Date Posted GAA Year Reference No SARO Number SARO Date Region Implementing Office Description
July 8, 2021 2021 WIN1C04170 GAA 2021 June 30, 2021 Cordillera Administrative Region Abra District Engineering Office
From: Construction of Isit Flood Control Phase III, Sta. 0+200 - Sta. 0+700, Dolores, Abra;
Physical Target: CW1: 94.80 Lineal meters;
Allocation= Php 20,000,000

To: Construction of Isit Flood Control Phase III, Sta. 0+200 - Sta. 0+700, Dolores, Abra;
Physical Target: CW1: 270 Lineal meters;
Allocation= Php 20,000,000

July 8, 2021 2021 WIN1C04167 GAA 2021 June 11, 2021 Cordillera Administrative Region Abra District Engineering Office
From: Rehabilitation/Construction of Sinalang - Peñarrubia Road Phase II, Peñarrubia, Abra;
Physical Target: CW1: 9.27 Lane Km;
Allocation= Php 50,000,000

To: Rehabilitation/Construction of Sinalang - Peñarrubia Road Phase II, Peñarrubia, Abra;
Physical Target: CW1: 8.2 Lane Km;
Allocation= Php 50,000,000

July 8, 2021 CY 2021 WIN1F06504 UACS NO. 310205100511000 May 20, 2021 National Capital Region NCR - Regional Office
As per GAA/Original
UACS No. 310205100511000
Project ID.: P00506023LZ

OO1: Ensure Safe and Reliable National Road System

Network Development – Construction of Missing Links/ New Roads
Laguna Lake Highway Extension (Phase 1), Taguig City
Physical Target: CW1 = Construction Concrete Road 1080 Lane Km
Unit Cost (P’000) = P 10,722.22 / Lane Km.
Allocation (P’000) = P 115,800.00
EAO (P’000) = P 4,200.00
Total (P’000) = P 120,000.00

As Modified

OO1: Ensure Safe and Reliable National Road System

Network Development – Construction of Missing Links/ New Roads
Laguna Lake Highway Extension (Phase 1), Taguig City
Physical Target: CW1 = Construction Concrete Road 2.06 Lane Km
CW2 = Construction of Concrete Bridge 124.20 sq.m.
RROW = 1,428.57 sq.m.
Unit Cost (P’000) = P 47,033.48 / Lane Km. P 94M/km
= P 71.75/ sq.m.
= P 7.00/ sq.m.
Allocation (P’000) = P 96,888.96
= P 8,911.04
= P10,000.00
EAO (P’000) = P 4,200.00
Total (P’000) = P 120,000.00
WIN1F06504
July 8, 2021 2021 WIN1E02378 FY 2021 GAA RA 11518 January 25, 2021 Region XIII Regional Office XIII
UACS No. 310201100721000
Project ID: P00501598MN

OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Primary Roads

FROM:

Daang Maharlika (Agusan-Davao Sect) - K1364 + 000 - K1367 + 000

Type of Work/Physical Target:

CW1 - Road Widening / 6.000 lane km.

Unit Cost: Php 16,887,500 / lane km.

Allocation: Php 101,325,000

EAO: Php 3,675,000

Total: Php 105,000,000

TO:

Daang Maharlika (Agusan-Davao Sect) - K1360 + 540 - K1361 + 000, K1364 + 000 - K1364 + 680

Type of Work/Physical Target:

CW1 - Road Widening / 2.280 lane km.

Unit Cost: Php 44,440,789.47 / lane km.

Estimated Cost: Php 101,325,000

EAO: Php 3,675,000

Total: Php 105,000,000
July 8, 2021 2021 WIN1C04187 GAA 2021 July 5, 2021 Cordillera Administrative Region Abra District Engineering Office
From: Abra-Ilocos Norte Rd - K0430+180 - K0430 + 300;
Type of Work: CW1: Reconstruction to Concrete Pavement;
Physical Target: CW1: 0.24 Lane Km;
Allocation= Php 100,000,000

To: Abra-Ilocos Norte Rd - K0450+000 - K0450 + 500;
Type of Work: CW1: Reconstruction to Concrete Pavement
CW2: Construction of Road Slope Protection Structure;
Physical Target: CW1: 1 Lane Km
CW2: 3,782.34 Square meters;
Allocation= Php 100,000,000


July 8, 2021 CY 2021 WIN1F06429 UACS NO. 320101106449000 February 24, 2021 National Capital Region North Manila District Engineering Office
As per GAA/Original
UACS No. 320101106449000
Project ID.: P00525815LZ

002: Protect Lives and Properties

Flood Management – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Bank Improvement (Steel Sheet Pile) along Estero dela Reina, Barangay 59, 52 Sta.0+944.90 to
Sta.0+982.30, Manila City
Physical Target: CW1 – Construction of Flood Mitigation Structure 92.50 l.m.
Unit Cost (P’000) = P 317.83 / l.m.
Allocation (P’000) = P 29,400.00
EAO (P’000) = P 600.00
Total (P’000) = P 30,000.00


002: Protect Lives and Properties

Flood Management – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Bank Improvement (Steel Sheet Pile) along Estero dela Reina, Barangay 59, 52 (LS) Sta.0+903.00 to
Sta.0+949.00, (RS) Sta. 0+911.70 to Sta. 0+958.20, Manila City
Physical Target: CW1 – Construction of Flood Mitigation Structure 92.50 l.m.
Unit Cost (P’000) = P 317.83 / l.m.
Allocation (P’000) = P 29,400.00
EAO (P’000) = P 600.00
Total (P’000) = P 30,000.00
WIN1F06429
July 8, 2021 CY 2021 WIN1F06429 UACS NO. 320101106449000 February 24, 2021 National Capital Region North Manila District Engineering Office
As per GAA/Original
UACS No. 320101106449000
Project ID.: P00525815LZ

002: Protect Lives and Properties

Flood Management – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Bank Improvement (Steel Sheet Pile) along Estero dela Reina, Barangay 59, 52 Sta.0+944.90 to
Sta.0+982.30, Manila City
Physical Target: CW1 – Construction of Flood Mitigation Structure 92.50 l.m.
Unit Cost (P’000) = P 317.83 / l.m.
Allocation (P’000) = P 29,400.00
EAO (P’000) = P 600.00
Total (P’000) = P 30,000.00


002: Protect Lives and Properties

Flood Management – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Bank Improvement (Steel Sheet Pile) along Estero dela Reina, Barangay 59, 52 (LS) Sta.0+903.00 to
Sta.0+949.00, (RS) Sta. 0+911.70 to Sta. 0+958.20, Manila City
Physical Target: CW1 – Construction of Flood Mitigation Structure 92.50 l.m.
Unit Cost (P’000) = P 317.83 / l.m.
Allocation (P’000) = P 29,400.00
EAO (P’000) = P 600.00
Total (P’000) = P 30,000.00
WIN1F06429
July 8, 2021 2021 WIN1E02376 FY 2021 GAA RA 11518 January 25, 2021 Region XIII Regional Office XIII
UACS No. 320102104204000
Project ID: P00522339MN

OO2: Protect Lives and Properties Against Major Floods - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers

FROM:

Rehabilitation of Flood Control Structure along Tago River(Package 2), San Miguel, Surigao del Sur

Type of Work/Physical Target:

CW1 - Rehabilitation / Major Repair of Flood Control Structure / 844.488 lm.

Unit Cost: Php 130,268.28 / lm.

Allocation: Php 110,010,000

EAO: Php 3,950,000

Total: Php 114,000,000

TO:

Rehabilitation of Flood Control Structure along Tago River(Package 2), San Miguel, Surigao del Sur

Type of Work/Physical Target:

CW1 - Major Repair of Flood Control Structure / 245 lm.

Unit Cost: Php 449,020.41 / lm.

Estimated Cost: Php 110,010,000

EAO: Php 3,950,000

Total: Php 114,000,000
July 8, 2021 2021 WIN1E02494 FY 2021 GAA RA 11518 January 25, 2021 Region XIII Regional Office XIII
UACS No. 300203101444000
Project ID: P00537633MN

Convergence and Special Support Program - Construction/ Improvement of Access Roads leading to Declared Tourism Destinations

FROM:

New Tubigon leading to Pinandagatan Falls,Sibagat, Agusan del Sur

Type of Work/Physical Target:

CW1 - Construction of Concrete Road / 5.0 lane km.

Unit Cost: Php 19,725,565.00 / lane km.

Allocation: Php 98,627,825

EAO: Php 3,577,175

Total: Php 102,205,000

TO:

New Tubigon leading to Pinandagatan Falls,Sibagat, Agusan del Sur

Type of Work/Physical Target:

CW1 - Construction of Concrete Road / 0.40 lane km.
CW2 - Construction of Gravel Road / 1.28 lane km.

Unit Cost: CW1 Php 16,432,724.75 / lane km.
CW2 Php 71,917,761.80 / lane km.

Estimated Cost: CW1 Php 6,573,089.90
CW2 Php 92,054,735.11

EAO: Php 3,577,175

Total: Php 102,205,000
July 7, 2021 CY 2021 WIN1F06468 UACS NO. 300209100009000 April 5, 2021 National Capital Region NCR - Regional Office
As per GAA/Original
UACS No. 300209100009000
Project ID.: P00531637LZ

Convergence and Special Support Program

Construction/Improvement of Access Roads leading to Railway Stations
Road 20 leading to Tandang Sora Station, Quezon City
Physical Target: CW1 = Construction of Drainage Structure 1600 l.m.
CW2 = Shoulder Paving / Construction 3200 sq.m.
Unit Cost (P’000) = P 6.13 / l.m.
= P 2.03 / sq.m.
Allocation (P’000) = P 9,557.36
= P 6,307.24
EAO (P’000) = P 575.40
Total (P’000) = P 16,440.00

As Modified

Convergence and Special Support Program

Construction/Improvement of Access Roads leading to Railway Stations
Road 20 leading to Tandang Sora Station, Quezon City
Physical Target: CW1 = Shoulder Paving/Construction 2484 sq.m.
Unit Cost (P’000) = P 5.61 / sq.m.
Allocation (P’000) = P 13,946.84
EAO (P’000) = P 488.14
Total (P’000) = P 14,434.98
Excess (P’000) = P 2,005.02
WIN1F06468
July 7, 2021 2021 WIN1F06454 GAA FY 2021 January 1, 2021 Region VIII Tacloban City District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Construction/ Upgrading/ Rehabilitation of Drainage along National Roads - Secondary Roads

AS PER GAA/ORIGINAL:

Tacloban-Baybay South Rd -K0911+000 – K0911+185

Physical Target: Allocation:

CW1-Construction of Drainage Structure P 4.900 M
along Road: 370 Lineal Meters

EAO P 0.100 M

Total P 5.00 M

AS MODIFIED:

Tacloban-Baybay South Rd K0911+000 – K0911+185

Physical Target: Allocation:

CW1-Construction of Drainage Structure P 4.900 M
along Road: 185 Lineal Meters

EAO P 0.100 M

Total P 5.00 M
July 7, 2021 2021 WIN1F06452 GAA FY 2021 January 1, 2021 Region VIII Tacloban City District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Construction/ Upgrading/ Rehabilitation of Drainage along National Roads - Tertiary Roads

AS PER GAA/ORIGINAL:

Burgos St – (S00031LT) Chainage 000 – Chainage 845

Physical Target: Allocation:

CW1-Construction of Drainage Structure P 22.540 M
along Road: 1,690 Lineal Meters

EAO P 0.460 M

Total P 23.00 M

AS MODIFIED:

Burgos St – (S00031LT) Chainage 000 – Chainage 688

Physical Target: Allocation:

CW1-Construction of Drainage Structure P 22.540 M
along Road: 688 Lineal Meters

EAO P 0.460 M

Total P 23.00 M
July 7, 2021 2021 WIN1F06342 GAA FY 2021 January 1, 2021 Region VIII Northern Samar 2nd District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Secondary Roads

AS PER GAA/ORIGINAL:

Sn Policarpo-Arteche-Lapinig Rd - K0851 + 050 - K0851 + 200, K0851 + 350 - K0851 + 841

Physical Target: Allocation:

CW1-Reconstruction to Concrete Pavement: P 28.572880 M
1.282 Lane Km
EAO P 0.583120 M

Total P 29.156 M

AS MODIFIED:

Sn Policarpo-Arteche-Lapinig Rd - K0851 + 050 - K0851 + 200, K0851 + 350 - K0852 + 176

Physical Target: Allocation:

CW1-Reconstruction to Concrete Pavement: P 28.572880 M
1.960 Lane Km
EAO P 0.583120 M

Total P 29.156 M
July 7, 2021 2021 WIN1F06451 GAA FY 2021 February 2, 2021 Region VIII Leyte 2nd District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Preventive Maintenance - Tertiary Roads

AS PER GAA/ORIGINAL:

Kiling-Tanauan-Tabontabon-Julita Rd - K0934 + 906 - K0935 + 000, K0936 + 000 - K0937 + 000

Physical Target: Allocation:

CW1-Preventive Maintenance of Road: P 10.29392 M
Concrete Reblocking: 2.188 Lane Km

EAO P 0.21008 M

Total P 10.504 M

AS MODIFIED:

Kiling-Tanauan-Tabontabon-Julita Rd - K0932 + (-638) - K0932 + 688, K0934 + 609 - K0935 + 000, K0936 + 000 - K0937 + 000

Physical Target: Allocation:

CW1-Preventive Maintenance of Road: P 10.29392 M
Concrete Reblocking: 1.0935 Lane Km

EAO P 0.21008 M

Total P 10.504 M
July 7, 2021 2021 WIN1F06474 GAA FY 2021 February 2, 2021 Region VIII Leyte 2nd District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Preventive Maintenance - Tertiary Roads

AS PER GAA/ORIGINAL:

La Paz-Javier-Bito Rd - K0066 + 000 - K0065 + 000

Physical Target: Allocation:

CW1-Preventive Maintenance of Road: P 9.80 M
Concrete Reblocking: 2.122 Lane Km

EAO P 0.20 M

Total P 10.00 M

AS MODIFIED:

La Paz-Javier-Bito Rd - K0066 + 000 - K0065 + 000, K0952 + 000 - K0953 + 142

Physical Target: Allocation:

CW1-Preventive Maintenance of Road: P 9.80 M
Concrete Reblocking: 1.0215 Lane Km

EAO P 0.20 M

Total P 10.00 M
July 7, 2021 2021 WIN1F06439 GAA FY 2021 February 2, 2021 Region VIII Leyte 2nd District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Preventive Maintenance - Tertiary Roads

AS PER GAA/ORIGINAL:

Mayorga-La Paz Rd - K0946 + 550 - K0947 + 215

Physical Target: Allocation:

CW1-Preventive Maintenance of Road: P 6.05738 M
Concrete Reblocking: 1.246 Lane Km

EAO P 0.12362 M

Total P 6.181 M

AS MODIFIED:

Mayorga-La Paz Rd - K0946 + (-026) - K0947 + 221.60

Physical Target: Allocation:

CW1-Preventive Maintenance of Road: P 6.05738 M
Concrete Reblocking: 1.278 Lane Km

EAO P 0.12362 M

Total P 6.181 M
July 7, 2021 2021 WIN1F06354 GAA FY 2021 January 1, 2021 Region VIII Northern Samar 2nd District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Secondary Roads

AS PER GAA/ORIGINAL:

Sn Policarpo-Arteche-Lapinig Rd - K0866 + 000 - K0866 + 959

Physical Target: Allocation:

CW1-Preventive Maintenance of Road: P 10.77216 M
Asphalt Overlay: 1.918 Lane Km

EAO P 0.21984 M

Total P 10.992 M

AS MODIFIED:

Sn Policarpo-Arteche-Lapinig Rd - K0866 + 000 - K0866 + 839

Physical Target: Allocation:

CW1-Preventive Maintenance of Road: P 10.77216 M
Asphalt Overlay: 1.678 Lane Km

EAO P 0.21984 M

Total P 10.992 M
July 7, 2021 2021 WIN1C04137 FY 2021 GAA December 1, 2020 Region III Pampanga 1st District Engineering Office
Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Primary Roads

Manila North Road - K0065+357 - K0065+562
July 7, 2021 2021 WIN1C04116 FY 2021 GAA December 28, 2020 Region III Pampanga 1st District Engineering Office
Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Tertiary Roads

Baliwag - Candaba - Sta. Ana Rd, K0075+220 - K0075+650 (Sta. Ana Section)
July 7, 2021 2021 WIN1F06450 GAA FY 2021 January 1, 2021 Region VIII Tacloban City District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Preventive Maintenance - Secondary Roads

AS PER GAA/ORIGINAL:

Rizal Avenida Ext Rd – K0905+(-440) – K0905+(-182), K0905+(-836) - K0905+(-440)

Physical Target: Allocation:

CW1-Preventive Maintenance of Road: P 14.700 M
Asphalt Overlay: 2.616 Lane Km

EAO P 0.300 M

Total P 15.00 M

AS MODIFIED:

Rizal Avenida Ext Rd – (S00016LT) - K0905+(-836) - K0905+(-248)

Physical Target: Allocation:

CW1-Preventive Maintenance of Road: P 14.700 M
Asphalt Overlay: 2.352 Lane Km

EAO P 0.300 M

Total P 15.00 M
July 7, 2021 2021 WIN1C04114 FY 2021 GAA December 28, 2020 Region III Pampanga 1st District Engineering Office
Asset Preservation - Preventive Maintenance - Primary Roads

Manila North Road , K0063+355 - K0063+800
July 7, 2021 2021 WIN1F06392 GAA FY 2021 January 1, 2021 Region VIII Tacloban City District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Preventive Maintenance - Tertiary Roads

AS PER GAA/ORIGINAL:

Burgos St – (S00008LT) Chainage 0 – Chainage 450

Physical Target: Allocation:

CW1-Preventive Maintenance of Road: P 9.832340 M
Asphalt Overlay: 1.744 Lane Km

EAO P 0.200660 M

Total P 10.033 M

AS MODIFIED:

Burgos St – (S00008LT) Chainage 0 – Chainage 450

Physical Target: Allocation:

CW1-Preventive Maintenance of Road: P 9.832340 M
Asphalt Overlay: 1.438 Lane Km

EAO P 0.200660 M

Total P 10.033 M
July 7, 2021 2021 WIN1F06391 GAA FY 2021 January 2, 2021 Region VIII Eastern Samar District Engineering Office
OO2: Protect Lives and Properties

Flood Management - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems

AS PER GAA/ORIGINAL:

Construction of Balangiga Flood Control along Balangiga River, Balangiga, Eastern Samar

Physical Target: Allocation:

CW1-Construction of Flood Mitigation Structure: P 49.00 M
472.789 Lineal Meters
EAO P 1.00 M

Total P 50.00 M

AS MODIFIED:

Construction of Balangiga Flood Control along Balangiga River, Balangiga, Eastern Samar

Physical Target: Allocation:

CW1-Construction of Flood Mitigation Structure: P 49.00 M
127.00 Lineal Meters
EAO P 1.00 M

Total P 50.00 M
July 7, 2021 2021 WIN1F06462 SR2021-02-000134 February 4, 2021 Region VI Aklan District Engineering Office
FROM:

ORGANIZATIONAL OUTCOME 1: Ensure Safe and Reliable National Road System

Network Development - Construction of By-Pass and Diversion Roads

Ibajay Bypass Road, Aklan

CW1- Construction of Concrete Road: 2.600 lane km - 38,600.00

ROW Acquisition: 22,000 sq.m - 28,950.00

EAO - 2,450.00

Total: 70,000.00

TO:

ORGANIZATIONAL OUTCOME 1: Ensure Safe and Reliable National Road System

Network Development - Construction of By-Pass and Diversion Roads

Ibajay Bypass Road, Aklan

CCW1- Construction of Concrete Road: 1.733 lane km - 39,200.00

ROW Acquisition: 22,000 sq.m - 28,350.00

EAO - 2,450.00

Total: 70,000.00
July 7, 2021 2021 WIN1F06326 GAA FY 2021 February 2, 2021 Region VIII Leyte 2nd District Engineering Office
OO2: Protect Lives and Properties

Flood Management - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems

AS PER GAA/ORIGINAL:

Construction of Binahaan Flood Control Structure and Drainage system, Binahaan River Basin, K002+847 - K003+622 (Left Side River Bank), Pastrana, Leyte

Physical Target: Allocation:

CW1-Construction of Flood Mitigation P 49.00 M
Structure: 663.25 Lineal Meters

EAO P 1.00 M

Total P 50.00 M

AS MODIFIED:

Construction of Binahaan Flood Control Structure and Drainage system, Binahaan River Basin, K000+850 - K001+513.25 (Right Side River Bank), Pastrana, Leyte

Physical Target: Allocation:

CW1-Construction of Flood Mitigation P 49.00 M
Structure: 663.25 Lineal Meters

EAO P 1.00 M

Total P 50.00 M
July 7, 2021 2021 WIN1F06475 SR2021-02-000156 February 4, 2021 Region VI Aklan District Engineering Office
FROM:

ORGANIZATIONAL OUTCOME 1: Ensure Safe and Reliable National Road System

Network Development - Construction of By-Pass and Diversion Roads

Tangalan Bypass Road, Aklan

CW1- Construction of Concrete Road: 3.00 lane km - 43,425.00

ROW Acquisition: 5,000 sq.m - 24,125.00

EAO - 2,450.00

Total: 70,000.00


TO:

ORGANIZATIONAL OUTCOME 1: Ensure Safe and Reliable National Road System

Network Development - Construction of By-Pass and Diversion Roads

Tangalan Bypass Road, Aklan

CW1- Construction of Concrete Road: 1.64 lane km - 44,100.00

ROW Acquisition: 5,000 sq.m - 23,450.00

EAO - 2,450.00

Total: 70,000.00
July 7, 2021 2021 WIN1F06475 SR2021-02-000156 February 4, 2021 Region VI Aklan District Engineering Office
FROM:

ORGANIZATIONAL OUTCOME 1: Ensure Safe and Reliable National Road System

Network Development - Construction of By-Pass and Diversion Roads

Tangalan Bypass Road, Aklan

CW1- Construction of Concrete Road: 3.00 lane km - 43,425.00

ROW Acquisition: 5,000 sq.m - 24,125.00

EAO - 2,450.00

Total: 70,000.00


TO:

ORGANIZATIONAL OUTCOME 1: Ensure Safe and Reliable National Road System

Network Development - Construction of By-Pass and Diversion Roads

Tangalan Bypass Road, Aklan

CW1- Construction of Concrete Road: 1.64 lane km - 44,100.00

ROW Acquisition: 5,000 sq.m - 23,450.00

EAO - 2,450.00

Total: 70,000.00
July 7, 2021 FY 2021 GAA WIN1F06315 FY 2021 GAA DPWH Infra Projects December 28, 2020 Region IV-B Palawan 1st District Engineering Office
UACS No. : 300117209138000
Project ID : P00564691LZ

LOCAL PROGRAM

Local roads and Bridges - Local Roads
Local Infrastructure Program

FROM :

Construction of Road from
Sitio Tibonbon to San Teodoro, Brgyu. Poblacion 5,
Coron, Palawan
Physical Target - CW1 - Construction of Concrete Road :
0.506 Lane Km
Allocation : Php 3.00 Million

TO :

Construction of Road in Brgy. Poblacion 5,
Coron, Palawan
Physical Target - CW1 - Construction of Concrete Road :
0.506 Lane Km
Allocation : Php 3.00 Million
July 7, 2021 FY 2021 GAA WIN1F06218 FY 2021 GAA DPWH Infra Projects December 28, 2020 Region IV-B Palawan 2nd District Engineering Office
UACS No. : 310202100817000
Project ID : P00505134LZ

001 : Ensure Safe and Reliable National Road System

Network Development - Road Widening - Secondary Roads

FROM :

PPSR Lct ( Abo-abo ) - Quezon Road,
K0129 + (-572) - K0129 + 975
Physical Target - CW1 - Road Widening : 3.094 Lane Km
Allocation : Php 32.394 Million

TO :

PPSr Jct ( Abo - abo) - Quezon Road,
K0129 + (-572) - K0129 + 544
Physical Target - CW1 - Road Widening : 2.232 Lane Km
Allocation : Php 32.394 Million
July 7, 2021 2021 WIN1F06466 GAA FY 2021 January 4, 2021 Region VIII Leyte 5th District Engineering Office
Local Program

Local - Local Roads and Bridges - Local Roads - Local Infrastructure Program

AS PER GAA/ORIGINAL:

Concreting of Roads (Barangay Hampipila, Barangay Burubud-an, Barangay Mag-atubang), Abuyog, Leyte


Physical Target: Allocation:

CW1-Construction of Concrete Road: P 1.485 M
0.130 Lane Km

EAO P 0.015 M

Total P 1.500 M

AS MODIFIED:

Concreting of Roads (Barangay Hampipila, Barangay Burubud-an, Barangay Mag-atubang), Abuyog, Leyte


Physical Target: Allocation:

CW1-Construction of Concrete Road: P 1.485 M
0.694 Lane Km

EAO P 0.015 M

Total P 1.500 M
July 7, 2021 2021 WIN1F06471 SR2021-02-000141 February 4, 2021 Region VI Aklan District Engineering Office
FROM:

ORGANIZATIONAL OUTCOME 2: Protect Lives and Properties Against Major Floods

Flood Management Program - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers

Construction of Flood Control Structure (Revetment Wall) along Aklan River, Barangay Poblacion, Malinao, Aklan

CW1- Construction of Flood Mitigation Structure: 650.77 lineal meters - 96,500.00

EAO - 3,500.00

Total: 100,000.00


TO:

ORGANIZATIONAL OUTCOME 2: Protect Lives and Properties Against Major Floods

Flood Management Program - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers

Construction of Flood Control Structure (Revetment Wall) along Aklan River, Barangay Poblacion, Malinao, Aklan

CW1- Construction of Flood Mitigation Structure: 700.40 lineal meters - 96,500.00

EAO - 3,500.00

Total: 100,000.00
July 7, 2021 2021 WIN1F06471 SR2021-02-000141 February 4, 2021 Region VI Aklan District Engineering Office
FROM:

ORGANIZATIONAL OUTCOME 2: Protect Lives and Properties Against Major Floods

Flood Management Program - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers

Construction of Flood Control Structure (Revetment Wall) along Aklan River, Barangay Poblacion, Malinao, Aklan

CW1- Construction of Flood Mitigation Structure: 650.77 lineal meters - 96,500.00

EAO - 3,500.00

Total: 100,000.00


TO:

ORGANIZATIONAL OUTCOME 2: Protect Lives and Properties Against Major Floods

Flood Management Program - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers

Construction of Flood Control Structure (Revetment Wall) along Aklan River, Barangay Poblacion, Malinao, Aklan

CW1- Construction of Flood Mitigation Structure: 700.40 lineal meters - 96,500.00

EAO - 3,500.00

Total: 100,000.00
July 7, 2021 2021 WIN1F06471 SR2021-02-000141 February 4, 2021 Region VI Aklan District Engineering Office
FROM:

ORGANIZATIONAL OUTCOME 2: Protect Lives and Properties Against Major Floods

Flood Management Program - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers

Construction of Flood Control Structure (Revetment Wall) along Aklan River, Barangay Poblacion, Malinao, Aklan

CW1- Construction of Flood Mitigation Structure: 650.77 lineal meters - 96,500.00

EAO - 3,500.00

Total: 100,000.00


TO:

ORGANIZATIONAL OUTCOME 2: Protect Lives and Properties Against Major Floods

Flood Management Program - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers

Construction of Flood Control Structure (Revetment Wall) along Aklan River, Barangay Poblacion, Malinao, Aklan

CW1- Construction of Flood Mitigation Structure: 700.40 lineal meters - 96,500.00

EAO - 3,500.00

Total: 100,000.00
July 7, 2021 2021 WIN1F06471 SR2021-02-000141 February 4, 2021 Region VI Aklan District Engineering Office
FROM:

ORGANIZATIONAL OUTCOME 2: Protect Lives and Properties Against Major Floods

Flood Management Program - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers

Construction of Flood Control Structure (Revetment Wall) along Aklan River, Barangay Poblacion, Malinao, Aklan

CW1- Construction of Flood Mitigation Structure: 650.77 lineal meters - 96,500.00

EAO - 3,500.00

Total: 100,000.00


TO:

ORGANIZATIONAL OUTCOME 2: Protect Lives and Properties Against Major Floods

Flood Management Program - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers

Construction of Flood Control Structure (Revetment Wall) along Aklan River, Barangay Poblacion, Malinao, Aklan

CW1- Construction of Flood Mitigation Structure: 700.40 lineal meters - 96,500.00

EAO - 3,500.00

Total: 100,000.00
July 7, 2021 2021 WIN1F06471 SR2021-02-000141 February 4, 2021 Region VI Aklan District Engineering Office
FROM:

ORGANIZATIONAL OUTCOME 2: Protect Lives and Properties Against Major Floods

Flood Management Program - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers

Construction of Flood Control Structure (Revetment Wall) along Aklan River, Barangay Poblacion, Malinao, Aklan

CW1- Construction of Flood Mitigation Structure: 650.77 lineal meters - 96,500.00

EAO - 3,500.00

Total: 100,000.00


TO:

ORGANIZATIONAL OUTCOME 2: Protect Lives and Properties Against Major Floods

Flood Management Program - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers

Construction of Flood Control Structure (Revetment Wall) along Aklan River, Barangay Poblacion, Malinao, Aklan

CW1- Construction of Flood Mitigation Structure: 700.40 lineal meters - 96,500.00

EAO - 3,500.00

Total: 100,000.00
July 7, 2021 2021 WIN1F06471 SR2021-02-000141 February 4, 2021 Region VI Aklan District Engineering Office
FROM:

ORGANIZATIONAL OUTCOME 2: Protect Lives and Properties Against Major Floods

Flood Management Program - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers

Construction of Flood Control Structure (Revetment Wall) along Aklan River, Barangay Poblacion, Malinao, Aklan

CW1- Construction of Flood Mitigation Structure: 650.77 lineal meters - 96,500.00

EAO - 3,500.00

Total: 100,000.00


TO:

ORGANIZATIONAL OUTCOME 2: Protect Lives and Properties Against Major Floods

Flood Management Program - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers

Construction of Flood Control Structure (Revetment Wall) along Aklan River, Barangay Poblacion, Malinao, Aklan

CW1- Construction of Flood Mitigation Structure: 700.40 lineal meters - 96,500.00

EAO - 3,500.00

Total: 100,000.00
July 7, 2021 2021 WIN1F06465 GAA FY 2021 January 4, 2021 Region VIII Leyte 5th District Engineering Office
Local Program

Local - Local Roads and Bridges - Local Roads - Local Infrastructure Program

AS PER GAA/ORIGINAL:

Rehabilitation of Barangay Road, Barangay Hinabay, Inopacan, Leyte

Physical Target: Allocation:

CW1-Rehabilitation of Paved Road: P 1.00 M
0.00 Lane Km

Total P 1.00 M

AS MODIFIED:

Rehabilitation of Barangay Road, Barangay Hinabay, Inopacan, Leyte

Physical Target: Allocation:

CW1-Rehabilitation of Paved Road: P 1.00 M
0.306 Lane Km

Total P 1.00 M
July 7, 2021 2021 WIN1F06471 SR2021-02-000141 February 4, 2021 Region VI Aklan District Engineering Office
FROM:

ORGANIZATIONAL OUTCOME 2: Protect Lives and Properties Against Major Floods

Flood Management Program - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers

Construction of Flood Control Structure (Revetment Wall) along Aklan River, Barangay Poblacion, Malinao, Aklan

CW1- Construction of Flood Mitigation Structure: 650.77 lineal meters - 96,500.00

EAO - 3,500.00

Total: 100,000.00


TO:

ORGANIZATIONAL OUTCOME 2: Protect Lives and Properties Against Major Floods

Flood Management Program - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers

Construction of Flood Control Structure (Revetment Wall) along Aklan River, Barangay Poblacion, Malinao, Aklan

CW1- Construction of Flood Mitigation Structure: 700.40 lineal meters - 96,500.00

EAO - 3,500.00

Total: 100,000.00
July 7, 2021 2021 WIN1F06471 SR2021-02-000141 February 4, 2021 Region VI Aklan District Engineering Office
FROM:

ORGANIZATIONAL OUTCOME 2: Protect Lives and Properties Against Major Floods

Flood Management Program - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers

Construction of Flood Control Structure (Revetment Wall) along Aklan River, Barangay Poblacion, Malinao, Aklan

CW1- Construction of Flood Mitigation Structure: 650.77 lineal meters - 96,500.00

EAO - 3,500.00

Total: 100,000.00


TO:

ORGANIZATIONAL OUTCOME 2: Protect Lives and Properties Against Major Floods

Flood Management Program - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers

Construction of Flood Control Structure (Revetment Wall) along Aklan River, Barangay Poblacion, Malinao, Aklan

CW1- Construction of Flood Mitigation Structure: 700.40 lineal meters - 96,500.00

EAO - 3,500.00

Total: 100,000.00
July 7, 2021 2021 WIN1F06471 SR2021-02-000141 February 4, 2021 Region VI Aklan District Engineering Office
FROM:

ORGANIZATIONAL OUTCOME 2: Protect Lives and Properties Against Major Floods

Flood Management Program - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers

Construction of Flood Control Structure (Revetment Wall) along Aklan River, Barangay Poblacion, Malinao, Aklan

CW1- Construction of Flood Mitigation Structure: 650.77 lineal meters - 96,500.00

EAO - 3,500.00

Total: 100,000.00


TO:

ORGANIZATIONAL OUTCOME 2: Protect Lives and Properties Against Major Floods

Flood Management Program - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers

Construction of Flood Control Structure (Revetment Wall) along Aklan River, Barangay Poblacion, Malinao, Aklan

CW1- Construction of Flood Mitigation Structure: 700.40 lineal meters - 96,500.00

EAO - 3,500.00

Total: 100,000.00
July 7, 2021 2021 WIN1C04183 GAA 2021 June 30, 2021 Cordillera Administrative Region CAR - Regional Office
From: Construction/Improvement of Dada - Beyeng - Kayapa Road, Dada, Beyeng and Kayapa, Bakun, Benguet;
Physical Target: CW1 : 0 Lane Km;
Allocation= Php 100,000,000

To: Construction/Improvement of Dada - Beyeng - Kayapa Road, Dada, Beyeng and Kayapa, Bakun, Benguet;
Physical Target: CW1 : 5 Lane Km;
Allocation= Php 100,000,000

July 7, 2021 2021 WIN1F06471 SR2021-02-000141 February 4, 2021 Region VI Aklan District Engineering Office
FROM:

ORGANIZATIONAL OUTCOME 2: Protect Lives and Properties Against Major Floods

Flood Management Program - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers

Construction of Flood Control Structure (Revetment Wall) along Aklan River, Barangay Poblacion, Malinao, Aklan

CW1- Construction of Flood Mitigation Structure: 650.77 lineal meters - 96,500.00

EAO - 3,500.00

Total: 100,000.00


TO:

ORGANIZATIONAL OUTCOME 2: Protect Lives and Properties Against Major Floods

Flood Management Program - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers

Construction of Flood Control Structure (Revetment Wall) along Aklan River, Barangay Poblacion, Malinao, Aklan

CW1- Construction of Flood Mitigation Structure: 700.40 lineal meters - 96,500.00

EAO - 3,500.00

Total: 100,000.00
July 7, 2021 2021 WIN1F06425 GAA FY 2021 February 2, 2021 Region VIII Leyte 2nd District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Primary Roads

AS PER GAA/ORIGINAL:

Daang Maharlika (LT) - K0935 + (-414) - K0936 + 086

Physical Target: Allocation:

CW1-Construction of Road Slope Protection P 29.40 M
Structure: 6,706.408 Square Meters
EAO P 0.60 M

Total P 30.00 M

AS MODIFIED:

Daang Maharlika (LT) - K0935 + (-604) - K0935 + (-508)

Physical Target: Allocation:

CW1-Construction of Road Slope Protection P 29.40 M
Structure: 2,188.00 Square Meters
EAO P 0.60 M

Total P 30.00 M
July 7, 2021 CY 2021 WINF106427 UACS NO. 300104219173000 April 26, 2021 National Capital Region Metro Manila 3rd District Engineering Office
Local – Buildings And As per GAA/Original
UACS No. 300104219173000
Project ID.: P00557343LZ

Local Program

Local – Buildings And Other Structures – Multipurpose/Facilities – Local Infrastructure Program
Construction of Multi-Purpose Building (Covered Court) Phase 2, Barangay Parada, Valenzuela City
Physical Target: CW1 = Construction of Multi-Purpose Building 1.00 No. of Bldg.
Unit Cost = P 4,950.0 / No. of Bldg.
Allocation (P’000) = P 4,950.00
EAO (P’000) = P 50.00
Total (P’000) = P 5,000.00

As Modified

Local Program

Other Structures – Multipurpose/Facilities – Local Infrastructure Program
Construction of Multi-Purpose Building (Covered Court) Phase 3, Barangay Parada, Valenzuela City
Physical Target: CW1 = Construction of Multi-Purpose Building 1.00 No. of Bldg.
Unit Cost = P 4,950.0 / No. of Bldg.
Allocation (P’000) = P 4,950.00
EAO (P’000) = P 50.00
Total (P’000) = P 5,000.00
WIN1F06427
July 7, 2021 2021 WIN1C04160 GAA 2021 June 30, 2021 Cordillera Administrative Region CAR - Regional Office
From: Mt Prov-Cagayan via Tabuk-Enrile Rd - K0417 + 400 - K0417 + 750;
Physical Target: CW1 : 3,835 Square meters;
Allocation= Php 100,000,000

To: Mt Prov-Cagayan via Tabuk-Enrile Rd - K0404 + 955 - K0405 + 060;
Physical Target: CW1 : 4,135.50 Square meters;
Allocation= Php 100,000,000

July 7, 2021 CY 2021 WIN1F06420 UACS NO. 310103100643000 March 4, 2021 National Capital Region Quezon City 2nd Engineering District Office
As per GAA/Original
UACS No. 310103100643000
Project ID.: P00505520LZ

OO1: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Secondary Roads
Kamias Road Rd – K0010+153 – K0010+730
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay L=2.308 lane km
Unit Cost (P’000) = P 4,336.54/ lane km
Allocation (P’000) = P 10,008.74
EAO (P’000) = P 204.26
Total (P’000) = P 10,213.00

As Modified

OO1: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Secondary Roads
Kamias Road Rd – K0010+153 – K0010+506
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay L=1.412 lane km
Unit Cost (P’000) = P 7,088.34/ lane km P14M/km
Allocation (P’000) = P 10,008.74
EAO (P’000) = P 204.26
Total (P’000) = P 10,213.00
WIN1F06420
July 7, 2021 2021 WIN1F06421 GAA FY 2021 February 2, 2021 Region VIII Leyte 2nd District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Primary Roads

AS PER GAA/ORIGINAL:

Palo-Carigara-Ormoc Rd - K0972 + 760 - K0973 + 280

Physical Target: Allocation:

CW1-Construction of Road Slope Protection P 33.026 M
Structure: 2,807.048 square meters
EAO P 0.674 M

Total P 33.700 M

AS MODIFIED:

Palo-Carigara-Ormoc Rd - K0972 + 776.13 - K0973 + 041.13

Physical Target: Allocation:

CW1-Construction of Road Slope Protection P 33.026 M
Structure: 1,883.00 square meters
EAO P 0.674 M

Total P 33.700 M
July 6, 2021 2021 WIN1E02290 FY 2021 GAA RA 11518 January 25, 2021 Region XIII Surigao del Norte 2nd District Engineering Office
UACS No. 300117210458000
Project ID: P00551467MN

FROM:

LOCAL PROGRAM - Local Roads and Bridges - Local Roads - Local Infrastructure Program

Construction/Rehabilitation (Completion) of Local Road, Barangay Poblacion, Bacuag, Surigao Del Norte

Type of Work/Physical Target:

CW1 - Construction of Concrete Road / 0.187 lane km.

Unit Cost: Php 10,588,235.29 / lane km.

Allocation: Php 1,980,000.00

EAO: Php 20,000.00

Total: Php 2,000,000.00

TO:

LOCAL PROGRAM - Local Roads and Bridges - Local Roads - Local Infrastructure Program

Construction/Rehabilitation (Completion) of Local Road, Barangay Poblacion, Bacuag, Surigao Del Norte

Type of Work/Physical Target:

CW1 - Construction of Concrete Road / 0.277 lane km.

Unit Cost: Php 7,148,014.44 / lane km.

Estimated Cost: Php 1,980,000.00

EAO: Php 20,000.00

Total: Php 2,000,000.00
July 6, 2021 FY 2021 GAA WIN1E02427 FY 2021 GAA RA 11518 January 1, 2021 Region XI Regional Office XI
MODIFICATION:

FROM: Local Program - Local Roads and Bridges - Local Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Road, Jct. Davao - Bukidnon Road (Calinan Section) - Wangan - Subasta - Tagakpan - Tungkalan - Tagurano - Catigan - Baracatan - Sibulan - Tibolo - Kapatagan Road, (Package C), Davao City
Physical Target:
CW1: 1.628 Lane Km (Construction of Concrete Road)
CW2: 0.772 Lane Km (Reconstruction to Concrete Pavement)
Allocation:
TOTAL: P 120,967,000.00
CW1: P 42,460,000.00 (Construction of Concrete Road)
CW2: P 74,273,155.00 (Reconstruction to Concrete Pavement)
EAO: P 4,233,845.00

TO: Local Program - Local Roads and Bridges - Local Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Road, Jct. Davao - Bukidnon Road (Calinan Section) - Wangan - Subasta - Tagakpan - Tungkalan - Tagurano - Catigan - Baracatan - Sibulan - Tibolo - Kapatagan Road, (Package C), Davao City
Physical Target:
CW1: 0.828 Lane Km (Construction of Concrete Road)
CW2: 0.772 Lane Km (Reconstruction to Concrete Pavement)
CW3: 286.20 sq. m. (Construction of Concrete Bridge)
Allocation:
TOTAL: P 120,967,000.00
CW1: P 31,321,129.00 (Construction of Concrete Road)
CW2: P 55,966,686.00 (Reconstruction to Concrete Pavement)
CW3: P 29,445,340.00 (Construction of Concrete Bridge)
EAO: P 4,233,845.00
July 6, 2021 FY 2021 GAA WIN1E02431 FY 2021 GAA RA 11518 January 1, 2021 Region XI Davao City District Engineering Office
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Tertiary Roads
Davao-Cotabato Old Rd - K1520+029 - K1521+361
Physical Target:
CW1: 7.932 Lane Km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 37,281,000.00
CW1: P 36,535,380.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 745,620.00

TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Tertiary Roads
Davao-Cotabato Old Rd - K1520+029 - K1520+683
Physical Target:
CW1: 2.616 Lane Km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 37,281,000.00
CW1: P 36,535,380.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 745,620.00
July 6, 2021 FY 2021 GAA WIN1E02453 FY 2021 GAA RA 11518 January 1, 2021 Region XI Regional Office XI
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads
Pres. Diosdado P. Macapagal Natl Hi-way -
K1728+730.167 - K1728+ 823.101, K1728+849.473 - K1728+911.375,
K1729+267.105 - K1729+ 287.105, K1735+820.448 - K1735+850
Physical Target:
CW1: 6,786.50 sq. m. (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 130,000,000.00
CW1: P 125,450,000.00 (Construction of Road Slope Protection Structure)
EAO: P 4,550,000.00

TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads
Pres. Diosdado P. Macapagal Natl Hi-way - K1729+001 - K1729+104
K1729+445 - K1729+521, K1729+932 - K1730+016
Physical Target:
CW1: 3,398.41 sq. m. (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 130,000,000.00
CW1: P 125,450,000.00 (Construction of Road Slope Protection Structure)
EAO: P 4,550,000.00
July 6, 2021 FY 2021 GAA WIN1E02428 FY 2021 GAA RA 11518 January 1, 2020 Region XI Davao City District Engineering Office
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Secondary Roads
5th Ave - K1510+(-822) - K1510+(-512)
Physical Target:
CW1: 1.800 Lane Km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 13,618,000.00
CW1: P 13,345,640.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 272,360.00

TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Secondary Roads
5th Ave - K1510+475 - K1510+599
Physical Target:
CW1: 0.890 Lane Km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 13,618,000.00
CW1: P 13,345,640.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 272,360.00
July 6, 2021 FY 2021 GAA WIN1E02429 FY 2021 GAA RA 11518 January 1, 2021 Region XI Davao City District Engineering Office
MODIFICATION:

FROM: Local Program - Local Roads and Bridges - Local Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Road at Cebole, Sitio Galacia, Brgy. Colosas, Paquibato District, Davao City
Physical Target:
CW1: 7.951 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 79,476,000.00
CW1: P 76,694,340.00 (Construction of Concrete Road)
EAO: P 2,781,660.00

TO: Local Program - Local Roads and Bridges - Local Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Road at Cebole, Sitio Galacia, Brgy. Colosas, Paquibato District, Davao City
Physical Target:
CW1: 2.640 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 79,476,000.00
CW1: P 76,694,340.00 (Construction of Concrete Road)
EAO: P 2,781,660.00
July 6, 2021 FY 2021 GAA WIN1E02439 FY 2021 GAA RA 11518 January 1, 2021 Region XI Davao de Oro 1st District Engineering Office
MODIFICATION:

FROM: OO2: Protect Lives and Properties Against Major Floods - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers
Construction of Revetment along Hijo River at Barangay New Asturias, Mawab, Davao de Oro
Physical Target:
CW1: 140.00 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 20,000,000.00
CW1: P 19,600,000.00 (Construction of Flood Mitigation Structure)
EAO: P 400,000.00

TO: OO2: Protect Lives and Properties Against Major Floods - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers
Construction of Revetment along Hijo River at Barangay New Asturias, Maco, Davao de Oro
Physical Target:
CW1: 140.00 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 20,000,000.00
CW1: P 19,600,000.00 (Construction of Flood Mitigation Structure)
EAO: P 400,000.00
July 6, 2021 FY 2021 GAA WIN1E02435 FY 2021 GAA RA 11518 January 1, 2021 Region XI Davao de Oro 1st District Engineering Office
MODIFICATION:

FROM: Local Program - Local Roads and Bridges - Local Roads - Local Infrastructure Program
Concreting of Road, Prosperidad, Montevista to Casoon, Monkayo, Davao de Oro
Physical Target:
CW1: 3.380 Lane km (Construction of Concrete Road)
Allocation:
TOTAL: P 50,000,000.00
CW1: P 49,500,000.00 (Construction of Concrete Road)
EAO: P 500,000.00

TO: Local Program - Local Roads and Bridges - Local Roads - Local Infrastructure Program
Concreting of Road, Prosperidad, Montevista to Casoon, Monkayo, Davao de Oro
Physical Target:
CW1: 4.691 Lane km (Construction of Concrete Road)
Allocation:
TOTAL: P 50,000,000.00
CW1: P 49,500,000.00 (Construction of Concrete Road)
EAO: P 500,000.00
July 5, 2021 2021 WIN1C04109 GAA 2021 June 25, 2021 Cordillera Administrative Region CAR - Regional Office
From: City Limit-Sto Tomas Rd - K0262 + 005 - K0262 + 150, K0263 + 250 - K0263 + 400;
Type of Work: CW1: Reconstruction to Concrete Pavement;
Physical Target: CW1 : 0.59 Lane Km;
Allocation= Php 200,000,000

To: City Limit-Sto Tomas Rd - K0255 + 1085 - K0255 + 1098.50, K0255 + 1806.50 - K0255 + 1857, K0258 + 454 – K0258 + 478.50, K0258 + 801 - K0258 + 847, K0259 + 065.50 - K0259 + 097.50, K0259 + 277 - K0259 + 292, K0259 + 336.50 - K0259 + 492, K0259 + 606 - K0259 + 612.50, K0259 + 684.50 - K0259 + 785, K0259 + 813 - K0259 + 840, K0259 + 927 - K0259 + 1093, K0260 + 000 - K0260 + 077, K0261 + 064 - K0261 + 088, K0261 + 693 - K0261 + 715.50, K0262 + 000 - K0262 + 180, K0262 + 522 - K0262 + 636, K0263 + 416 - K0263 + 478;
Type of Work: CW1: Reconstruction to Concrete Pavement
CW2: Construction of Road Slope Protection Structure;
Physical Target: CW1 : 1.244 Lane Km
CW2: 6,754 Square meters;
Allocation= Php 200,000,000

July 5, 2021 2021 WIN1C04124 GAA 2021 June 25, 2021 Cordillera Administrative Region CAR - Regional Office
From: Construction/Improvement of Beyeng - Tacadang Road, Tacadang, Kibungan, Benguet;
Physical Target: CW1 : 0 Lane Km;
Allocation= Php 100,000,000

To: Construction/Improvement of Beyeng - Tacadang Road, Tacadang, Kibungan, Benguet;
Physical Target: CW1 : 6.36 Lane Km;
Allocation= Php 100,000,000

July 5, 2021 2021 WIN1C04091 GAA 2021 June 28, 2021 Cordillera Administrative Region CAR - Regional Office
From: Nueva Vizcaya-Ifugao-Mt. Province Bdry Rd - K0312 + 060 - K0314 + 000, K0321 + 232 - K0322 + 374, K0323 + 770 - K0334 + 500;
Physical Target: CW1 : 27.846 Lane Km;
Allocation= Php 20,000,000

To: Nueva Vizcaya-Ifugao-Mt. Province Bdry Rd - K0312 + 060 - K0313+ 677;
Physical Target: CW1 : 3.246 Lane Km;
Allocation= Php 20,000,000

July 5, 2021 2021 WIN1C04066 GAA 2021 June 22, 2021 Cordillera Administrative Region Abra District Engineering Office
From: Abra-Ilocos Norte Rd - K0434+460 - K0434 + 550;
Type of Work: CW1: Reconstruction to Concrete Pavement;
Physical Target: CW1: 0.18 Lane Km;
Allocation= Php 100,000,000

To: Abra-Ilocos Norte Rd - K0450 + 800 - K0451 + 000;
Type of Work: CW1: Reconstruction to Concrete Pavement
CW2: Construction of Road Slope Protection Structure;
Physical Target: CW1: 0.4 Lane Km
CW2: 3,878.73 Square meters;
Allocation= Php 100,000,000


July 5, 2021 2021 WIN1C04061 GAA 2021 June 22, 2021 Cordillera Administrative Region Abra District Engineering Office
From: Construction of Patoc Flood Control, Sta. 0+100 - 0+600, Bucay, Abra;
Physical Target: CW1: 500 Lineal meters;
Allocation= Php 30,000,000

To: Construction of Patoc Flood Control, Sta. 0+100 - 0+600, Bucay, Abra;
Physical Target: CW1: 665 Lineal meters;
Allocation= Php 30,000,000


July 5, 2021 2021 WIN1C04096 GAA 2021 June 28, 2021 Cordillera Administrative Region Abra District Engineering Office
From: Abra-Kalinga Rd - K0455 + 500 - K0456 + 600;
Type of Work: CW1: Reconstruction to Concrete Pavement;
Physical Target: CW1: 2.134 Lane Km;
Allocation= Php 99,000,000

To: Abra-Kalinga Rd - K0455 + 100 - K0456 + 600; Type of Work: CW1: Reconstruction to Concrete Pavement
CW2: Construction of Road Slope Protection Structure;
Physical Target: CW1: 2.934 Lane Km
CW2: 2,922.93 Square meters;
Allocation= Php 99,000,000

July 5, 2021 2021 WIN1C04095 GAA 2021 June 28, 2021 Cordillera Administrative Region Abra District Engineering Office
From: Abra-Ilocos Norte Rd - K0432+200 - K0432 + 500;
Type of Work: CW1: Reconstruction to Concrete Pavement;
Physical Target: CW1: 0.60 Lane Km;
Allocation= Php 99,000,000

To: Abra-Ilocos Norte Rd - K0432+200 - K0432 + 500;
Type of Work: CW1: Reconstruction to Concrete Pavement
CW2: Construction of Road Slope Protection Structure;
Physical Target: CW1: 0.60 Lane Km
CW2: 3,751.56 Square meters;
Allocation= Php 99,000,000

July 5, 2021 2021 WIN1C04099 GAA 2021 June 28, 2021 Cordillera Administrative Region Abra District Engineering Office
From: Abra-Cervantes Rd - K0446 + 000 - K0453 + 769;
Physical Target: CW1: 15.622 Lane Km;
Allocation= Php 50,000,000

To: Abra-Cervantes Rd - K0446 + 000 - K0450 + 114;
Physical Target: CW1: 8.36 Lane Km;
Allocation= Php 50,000,000
July 5, 2021 2021 WIN1C04112 GAA 2021 June 28, 2021 Cordillera Administrative Region Abra District Engineering Office
From: Abra-Ilocos Norte Rd - K0435+050 - K0435 + 250;
Type of Work: CW1: Reconstruction to Concrete Pavement;
Physical Target: CW1: 0.40 Lane Km;
Allocation= Php 100,000,000

To: Abra-Ilocos Norte Rd - K0435 + 200 - K0435 + 350;
Type of Work: CW1: Reconstruction to Concrete Pavement
CW2: Construction of Road Slope Protection Structure;
Physical Target: CW1: 0.30 Lane Km
CW2: 3,891.69 Square meters;
Allocation= Php 100,000,000

July 5, 2021 2021 WIN1C04139 GAA 2021 June 28, 2021 Cordillera Administrative Region Abra District Engineering Office
From: Rehabilitation/Improvement of Villaviciosa Road Phase 1, Villaviciosa, Abra;
Physical Target: CW1: 10 Lane Km;
Allocation= Php 50,000,000

To: Rehabilitation/Improvement of Villaviciosa Road Phase 1, Villaviciosa, Abra;
Physical Target: CW1: 6 Lane Km;
Allocation= Php 50,000,000

July 5, 2021 2021 WIN1C04142 GAA 2021 June 28, 2021 Cordillera Administrative Region Abra District Engineering Office
From: Construction of Danglas Barrio Road, Danglas, Abra;
Physical Target: CW1: 8 Lane Km;
Allocation= Php 50,000,000

To: Construction of Danglas Barrio Road, Danglas, Abra;
Physical Target: CW1: 7.122 Lane Km;
Allocation= Php 50,000,000

July 5, 2021 2021 WIN1C04098 GAA 2021 June 28, 2021 Cordillera Administrative Region Abra District Engineering Office
From: Abra-Kalinga Rd - K0450 + 750 - K0451 + 800;
Type of Work: CW1: Reconstruction to Concrete Pavement;
Physical Target: CW1: 2 Lane Km;
Allocation= Php 99,000,000

To: Abra-Kalinga Rd - K0449 + 000 - K0451 + 800;
Type of Work: CW1: Reconstruction to Concrete Pavement
CW2: Construction of Road Slope Protection Structure;
Physical Target: CW1: 5.438 Lane Km
CW2: 2,121.84 Square meters;
Allocation= Php 99,000,000

July 5, 2021 2021 WIN1C04135 GAA 2021 June 25, 2021 Cordillera Administrative Region Abra District Engineering Office
From: Abra-Kalinga Rd - K0451 + 800 - K0453 + 000;
Type of Work: CW1: Reconstruction to Concrete Pavement;
Physical Target: CW1: 2.226 Lane Km;
Allocation= Php 99,000,000

To: Abra-Kalinga Rd - K0467 + 000 - K0468 + 000;
Type of Work: CW1: Reconstruction to Concrete Pavement
CW2: Construction of Road Slope Protection Structure;
Physical Target: CW1: 1.922 Lane Km
CW2: 3,204 Square meters;
Allocation= Php 99,000,000

July 5, 2021 2021 WIN1C04111 GAA 2021 June 25, 2021 Cordillera Administrative Region Abra District Engineering Office
From: Abra-Ilocos Norte Rd - K0435 + 600 - K0436 + 000;
Type of Work: CW1: Reconstruction to Concrete Pavement;
Physical Target: CW1: 0.492 Lane Km;
Allocation= Php 99,000,000

To: Abra-Ilocos Norte Rd - K0435 + 420 - K0436 + 000;
Type of Work: CW1: Reconstruction to Concrete Pavement
CW2: Construction of Road Slope Protection Structure;
Physical Target: CW1: 0.852 Lane Km
CW2: 3,566.74 Square meters;
Allocation= Php 99,000,000

July 5, 2021 2021 WIN1C04125 GAA 2021 June 25, 2021 Cordillera Administrative Region Abra District Engineering Office
From: Rehabilitation/Improvement of Lagangilang Access Road, Abra - Kalinga Road Junction - Pagpagatpat, Aguet-Pagpagatpat, Lagangilang, Abra;
Physical Target: CW1: 0.978 Lane Km;
Allocation= Php 20,000,000

To: Rehabilitation/Improvement of Lagangilang Access Road, Abra - Kalinga Road Junction - Pagpagatpat, Aguet-Pagpagatpat, Lagangilang, Abra;
Physical Target: CW1: 2.746 Lane Km;
Allocation= Php 20,000,000

July 5, 2021 2021 WIN1C04126 GAA 2021 June 25, 2021 Cordillera Administrative Region Ifugao 1st District Engineering Office
From: Construction of Regio Regimental Magulon, Lamut to Sitio Maloy, Cawayan, Asipulo Road, Magulon Cawayan, Lamut Asipulo, Ifugao;
Physical Target: CW1: 0.507 Lane Km;
Allocation= Php 5,000,000

To: Construction of Sitio Regimental, Magulon, Lamut to Sitio Maloy, Cawayan, Asipulo Road, Magulon, Lamut and Cawayan, Asipulo, Ifugao ;
Physical Target: CW1: 2.00 Lane Km;
Allocation= Php 5,000,000

July 5, 2021 2021 WIN1C04126 GAA 2021 June 25, 2021 Cordillera Administrative Region Ifugao 1st District Engineering Office
From: Construction of Regio Regimental Magulon, Lamut to Sitio Maloy, Cawayan, Asipulo Road, Magulon Cawayan, Lamut Asipulo, Ifugao;
Physical Target: CW1: 0.507 Lane Km;
Allocation= Php 5,000,000

To: Construction of Sitio Regimental, Magulon, Lamut to Sitio Maloy, Cawayan, Asipulo Road, Magulon, Lamut and Cawayan, Asipulo, Ifugao ;
Physical Target: CW1: 2.00 Lane Km;
Allocation= Php 5,000,000

July 5, 2021 2021 WIN1C04068 GAA 2021 June 11, 2021 Cordillera Administrative Region Ifugao 2nd District Engineering Office
From: Construction of Barangay Mapawoy to Barangay Bongan Road, Mapawoy, Mayoyao, Ifugao;
Type of Work: Construction of Gravel Road;
Physical Target: CW1: 0.72 Lane Km;
Allocation= Php 5,000,000

To: Construction of Barangay Mapawoy to Barangay Bongan Road, Mapawoy, Mayoyao, Ifugao;
Type of Work: Construction of Concrete Road;
Physical Target: CW1: 0.364 Lane Km;
Allocation= Php 5,000,000

July 5, 2021 2021 WIN1C04078 GAA 2021 June 23, 2021 Cordillera Administrative Region Mountain Province 1st District Engineering Office
From: Construction of Katao Flood Control, Sta. 83 + 617 – Sta. 83 + 957 (R.S.), Paracelis, Mountain Province;
Physical Target: CW1: 245 Lineal meters;
Allocation= Php 20,000,000

To: Construction of Katao Flood Control, Sta. 82 + 580 – Sta. 82 + 720 (R.S.), Sta. 83 + 130 – Sta. 83 +192 (R.S.), Paracelis, Mountain Province;
Physical Target: CW1: 245 Lineal meters;
Allocation= Php 20,000,000

July 3, 2021 CY 2021 WIN1F06224 UACS NO. 310102100598000 May 5, 2021 National Capital Region Las Piñas - Muntinlupa District Engineering Office
As per GAA/Original
UACS No. 310102100598000
Project ID.: P00505480LZ

Organizational Outcome 001: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Secondary Roads
Zapote – Alabang – K0019+319 – K0019+689, K0019+691 – K0019+813
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay 1.968 km
Unit Cost (P’000) = P4,336.45 / lane km
Allocation = P 8,526,000.00
EAO = P 174,000.00
Total = P 8,700,000.00


As Modified

Organizational Outcome 001: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Secondary Roads
Zapote – Alabang – K0019+319 – K0019+493.03
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay 0.696 km
Unit Cost (P’000) = P12,250 / lane km P24M/km.
Allocation = P 8,526,000.00
EAO = P 174,000.00
Total = P 8,700,000.00
WIN1F06224
July 3, 2021 CY 2021 WIN1F0632 UACS NO. 310102100574000 May 5, 2021 National Capital Region Las Piñas - Muntinlupa District Engineering Office
As per GAA/Original
UACS No. 310102100574000
Project ID.: P00505479LZ

Organizational Outcome 001: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Secondary Roads
Zapote – Alabang – K0016+000 – K0016+424
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay 1.696 km
Unit Cost (P’000) = P44,251.736 / lane km
Allocation = P 75,050,945.00
EAO = P 2,722,055.00
Total = P 77,773,000.00







As Modified

Organizational Outcome 001: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Secondary Roads
Zapote – Alabang – K0015+000 – K0016+232.71
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay 4.931 km
Unit Cost (P’000) = P15,220.228 / lane km P30M/km.
Allocation = P 75,050,945.00
EAO = P 2,722,055.00
Total = P 77,773,000.00
WIN1F06238
July 3, 2021 CY 2021 WIN1F06237 UACS NO. 310101100412000 May 5, 2021 National Capital Region Las Piñas - Muntinlupa District Engineering Office
As per GAA/Original
UACS No. 310101100412000
Project ID.: P00505481LZ

Organizational Outcome 001: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Primary Roads
Parañaque – Sucat Road – Chainage 0 – Chainage 158
Physical Target: CW1 = Asphalt Overlay 0.632 Lane Km
Unit Cost (P’000) = P6,684.78 / lane km
Allocation = P 4,224,780.00
EAO = P 86,220.00
Total = P 4,311,000.00


As Modified

Organizational Outcome 001: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Primary Roads
Parañaque – Sucat Road, Ch.0 – Ch. 95.17
Physical Target: CW1 = Asphalt Overlay 0.632 lane km
Unit Cost (P’000) = P6,684.78 / lane km P30M/km.
Allocation = P 4,224,780.00
EAO = P 86,220.00
Total = P 4,311,000.00
WIN1F06237
July 3, 2021 CY 2021 WIN1F06249 UACS NO. 300104219083000 May 5, 2021 National Capital Region Las Piñas - Muntinlupa District Engineering Office
As per GAA/Original
UACS No. 300104219083000
Project ID.: P00557252LZ

Local Program
Local – Buildings and Other Structures – Multipurpose / Facilities – Local Infrastructure Program

Construction of Multi-Purpose Building Phase I, Barangay Pamplona 3, Las Piñas City
Physical Target: CW1 = Construction of Mult-Purpose Building 1 bldg
Unit Cost (P’000) = P 25,740.00 / bldg.
Allocation (P’000) = P25,740.00
EAO (P’000) = P 260.00
Total (P’000) = P 26,000.00

As Modified

Local Program
Local – Buildings and Other Structures – Multipurpose / Facilities – Local Infrastructure Program

Construction of Multi-Purpose Building Phase I, Barangay Pamplona 3, Las Piñas City
Physical Target: CW1 = Construction of Multi-Purpose Building 5 bldg.
Unit Cost (P’000) = P 5,148.00 / bldg.
Allocation (P’000) = P25,740.00
EAO (P’000) = P 260.00
Total (P’000) = P 26,000.00
WIN1F06249
July 3, 2021 CY 2021 WIN1B01169 UACS NO. 31011110026900 May 6, 2021 National Capital Region Las Piñas - Muntinlupa District Engineering Office
As per GAA/Original
UACS No. 310111100269000
Project ID.: P00505332LZ

Organizational Outcome 001: Ensure Safe and Reliable National Road System
Asset Preservation – Construction/ Upgrading/ Rehabilitation of Drainage along National Roads-
Secondary Roads
PPTA Rd = K0024+(-416) – K0024+384, K0024+391 – K0024+840
Physical Target: CW1 = Construction of Drainage Structure along Road 1,249 Lineal Meters
Unit Cost (P’000) = P 13.60 / Lineal Meter
Allocation = P16,992,220.00
EAO = P 346,780.00
Total = P 17,339,000.00

As Modified

Organizational Outcome 001: Ensure Safe and Reliable National Road System
Asset Preservation – Construction/ Upgrading/ Rehabilitation of Drainage along National Roads-
Secondary Roads
PPTA Rd = K0027+346 – K0027+093
Physical Target: CW1 = Construction of Drainage Structure along Road 253 Lineal Meters
Unit Cost (P’000) = P 67.16 / Lineal Meter
Allocation = P16,992,220.00
EAO = P 346,780.00
Total = P 17,339,000.00
WIN1B01169
July 3, 2021 CY 2021 WIN1B01171 UACS NO. 310110100204000 May 6, 2021 National Capital Region Las Piñas - Muntinlupa District Engineering Office
As per GAA/Original
UACS No. 310110100204000
Project ID.: P00505331LZ

Organizational Outcome 001: Ensure Safe and Reliable National Road System
Asset Preservation – Construction/ Upgrading/ Rehabilitation of Drainage along National Roads-
Primary Roads
Quirino Avenue – K0012+176 – K0013+044
Physical Target: CW1 = Construction of Drainage Structure along Road 1,722 Lineal Meters
Unit Cost (P’000) = P 45.16 / Lineal Meter
Allocation = P39,200,000.00
EAO = P 800,000.00
Total = P 40,000,000.00

As Modified

Organizational Outcome 001: Ensure Safe and Reliable National Road System
Asset Preservation – Construction/ Upgrading/ Rehabilitation of Drainage along National Roads-
Primary Roads
Quirino Avenue – K0012+176 – K0012+744
Physical Target: CW1 = Construction of Drainage Structure along Road 701 Lineal Meters
Unit Cost (P’000) = P 55.92 / Lineal Meter
Allocation = P39,200,000.00
EAO = P 800,000.00
Total = P 40,000,000.00
WIN1B01171
July 3, 2021 CY 2021 WIN1F06414 UACS NO. 310102100628000 May 6, 2021 National Capital Region Quezon City 2nd Engineering District Office
As per GAA/Original
UACS No. 310102100628000
Project ID.: P00515891LZ

OO1: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Secondary Roads
Cordillera St. (S05361LZ) K0006+(-410) – K0006+528
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay L=1.876 lane km
Unit Cost (P’000) = P 6,268.66/ lane km
Allocation (P’000) = P 11,760.00
EAO (P’000) = P 240.00
Total (P’000) = P 12,000.00

As Modified

OO1: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Secondary Roads
Cordillera St. (S05361LZ) K0006+(-155) – K0006+528
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay L=1.365 lane km
Unit Cost (P’000) = P 8,615.38/ lane km P 17.2 M/Km
Allocation (P’000) = P 11,760.00
EAO (P’000) = P 240.00
Total (P’000) = P 12,000.00
WIN1F06414
July 3, 2021 CY 2021 WIN1F06410 UACS NO. 310103100644000 May 6, 2021 National Capital Region Quezon City 2nd Engineering District Office
As per GAA/Original
UACS No. 310103100644000
Project ID.: P00505524LZ

OO1: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Tertiary Roads
Tomas Morato – K0009+(-090) – K0009+127, K0009+1073 – K0009+1172,
K0009+127-K0009+1073
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay L=4.952 lane km
Unit Cost (P’000) = P 4,336.18/ lane km
Allocation (P’000) = P 21,472.78
EAO (P’000) = P 438.22
Total (P’000) = P 21,911.00

As Modified

OO1: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Tertiary Roads
Tomas Morato – K0009+(-090) – K0009+653,
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay L=2.972 lane km
Unit Cost (P’000) = P 7,225.03/ lane km P 14.4 M/Km.
Allocation (P’000) = P 21,472.78
EAO (P’000) = P 438.22
Total (P’000) = P 21,911.00
WIN1F06410
July 3, 2021 CY 2021 WIN1F06417 UACS No. 320101106441000 May 7, 2021 National Capital Region North Manila District Engineering Office
As per GAA/Original
UACS No. 320101106441000
Project ID.: P00525827LZ

002: Protect Lives and Properties

Flood Management – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Rehabilitation of RCPC along Blumentritt Extension, Chainage 251.70 to Chainage 963.00, Manila City
Physical Target: CW1 – Construction of Flood Mitigation Structure 895.70 l.m.
CW2 – Construction of Concrete Road
Unit Cost (P’000) = P 31.75 / l.m.
= P 22.97/ l.m.
Allocation (P’000) = P 28,430.00
= P 20,570.00
EAO (P’000) = P 1,000.00
Total (P’000) = P 50,000.00


002: Protect Lives and Properties

Flood Management – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Rehabilitation of RCPC along Blumentritt Extension, Chainage 251.70 to Chainage 948 and Chainage 435.20
to Chainage 634.60, Manila City
Physical Target: CW1 – Construction of Flood Mitigation Structure 895.70 l.m.
CW2 – Construction of Concrete Road P 44 M/Km
Unit Cost (P’000) = P 31.75 / l.m.
= P 22.97/ l.m.
Allocation (P’000) = P 28,430.00
= P 20,570.00
EAO (P’000) = P 1,000.00
Total (P’000) = P 50,000.00
WIN1F06417
July 2, 2021 FY 2021 GAA WIN1F06316 FY 2021 GAA DPWH Infra Projects December 28, 2020 Region IV-B Southern Mindoro Engineering District Office
UACS No. : 300117209177000
Project ID : P00564730LZ

LOCAL PROGRAM

Local Roads and Bridges - Local Roads -
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM :

Construction of Road,
Barangay Kaligtasan, Bongabong, Oriental Mindoro
Physical Target - CW1 - Construction of Concrete Road :
0.00 Lane Km
Allocation : Php 1.00 Million

TO :

Construction of Road,
Barangay Kaligtasan, Bongabong, Otiental Mindoro
Physical Target - CW1 - Construction of Concrete Road :
0.1948 Lane Km
Allocation : Php 1.00 Million
July 2, 2021 CY 2021 WIN1B01165 UACS NO. 300209100008000 May 2, 2021 National Capital Region NCR - Regional Office
As per GAA/Original
UACS No. 300209100008000
Project ID.: P00531635LZ

Convergence and Special Support Program

Construction/Improvement of Access Roads leading to Railway Stations
Old Sauyo Road leading to Quirino Highway Station, Quezon City
Physical Target: CW1 = Construction of Drainage Structure 1200 l.m.
CW2 = Shoulder Paving / Construction 2400 l.m.
Unit Cost (P’000) = P 6.13 / l.m.
= P 2.03 / sq.m.
Allocation (P’000) = P 7,365.85
= P 4,860.71
EAO (P’000) = P 443.35
Total (P’000) = P 12,670.00

As Modified

Convergence and Special Support Program

Construction/Improvement of Access Roads leading to Railway Stations
Old Sauyo Road leading to Quirino Highway Station, Quezon City
Physical Target: CW1 = Shoulder Paving / Construction 2965 sq.m.
Unit Cost (P’000) = P 4.12 / l.m.
Allocation (P’000) = P 12,226.55
EAO (P’000) = P 443.35
Total (P’000) = P 12,670.00
WIN1B01165
July 2, 2021 FY 2021 GAA WIN1F06246 FY 2021 GAA DPWH Infra Projects December 28, 2020 Region IV-B Southern Mindoro Engineering District Office
UACS No. : 300104222161000
Project ID : P00560691LZ

LOCAL PROGRAM

Local - Building and Other Structures - Multipurpose/Facilities -
Local Infrastructure Program

FROM :

Construction of Multi-Purpose Building (Phase 2),
Barangay Nasukob, Bulalacao, Oriental Mindoro
Physical Target - CW1 - Construction of Multi-Purpose Building :
1 No. of Building
Allocation : Php 4.00 Million

TO :

Construction of Multi-Purpose Building,
Barangay Nasukob, Bulalacao, Oriental Mindoro
Physical Target - CW1 - Construction of Multi-Purpose Building :
1 No. of Building
Allocation : Php 4.00 Million
July 2, 2021 CY 2021 WIN1F06359 UACS NO. 300209100005000 May 2, 2021 National Capital Region NCR - Regional Office
As per GAA/Original
UACS No. 300209100005000
Project ID.: P00531629LZ

Convergence and Special Support Program

Construction/Improvement of Access Roads leading to Railway Stations
Genaral Ave. leading to Tandang Sora Station, Quezon City
Physical Target: CW1 = Construction of Drainage Structure 1038 l.m.
CW2 = Shoulder Paving / Construction 2092 l.m.
Unit Cost (P’000) = P 6.07 / l.m.
= P 2.01 / sq.m.
Allocation (P’000) = P 6,299.52
= P 4,199.68
EAO (P’000) = P 380.80
Total (P’000) = P 10,880.00

As Modified

Convergence and Special Support Program

Construction/Improvement of Access Roads leading to Railway Stations
Genaral Ave. leading to Tandang Sora Station, Quezon City
Physical Target: CW1 = Construction of Drainage Structure 2478 sq.m.
Unit Cost (P’000) = P 4.24 / sq.m.
Allocation (P’000) = P 10,499.20
EAO (P’000) = P 380.80
Total (P’000) = P 10,880.00
WIN1F06359
July 2, 2021 CY 2021 WIN1F06191 UACS NO. 320101106448000 May 2, 2021 National Capital Region North Manila District Engineering Office
As per GAA/Original
UACS No. 320101106448000
Project ID.: P00525814LZ

002: Protect Lives and Properties

Flood Management – Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Bank Improvement (Steel Sheet File) along Estero dela Reina, Barangay 58, 56 & 51 Sta. 0+628.60
to Sta. 0+702.60 (LS); Sta. 0+757.10 to Sta. 0+841.50 (RS), Manila City
Physical Target: CW1 = Construction of Flood Mitigation Structure 119.40 l.m.
Unit Cost (P’000) = P328.30 / l.m.
Allocation (P’000) = P 39,200.00
EAO (P’000) = P 800.00
Total (P’000) = P 40,000.00

As Modified

002: Protect Lives and Properties

Flood Management – Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Bank Improvement (Steel Sheet File) along Estero dela Reina, Barangay 58, 56 & 51 (LS) Sta. 0+723.90
to Sta. 0+783.60; (RS) Sta. 0+732.60 to Sta. 0+792.30, Manila City
Physical Target: CW1 = Construction of Flood Mitigation Structure 119.40 l.m.
Unit Cost (P’000) = P328.300 M/ LM
Allocation (P’000) = P 39,200.00
EAO (P’000) = P 800.00
Total (P’000) = P 40,000.00
WIN1F06191
July 2, 2021 CY 2021 WIN1F06191 UACS NO. 320101106448000 May 2, 2021 National Capital Region North Manila District Engineering Office
As per GAA/Original
UACS No. 320101106448000
Project ID.: P00525814LZ

002: Protect Lives and Properties

Flood Management – Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Bank Improvement (Steel Sheet File) along Estero dela Reina, Barangay 58, 56 & 51 Sta. 0+628.60
to Sta. 0+702.60 (LS); Sta. 0+757.10 to Sta. 0+841.50 (RS), Manila City
Physical Target: CW1 = Construction of Flood Mitigation Structure 119.40 l.m.
Unit Cost (P’000) = P328.30 / l.m.
Allocation (P’000) = P 39,200.00
EAO (P’000) = P 800.00
Total (P’000) = P 40,000.00

As Modified

002: Protect Lives and Properties

Flood Management – Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Bank Improvement (Steel Sheet File) along Estero dela Reina, Barangay 58, 56 & 51 (LS) Sta. 0+723.90
to Sta. 0+783.60; (RS) Sta. 0+732.60 to Sta. 0+792.30, Manila City
Physical Target: CW1 = Construction of Flood Mitigation Structure 119.40 l.m.
Unit Cost (P’000) = P328.300 M/ LM
Allocation (P’000) = P 39,200.00
EAO (P’000) = P 800.00
Total (P’000) = P 40,000.00
WIN1F06191
July 2, 2021 CY 2021 WIN1F06201 UACS NO. 310102100619000 May 2, 2021 National Capital Region North Manila District Engineering Office
As per GAA/Original
UACS No. 310102100619000
Project ID.: P00505439LZ

001: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Secondary Roads
R-10 – K0004+1192 – K0004+1214, K0004+471 – K0004+1192
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay L=2.972 km
Unit Cost (P’000) = P8,160.18 / lane km
Allocation (P’000) = P 24,252,060.00
EAO = P 494,940.00
Total (P’000) = P 24,747,000.00

As Modified

001: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Secondary Roads
R-10 – K0005+(-591.80) – K0006+(-065.80)
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay L=2.972 km
Unit Cost (P’000) = P8,160.18 / lane km P16M/lm
Allocation (P’000) = P 24,252,060.00
EAO = P 494,940.00
Total (P’000) = P 24,747,000.00
WIN1F06201
July 2, 2021 CY 2021 WIN1F06207 UACS NO. 31010300630000 May 2, 2021 National Capital Region North Manila District Engineering Office
As per GAA/Original
UACS No. 31010300630000
Project ID.: P00505500LZ

001: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Tertiary Roads
Rodriguez St – Chainage 0 – Chainage 399
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay L=1.039 lane km
Unit Cost (P’000) = P4,336.35 / lane km
Allocation (P’000) = P 4,501.14
EAO = P 91.86
Total (P’000) = P 4,593.00

As Modified

001: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Tertiary Roads
Rodriguez St – Chainage 0 – Chainage 184.70
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay L=1.039 lane km
Unit Cost (P’000) = P4,336.35 / lane km P8.6M/lm
Allocation (P’000) = P 4,501.14
EAO = P 91.86
Total (P’000) = P 4,593.00
WIN1F06207

July 2, 2021 CY 2021 WIN1F06211 UACS NO. 310103100632000 May 2, 2021 National Capital Region North Manila District Engineering Office
As per GAA/Original
UACS No. 310103100632000
Project ID.: P00505501LZ

001: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Tertiary Roads
Vitas St – Chainage 0 – Chainage 573
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay L=1.146 km
Unit Cost (P’000) = P4,336.45 / lane km
Allocation (P’000) = P 4,969.58
EAO = P 101.42
Total (P’000) = P 5,071.00

As Modified

001: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Tertiary Roads
Vitas St – Chainage 0 – Chainage 289.40
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay L=1.146 km
Unit Cost (P’000) = P4,336.45 / lane km / P8.6/M
Allocation (P’000) = P 4,969.58
EAO = P 101.42
Total (P’000) = P 5,071.00
WIN1F06211
July 2, 2021 CY 2021 WIN1F06254 UACS NO. 310105100521000 May 2, 2021 National Capital Region North Manila District Engineering Office
As per GAA/Original
UACS No. 310105100521000
Project ID.: P00505440LZ

OO1: Ensure Safe and Reliable National Road System

Asset Preservation – Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads – Secondary Roads
R-10 – K0006 + 444 – K0006+516
Physical Target: CW1 = Rehabilitation of Paved Road L=0.216 lane km
Unit Cost (P’000) = P 18,801.48 / lane km
Allocation (P’000) = P 4,061.12
EAO (P’000) = P 82.88
Total (P’000) = P 4,144.00


As Modified

OO1: Ensure Safe and Reliable National Road System

Asset Preservation – Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads – Secondary Roads
R-10 – K0006 + (-049.4) – K0006+010.6
Physical Target: CW1 = Rehabilitation of Paved Road L=0.216 lane km
Unit Cost (P’000) = P 18,801.48 / lane km P37.6 M/km
Allocation (P’000) = P 4,061.12
EAO (P’000) = P 82.88
Total (P’000) = P 4,144.
WIN1F06254
July 2, 2021 CY 2021 WIN1F06281 UACS NO. 320101106462000 May 2, 2021 National Capital Region North Manila District Engineering Office
As per GAA/Original
UACS No. 320101106462000
Project ID.: P00525828LZ

002: Protect Lives and Properties

Flood Management – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Rehabilitation of RCPC along Lardizabal Street, Chainage 000.00 to Chainage 2185.10, Manila City
Physical Target: CW1 – Construction of Flood Mitigation Structure 635.00 l.m.
Unit Cost (P’000) = P 77.16 / l.m.
Allocation (P’000) = P 49,000.00
EAO (P’000) = P 1,000.00
Total (P’000) = P 50,000.00


002: Protect Lives and Properties

Flood Management – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Rehabilitation of RCPC along Lardizabal Street, Sta. 0+000.00 to Sta. 0+266.00 and
Sta. 0+000.00 to Sta. 0+369.00, Manila City
Physical Target: CW1 – Construction of Flood Mitigation Structure 635.00 l.m.
Unit Cost (P’000) = P 77.16 / l.m.
Allocation (P’000) = P 49,000.00
EAO (P’000) = P 1,000.00
Total (P’000) = P 50,000.00
WIN1F06281
July 2, 2021 CY 2021 WIN1F06320 UACS NO. 320101106441000 May 2, 2021 National Capital Region North Manila District Engineering Office
As per GAA/Original
UACS No. 320101106441000
Project ID.: P00525807LZ

002: Protect Lives and Properties

Flood Management – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Bank Improvement (Steel Sheet Pile) along Estero de Quiapo, Brgy. 393 (Phase I), Sta. 0+500.00
to Sta. 0+658.40
Physical Target: CW1 – Construction of Flood Mitigation Structure 117.20 l.m.
Unit Cost (P’000) = P 324.321 / l.m.
Allocation (P’000) = P 38,010.28
EAO (P’000) = P 775.72
Total (P’000) = P 38,786.00


002: Protect Lives and Properties

Flood Management – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Bank Improvement (Steel Sheet Pile) along Estero de Quiapo, Brgy. 393 (Phase I), Sta. 0+500.00
to Sta. 0+617.20
Physical Target: CW1 – Construction of Flood Mitigation Structure 117.20 l.m.
Unit Cost (P’000) = P 324.321 / l.m. P342,320/lm
Allocation (P’000) = P 38,010.28
EAO (P’000) = P 775.72
Total (P’000) = P 38,786.00
WIN1F06320
July 2, 2021 CY 2021 WIN1F06252 UACS NO. 310103100642000 May 5, 2021 National Capital Region Quezon City 2nd Engineering District Office
As per GAA/Original
UACS No. 310103100642000
Project ID.: P00505525LZ

OO1: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Secondary Roads
Hemady St – K0009+(-615) – K0009+(-479), K0009+(-682) – K0009+(-615),
K0009+(-979) – K0009+(-682)
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay 1.364 lane km
Unit Cost (P’000) = P 4,336.71 / lane km
Allocation (P’000) = P 5,915.28
EAO (P’000) = P 120.72
Total (P’000) = P 6,036.00

As Modified

OO1: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Secondary Roads
Hemady St – K0009+(-979) – K0009+(-698)
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay 0.843 lane km
Unit Cost (P’000) = P 7,016.94 / lane km
Allocation (P’000) = P 5,915.28
EAO (P’000) = P 120.72
Total (P’000) = P 6,036.00
WIN1F06252

July 2, 2021 CY 2021 WIN1F06355 UACS NO. 310105100494000 May 5, 2021 National Capital Region Quezon City 2nd Engineering District Office
As per GAA/Original
UACS No. 310105100494000
Project ID.: P00505527LZ

OO1: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Secondary Roads
South Ave (Timog Ave) K0010+(-890) – K0010+(-570),
K0010+(-964) - K0010+(-890)
Physical Target: CW1 = Reconstruction to concrete Pavement 2.02 lane km
Unit Cost (P’000) = P 34,836.5 / lane km
Allocation (P’000) = P 70,369.73
EAO (P’000) = P 2,552.270
Total (P’000) = P 72,922.00

As Modified

OO1: Ensure Safe and Reliable National Road System

Asset Preservation – Preventive Maintenance – Secondary Roads
South Ave (Timog Ave) K0010+(-964) – K0010+(-890),
K0010+(-890) - K0010+144, K0009+(-213) – K0009+119
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay L=2.02 lane km
Unit Cost (P’000) = P 11,354.79 / lane km P22M/km
Allocation (P’000) = P 70,369.73
EAO (P’000) = P 2,552.270
Total (P’000) = P 72,922.00
WIN1F06355
July 2, 2021 CY 2021 WIN1F06334 UACS NO. 310106100553000 May 5, 2021 National Capital Region Malabon-Navotas District Engineering Office
As per GAA/Original
UACS No. 310106100553000
Project ID.: P00505482LZ

OO1: Ensure Safe and Reliable National Road System

Asset Preservation – Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads – Tertiary Roads
MH Del Pilar St (Malabon) –K0013+462 – K0013+496
Physical Target: CW1 = Rehabilitation of Paved Road: 0.068 lane km
Unit Cost = P 18,375.00 / lane km
Allocation (P’000) = P 1,249.50
EAO (P’000) = P 25.50
Total (P’000) = P 1,275.00

As Modified

OO1: Ensure Safe and Reliable National Road System

Asset Preservation – Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads – Tertiary Roads
MH Del Pilar St (Malabon) –K0013+570 – K0013+601.50
Physical Target: CW1 = Rehabilitation of Paved Road: 0.063 lane km
Unit Cost = P 19,825.29714 / lane km P39.6M/km.
Allocation (P’000) = P 1,248.99
EAO (P’000) = P 25.50
Total (P’000) = P 1,275.00
WIN1F06334
July 2, 2021 2021 WIN1F06283 FCR 2021 RA 11518 December 28, 2020 Region VI Capiz 1st District Engineering Office
FROM:


ORGANIZATIONAL OUTCOME 1: Ensure Safe and Reliable National Road System

Network Development Program - Road Widening - Secondary Roads

Roxas City-Cagay-Sibaguan-Balijuagan-Cudian-Ivisan Rd - K0108 + 203 - K0108 + 887

CW1- Road Widening: 1.368 lane km - 17,428.32

EAO - 355.68

Total: 17,784.00

TO:


ORGANIZATIONAL OUTCOME 1: Ensure Safe and Reliable National Road System

Network Development Program - Road Widening - Secondary Roads

Roxas City-Cagay-Sibaguan-Balijuagan-Cudian-Ivisan Rd - K0108 + 203 - K0108 + 879


CW1- Road Widening: 1.352 lane km - 17,428.32

EAO - 355.68

Total: 17,784.00
July 2, 2021 2021 WIN1F06406 FCR 2021 RA 11518 December 28, 2020 Region VI Capiz 1st District Engineering Office
FROM:

ORGANIZATIONAL OUTCOME 1: Ensure Safe and Reliable National Road System

Asset Preservation Program - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Secondary Roads

Iloilo East Coast-Capiz Rd - K0118 + 137 - K0118 + 288

CW1- Reconstruction to Concrete Pavement: 0.365 lane km - 7,491.12

EAO - 152.88

Total: 7,644.00


TO:

ORGANIZATIONAL OUTCOME 1: Ensure Safe and Reliable National Road System

Asset Preservation Program - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Secondary Roads

Iloilo East Coast-Capiz Rd - K0118 + 137 - K0118 + 288

CW1- Reconstruction to Concrete Pavement: 0.302 lane km - 7,491.12

EAO - 152.88

Total: 7,644.00