program - Construction/Upgrading/Rehabilitation of Drainage along National Roads - Secondary Roads – Sn Fernando North Rd – K0001+950 – K0002+070, K0006+338 – K0006+520, K0006+985 – K0007+101, K0007+104 – K0007+141, K0008+389 – K0008+565, K0008+860 – K0009+200, K0009+315 – K0009+415, K0015+106 – K0015+414, K0015+516 – K0015+695, K0016+089 – K0016+348, K0016+454 – K0016+952, K0018+224 – K0018+506, K0021+022 – K0021+084, K0023+130 – K0023+268, K0024+146 – K0024+383, K0025+000 – K0025+708, K0021+250 – K0021+421, K0021+426 – K0021+947
Physical Target - CW1 - Construction of Drainage Structure along Road/ 5,061 lm.
Unit Cost: Php 13,306.17/lm.
Estimated Cost: Php 68.785M
(As Modified)

May 15, 2018 FY 2018 WIN8G01991 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
OO1: Ensure Safe and Reliable National Road System –
Asset Preservation Program - Construction/Upgrading/Rehabilitation of Drainage along National Roads - Secondary Roads – Sn Fernando North Rd – K0001+950 – K0002+070, K0006+338 – K0006+520, K0006+985 – K0007+101, K0007+104 – K0007+141, K0008+389 – K0008+565, K0008+860 – K0009+200, K0009+315 – K0009+415, K0015+106 – K0015+414, K0015+516 – K0015+695, K0016+089 – K0016+348, K0016+454 – K0016+952, K0018+224 – K0018+506, K0021+022 – K0021+084, K0023+130 – K0023+268, K0024+146 – K0024+383, K0025+000 – K0025+708, K0021+250 – K0021+421, K0021+426 – K0021+947
Physical Target - CW1 - Construction of Drainage Structure along Road/ 5,061 lm.
Unit Cost: Php 13,306.17/lm.
Estimated Cost: Php 68.785M
(As Modified)

May 15, 2018 FY 2018 WIN8G01983 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
OO1: Ensure Safe and Reliable National Road System –
Asset Preservation Program - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads – Tertiary Roads – Sn Pascual-Claveria Rd – K0007+000 – K0008+000, K0009+000 – K0010+314, K0013+232 – K0014+400, K0047+214 – K0048+000, K0048+238 – K0048+438, K0048+538 – K0048+601, K0048+862 – K0049+000, K0053+000 – K0053+200, K0053+474 – K0053+574, K0053+874 – K0054+000
Physical Target - CW1- Rehabilitation of Paved Road/ 9.3228 lane-km
Unit Cost: Php 17.57M/ lane-km
Estimated Cost: Php 169.73M
(As Modified)
May 15, 2018 FY 2018 GAA WIN8C02717 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Norte District Engineering Office

MODIFICATION:

FROM: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Dagohoy-Sitio Paition Road leading to Pabahay sa Lumad, incl. Bridge, Brgy. Dagohoy, Talaingod, Davao del Norte
Physical Target:
CW1: 6.480 Lane Km (Construction of Concrete Road)
CW2: 381.600 sq. m. (Construction of Concrete Bridge)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 57,900,000.00 (Construction of Concrete Road)
CW2: P 38,600,000.00 (Construction of Concrete Bridge)
EAO: P 3,500,000.00

TO: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Dagohoy-Sitio Paiton Road leading to Pabahay sa Lumad, Brgy. Dagohoy, Talaingod, Davao del Norte
Physical Target:
CW1: 7.810 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Construction of Concrete Road)
EAO: P 3,500,000.00
May 15, 2018 FY 2018 GAA WIN8C02736 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Norte District Engineering Office

MODIFICATION:

FROM: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Access Roads leading to Tagum Energy Park, Brgy. Apokon to Hijo Resources to Lanikai Boutique Hotel and Banana Beach, Brgy. Madaum, Tagum City, Davao del Norte
Physical Target:
CW1: 6.668 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Construction of Concrete Road)
EAO: P 3,500,000.00

TO: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Access Roads leading to Tagum Energy Park, Brgy. Apokon to Hijo Resources to Lanikai Boutique Hotel and Banana Beach, Brgy. Madaum, Tagum City, Davao del Norte
Physical Target:
CW1: 7.367 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Construction of Concrete Road)
EAO: P 3,500,000.00
May 15, 2018 FY 2018 GAA WIN8C02748 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Norte District Engineering Office

MODIFICATION:

FROM: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Panas, Carcor-Patrocenio to El Salvador to Nabunturan leading to Tinagong Busay Cave and View Deck and Balaan Bukid, Brgy. Carcor, New Corella, Davao del Norte
Physical Target:
CW1: 9.010 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: 100,000,000.00
CW1: P 96,500,000.00 (Construction of Concrete Road)
EAO: P 3,500,000.00

TO: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Panas, Carcor-Patrocenio to El Salvador to Nabunturan leading to Tinagong Busay Cave and View Deck and Balaan Bukid, Brgy. Carcor, New Corella, Davao del Norte
Physical Target:
CW1: 3.560 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: 100,000,000.00
CW1: P 96,500,000.00 (Construction of Concrete Road)
EAO: P 3,500,000.00
May 15, 2018 FY 2018 GAA WIN8C02751 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Norte District Engineering Office

MODIFICATION:

FROM: Local Program – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure Including Local Projects
Rehabilitation of Road Purok 2 – Purok 9, Brgy. Cabaywa, Asuncion, Davao del Norte
Physical Target:
CW1: 0.220 Lane Km (Rehabilitation of Concrete Road)
Allocation:
TOTAL: P 2,000,000.00
CW1: P 1,960,000.00 (Rehabilitation of Concrete Road)
EAO: P 40,000.00

TO: Local Program – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure Including Local Projects
Rehabilitation of Road Purok 2 – Purok 9, Brgy. Cabaywa, Asuncion, Davao del Norte
Physical Target:
CW1: 0.220 Lane Km (Construction of Gravel Road)
Allocation:
TOTAL: P 2,000,000.00
CW1: P 1,960,000.00 (Construction of Gravel Road)
EAO: P 40,000.00
May 15, 2018 FY 2018 GAA WIN8C02718 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Norte District Engineering Office

MODIFICATION:

FROM: Local Program – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure Including Local Projects
Rehabilitation of Road Purok 8 – Purok 5, Sto. Niño, - Purok Falcata, Brgy. Sawata, Davao del Norte
Physical Target:
CW1: 0.430 Lane Km (Rehabilitation of Concrete Road)
Allocation:
TOTAL: P 5,000,000.00
CW1: P 4,900,000.00 (Rehabilitation of Concrete Road)
EAO: P 100,000.00

TO: Local Program – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure Including Local Projects
Rehabilitation of Road Purok 8 – Purok 5, Sto. Niño, - Purok Falcata, Brgy. Sawata, Davao del Norte
Physical Target:
CW1: 0.722 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 5,000,000.00
CW1: P 4,900,000.00 (Construction of Concrete Road)
EAO: P 100,000.00
May 15, 2018 FY 2018 GAA WIN8C02756 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Norte District Engineering Office

MODIFICATION:

FROM: Local Program – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure Including Local Projects
Rehabilitation of Road Brgy. Sanangan, San Isidro – Brgy. Sta. Felomina, Asuncion, Brgy. San Miguel, San Isidro, Davao del Norte
Physical Target:
CW1: 0.430 Lane Km (Rehabilitation of Concrete Road)
Allocation:
TOTAL: P 5,000,000.00
CW1: P 4,900,000.00 (Rehabilitation of Concrete Road)
EAO: P 100,000.00

TO: Local Program – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure Including Local Projects
Rehabilitation of Road Brgy. Sanangan, San Isidro – Brgy. Sta. Felomina, Asuncion, Brgy. San Miguel, San Isidro, Davao del Norte
Physical Target:
CW1: 0.540 Lane Km (Rehabilitation of Concrete Road)
Allocation:
TOTAL: P 5,000,000.00
CW1: P 4,900,000.00 (Rehabilitation of Concrete Road)
EAO: P 100,000.00
May 15, 2018 FY 2018 GAA WIN8C02728 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Norte District Engineering Office
MODIFICATION:

FROM: Local Program – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure Including Local Projects
Construction of Road Park. 8, Upper La Filipia – Prk. San Isidro, Brgy. La Filipina, Tagum City, Davao del Norte
Physical Target:
CW1: 2.220 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 10,000,000.00
CW1: P 9,800,000.00 (Construction of Concrete Road)
EAO: P 200,000.00

TO: Local Program – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure Including Local Projects
Construction of Road Park. 8, Upper La Filipina – Prk. San Isidro, Brgy. La Filipina, Tagum City, Davao del Norte
Physical Target:
CW1: 1.580 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 10,000,000.00
CW1: P 9,800,000.00 (Construction of Concrete Road)
EAO: P 200,000.00
May 15, 2018 FY 2018 GAA WIN8C02779 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Norte District Engineering Office
MODIFICATION:

FROM: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Brgy. Liboganon Road leading to Local Beach Resorts, Brgy. Liboganon, Tagum City, Davao del Norte
Physical Target:
CW1: 8.000 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 60,000,000.00
CW1: P 57,900,000.00 (Construction of Concrete Road)
EAO: P 2,100,000.00

TO: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Brgy. Liboganon Road leading to Local Beach Resorts, Brgy. Liboganon, Tagum City, Davao del Norte
Physical Target:
CW1: 4.495 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 60,000,000.00
CW1: P 57,900,000.00 (Construction of Concrete Road)
EAO: P 2,100,000.00
May 15, 2018 FY 2018 GAA WIN8C02729 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Norte District Engineering Office
MODIFICATION:

FROM: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Access Road leading to Tribal Village, Tibyun Cave, San Miguel Cave and Paradise Cave, New Corella, Davao del Norte
Physical Target:
CW1: 9.760 lane km (Construction of Concrete Road)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Construction of Concrete Road)
EAO: P 3,500,000.00

TO: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Access Road leading to Tribal Village, Tibyun Cave, San Miguel Cave and Paradise Cave, New Corella, Davao del Norte
Physical Target:
CW1: 6.920 lane km (Construction of Concrete Road)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Construction of Concrete Road)
EAO: P 3,500,000.00
May 15, 2018 FY 2018 GAA WIN8C02982 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao City District Engineering Office

MODIFICATION:

FROM: Convergence and Special Support Program
Construction/ Improvement of Access Roads leading to Declared Tourism Destinations
Matina Aplaya-Punta Dumalag Road Leading to Seagull Beach Resort-Pawikan Sanctuary and Felis Beach Resort, Brgy. Matina Aplaya, Davao City
Physical Targets:
CW1: 3.392 Lane km (Reconstruction from Paved to Concrete)
Allocation:
TOTAL: P 12,561,000.00
CW1: P 12,309,780.00 (Reconstruction from Paved to Concrete)
EAO: P 251,220.00

TO: Convergence and Special Support Program
Construction/ Improvement of Access Roads leading to Declared Tourism Destinations
Matina Aplaya-Punta Dumalag Road Leading to Seagull Beach Resort-Pawikan Sanctuary and Felis Beach Resort, Brgy. Matina Aplaya, Davao City
Physical Targets:
CW1: 0.202 Lane km (Construction of Concrete Road)
CW2: 3,037.32 sq.m. (Additional Lane Width)
Allocation:
TOTAL: P 12,561,000.00
CW1: P 1,656,470.00 (Construction of Concrete Road)
CW2: P 10,653,310.00 (Additional Lane Width)
EAO: P 251,220.00
May 13, 2018 FY 2018 WIN8C02663 300117201978000 May 3, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300117201978000
Project ID: P00250079MN

Local Program:

Local Roads and Bridges - Local Roads - Local Infrastructure Program

Concreting of Lapakan Road, Zamboanga City

Physical Target:
CW-1 - Construction of Concrete Road: 0.30 lane km.
Unit Cost: P 6,600,000.00/lane km.
EAO: P 20,000.00
Allocation: 2,000,000.00
May 13, 2018 FY 2018 WIN8C02723 300117201976000 May 3, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300117201976000
Project ID: P00250077MN

Local Program:

Local Roads and Bridges - Local Roads - Local Infrastructure Program

Concreting of Road, Cacao, Zamboanga City

Physical Target:
CW-1 - Construction of Concrete Road: 0.16 lane km.
Unit Cost: P 12,375,000.00/lane km.
EAO: P 20,000.00
Allocation: P 2,000,000.00
May 13, 2018 FY 2018 WIN8C02786 300117201977000 May 3, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300117201977000
Project ID: P00250078MN

Local Program:

Local Roads and Bridges - Local Roads - Local Infrastructure Program

Concreting of Road, Culianan, Zamboanga City

Physical Target:
CW-1 - Construction of Concrete Road: 0.26 lane km.
Unit Cost: P 7,615,384.62/lane km.
EAO: P 20,000.00
Allocation: P 2,000,000.00
May 13, 2018 FY 2018 WIN8C02703 300117201980000 May 3, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300117201980000
Project ID: P00250081MN

Local Program:

Local Roads and Bridges - Local Roads - Local Infrastructure Program

Concreting of Road, Lumbangan, Zamboanga City

Physical Target:
CW-1 - Construction of Concrete Road: 0.18 lane km.
Unit Cost: P 8,250,000.00/lane km.
EAO: P 15,000.00
Allocation: P 1,500,000.00
May 13, 2018 FY 2018 WIN8C02664 300117201974000 May 3, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300117201974000
Project ID: P00250063MN

Local Program:

Local Roads and Bridges - Local Roads - Local Infrastructure Program

Concreting of Road, Brgy. Zambowood, Zamboanga City

Physical Target:
CW-1 - Construction of Concrete Road: 0.12 lane km.
Unit Cost: P 12,375,000.00
EAO: P 15,000.00
Allocation: P 1,500,000.00
May 13, 2018 FY 2018 WIN8C02705 300109200212000 May 3, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300109200212000
Project ID: P00251840MN

Local Program:

Flood Control and Drainage - Drainage/Protection Works - Local Infrastructure Program

Construction/Rehabilitation of Drainage Facilities, Brgy. Baliwasan, Zamboanga City

Physical Target:
CW-1 - Construction of Drainage Structure: 260.72 ln.m.
Unit Cost: P 11,391.53/lane km.
EAO: P 30,000.00
Allocation: P 3,000,000.00
May 13, 2018 FY 2018 WIN8C2684 300117201962000 May 3, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300117201962000
Project ID: P00251830MN

Local Program:

Local Roads and Bridges - Local Roads - Local Infrastructure Program

Concreting of Road Including Drainage Facilities Tumaga - Aurora, Tumaga, Zamboanga City

Physical Target:
CW-1 - Construction of Concrete Road: 1.26 lane km.
Unit Cost: P 8,878,571.43/lane km.
EAO: P 113,000.00
Allocation: P 11,300,000.00
May 13, 2018 FY 2018 WIN8C02785 310305100429000 May 3, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 310305100429000
Project ID: P00201115MN

OO1: Ensure Safe and Reliable National Road System - Bridge

Widening of Permanent Bridges

San Ignacio Br. (B00555MN) along Governor Camins Rd

Physical Target:
CW-1 - Widening of Bridge: 151.11 sq.m.
Unit Cost: P 110,118.46/sq.m.
CW-2 - ROW: 900.00 sq.m.
Unit Cost: P 1,111.11/sq.m.
EAO: P 360,000.00
Allocation: P 18,000,000.00
May 13, 2018 FY 2018 WIN8C02760 300117201963000 May 3, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300117201963000
Project ID: P00251829MN

Local Program:

Local Roads and Bridges - Local Roads - Local Infrastructure Program

Concreting of Road Leading to San Roque National High School(Including Drainage Facilities), San Roque, Zamboanga City

Physical Target:
CW-1 - Construction of Concrete Road: 1.28 lane km.
Unit Cost: P 11,601,562.50/lane km.
EAO: P 150,000.00
Allocation: P 15,000,000.00
May 13, 2018 FY 2018 WIN8C02687 310305100441000 May 3, 2018 Region IX Zamboanga Sibugay 2nd District Engineering Office
UACS No. 310305100441000
Project ID: P00201136MN

OO1: Ensure Safe and Reliable National Road System - Bridge - Widening of Permanent Bridges

Calapan (B00489MN) along Lanao - Pagadian - Zamboanga City Rd

Physical Target:
CW-1 - Widening of Bridge: 399.20 square meters
Unit Cost: P 67,443.64/square meter
ROW Acquisition: 1,395.00 sq.m.
Unit Cost: P 300/sq.m.
EAO: P 0.558 M
Allocation: P 27.90 M
May 13, 2018 FY 2018 WIN8C02755 310305100440000 May 3, 2018 Region IX Zamboanga Sibugay 2nd District Engineering Office
UACS No. 310305100440000
Project ID: P00201135MN

OO1: Ensure Safe and Reliable National Road System - Bridge - Widening of Permanent Bridges

Batu Br. (B00488MN) along Lanao-Pagadian-Zamboanga City Rd

Physical Target:
CW-1 - Widening of Bridge: 506.18 square meters
Unit Cost: P 69,642.12/square meter
ROW Acquisition: 1,826.50 sq.m.
Unit Cost: P 300/sq.m.
EAO: P 0.7306 M
Allocation: P 36.53 M
May 13, 2018 FY 2018 WIN8C02675 310305100442000 May 3, 2018 Region IX Zamboanga Sibugay 2nd District Engineering Office
UACS No. 310305100442000
Project ID: P00201137MN

OO1: Ensure Safe and Reliable National Road System - Bridge - Widening of Permanent Bridges

Dipala Br. (B00491MN) along Lanao-Pagadian-Zamboanga City Rd

Physical Target:
CW-1 - Widening of Bridge: 399.20 square meters
Unit Cost: P 67,226.08/square meter
ROW Acquisition: 1,390.50 sq.m.
Unit Cost: P 300/sq.m.
EAO: P 0.5562 M
Allocation: P 27.81 M
May 13, 2018 FY 2018 WIN8C02678 310305100443000 May 3, 2018 Region IX Zamboanga Sibugay 2nd District Engineering Office
UACS No. 310305100443000
Project ID: P00201138MN

OO1: Ensure Safe and Reliable National Road System - Bridge - Widening of Permanent Bridges

Lumbayao Br. (B00492MN) along Lanao-Pagadian-Zamboanga City Rd

Physical Target:
CW-1 - Widening of Bridge: 371.52 square meters
Unit Cost: P 67,273.63/square meter
ROW Acquisition: 1,295.00 sq.m.
Unit Cost: P 300/sq.m.
EAO: P 0.518 M
Allocation: P 25.90 M
May 13, 2018 FY 2018 WIN8C02873 300117201985000 May 7, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300117201985000
Project ID: P 00250085MN

Local Program:

Local Roads and Bridges - Local Roads - Local Infrastructure Program

Concreting of Road, Quiniput, Zamboanga City

Physical Target:
CW-1 - Construction of Concrete Road: 0.22 lane km.
Unit Cost: P 9,000,000.00/lane km.
EAO: P 20,000.00
Allocation: P 2,000,000.00
May 13, 2018 FY 2018 WIN8C02861 300116201151000 May 7, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300116201151000
Project ID: P00258445MN

Local Program:

Local Roads and Bridges - Local Roads -
Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects

Concreting of San Roque Road, San Roque, Zamboannga City

Physical Target:
CW-1 - Construction of Concrete Road: 0.53 lane km.
Unit Cost: P 5,547,169.81/lane km.
EAO: P 60,000.00
Allocation: P 3,000,000.00
May 13, 2018 FY 2018 WIN8C02864 300117201969000 May 7, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300117201969000
Project ID: P00250060MN

Local Program:

Local Roads and Bridges - Local Roads - Local Infrastructure Program

Concreting of Road, Taguiti, Zamboanga City

Physical Target:
CW-1 - Construction of Concrete Road: 0.32 lane km.
Unit Cost: P 4,640,625.00/lane km.
EAO: P 15,000.00
Allocation: P 1,500,000.00
May 13, 2018 FY 2018 WIN8C02874 300117201987000 May 7, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300117201987000
Project ID: P 00250087MN

Local Program:

Local Roads and Bridges - Local Roads - Local Infrastructure Program

Concreting of Road, Tigbalabag, Zamboanga City

Physical Target:
CW-1 - Construction of Concrete Road: 0.18 lane km.
Unit Cost: P 8,250,000.00/lane km.
EAO: P 15,000.00
Allocation: P 1,500,000.00
May 13, 2018 FY 2018 WIN8C02887 300117201972000 May 7, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300117201972000
Project ID: P00250062MN

Local Program:

Local Roads and Bridges - Local Roads - Local Infrastructure Program

Concreting of Road, Tumitus, Zamboanga City

Physical Target:
CW-1 - Construction of Concrete Road: 0.31 lane km.
Unit Cost: 4,790,322.58/lane km.
EAO: P 15,000.00
Allocation: P 1,500,000.00
May 13, 2018 FY 2018 WIN8C02865 300117201986000 May 7, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300117201986000
Project ID: P00250086MN

Local Program:

Local Roads and Bridges - Local Roads - Local Infrastructure Program


Concreting of Road, Sibulao, Zamboanga City

Physical Target:
CW-1 - Construction of Concrete Road: 0.28 lane km.
Unit Cost: P 5,303,571.43/lane km.
EAO: P 15,000.00
Allocation: P 1,500,000.00
May 13, 2018 FY 2018 WIN8C02890 300117201984000 May 7, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300117201984000
Project ID: P00250084MN

Local Program:

Local Roads and Bridges - Local Roads - Local Infrastructure Program

Concreting of Road, Panubigan, Zamboanga City

Physical Target:
CW-1 - Construction of Concrete Road: 0.26 lane km.
Unit Cost: P 5,711,538.46/lane km.
EAO: P 15,000.00
Allocation: P 1,500,000.00
May 13, 2018 FY 2018 WIN8C02962 300117201988000 May 8, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300117201988000
Project ID: P00251838MN

Local Program:

Local Roads and Bridges - Local Roads - Local Infrastructure Program

Road Concreting including drainage facilities, Brgy. Baluno, Zamboanga City

Physical Target:
CW-1 - Construction of Concrete Road: 0.54 lane km.
Unit Cost: P 9,166,666.67/lane km.
EAO: P 50,000.00
Allocation: P 5,000,000.00
May 13, 2018 FY 2018 WIN8C02942 300107200218000 May 7, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300107200218000
Project ID: P00251831MN

Local Program:

Flood Control and Drainage - Flood Control Structures/Facilities - Local Infrastructure Program

Construction of Drainage Facilities at Southcom Village, Upper Calarian, Zamboanga City

Physical Target:
CW-1 - Construction of Drainage Structure: 399.36 l.m.
Unit Cost: P 8,676.382/l.m.
EAO: P 35,000.00
Allocation: P 3,500,000.00
May 13, 2018 FY 2018 WIN8C02889 300109200209000 May 7, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300109200209000
Project ID: P00250072MN

Local Program:

Local - Flood Control and Drainage - Drainage/Protection Works - Local Infrastructure Program

Construction of Drainage System, Talon-Talon, Zamboanga City

Physical Target:
CW-1 - Construction of Drainage System: 226.00 l.m.
Unit Cost: P 8,761.06/l.m.
EAO: P 20,000.00
Allocation: P 2,000,000.00
May 13, 2018 FY 2018 WIN8C02888 300109200211000 May 7, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300109200211000
Project ID: P00250074MN

Local Program:

Local - Flood Control and Drainage - Drainage/Protection Works - Local Infrastructure Program

Construction of Drainage System, Tugbungan, Zamboanga City

Physical Target:
CW-1 - Construction of Drainage Structure: 220.00 l.m.
Unit Cost: P 9,000.00/l.m.
EAO: P 20,000.00
Allocation: P 2,000,000.00
May 13, 2018 FY 2018 WIN8C02883 300109200210000 May 7, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300109200210000
Project ID: P00250073MN

Local Program:

Local - Flood Control and Drainage - Drainage/Protection Works - Local Infrastructure Program

Construction of Drainage System, Tetuan, Zamboanga City

Physical Target:
CW-1 - Construction of Drainage System: 310.00 l.m.
Unit Cost: P 9,580.65/l.m.
EAO: P 30,000.00
Allocation: P 3,000,000.00
May 13, 2018 FY 2018 WIN8C02882 320101102150000 May 7, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 320101102150000
Project ID: P00221868MN

OO2: Protect Lives and Properties Against Major Floods-Construction/Maintenance of Flood Mitigation Structures and Drainage Systems

Construction of Flood Control Structure along Sibulao River at Sibulao Section, (Including Right of Way Acquisition), Zamboanga City

Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 915.00 l.m.
Unit Cost: P 52,732.24/l.m.
ROW: 740.00 sq.m.
Unit Cost: P 1,013.51/sq.m.
EAO: P 1,000,000.00
Allocation: P 50,000,000.00
May 13, 2018 FY 2018 WIN8C02929 310103100210000 May 7, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 310103100210000
Project ID: P00200063MN

OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Tertiary Roads

Old Rd. (Ayala - Talisayan) - K1958+136 - K1958+436

Physical Target:
CW-1 - Preventive Maintenance: 0.60 lane km.
Unit Cost: P 7,350,000.00
EAO: P 90,000.00
Allocation: P 4,500,000.00
May 13, 2018 FY 2018 WIN8C02872 310201100186000 May 7, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 310201100186000
Project ID: P00200595MN

OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads

Pagadian City - Zamboanga City Road including ROW - K1935+559 - K1935+965

Physical Target:
CW-1 - Road Widening: 1.62 lane km.
Unit Cost: P 22,557,027.97/lane km.
ROW: 5,440.40 sq.m.
Unit Cost: P 11,020.91/sq.m.
EAO: P 3,500,000.00
Allocation: P 100,000,000.00
May 13, 2018 FY 2018 WIN8C02868 300109200213000 May 7, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300109200213000
Project ID: P00251839MN

Local Program:

Flood Control and Drainage - Drainage/Protection Works - Local Infrastructure Program

Construction/Rehabilitation of Drainage Facilities, Brgy. Camino Nuevo, Zamboanga City

Physical Target:
CW-1 - Construction of Drainage Structure: 144.60 lm.
Unit Cost: P 13,692.95/ln.m.
EAO: P 20,000.00
Allocation: P 2,000,000.00
May 12, 2018 FY 2018 WIN8G01879 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Camarines Sur 2nd District Engineering Office
UACS No.: 310110100027000
Project ID: P00200661LZ
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Construction/Upgrading/Rehabilitation of Drainage along National Roads - Primary Roads - Daang Maharlika (LZ) - K0454+674 - K0455+013
Physical Target - Construction of Drainage Structure along Road: 718.00 lm.
Unit Cost: Php24.212T/lm
Estimated Cost: Php17.739M
(As Modified)
May 12, 2018 FY 2018 WIN8G01908 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Camarines Sur 2nd District Engineering Office
UACS No.: 310207100025000
Project ID: P00202630LZ
OO1: Ensure Safe and Reliable National Road System - Network Development Program - Off-Carriageway Improvement - Primary Road - Daang Maharlika (LZ) - K0449+719, K0437++187, K0440+241
Physical Target - CW1 - Off-Carriageway Improvement - : Flaring of Intersections: 3.0 Number of Intersections
Unit Cost: Php 8.970M/Intersection
Estimated Cost: Php27.460M
(As Modified)

May 12, 2018 FY 2018 WIN8G02009 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Camarines Sur 2nd District Engineering Office
UACS No.: 310109100086000
Project ID: P00200934LZ
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse and Land Slide - Tertiary Roads - Hanawan-Consocep Rd - K0471+485 - K0471+532, K0471+600 - K0471+743
Physical Target - Construction of Road Slope Protection Structure/ 190.00sq.m.
Unit Cost: Php5,776.84/sq.m.
Estimated Cost: Php1.120M
(As Modified)
May 12, 2018 FY 2018 WIN8G02003 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
UACS No.: 310205100009000
Project ID: p00201152LZ
OO1: Ensure Safe and Reliable National Road System - Network Development Program - Construction of Missing Links/New Roads - Bacon-Manito Road incl. Bridge, Sorsogon
Physical Target - CW1 - Construction of Concrete Road/ 5.77 lane-km
CW2 - Construction of Concret Bridge/ 601.97 sq.m.
Unit Cost: CW1: Php19.338M/lane-km
CW2: Php55.10T/sq.m.
Estimated Cost: Php 150.0M
(As Modified)
May 12, 2018 FY 2018 WIN8G02019 FY 2018 GAA R.A. 10964 December 28, 2017 Region V Regional Office V
UACS No.: 300204100012000
Project ID: P00230358LZ
Convergence and Special Support Program – Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zone – Balud National Road connecting Barangay Danao in support of Agribusiness, Balud, Masbate
Physical Target - Construction of Concrete Road/ 12.96128 lane-km
Unit Cost: Php14.146M/lane-km
Estimated Cost: Php190.0M
(As Modified)
May 12, 2018 FY 2018 WIN8G02064 FY 2018 GAA R.A. 10964 December 28, 2017 Region V Regional Office V
OO1: Ensure Safe and Reliable National Road System – Bridge Program – Widening of Permanent Bridges - Baraca Br. 2 (B04478LZ) along Daang Maharlika (LZ)
Physical Target - CW1 - Widening of Bridge/547.10sq.m.
Unit Cost: Php 97.012T/sq.m.
Estimated Cost: Php 55.00M
(As Modified)

May 12, 2018 FY 2018 WIN8G01999 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
UACS No.: 300203100060000
Project ID: P00230362LZ
Convergence and Special Support Program – Construction/Improvement of Access Roads leading to Declared Tourism Destinations - Bulan-Matnog-Sta. Magdalena-Bulusan Road (Bulan Section) leading to Bulusan National Park, Sorsogon
Physical Target - CW1 - Construction of Concrete Road/3.76 lane-km
CW2 - Construction of Drainage Structure along Road/2,142.62 lm.
Unit Cost: CW1 - Php 22.81M/lane-km
CW2 - Php 14.01T/lm
Estimated Cost: Php 120.0M
(As Modified)
May 12, 2018 FY 2018 WIN8C02562 UACS No. 320102100505000 April 10, 2018 Region IX Zamboanga Sibugay 1st District Engineering Office
UACS No. 320102100505000
Project ID: P00220410MN
OO2: Protect Lives and Properties
Construction/Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers
Construction of Flood Control along Imelda-Bayog-Kumalarang - Lapuyan - Margostubig Road, Part of Sibuguey River, Brgy. Paradise, Diplahan, Zamboanga Sibugay (Sta. 00+689.50 - Sta. 00+738.70)
Physical Target:
CW-1- Construction of Flood Mitigation Structure: 49.20 lineal meters
Unit Cost: P 125,507.72/lineal meters
EAO: P 126,020.00
Allocation: P 6,301,000.00
May 12, 2018 FY 2018 WIN8G02001 FY 2018 GAA R.A. 10964 December 28, 2017 Region V Regional Office V
UACS No.: 310105100014000
Project ID: P00202639LZ
OO1: Ensure Safe and Reliable National Road System – Asset Preservation Program - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Secondary Roads - Catanduanes Cir Rd - K0052+416 - K0052+949, K0053+000 - K0053+350, K0054+000 - K0055+125, K0055+470 - K0056+089, K0108+421 - K0109+000, K0114+000 - K0114+151, K0118+000 - K0118+665, K0129+806 - K0130+011, K0182+400 - K0183+001, K0186+500 - K0187+000
Physical Target - CW1 - Rehabilitation of Paved Road/ 10.62 lane-km
Unit Cost: Php13.95M/lane-km
Estimated Cost: Php153.46M
(As Modified)

May 12, 2018 FY 2018 WIN8G02024 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
UACS No.: 310202100035000
Project ID: P00201384LZ
OO1: Ensure Safe and Reliable National Road System – Road Widening – Secondary Roads - Catanduanes Cir Rd - K0195+854 - K0196+842, K0197+000 - K0198+000
Physical Target - CW1 - Road Widening/ 3.9982 lane-km
Unit Cost: Php 14.689M/lane-km
Estimated Cost: Php 60.859M
(As Modified)

May 12, 2018 FY 2018 WIN8G01869 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
UACS No.: 320101100296000
Project ID: P00223246LZ
OO2: Protect Lives and Properties Against Major Floods – Flood Management Program – Construction/Maintenance of Flood Mitigation Structures and Drainage System - Construction of Flood Control Structures along Downstream Fabrica Bridge both side Sta. 4+190 to Sta. 4+585.55, Bulan, Sorsogon
Physical Target - CW1-Construction of Flood Mitigation Structure/ 573.03lm
Unit Cost: Php168.40T/lm.
Estimated Cost: Php100.0M
(As Modified)