May 18, 2018 |
2018 |
WIN8C02980 |
FY 2018 GAA R.A 10964 |
January 1, 2018 |
Region XI |
Davao de Oro 1st District Engineering Office |
MODIFICATION
FROM: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Concreting of Road, Aguinaldo, Laak, Compostela Valley
Physical Target:
CW1: 0.300 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 3,000,000.00
CW1: P 2,940,000.00 (Construction of Concrete Road)
EAO: P 60,000.00
TO: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Concreting of Road, Aguinaldo, Laak, Compostela Valley
Physical Target:
CW1: 0.340 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 3,000,000.00
CW1: P 2,940,000.00 (Construction of Concrete Road)
EAO: P 60,000.00 |
May 18, 2018 |
2018 |
WIN8C02973 |
FY 2018 GAA R.A 10964 |
January 1, 2018 |
Region XI |
Davao de Oro 1st District Engineering Office |
MODIFICATION
FROM: OO2 Protect Lives and Properties
Flood Management – Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Rechanneling and Construction of Revetment along Kalamokan Creek, Barangay Poblacion, New Bataan, Compostela Valley
Physical Target:
CW1: 750 Lineal Meters (Construction of Revetment)
CW2: 53,000 Cubic Meters (Channelization)
ALLOCATION:
TOTAL: P 50,000,000.00
CW1: P 20,555,726.00
CW2: P 28,444,274.00
EAO: P 1,000,000.00
TO: OO2 Protect Lives and Properties
Flood Management – Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Rechanneling and Construction of Revetment along Kalamokan Creek, Barangay Poblacion, New Bataan, Compostela Valley
Physical Target:
CW1: 2,276 Lineal Meters (Construction of Revetment)
CW2: 66,007 Cubic Meters (Channelization)
ALLOCATION:
TOTAL: P 50,000,000.00
CW1: P 37,161,352.00
CW2: P 11,838.648.00
EAO: P 1,000,000.00 |
May 18, 2018 |
2018 |
WIN8C02981 |
FY 2018 GAA R.A 10964 |
January 1, 2018 |
Region XI |
Davao de Oro 1st District Engineering Office |
MODIFICATION:
FROM: Local Program
Local - Local Roads and Bridges - Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Concreting of Anislagan Road, Maco, Compostela Valley
Physical Target:
CW1 - 0.600 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 6,000,000.00
CW1 - P 5,880,000.00 (Construction of Concrete Road)
EAO - P 120,000.00
TO : Local Program
Local - Local Roads and Bridges - Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Concreting of Anislagan Road, Maco, Compostela Valley
Physical Target:
CW1 - 0.666 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 6,000,000.00
CW1 - P 5,880,000.00
EAO - P 120,000.00
|
May 18, 2018 |
2018 |
WIN8C02972 |
FY 2018 GAA R.A 10964 |
January 1, 2018 |
Region XI |
Davao de Oro 1st District Engineering Office |
MODIFICATION
FROM: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Concreting of Circumferential Road, Magading, Nabunturan, Compostela Valley
Physical Target:
CW1: 0.500 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 5,000,000.00
CW1: P 4,900,000.00 (Construction of Concrete Road)
EAO: P 100,000.00
TO: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Concreting of Circumferential Road, Magading, Nabunturan, Compostela Valley
Physical Target:
CW1: 0.716 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 5,000,000.00
CW1: P 4,900,000.00 (Construction of Concrete Road)
EAO: P 100,000.00 |
May 18, 2018 |
2018 |
WIN8C02993 |
FY 2018 GAA R.A 10964 |
January 1, 2018 |
Region XI |
Davao de Oro 1st District Engineering Office |
MODIFICATION:
FROM: Local Program
Local - Local Roads and Bridges - Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction of Tan-awan Road, Malinawon, Mawab, Compostela Valley
Physical Target:
CW1 - 0.650 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 6,500,000.00
CW1 - P 6,370,000.00 (Construction of Concrete Road)
EAO - P 130,000.00
TO: Local Program
Local - Local Roads and Bridges - Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction of Tan-awan Road, Malinawon, Mawab, Compostela Valley
Physical Target:
CW1 - 0.842 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 6,500,000.00
CW1 - P 6,370,000.00 (Construction of Concrete Road)
EAO - P 130,000.00
|
May 18, 2018 |
2018 |
WIN8C02999 |
FY 2018 GAA R.A 10964 |
January 1, 2018 |
Region XI |
Davao de Oro 1st District Engineering Office |
MODIFICATION
FROM: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Road, Langtud to National Highway, Laak, Compostela Valley
Physical Target:
CW1: 1.200 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 12,000,000.00
CW1: P 11,580,000.00 (Construction of Concrete Road)
EAO: P 420,000.00
TO: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Road, Langtud to National Highway, Laak, Compostela Valley
Physical Target:
CW1: 1.324 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 12,000,000.00
CW1: P 11,580,000.00 (Construction of Concrete Road)
EAO: P 420,000.00 |
May 18, 2018 |
2018 |
WIN8C02978 |
FY 2018 GAA R.A 10964 |
January 1, 2018 |
Region XI |
Davao de Oro 1st District Engineering Office |
MODIFICATION:
FROM: 002: Protect Lives and Properties
Flood Management - Construction / Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Revetment, Brgy. Napnapan, Pantukan, Compostela Valley
Physical Target:
CW1 - 1,050 Lineal meters (Construction of Revetment)
CW2 - 3,500 cubic meters (Channelization)
ROW - 2,343 square meters
ALLOCATION:
TOTAL: P 35,000,000.00
CW1 - P 31,734,487.00 (Construction of Revetment)
CW2 - P 2,163,713.00 (Channelization)
ROW - P 401,800.00
EAO - P 700,000.00
TO: 002: Protect Lives and Properties
Flood Management - Construction / Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Revetment, Brgy. Napnapan, Pantukan, Compostela Valley
Physical Target:
CW1 - 687.28 Lineal meters (Construction of Revetment)
CW2 - 1,463 cubic meters (Channelization)
ROW - 2,343 square meters
ALLOCATION:
TOTAL: P 35,000,000.00
CW1 - P 32,540,500.00 (Construction of Revetment)
CW2 - P 1,357,700.00 (Channelization)
ROW - P 401,800.00
EAO - P 700,000.00 |
May 18, 2018 |
2018 |
WIN8C02992 |
FY 2018 GAA R.A 10964 |
January 1, 2018 |
Region XI |
Davao de Oro 1st District Engineering Office |
MODIFICATION
FROM: OO2 Protect Lives and Properties
Flood Management – Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Rechanneling and Construction of Revetment along Manat River, Barangay Banagbanag, Montevista, Compostela Valley
Physical Target:
CW1: 337 Lineal Meters (Construction of Revetment)
CW2: 4,267 Cubic Meters (Channelization)
ROW: 1,714 Square Meters
ALLOCATION:
TOTAL: P 50,000,000.00
CW1: P 44,733,834.00 (Construction of Revetment)
CW2: P 3,972,166.00 (Channelization)
ROW: P 294,000.00
EAO: P 1,000,000.00
TO: OO2 Protect Lives and Properties
Flood Management – Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Rechanneling and Construction of Revetment along Manat River, Barangay Banagbanag, Montevista, Compostela Valley
Physical Target:
CW1: 674.40 Lineal Meters (Construction of Revetment)
CW2: 4,267 Cubic Meters (Channelization)
ROW: 1,714 Square Meters
ALLOCATION:
TOTAL: P 50,000,000.00
CW1: P 46,382,278.00 (Construction of Revetment)
CW2: P 2,323,721.00 (Channelization)
ROW: P 294,000.00
EAO: P 1,000,000.00 |
May 18, 2018 |
2018 |
WIN8C02985 |
FY 2018 GAA R.A 10964 |
January 1, 2018 |
Region XI |
Davao de Oro 1st District Engineering Office |
MODIFICATION
FROM: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Concreting of Road at Brgy. Dumlan to Brgy. Libaylibay Section Maco, Compostela Valley
Physical Target:
CW1: 1.500 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 15,000,000.00
CW1: P 14,700,000.00 (Construction of Concrete Road)
EAO: P 300,000.00
TO: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Concreting of Road at Brgy. Dumlan to Brgy. Libaylibay Section Maco, Compostela Valley
Physical Target:
CW1: 2.282 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 15,000,000.00
CW1: P 14,700,000.00 (Construction of Concrete Road)
EAO: P 300,000.00 |
May 18, 2018 |
2018 |
WIN8C02986 |
FY 2018 GAA R.A 10964 |
January 1, 2018 |
Region XI |
Davao de Oro 1st District Engineering Office |
MODIFICATION:
FROM: 002: Protect Lives and Properties
Flood Management - Construction / Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Revetment at Manat River, Olaycon Section, Monkayo, Compostela Valley
Physical Target:
CW1 - 360 Lineal meters (Construction of Revetment)
CW2 - 55,000 cubic meters (Channelization)
ROW - 1,286 square meters
ALLOCATION:
TOTAL: P 85,000,000.00
CW1 - P 57,214,850.00 (Construction of Revetment)
CW2 - P 24,520,650.00 (Channelization)
ROW - P 289,500.00
EAO - P 2,975,000.00
TO: 002: Protect Lives and Properties
Flood Management - Construction / Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Revetment at Manat River, Olaycon Section, Monkayo, Compostela Valley
Physical Target:
CW1 - 373.6 Lineal meters (Construction of Revetment)
CW2 - 61,208 cubic meters (Channelization)
ROW - 1,286 square meters
ALLOCATION:
TOTAL: P 85,000,000.00
CW1 - P 71,107,054.00 (Construction of Revetment)
CW2 - P 10,628,446.00 (Channelization)
ROW - P 289,500.00
EAO - P 2,975,000.00 |
May 18, 2018 |
2018 |
WIN8C03005 |
FY 2018 GAA R.A 10964 |
January 1, 2018 |
Region XI |
Davao de Oro 1st District Engineering Office |
MODIFICATION
FROM: Convergence and Special Support Program
Construction / Improvement of Access Roads leading to Declared Tourism Destinations
Magsaysay Road leading to Aqualime Mountain Resort, Brgy. Magsaysay, Nabunturan, Compostela Valley
Physical Target:
CW1 – 2.525 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 30,000,000.00
CW1 - P 29,400,000.00 (Construction of Concrete Road)
EAO - P 600,000.00
TO: Convergence and Special Support Program
Construction / Improvement of Access Roads leading to Declared Tourism Destinations
Magsaysay Road leading to Aqualime Mountain Resort, Brgy. Magsaysay, Nabunturan, Compostela Valley
Physical Target:
CW1 – 2.273 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 30,000,000.00
CW1 - P 29,400,000.00 (Construction of Concrete Road)
EAO - P 600,000.00 |
May 17, 2018 |
FY - 2018 |
WIN8F05436 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Romblon District Engineering Office |
001 - Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction/Upgrading
of Damaged Paved Roads - Secondary Roads
FROM:
Tablas Circumferential Rd
K0084+315 - K0084+560
CW1:0.490 Lane Km ( Reconstruction from Paved
to Concrete )
Allocation: 6,600,000 Php
TO:
Tablas Circumferential Rd
K0077+220 - K0077+420
CW1: 0.40 Lane Km ( Reconstruction from Paved
to Concrete )
Allocation: 6,600,000 Php |
May 17, 2018 |
FY - 2018 |
WIN8F05432 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Romblon District Engineering Office |
001 - Ensure Safe and Reliable National Road System
Network Development - Off-Carriageway Improvement
- Secondary Roads
FROM:
Tablas Circumferential Rd
K0050+000 - K0052+485,
K0054+000 - K0055+125,
K0083+000 - K0083+398,
K0083+541 - K0084+315,
K0084+560 - K0087+000,
K0091+048 - K0091+670,
K0096+000 - K0097+233,
K0102+894 - K0103+052
CW1: 27,747 square meters
( Off-Carriageway Improvement: Shoulder Paving/
Construction )
Allocation: 89,377,000 Php
TO:
Tablas Circumferential Rd.
K0050+000 - K0052+477,
K0054+000 - K0055+134,
K0083+000 - K0083+990,
K0084+560 - K0086+792,
K0091+048 - K0091+670,
K0096+000 - K0097+254,
K0102+894 - K0103+.45.70
CW1: 28,123.26 square meters
( Off-Carriageway Improvement: Shoulder Paving/
Construction )
Allocation: 89,377,000 Php |
May 17, 2018 |
FY - 2018 |
WIN8F05442 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Palawan 1st District Engineering Office |
Convergence Special Support Program
Convergence and Special Support - Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones
FROM:
Access Road leading to Fishing Industry
Taytay, Palawan
CW1: 4 lane km ( Construction of Concrete Road )
Allocation: 50,000,000 Php
TO:
Access Road leading to Fishing Induatry
Taytay, Palawan
CW1: 3.556 Lane Km ( Construction of Concrete Road )
Allocation: 50,000,000 Php
|
May 17, 2018 |
FY - 2018 |
WIN8F05435 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Palawan 1st District Engineering Office |
Convergence Special Support Program
Convergence and Special Support -
Construction/Improvement of Access Roads leading to
Trades, Industries and Economic Zones
FROM:
Access Road leading to Mussel Production and
Fishing Industry, Taytay, Palawan
CW1: 4 lane Km ( Construction of Concrete Road )
Allocation: 50,000,000 Php
TO:
Access Road leading to Mussel Production and
Fishing Industry, Taytay, Palawan
CW1: 3.4136 Lane Km ( Construction of Concrete Road )
Allocation: 50,000,000 Php |
May 17, 2018 |
FY 2018 |
WIN8C02688 |
320101102199000 |
May 3, 2018 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No. 320101102199000
Project ID: P00221451MN
OO2: Protect Lives and Properties Against Major Floods-Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Flood Control Project Phase I in Metro Brgys. of Ipil, (Don Andres - Bangkerohan, Lower Taway, ), Ipil, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 784.84 lineal meters
Unit Cost: P 36,185.72/lineal meter
ROW Acquisition: 3,333.33 sq.m.
Unit Cost: P 300/sq.m.
EAO: P 0.6 M
Allocation: P 30 M |
May 17, 2018 |
FY - 2018 |
WIN8F05433 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Palawan 1st District Engineering Office |
Convergence Special Support Program
Convergence and Special Support -
Construction/Improvement of Access Roads leading to
Trades, Industries and Economic Zones
FROM:
Access Road leading to Seaweed Plantations in
Brgy. Sta. Teresita, Dumaran, Palawan
CW1: 4 lane Km ( Construction of Concrete Road )
Allocation: 50,000,000 Php
TO:
Access Road leading to Seaweed Plantation in
Brgy. Sta. teresita, Dumaran, Palawan
CW1: 3.054 Lane Km ( Construction of Concrete Road )
Allocation: 50,000,000 Php |
May 17, 2018 |
FY 2018 |
WIN8C02686 |
300116201168000 |
May 3, 2018 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No. 300116201168000
Project ID: P00240256MN
Local Program:
Local Roads and Bridges - Local Roads -
Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Improvement/Construction/Concreting of Labasan - Camaga Road, Siay, Zamboanga Sibugay (Phase II)
Sta. 3+111.00 - Sta. 3+745.12,
Sta. 4+045.84 - Sta. 5+378.00
Physical Target:
CW-1 - Construction of Concrete Road:
3.93256 lane km.
Unit Cost: P 7,476,046.14/lane km.
EAO: P 0.600 M
Allocation: P 30 M |
May 17, 2018 |
FY 2018 |
WIN8C02685 |
300117202015000 |
May 3, 2018 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No. 300117202015000
Project ID: P00251466MN
Local Program:
Local Roads and Bridges - Local Roads - Local Infrastructure Program
Construction of Barangay Road, Brgy. Don Andres, Ipil, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Concrete Road:
0.19 lane km.
Unit Cost: P 5,263,157.89/lane km.
Allocation: P 1 M |
May 17, 2018 |
FY - 2018 |
WIN8F05431 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Palawan 1st District Engineering Office |
001 - Ensure Safe and Reliable National Road System
Network Development - Paving of Unpaved Roads -
Secondary Roads
FROM:
El Nido - Jct New ibahay Rd.
K0276+168 - K0276+268,
K0276+287 - K0276+337
CW1: 0.30 lane Km ( Paving of Unpaved Road )
Allocation: 5,100,000 Php
TO:
El Nido - New Ibahay Rd
K0276+168.00 - K0276+264.50,
K0276+291.00 - K0276+330.00
CW1: 0.2712 lane Km ( Paving of Unpaved Road )
Allocation: 5,100,000 Php |
May 17, 2018 |
FY 2018 |
WIN8C02682 |
320101102193000 |
May 3, 2018 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No. 320101102193000
Project ID: P00220661MN
OO2: Protect Lives and Properties Against Major Floods-Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control, Brgy. Guintolan, Naga, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 510 lineal meters
Unit Cost: P 47,303.92/lineal meter
ROW Acquisition: 1,250 square meters
Unit Cost: P 300.00/square meter
EAO: P 0.5 M
Allocation: P 30 M |
May 17, 2018 |
FY - 2018 |
WIN8F05434 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Mindoro Oriental District Engineering Office |
002 - Protect Lives and Properties against Major Floods
Flood Management - Construction/Rehabilitation of
Flood Mitigation Facilities along Major River Basins
and Principal Rivers
FROM:
Rehabilitation/Reconstruction of Alag Gabions,
Baco, Oriental Mindoro
CW1:36.40 l. m. ( Construction of Flood Control
Mitigation Structure )
Allocation: 4,530,000 Php
TO:
Rehabilitation/Reconstruction Of Alag Gabions,
Baco, Oriental Mindoro
CW1: 126.00 l. m. ( Construction of Flood
Mitigation Structure )
Allocation: 4,530,000 Php |
May 17, 2018 |
FY 2018 |
WIN8C02681 |
320101102188000 |
May 3, 2018 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No. 320101102188000
Project ID: P00220109MN
OO2: Protect Lives and Properties Against Major Floods-Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Comprehensive Drainage System within Metro Ipil Area, Ipil, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 985.66 lineal meters
Unit Cost: P 24,247.71/lineal meter
ROW Acquisition: 2,000.00 sq.m.
Unit Cost: P 300/sq.m.
EAO: P 0.5 M
Allocation: P 25 M |
May 17, 2018 |
FY - 2018 |
WIN8F05454 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Marinduque District Engineering Office |
Local Program
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects
- Buildings and Other Structures
FROM:
Concreting of Brgy. Libtangin MPB,
Gasan marinduque
CW1: 1 Bldg ( Construction of Multi Purpose Building )
Allocation; 4,000,000 Php
TO:
Construction / (Completion) of Brgy. Libtangin MPB,
Gasan, Marinduque
CW1: 1 Bldg ( Construction of Multi Purpose Building )
Allocation: 4,000,000 Php |
May 17, 2018 |
FY 2018 |
WIN8C02677 |
320101102189000 |
May 3, 2018 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No. 320101102189000
Project ID: P00220411MN
OO2: Protect Lives and Properties Against Major Floods-Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control along Kabasalan River, FL Pena, Kabasalan, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 380.00 lineal meters
Unit Cost: P 63,486.84/lineal meter
ROW Acquisition: 1,250.00 sq.m.
Unit Cost: P 300/sq.m.
EAO: P 0.5 M
Allocation: P 25 M |
May 17, 2018 |
FY 2018 |
WIN8C02673 |
320101102194000 |
May 3, 2018 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No. 320101102194000
Project ID: P00220662MN
OO2: Protect Lives and Properties Against Major Floods-Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control, Brgy. Poblacion, Naga, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 499.30 lineal meters
Unit Cost: P 48,317.64/lineal meter
ROW Acquisition: 1,250.00 square meters
Unit Cost: P 300.00/square meter
EAO: P 0.5 M
Allocation: P 25 M |
May 17, 2018 |
FY 2018 |
WIN8C02672 |
320101102195000 |
May 3, 2018 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No. 320101102195000
Project ID: P00220664MN
OO2: Protect Lives and Properties Against Major Floods-Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control, Brgy. Sta. Clara, Naga, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 656 lineal meters
Unit Cost: CW-1 - Construction of Flood Mitigation Structure: P 44,131.10/lineal meter
ROW Acquisition: 1,500 square meters
Unit Cost: P 300.00/square meter
EAO: P 0.6 M
Allocation: P 30 M |
May 17, 2018 |
FY 2018 |
WIN8C02671 |
320101102192000 |
May 3, 2018 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No. 320101102192000
Project ID: P00221059MN
OO2: Protect Lives and Properties Against Major Floods-Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control Structure along Sanito River, Brgy. Sanito, Ipil, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 161.50 lineal meters
Unit Cost: P 115,170.28/lineal meter
ROW Acquisition: 3,333.33 sq.m.
Unit Cost: P 300/sq.m.
EAO: P 1.00 M
Allocation: P 20 M
|
May 17, 2018 |
FY 2018 |
WIN8C02670 |
300117202014000 |
May 3, 2018 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No. 300117202014000
Project ID: P00251472MN
Local Program:
Local Roads and Bridges - Local Roads - Local Infrastructure Program
Construction of Barangay Road, Brgy. Concepcion, Kabasalan, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Concrete Road:
0.305 lane km.
Unit Cost: P 4,852,941.18/lane km.
EAO: P 0.015 M
Allocation: P 1.5 M |
May 17, 2018 |
FY 2018 |
WIN8C02669 |
320102100517000 |
May 3, 2018 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No. 320102100517000
Project ID: P00221747MN
OO2: Protect Lives and Properties Against Major Floods-Flood Management -
Construction/Rehabilitation of Flood Mitigation Facilities along Major River Basins and Principal Rivers
Construction of Flood Control Structure along Sibuguey River (Phase VI), Siay, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 618 lineal meters
Unit Cost: CW-1 - Construction of Flood Mitigation Structure: P 62,459.55/lineal meter
ROW Acquisition: 2,000 square meters
Unit Cost: P 300.00/square meter
EAO: P 0.8 M
Allocation: P 40 M |
May 17, 2018 |
FY 2018 |
WIN8C02668 |
320101102198000 |
May 3, 2018 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No. 320101102198000
Project ID: P00222748MN
OO2: Protect Lives and Properties Against Major Floods-Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Upper Tungawan Flood Control Structure along Tungawan River, Tungawan, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 183.50 lineal meters
Unit Cost: CW-1 - Construction of Flood Mitigation Structure: P 36,811.99/lineal meter
ROW Acquisition: 350.00 square meters
Unit Cost: P 300.00/square meter
EAO: P 0.140 M
Allocation: P 7.0 M |
May 17, 2018 |
FY - 2018 |
WIN8F05441 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Marinduque District Engineering Office |
Local Program
Construction/Repair/rehabilitation/Improvement of
Various Infrastructure including Local Projects
FROM:
Concreting of 1,865 m. Dampulan - Mabilog road,
Barangay Dampulan, Torrijos, Marinduque
CW1: 1.640 Lane km ( Construction of Concrete Road )
Allocation: 9,325,000 Php
TO:
Concreting of 1.865 lane km Dampulan - Mabilog road,
Barangay Dampulan, Torrijos, Marinduque
CW1: 1.865 Lane Km ( Construction of Concrete Road )
Allocation: 9,325,000 Php |
May 17, 2018 |
FY 2018 |
WIN8G02183 |
FY 2018 GAA |
January 4, 2018 |
Region III |
Nueva Ecija 1st District Engineering Office |
Asset Preservation Program – Preventive Maintenance – Secondary Roads – San Jose City – Rizal Rd via Pinili – Porais – Villa Joson (Palarilla) Rd, K0165+128.70 – K0165+515, K0167+000 – K0168+000, K0172+000 – K0172+067, K0172+737 – K0173+508, K0174+477 – K0174+912.70 |
May 17, 2018 |
FY 2018 |
WIN8G02188 |
FY 2018 GAA |
January 4, 2018 |
Region III |
Nueva Ecija 1st District Engineering Office |
Asset Preservation Program - Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads – Secondary Roads – Bongabon – Rizal – Aurora Rd, K0152+560 – K0152+740, K0152+740 – K0153+197 |
May 16, 2018 |
FY - 2018 |
WIN8F05373 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Marinduque District Engineering Office |
Local Program
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects
FROM:
Concreting of Brgy. Pili Road,
Mogpog, Marinduque
CW1: 1.055 Lane Km ( Construction of Concrete Road )
Allocation: 6,000,000 Php
TO:
Concreting of Brgy. Pili Road,
Mogpog, Martinduque
CW1: 1.404 lane Km ( Construction of Concrete Road )
Allocation: 6,000,000 Php |
May 16, 2018 |
FY - 2018 |
WIN8F05389 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Marinduque District Engineering Office |
Local Program
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects
- Flood Control Structures/Facilities
FROM:
Construction of Brgy. Bamban Flood Control,
Boac, marinduque
CW1: 179.00 lin.m. ( Construction of Revetment )
Allocation: 6,000,000 Php
TO:
Construction of brgy. Bamban Flood Control,
Boac, Marinduque
CW1: 108.00 lin.m. ( Construction of Revetment )
Allocation: 6,000,000 Php |
May 16, 2018 |
FY - 2018 |
WIN8F05399 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Marinduque District Engineering Office |
Local Program
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects
- Flood Control Structures/Facilities
FROM:
Construction of brgy. Duyay Flood Control,
Boac, Marinduque
CW1: 89.00 lin.m. ( Construction of Revetment )
Allocation: 3,000,000 Php
TO:
Construction of Brgy. Duyay Flood Control,
Boac, Marinduque
CW1: 54.00 lin.m. ( Construction of Revetment )
Allocation: 3,000,000 Php |
May 16, 2018 |
FY - 2018 |
WIN8F05400 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Marinduque District Engineering Office |
Local Program
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects
FROM:
Concreting of Brgy. Maligaya,
Boac, Marinduque
CW1: 0.352 Lane Km ( Construction of Concrete Road )
Allocation: 2,000,000 Php
TO:
Concreting of Brgy. Maligaya,
Boac, Marinduque
CW1: 0.495 Lane Km ( Construction of Concrete Road )
Allocation: 2,000,000 Php |
May 16, 2018 |
FY - 2018 |
WIN8F05375 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Marinduque District Engineering Office |
Local Program
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects
FROM:
Concreting of 2 km. Bayanan to Sampalukan road,
Barangay Marlangga, Torrijos, Marinduque
CW1: 1.759 Lane Km ( Construction of Concrete Road )
Allocation: 10,000,000 Php
TO:
Concreting of 2 lane km Bayanan to Sampalukan road,
Barangay Marlanga, Torrijos, Marinduque
CW1: 2.00 Lane Km ( Construction of Concrete Road )
Allocation: 10,000,000 Php |
May 16, 2018 |
FY - 2018 |
WIN8F05414 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Marinduque District Engineering Office |
Local Program
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects
FROM:
Concreting of 2.5 km Bangwayin-Pakaskasan road,
Barangay Bangwayin, Torrijos, Marinduque
CW1: 2.199 Lane Km ( Construction of Concrete Road )
Allocation; 12,500,000 Php
TO:
Concreting of 2.5 lane km Bangwayin-Pakaskasan road,
Barangay Bangwayin, Torrijos, Marinduque
CW1: 2.500 Lane Km ( Construction of Concrete Road )
Allocation: 12,500,000 Php |
May 16, 2018 |
FY 2018 |
WIN8C02995 |
310208100126000 |
April 5, 2018 |
Region IX |
Zamboanga del Norte 3rd District Engineering Office |
UACS No. 310208100126000
Project ID: P00200812MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Off-Carriageway Improvement - Secondary Roads
Rizal-Dakak-Dapitan Coastal Loop Rd including RROW
K1860+254.00 - K1868+570.74
Physical Target:
CW-1 - Off-Carriageway Improvement: Shoulder Paving/Construction
11,883.89 sq.m.
Unit Cost: P 1,615.63/sq.m.
ROW: 267 sq.m.
Unit Cost: P 1,498.13/sq.m.
EAO: P 400,000
Allocation: P 20,000,000.00 |
May 16, 2018 |
FY 2018 |
WIN8C02967 |
300116200128000 |
May 9, 2018 |
Region IX |
Regional Office IX |
UACS No. 300116200128000
Project ID: P00257849MN
Local Roads and Bridges - Local Roads -
Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Boulevard, Liloy, Zamboanga del Norte
Physical Target:
CW-1 - Paving of Unpaved Roads:
3.06 lane km.
Unit Cost: P 18,167,808.19/lane km
CW-2 - Embankment: 58,533.1917 cu.m.
Unit Cost: P 698.86/cu.m.
EAO: P 3,500,000.00
Allocation: P 100,000,000.00 |
May 16, 2018 |
FY 2018 |
WIN8C02968 |
300204100002000 |
May 9, 2018 |
Region IX |
Regional Office IX |
UACS No. 300204100002000
Project ID: P00230001MN
CSSP: Convergence and Special Support Program - Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones
Access Road at Sitio Anuling, Pamucutan to Sta. Rita in support of High Value Crops (Abaca, Cacao, Rubber and Coffee), Upper La Paz, Zamboanga City
Physical Target:
CW-1 - Const. of Concrete Road:
2.56 lane km.
Unit Cost: P 47,119,140.63/lane km.
EAO: P 4,375,000.00
Allocation: P 125,000,000.00 |
May 16, 2018 |
FY - 2018 |
WIN8F05443 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Romblon District Engineering Office |
001 - Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance
- Secondary Roads
FROM:
Tablas Circumferential Rd
K0098+100 - K0098+240
CW1: .280 Lane Km ( Preventive Maintenance of Road )
Allocation 1,247,000 Php
TO:
Tablas Circumferential Rd
K0098+100 - K0098+181.50
CW1: 0.163 Lane Km ( Preventive maintenance of Road )
Allocation: 1,247,000 Php |
May 16, 2018 |
FY 2018 |
WIN8C02969 |
310212100036000 |
May 9, 2018 |
Region IX |
Regional Office IX |
UACS No. 310212100036000
Project ID: P00200864MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Paving of Unpaved Roads - Tertiary Roads
Sindangan-Bayog-Lakewood Rd - (S01059MN) -
Sta. 1938+722.00 - Sta. 1938+810.00,
Sta. 1945+740.00 - Sta. 1946+460.00
Physical Target:
CW-1 - Paving of Unpaved Road:
1.62 lane km.
Unit Cost: P 93,775,921.98/lane km.
ROW: 8,276.69 sq.m.
Unit Cost: P 300/sq.m.
EAO: P 5,600,000.00
Allocation: P 160,000,000.00 |
May 16, 2018 |
FY - 2018 |
WIN8F05437 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Romblon District Engineering Office |
001 - Ensure Safe and Reliable National Road System
Network Development - Paving of Unpaved Roads
- Tertiary Roads
FROM:
Lubi - Binoog Rd
K0065+836 - K0068+319
CW1: 4.884 Lane Km ( Paving of Unpaved Roads )
Allocation: 100,000,000 Php
TO:
Lubi - Binoog Rd
K0065+836 - K0067+661.87
CW1: 3.42774 Lane Km ( Paving of Unpaved Road )
Allocation: 100,000,000 Php
|
May 16, 2018 |
FY 2018 |
WIN8C02965 |
320101100070000 |
May 9, 2018 |
Region IX |
Regional Office IX |
UACS No. 320101100070000
Project ID: P00220517MN
OO2: Protect Lives and Properties Against Major Floods-Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control Structure along Dipolog River Basin, Dipolog City, Zamboangna del Norte
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 479.04 lm.
Unit Cost: P 241,583.88/lm
ROW: 238.86 sq.m.
Unit Cost: P 300/sq.m.
EAO: P 4,200,000.00
Allocation: P 120,000,000.00 |
May 16, 2018 |
FY 2018 |
WIN8C02964 |
320101100236000 |
May 9, 2018 |
Region IX |
Regional Office IX |
UACS No. 320101100236000
Project ID: P00221447MN
OO2: Protect Lives and Properties Against Major Floods-Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Extension of Flood Control Structure along Siocon River (Downstream), Siocon, Zamboanga del Norte
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 569.50 lm
Unit Cost: P 184,950.83/lm
ROW: 203.48 sq.m.
Unit Cost: P 300/sq.m.
EAO: P 3,822,455.00
Allocation: P 109,213,000.00 |
May 16, 2018 |
FY 2018 |
WIN8C02966 |
320101100237000 |
May 9, 2018 |
Region IX |
Regional Office IX |
UACS No. 320101100237000
Project ID: P00221448MN
OO2: Protect Lives and Properties Against Major Floods-Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Extension of Flood Control Structure along Siocon River (Upstream), Siocon, Zamboanga del Norte
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 443.50 lm
Unit Cost: P 228,259.62/lm
ROW: 306.20 sq.m.
Unit Cost: P 300/sq.m.
EAO: P 3,675,000.00
Allocation: P 105,000,000.00 |
May 16, 2018 |
FY 2018 |
WIN8C02970 |
310201100185000 |
May 9, 2018 |
Region IX |
Regional Office IX |
UACS No. 310201100185000
Project ID: P00200596MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Pagadian City - Zamboanga City Rd
K1936+374.00 - K1936+765.00,
K1936+765.00 - K1936+980.00,
K1937+020.00 - K1937+160.00,
K1937+160.00 - K1937+180.00,
K1937+180.00 - K1937+360.00,
K1937+360.00 - K1937+400.00,
K1937+460.00 - K1937+511.00
Physical Target:
CW-1 - Road Widening-Primary Road:
1.572 lane km.
Unit Cost: P 34,431,377.72/lane km.
CW-2 - ROW: 462,912.91 sq.m.
Unit Cost: P 300/sq.m.
EAO: P 7,000,000.00
Allocation: P 200,000,000.00 |
May 16, 2018 |
FY 2018 |
WIN8C02943 |
300117201991000 |
May 7, 2018 |
Region IX |
Zamboanga City 2nd District Engineering Office |
UACS No. 300117201991000
Project ID: P00251835MN
Local Program:
Local Roads and Bridges - Local Roads - Local Infrastructure Program
Road Concreting, Brgy. Recodo, Zamboanga City
Physical Target:
CW-1 - Construction of Concrete Road:
0.41 lane km.
Unit Cost: P 7,243,902.44/lane km.
EAO: P 30,000.00
Allocation: P 3,000,000.00 |
May 16, 2018 |
FY 2018 |
WIN8G02192 |
SR2018-01-001268 |
January 29, 2018 |
Region III |
Regional Office III |
Network Development Program
Road Widening - Tertiary Roads
Baliwag - Candaba - Sta Ana Rd
K0058+ (-555) - K0059+452, K0062+054 - K0062+681, K0063+963 - K0064+160, K0064+980 - K0065+321, K0066+162 - K0067+428 |
May 16, 2018 |
FY 2018 |
WIN8C02936 |
300117201967000 |
May 7, 2018 |
Region IX |
Zamboanga City 2nd District Engineering Office |
UACS No. 300117201967000
Project ID: P00250058MN
Local Program:
Local Roads and Bridges - Local Roads - Local Infrastructure Program
Concreting of Road, Brgy. Limaong, Zamboanga City
Physical Target:
CW-1 - Construction of Concrete Road:
0.33 lane km.
Unit Cost: P 4,500,000.00
EAO: P 15,000.00
Allocation: P 1,500,000.00 |
May 16, 2018 |
FY 2018 |
WIN8C02896 |
UACS No. 320102100507000 |
May 7, 2018 |
Region IX |
Zamboanga Sibugay 1st District Engineering Office |
UACS No. 320102100507000
Project ID: P00220489MN
OO2: Protect Lives and Properties
Construction/Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers
Construction of Flood Control Structure (Boulevard) along Sibuguey River, Imelda, Zamboanga Sibugay (Sta. 00+000 - Sta. 00+360, Sta. 00+000 - Sta. 00+064)
Physical Target:
CW-1- Construction of Flood Mitigation Structure: 424 Lineal Meters
Unit Cost: P 62,336.38/ Lineal Meters
Physical Target:
ROW: 162 sq.m.
Unit Cost: P 3,206.01/Sq. m.
EAO: P 550,000.00
Allocation: P 27,500,000.00 |
May 16, 2018 |
FY 2018 |
WIN8C02932 |
300117201979000 |
May 7, 2018 |
Region IX |
Zamboanga City 2nd District Engineering Office |
UACS No. 300117201979000
Project ID: P00250080MN
Local Program:
Local Roads and Bridges - Local Roads - Local Infrastructure Program
Concreting of Road, Lumayang, Zamboanga City
Physical Target:
CW-1 - Construction of Concrete Road:
0.19 lane km.
Unit Cost: P 7,815,789.47/lane km.
EAO: P 15,000.00
Allocation: P 1,500,000.00 |
May 16, 2018 |
FY 2018 |
WIN8C02931 |
300117201964000 |
May 7, 2018 |
Region IX |
Zamboanga City 2nd District Engineering Office |
UACS No. 300117201964000
Project ID: P00250075MN
Local Program:
Local Roads and Bridges - Local Roads - Local Infrastructure Program
Concreting of Road, Arena Blanco, Zamboanga City
Physical Target:
CW-1 - Construction of Concrete Road:
0.44 lane km.
Unit Cost: P 4,500,000.00
EAO: P 20,000.00
Allocation: P 2,000,000.00 |
May 16, 2018 |
FY 2018 |
WIN8C02930 |
300117201982000 |
May 7, 2018 |
Region IX |
Zamboanga City 2nd District Engineering Office |
UACS No. 300117201982000
Project ID: P00250082MN
Local Program:
Local Roads and Bridges - Local Roads - Local Infrastructure Program
Concreting of Road, Mampang, Zamboanga City
Physical Target:
CW-1 - Construction of Concrete Road:
0.42 lane km.
Unit Cost: P 4,714,285.71/lane km.
EAO: P 20,000.00
Allocation: P 2,000,000.00 |
May 16, 2018 |
FY 2018 |
WIN8C02928 |
300117201990000 |
May 7, 2018 |
Region IX |
Zamboanga City 2nd District Engineering Office |
UACS No. 300117201990000
Project ID:P00251837MN
Local Program:
Local Roads and Bridges - Local Roads - Local Infrastructure Program
Road Concreting, Brgy. Limpapa, Zamboanga City
Physical Target:
CW-1 - Construction of Concrete Road:
0.35 lane km.
Unit Cost: P 11,314,285.71/lane km.
EAO: P 40,000.00
Allocation: P 4,000,000.00 |
May 16, 2018 |
FY 2018 |
WIN8C02870 |
300117201966000 |
May 7, 2018 |
Region IX |
Zamboanga City 2nd District Engineering Office |
UACS No. 300117201966000
Project ID: P00250057MN
Local Program:
Local Roads and Bridges - Local Roads - Local Infrastructure Program
Concreting of Road, Brgy. Lamisahan, Zamboanga City
Physical Target:
CW-1 - Construction of Concrete Road:
0.28 lane km.
Unit Cost: P 7,071,428.57/lane km.
EAO: P 20,000.00
Allocation: P 2,000,000.00 |
May 16, 2018 |
FY 2018 |
WIN8C02869 |
300116201149000 |
May 7, 2018 |
Region IX |
Zamboanga City 2nd District Engineering Office |
UACS No. 300116201149000
Project ID: P00258443MN
Local Program:
Local Roads and Bridges - Local Roads -
Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Concreting of Cabatangan Road, Cabatangan, Zamboanga City
Physical Target:
CW-1 - Construction of Concrete Road:
0.68 lane km.
Unit Cost: P 7,638,235.29/lane km.
EAO: P 106,000.00
Allocation: P 5,300,000.00 |
May 16, 2018 |
FY 2018 |
WIN8C02866 |
300117201983000 |
May 7, 2018 |
Region IX |
Zamboanga City 2nd District Engineering Office |
UACS No. 300117201983000
Project ID: P00250083MN
Local Program:
Local Roads and Bridges - Local Roads - Local Infrastructure Program
Concreting of Road, Muti, Zamboanga City
Physical Target:
CW-1 - Construction of Concrete Road:
0.43 lane km.
Unit Cost: P 4,604,651.16/lane km.
EAO: P 20,000.00
Allocation: P 2,000,000.00 |
May 16, 2018 |
FY 2018 GAA |
WIN8C02714 |
FY 2018 GAA RA 10964 |
January 1, 2018 |
Region XI |
Davao del Norte District Engineering Office |
MODIFICATION:
FROM: Local Program – Local Roads and Bridges – Local Roads –Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure Including Local Projects
Improvement of Road Junction Highway Apokon, Prk. Durian, Tagum City, Davao del Norte
Physical Target:
CW1: 1.770 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 8,000,000.00
CW1: P 7,840,000.00 (Construction of Concrete Road)
EAO: P 160,000.00
TO: Local Program – Local Roads and Bridges – Local Roads –Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure Including Local Projects
Improvement of Road Junction Highway Apokon, Prk. Durian, Tagum City, Davao del Norte
Physical Target:
CW1: 1.227 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 8,000,000.00
CW1: P 7,840,000.00 (Construction of Concrete Road)
EAO: P 160,000.00 |
May 16, 2018 |
FY 2018 GAA |
WIN8C02712 |
FY 2018 GAA RA 10964 |
January 1, 2018 |
Region XI |
Davao del Norte District Engineering Office |
MODIFICATION:
FROM: Local Program – Local Roads and Bridges – Local Roads – Local Infrastructure Program
Construction of Roads, Panabo City, Davao del Norte
Physical Target:
CW1: 0.200 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 1,000,000.00
CW1: P 1,000,000.00
TO: Local Program – Local Roads and Bridges – Local Roads – Local Infrastructure Program
Construction of Roads, Panabo City, Davao del Norte
Physical Target:
CW1: 0.116 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 1,000,000.00
CW1: P 1,000,000.00 |
May 16, 2018 |
FY - 2018 |
WIN8F05438 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Romblon District Engineering Office |
001 - Ensure safe and Reliable National Road System
Network Development - Construction of Missing Links/
New Roads
FROM:
Odiongan East - West Road, incl. ROW Romblon
CW1: 2.450 Lane Km ( Construction of Missing Links/
New Roads )
CW2: 12,250 sq.m. ( ROW Acquisition )
Total Allocation: 53,900,000 Php
TO:
Odiongan East - West Road, incl. ROW< Romblon
CW1: 1.29 Lane Km ( Construction of Missing Links/
New Roads )
CW2: 12,250 sq.m. ( ROW Acquisition )
Total Allocation: 53,900,000 Php |
May 16, 2018 |
FY - 2018 |
WIN8F05440 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Romblon District Engineering Office |
002 - Protect Lives and Properties Against major Floods
Flood Management Program -
- Construction/Maintenance of Flood Mitigation Structure
and Drainage System
FROM:
Construction of Agnipa Flood Control Structure along
Romblon-Cogon-Sablayan Circumferential Road,
Agnipa, Romblon
CW1: 767.00 lin.m. ( Construction of Flood Mitigation
Structure )
Allocation: 48,250,000 Php
TO:
Construction of Agnipa Flood Control Structure along
Romblon-Cogon-Sablayan Circumferential Road,
Agnipa, Romblon
CW1: 1,284.00 lin.m. ( Construction of Flood Mitigation
Structure )
Allocation: 48,250,000 Php |
May 16, 2018 |
FY 2018 GAA |
WIN8C02731 |
FY 2018 GAA RA 10964 |
January 1, 2018 |
Region XI |
Davao del Norte District Engineering Office |
MODIFICATION:
FROM: OO2: Protect Lives and Properties Against Major Floods
Flood Management- Construction/Rehabilitation of Flood Mitigation Structures along Major River Basins and Principal Rivers
Construction of Concrete Revetment on Steel Sheet Piles along Tagum-Libuganon River, Downstream/ Upstream Miranda Bridge II incl. ROW, Tagum City, Davao del Norte
Physical Target:
CW1: 813.00 Lineal Meters (Construction of Flood Mitigation Structures)
Allocation:
TOTAL: P 100,000,000.000
CW1: P 96,500,000.00 (Construction of Flood Mitigation Structures)
EAO: P 3,500,000.00
TO: OO2: Protect Lives and Properties Against Major Floods
Flood Management- Construction/Rehabilitation of Flood Mitigation Structures along Major River Basins and Principal Rivers
Construction of Concrete Revetment on Steel Sheet Piles along Tagum-Libuganon River, Downstream/ Upstream Miranda Bridge II incl. ROW, Tagum City, Davao del Norte
Physical Target:
CW1: 617.00 Lineal Meters (Construction of Flood Mitigation Structures)
ROW: 13,460.00 sq. m.
Allocation:
TOTAL: P 100,000,000.000
CW1: P 94,000,000.00 (Construction of Flood Mitigation Structures)
ROW: P 2,500,000.00
EAO: P 3,500,000.00 |
May 16, 2018 |
FY 2018 |
WIN8C02937 |
320102100515000 |
May 7, 2018 |
Region IX |
Zamboanga Sibugay 1st District Engineering Office |
UACS No: 320102100515000
Project ID: P00220561MN
OO2: Protect Lives and Properties
Construction/Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers
Construction of Flood Control Structure, (Revetment Wall) along Sibuguey River, Brgy. Bulawan, Payao, Zamboanga Sibugay (Sta. 01+144.50 - Sta. 01+265 & Sta. 00+560 - Sta. 00+666)
Physical Target:
CW-1 - Construction of Revetment: 226.50 Lineal meters
Unit Cost: P 110,145.08/Lineal meters
EAO: P 509,140
Allocation: P 25,457,000 |
May 16, 2018 |
FY 2018 |
WIN8C03001 |
300116200019000 |
May 10, 2018 |
Region IX |
Zamboanga Sibugay 1st District Engineering Office |
UACS No: 300116200019000
Project ID: P00257781MN
Local Program
Local Roads and Bridges - Local Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Concreting of Road Maganay - La Dicha Road, Maganay, Buug, Zamboanga Sibugay, Sta. 00+000 to Sta. 01+720
Physical Target:
CW-1 - Construction of Concrete Road: 3.44 Lane km
Unit Cost: P 5,358,652.03/Lane km
CW-2 - Construction of Drainage Structure: 199 lm
Unit Cost: P 4,352.95/ lm
EAO: P 700,000
Allocation: P 20,000,000 |
May 16, 2018 |
FY 2018 |
WIN8C02851 |
310103100211000 |
May 7, 2018 |
Region IX |
Zamboanga Sibugay 1st District Engineering Office |
UACS No: 310103100211000
Project ID: P00201577MN
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Tertiary Roads
Diplahan Jct-Malangas Port Rd - K1740+(-322) - K1740+731, K1743+167 - K1743+279.50
Physical Target:
CW-1 - Preventive Maintenance of Road: Asphalt Overlay: 2.331 Lane km
Unit Cost: P 11,091,976.13/ lane km
CW-2 - Preventive Maintenance of Road: Concret Reblocking: 0.12 Lane km
Unit Cost: P13,205,030.42/Lane km
EAO: P 560,000
Allocation: P 28,000,000 |
May 16, 2018 |
FY 2018 |
WIN8C02858 |
310101100023000 |
May 7, 2018 |
Region IX |
Zamboanga Sibugay 1st District Engineering Office |
UACS No: 310101100023000
Project ID: P00200001MN
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Primary Roads
Lanao - Pagadian - Zamboanga City Rd - K1729+541 - K1731+325,K1731+350 - K1732+000, K1732+989 - L1733+276, K1743+906 - K1744+200, K1744+724.50 - K1746+000
Physical Target:
CW-1 - Preventive Maintenance of Road: Asphalt Overlay 7.941 Lane km
Unit Cost: P 11,275,141,62/Lane km
CW-2 - Preventive Maintenance of Road:Concrete Reblocking 0.588 Lane km
Unit Cost: P 11,843,708.13/lane km
EAO: P 3,500,000
Allocation: P 100,000,000 |
May 16, 2018 |
FY 2018 GAA |
WIN8C02724 |
FY 2018 GAA RA 10964 |
January 1, 2018 |
Region XI |
Davao del Norte District Engineering Office |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System – Network Development
Off-Carriageway Improvement – Primary Roads
Daang Maharlika (MN) –
K1450+117 – K1453+240, K1462+460 – K1462+760
Physical Target:
CW1: 6,892.00 sq. m. (Off-Carriageway Improvement: Shoulder Paving/Construction)
Allocation:
TOTAL: P 73,842,000.00
CW1: P 71,257,530.00 (Off-Carriageway Improvement: Shoulder Paving/Construction)
EAO: P 2,584,470.00
TO: OO1: Ensure Safe and Reliable National Road System – Network Development
Off-Carriageway Improvement – Primary Roads
Daang Maharlika (MN) –
K1451+360 – K1453+240, K1462+460 – K1462+760
Physical Target:
CW1: 23,200.71 sq. m. (Off-Carriageway Improvement: Shoulder Paving/Construction)
Allocation:
TOTAL: P 73,842,000.00
CW1: P 71,257,530.00 (Off-Carriageway Improvement: Shoulder Paving/Construction)
EAO: P 2,584,470.00 |
May 16, 2018 |
FY 2018 GAA |
WIN8C02732 |
FY 2018 GAA RA 10964 |
January 1, 2018 |
Region XI |
Davao del Norte District Engineering Office |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System – Asset Preservation
Construction/Upgrading/Rehabilitation of Drainage along National Roads – Secondary Roads
Tagum City Diversion Rd incl. ROW –
K1455+(-551) – K1456+138
Physical Target:
CW1: 4,914.00 lineal meters (Construction of Drainage Structure along Road)
ROW: 3,526.00 sq. m.
Allocation:
TOTAL: P 75,900,000.00
CW1: P 71,046,195.00 (Construction of Drainage Structure along Road)
ROW: P 2,197,305.00
EAO: P 2,656,500.00
TO: OO1: Ensure Safe and Reliable National Road System – Asset Preservation
Construction/Upgrading/Rehabilitation of Drainage along National Roads – Secondary Roads
Tagum City Diversion Rd incl. ROW –
K1455+(-605) – K1456+840
Physical Target:
CW1: 5,078.14 lineal meters (Construction of Drainage Structure along Road)
ROW: 3,526.00 sq. m.
Allocation:
TOTAL: P 75,900,000.00
CW1: P 70,966,500.00 (Construction of Drainage Structure along Road)
ROW: P 2,277,000.00
EAO: P 2,656,500.00 |
May 16, 2018 |
FY 2018 |
WIN8C02871 |
310109100125000 |
May 7, 2018 |
Region IX |
Zamboanga Sibugay 1st District Engineering Office |
UACS No: 310109100125000
Project ID: P00200262MN
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
Jct. Imelda-Alicia Rd - K1750+870 - K1750+975, K1751+340 - K1751+405, K1751+430 - K1751+513, K1753+160 - K1753+246, K1753+700 - K1753+835, K1753+840 - K1753+903, K1753+910 - K1754+012, K1756+240 - K1756+395
Physical Target:
CW-1 - Construction of Road Slope Protection Structure: 6,453.83 Square meters
Unit Cost: P 7,592.39/Square meters
EAO: P 1,000,000
Allocation: P 50,000,000 |
May 16, 2018 |
FY 2018 |
WIN8C02787 |
320101102191000 |
May 3, 2018 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No. 320101102191000
Project ID: P00220738MN
OO2: Protect Lives and Properties Against Major Floods-Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control Structure along Kabasalan River, Kabasalan, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 234.00 lineal meters
Unit Cost: P 87,948.72/lineal meter
EAO: P 0.42 M
Allocation: P 21 M |
May 16, 2018 |
FY 2018 |
WIN8C02754 |
320101102197000 |
May 3, 2018 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No. 320101102197000
Project ID: P00222749MN
OO2: Protect Lives and Properties Against Major Floods-Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Sto. Niño Flood Control Structure along Tungawan River, Tungawan, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 73.0 lineal meters
Unit Cost: P 26,849.32/lineal meter
EAO: P 0.04 M
Allocation: P 2.0 M |
May 16, 2018 |
FY 2018 GAA |
WIN8C02719 |
FY 2018 GAA RA 10964 |
January 1, 2018 |
Region XI |
Davao del Norte District Engineering Office |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System – Asset Preservation
Preventive Maintenance – Secondary Roads
Tagum-Panabo Circum Rd –
K1457+(-913) – K1458+000, K 1460+127 – K1460+939
Physical Target:
CW1: 11.100 Lane Km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 73,645,000.00
CW1: P 71,076,110.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 2,577,890.00
TO: OO1: Ensure Safe and Reliable National Road System – Asset Preservation
Preventive Maintenance – Secondary Roads
Tagum-Panabo Circum Rd –
K1457+(-913) – K1457+750, K 1460+127 – K1460+939
Physical Target:
CW1: 9.900 Lane Km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 73,645,000.00
CW1: P 71,076,110.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 2,577,890.00 |
May 16, 2018 |
2018 |
310204100292000 |
GAA FY 2018 |
January 1, 2018 |
Region II |
Regional Office II |
OO1: Ensure Safe and Reliable National Road System - Network Development Program - Construction of By-Pass and Diversion Roads
Tuguegarao West Diversion Road - (Jct Carig-Linao-Atulayan-Bagay-Buntun), incl. ROW, Cagayan |
May 16, 2018 |
FY 2018 |
WIN8C02720 |
320101102196000 |
May 3, 2018 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No. 320101102196000
Project ID: P00220663MN
OO2: Protect Lives and Properties Against Major Floods-Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Libertad Flood Control Structure along Tungawan River, Tungawan, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 164 lineal meters
Unit Cost: P 58,841.46/lineal meter
ROW Acquisition: 500 square meters
Unit Cost: P 300.00/square meter
EAO: P 0.2 M
Allocation: P 10 M |
May 16, 2018 |
2018 |
310204100293000 |
GAA FY 2018 |
January 1, 2018 |
Region II |
Regional Office II |
OO1: Ensure Safe and Reliable National Road System - Network Development Program - Construction of By-Pass and Diversion Roads
Tuguegarao-Solana Diversion Road, incl. ROW, Cagayan |
May 16, 2018 |
FY 2018 |
WIN8C02867 |
300203100522000 |
May 7, 2018 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No: 300203100522000
Project ID: P00230027MN
CSSP: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Declared Tourism Destination
NRJ leading to Simata Adventure Park, Brgy. Simata, Molave, Zamboanga del Sur
Physical Target:
CW-1 - Construction of Concrete Road: 2.37 lane km
Unit Cost: P 10.338M/lane km
EAO: 0.50M
Allocation: 25.0M |
May 16, 2018 |
2018 |
310205100089000 |
GAA FY 2018 |
January 1, 2018 |
Region II |
Regional Office II |
OO1: Ensure Safe and Reliable National Road System - Network Development Program - Construction of Missing Links/New Roads
Jct Victoria-Maddela-Alicia-Kasibu, Nueva Vizcaya Road, Quirino |
May 16, 2018 |
FY 2018 |
WIN8C02715 |
310109100126000 |
May 3, 2018 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No. 310109100126000
Project ID: P00200263MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
Crossing Sta. Clara - Sandayong Rd -
K1806+360.00 - K1806+440.00,
K1806+655.00 - K1806+680.00,
K1809+520.00 - K1809+555.00,
K1809+580.00 - K1809+635.00,
K1810+045.00 - K1810+080.00,
K1810+150.00 - K1810+220.00,
K1810+220.00 - K1810+280.00,
K1810+280.00 - K1810+320.00
Physical Target:
CW-1 - Construction of Road Slope Protection Structure: 11,070 square meters
Unit Cost: P 3,748.42/square meter
ROW Acquisition: 2,150 sq.m.
Unit Cost: P 300/sq.m.
EAO: P 0.86 M
Allocation: P 43 M |
May 16, 2018 |
2018 |
300203100222000 |
GAA FY 2018 |
January 1, 2018 |
Region II |
Cagayan 1st District Engineering Office |
Convergence and Special Support Program - Construction/ Improvement of Access Roads leading to Declared Tourism Destinations
Poblacion Sta. Ana - Marede - Sta. Clara - Patunungan - Sinago Road leading to Boacag Falls & Sinago Coves, incl. Bridge, Dungeg, Sta. Ana, Cagayan |
May 16, 2018 |
2018 |
310106100101000 |
GAA FY 2018 |
January 1, 2018 |
Region II |
Cagayan 1st District Engineering Office |
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Tertiary Roads
Jct Gattaran-Cumao-Capissayan-Sta Margarita-Bolos Point Rd - K0566+(-399)-K0566+006.50, K0566+060.70-K0566+092.60, K0566+119.70-K0566+142.40, K0566+160.60-K0566+197.50, K0K0566+206.50-K0566+422, K0566+215.70-K0566+246.50, K0566+260-K0566+659.65, K0566+431-K0566+659.65, K0566+682.40-K0566+745.60, K0566+682.40-K0566+727.60, K0566+786.40-K0567+000, K0567+004.50-K0567+343, K0567+373.60-K0567+396.30, K0567+437.70-K0567+605, K0567+673.40-K0567+695.90, K0567+786.70-K0567+804.80, K0567+886.20-K0567+945.30, K0567+958.90-K0568+017.80, K0568+167.10-K0568+221.50, K0568+262.40-K0568+298.70, K0568+321.20-K0568+389.70, K0568+461.80-K568+506.60, K0568+561-K0568+602, K0568+905.40-K0568+928.20, K0569+105.40-K0569+128.20, K0569+200.10-K0569+214.40, K0569+349.40-K0569+367.40, K0569+603.40-K0569+630.30, K0569+786.10-K0569+817.80, K0569+854-K0569+881.20, K0570+000-K0570+190 |
May 16, 2018 |
FY 2018 |
WIN8C02859 |
300204100198000 |
May 7, 2018 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No: 300204100198000
Project ID: P00230030MN
CSSP: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones
NRJ to Brgy. Bobongan to Brgy. Poblacion in support of Engineered Bamboo, Ramon Magsaysay, Zamboanga del Sur
Physical Target:
CW-1 - Construction of Concrete Road: 2.20 lane km
Unit Cost: P 8.909M/lane km
EAO: P 19.60M
Allocation: 20.0M |
May 16, 2018 |
FY 2018 |
WIN8C02710 |
300117202016000 |
May 3, 2018 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No. 300117202016000
Project ID: P00251465MN
Local Program:
Local Roads and Bridges - Local Roads - Local Infrastructure Program
Construction of Barangay Road, Brgy. Labe, Ipil, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Concrete Road: 0.174 lane km.
Unit Cost: P 5,747,126.44/lane km.
Allocation: P 1 M |
May 16, 2018 |
2018 |
310204100005000 |
GAA FY 2018 |
January 1, 2018 |
Region II |
Cagayan 1st District Engineering Office |
OO1: Ensure Safe and Reliable National Road System - Network Development Program- Construction of By-Pass and Diversion Roads
Alcala Bypass Road, incl. ROW and Slope Protection, Cagayan |
May 16, 2018 |
FY 2018 GAA |
WIN8C02713 |
FY 2018 GAA RA 10964 |
January 1, 2018 |
Region XI |
Davao del Norte District Engineering Office |
MODIFICATION:
FROM: OO2: Protect Lives and Properties Against Major Floods – Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Concrete Revetment on Steel Sheet Piles and Construction of Earth Dike along Saug River incl. ROW, Canatan Section, Asuncion, Davao del Norte
Physical Target:
CW1: 2,400.00 lineal meters (Construction of Dike)
Allocation:
TOTAL: P 64,000,000.00
CW1: P 61,760,000.00 (Construction of Dike)
EAO: P 2,240,000.00
TO: OO2: Protect Lives and Properties Against Major Floods – Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Concrete Revetment on Steel Sheet Piles and Construction of Earth Dike along Saug River incl. ROW, Canatan Section, Asuncion, Davao del Norte
Physical Target:
CW1: 2,298.00 lineal meters (Construction of Dike)
CW2: 137.00 lineal meters (Construction of Revetment)
ROW: 25,720.00 sq. m.
Allocation:
TOTAL: P 64,000,000.00
CW1: P 34,891,896.54 (Construction of Dike)
CW2: P 23,988,103.46 (Construction of Revetment)
ROW: P 2,880,000.00
EAO: P 2,240,000.00 |
May 16, 2018 |
FY 2018 |
WIN8C02941 |
UACS No. 320102100504000 |
May 7, 2018 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 320102100504000
Project ID: P00220932MN
OO2: Protect Lives and Properties Against Major Floods
Construction/Rehabilitataion of Flood Mitigation Facilities within Major River Basins and Principal Rivers
Construction of Revetment with Steel Sheet Piles along Mapangi River, Zamboanga del Sur
Physical Target:
CW-1- Construction of Revetment: 480.00 l.m.
Unit Cost: P 102,083.33/l.m.
EAO: P 1.00M
Allocation: P 50.00M |
May 16, 2018 |
2018 |
WIN8C02891 |
FY 2018 GAA RA 10964 |
January 1, 2017 |
Region XI |
Davao del Norte District Engineering Office |
MODIFICATION:
FROM: Local Program – Local Roads and Bridges – Local Roads – Local Infrastructure Program
Construction of Roads, Samal, Davao del Norte
Physical Target:
CW1: 0.200 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 1,000,000.00
CW1: P 1,000,000.00 (Construction of Concrete Road)
TO: Local Program – Local Roads and Bridges – Local Roads – Local Infrastructure Program
Construction of Roads, Samal, Davao del Norte
Physical Target:
CW1: 0.140 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 1,000,000.00
CW1: P 1,000,000.00 (Construction of Concrete Road) |
May 16, 2018 |
GAA FY 2018 |
WIN8F05492 |
UACS No. 320101100115000 |
January 1, 2018 |
National Capital Region |
NCR - Regional Office |
As per GAA/Original
UACS No. 320101100115000
Project ID: P00222765LZ
WIN8F05492
Organizational Outcome 002: Protect Lives and Properties
Flood Management – Construction/ Maintenance of Flood Mitigation s Structures and Drainage System
Construction of Marikina River Drainage Outfall, Brgy. J. Dela Peña, Marikina City
Physical Target: CW1-Construction of Drainage Structure L=990 lineal meter
Unit Cost (P’000): P97.60/ lineal meter
Allocation: P 96,625,450.00
EAO P 3,504,550.00
Total: P 100,130,000.00
As Modified
UACS No. 320101100115000
Project ID: P00222765LZ
WIN8F05492
Organizational Outcome 002: Protect Lives and Properties
Flood Management – Construction/ Maintenance of Flood Mitigation s Structures and Drainage System
Construction of Marikina River Drainage Outfall, Brgy. J. Dela Peña, Marikina City
Physical Target: CW1-Construction of Drainage Structure L=480 lineal meter
Unit Cost (P’000): P201.30/ lineal meter
Allocation: P 96,625,450.00
EAO P 3,504,550.00
Total: P 100,130,000.00
|
May 16, 2018 |
GAA FY 2018 |
WIN8F05485 |
UACS No. 320101100374000 |
January 1, 2018 |
National Capital Region |
Malabon-Navotas District Engineering Office |
UACS No. 320101100374000
Project ID: P00221396LZ
WIN8F05485
Organizational Outcome 2: Protect Lives and Properties
Flood Management Program – Construction/ Maintenance of Flood Mitigation Structures and
Drainage Systems
Construction/Sealing of South Pinagkabalian River from Brgy. Muzon to Brgy. Dampalit, (Sta. 1+443 to Sta. 1+483), Malabon City
Physical Target: CW1 – Construction of Revetment: 40.0 lm
EAO P 0.24 M
Unit Cost: P 294,000.00/ lm
Allocation: P 11.76 M
Total: P 12 M
As Modified
UACS No. 320101100374000
Project ID: P00221396LZ
WIN8F05485
Organizational Outcome 2: Protect Lives and Properties
Flood Management Program – Construction/ Maintenance of Flood Mitigation Structures and
Drainage Systems
Construction/Sealing of South Pinagkabalian River from Brgy. Muzon to Brgy. Dampalit, (Sta. 1+443 to Sta. 1+483) and (Sta. 0+253 to Sta. 0+267), Malabon City
Physical Target: CW1 – Construction of Revetment: 54.0 lm
EAO P 0.24 M
Unit Cost: P 211,772.22/ lm
Estimated Cost: P 11.43 M
Excess: P 0.327 M
Total: P 12 M
|
May 16, 2018 |
GAA FY 2018 |
WIN8G02239 |
UACS No. 300104200277000 |
January 1, 2018 |
National Capital Region |
Quezon City 1st Engineering District Office |
As per GAA/Original
UACS No. 300104200277000
Project ID: P00249596LZ
WIN8G02239
Local Program
Local – Local Buildings and Other Structures – Multipurpose/ Facilities – Local Infrastructure Program
Repair/ Rehab of Multipurpose Building, Inner Wheel, Payatas A, Brgy. Payatas, Quezon City
Physical Target: CW1-Rehabilitation/ Major of Multi-Purpose Building – 1.0
Unit Cost (P’000): P1,980.00/ Bldg.
Allocation: P 1,980,000.00 M
EAO P 20,000.00
Total: P 2,000,000.00 M
As Modified
UACS No. 300104200277000
Project ID: P00249596LZ
WIN8G02239
Local Program
Local – Local Buildings and Other Structures – Multipurpose/ Facilities – Local Infrastructure Program
Repair/ Rehab of Multipurpose Building, Inner Wheel, Brgy. Holy Spirit, Quezon City
Physical Target: CW1-Rehabilitation/ Major of Multi-Purpose Building – 1.0
Unit Cost (P’000): P1,980.00/ Bldg.
Allocation: P 1,980,000.00 M
EAO P 20,000.00
Total: P 2,000,000.00 M
|
May 16, 2018 |
GAA FY 2018 |
WIN8F05483 |
UACS No. 300103200085000 |
January 1, 2018 |
National Capital Region |
Metro Manila 1st District Engineering Office |
As per GAA/Original
UACS No. 300103200085000
Project ID: P00240455LZ
WIN8F05483
Local Program
Building and Other Structures – Multipurpose/ Facilities – Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Multi – Purpose Building at Barangay.Sta. Tañong, Marikina City
Physical Target: CW1-Construction of Multi-Purpose Building – 1 Building
Unit Cost (P’000): P17,640.00/bldg..
Allocation: P 17,640.00 M
EAO P 360.00 M
Total: P 18,000.00 M
As Modified
UACS No. 300103200085000
Project ID: P00240455LZ
WIN8F05483
Local Program
Building and Other Structures – Multipurpose/ Facilities – Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Multi – Purpose Building at Barangay Tañong, Marikina City
Physical Target: CW1-Construction of Multi-Purpose Building – 1 Building
Unit Cost (P’000): P17,640.00/bldg..
Allocation: P 17,640.00 M
EAO P 360.00 M
Total: P 18,000.00 M
|
May 16, 2018 |
GAA FY 2018 |
WIN8F05486 |
UACS No. 320101100094000 |
January 1, 2018 |
National Capital Region |
Metro Manila 2nd District Engineering Office |
As per GAA/Original
UACS No. 320101100094000
Project ID: P00222865LZ
WIN8F05486
002: Protect Lives and Properties
Flood Management – Construction / Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control Structures including Bridge and Approach at Don Galo River, Parañaque City
Physical Target: CW1 Construction of Drainage Structure along Road L=316 lineal meter
Unit Cost (P’000): P198,496.83/ l.m.
Allocation: P 62,725,000.00
EAO P 2,275,000.00
Total: P 65,000,000.00
As Modified
UACS No. 320101100094000
Project ID: P00222865LZ
WIN8F05486
002: Protect Lives and Properties
Flood Management – Construction / Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control Structures including Bridge and Approach at Don Galo, Parañaque City
Physical Target: CW1 Construction of Drainage Structure along Road L=440 lineal meter
Unit Cost (P’000): P198,496.83/ l.m.
Allocation: P 62,725,000.00
EAO P 2,275,000.00
Total: P 65,000,000.00
|
May 16, 2018 |
GAA FY 2018 |
WIN8F05488 |
UACS No. 300116200369000 |
January 1, 2018 |
National Capital Region |
Metro Manila 3rd District Engineering Office |
As per GAA/Original
UACS No. 300116200369000
Project ID: P00240550LZ
WIN8F05488
Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including
Local Projects – Local Roads and Bridges
Local Roads and Bridges – Local Roads
Upgrading of Road with Drainage System along Purificacion Street, Brgy. 183, Caloocan City
Physical Target: CW1-Rehabilitation of Concrete Road 0.836 Lane Km
EAO – P 0.300 M
Unit Cost (P’000): P17,583.73/ lane km
Allocation: P 14.70 M
Total: P 15 M
As Modified
UACS No. 300116200369000
Project ID: P00240550LZ
WIN8F05488
Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including
Local Projects – Local Roads and Bridges
Local Roads and Bridges – Local Roads
Upgrading of Road with Drainage System along Purificacion Street, Brgy. 183, Caloocan City
Physical Target: CW1-Rehabilitation of Concrete Road 0.698 Lane Km
EAO – P 0.300 M
Unit Cost (P’000): P21,060.17/ lane km
Allocation: P 14.70 M
Total: P 15 M
|
May 16, 2018 |
GAA FY 2018 |
WIN8F05487 |
UACS No. 300116200317000 |
January 1, 2018 |
National Capital Region |
Metro Manila 3rd District Engineering Office |
As per GAA/Original
UACS No. 300116200317000
Project ID: P00240614LZ
WIN8F05487
Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including
Local Projects – Local Roads and Bridges
Local Roads and Bridges – Local Roads
Improvement of Road and drainage system-Balubaran Road, Brgy. Malinta (from MacArthur HW Balubaran to Zapra St., Brgy. Maysan to T. Santiago St.), Brgy. Veinte Reales, Valenzuela City
Physical Target: CW1-Rehabilitation of Concrete Road 1.060 Lane Km
EAO – P 0.420 M
Unit Cost (P’000): P19,415.09/ lane km
Allocation: P 20.580 M
Total: P 21.00 M
As Modified
UACS No. 300116200317000
Project ID: P00240614LZ
WIN8F05487
Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including
Local Projects – Local Roads and Bridges
Local Roads and Bridges – Local Roads
Improvement of Road and drainage system-Balubaran Road, Brgy. Malinta (from MacArthur HW Balubaran to Zapra St., Brgy. Maysan to T. Santiago St.), Brgy. Veinte Reales, Valenzuela City
Physical Target: CW1-Rehabilitation of Concrete Road 1.434 Lane Km
EAO – P 0.420 M
Unit Cost (P’000): P14,351.46/ lane km
Allocation: P 20.580 M
Total: P 21.00 M
|
May 16, 2018 |
FY 2018 GAA |
WIN8C02902 |
FY 2018 GAA RA 10964 |
January 1, 2018 |
Region XI |
Davao del Norte District Engineering Office |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System – Asset Preservation
Construction/Upgrading/Rehabilitation of Drainage along National Roads – Primary Roads
Surigao-Davao Coastal Rd incl. ROW – K1823+512 – K1825+702
Physical Target:
CW1: 3,063.00 lineal meters (Construction of Drainage Structure along Road)
ROW: 6,128.00 sq. m.
Allocation:
TOTAL: P 78,065,000.00
CW1: P 71,819,725.00 (Construction of Drainage Structure along Road)
ROW: P 3,390,045.00
EAO: P 2,732,275.00
TO: OO1: Ensure Safe and Reliable National Road System – Asset Preservation
Construction/Upgrading/Rehabilitation of Drainage along National Roads – Primary Roads
Surigao-Davao Coastal Rd incl. ROW – K1823+512 – K1825+406
Physical Target:
CW1: 2,379.42 lineal meters (Construction of Drainage Structure along Road)
ROW: 6,128.00 sq. m.
Allocation:
TOTAL: P 78,065,000.00
CW1: P 71,819,725.00 (Construction of Drainage Structure along Road)
ROW: P 3,513,000.00
EAO: P 2,732,275.00 |
May 16, 2018 |
FY 2018 GAA |
WIN8C02886 |
FY 2018 GAA RA 10964 |
January 1, 2018 |
Region XI |
Davao del Norte District Engineering Office |
MODIFICATION:
FROM: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Sitio Pandulian, Mabantao-Florida-Suaon Road leading to Kapalong Woodland Resort, Davao del Norte
Physical Target:
CW1: 9.010 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Construction of Concrete Road)
EAO: P 3,500,000.00
FROM: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Sitio Pandulian, Mabantao-Florida-Suaon Road leading to Kapalong Woodland Resort, Davao del Norte
Physical Target:
CW1: 9.468 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Construction of Concrete Road)
EAO: P 3,500,000.00 |
May 16, 2018 |
GAA FY 2018 |
WIN8F05493 |
UACS No. 300116200367000 |
January 1, 2018 |
National Capital Region |
Metro Manila 3rd District Engineering Office |
As per GAA/Original
UACS No. 300116200367000
Project ID: P00240626LZ
WIN8F05493
Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including
Local Projects – Local Roads and Bridges
Local Roads and Bridges – Local Roads
Rehabilitation of Roads and Drainage in San Simon, Brgy. Dalandanan, Valenzuela City
Physical Target: CW1-Rehabilitation of Concrete Road 1.142 Lane Km
EAO – P 0.130 M
Unit Cost (P’000): P5,557.93/ lane km
Allocation: P 6.370 M
Total: P 6.50 M
As Modified
As per GAA/Original
UACS No. 300116200367000
Project ID: P00240626LZ
WIN8F05493
Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including
Local Projects – Local Roads and Bridges
Local Roads and Bridges – Local Roads
Rehabilitation of Roads and Drainage in San Simon, Brgy. Dalandanan, Valenzuela City
Physical Target: CW1-Rehabilitation of Concrete Road 0.562 Lane Km
EAO – P 0.130 M
Unit Cost (P’000): P5,557.93/ lane km
Allocation: P 6.370 M
Total: P 6.50 M
|