DPWH completes 2 new flood control projects in Central Iloilo towns

The Department of Public Works and Highways (DPWH) completed two (2) flood control structures along Jalaur River to protect the residents of Barangays Tabucan, Barotac Nuevo and Poblacion, Passi City in Iloilo.

The flood control project in Barotac Nuevo, built in the amount of P46.9 million, is composed of a 254.8-lineal meter structure including drainage and 181-lineal meter groundsill (gabions).

On the other hand, Passi City’s P23.2-million project involved the construction of a 186.4-lineal meter revetment wall.

DPWH completes 2 new flood control projects in Central Iloilo towns

The Department of Public Works and Highways (DPWH) completed two (2) flood control structures along Jalaur River to protect the residents of Barangays Tabucan, Barotac Nuevo and Poblacion, Passi City in Iloilo.

The flood control project in Barotac Nuevo, built in the amount of P46.9 million, is composed of a 254.8-lineal meter structure including drainage and 181-lineal meter groundsill (gabions).

On the other hand, Passi City’s P23.2-million project involved the construction of a 186.4-lineal meter revetment wall.

New road to benefit indigenous communities in Caraga, underway

Progress of works for the Department of Public Works and Highways’ (DPWH) 2-lane Sampaguita – Makilos Road project connecting Agusan del Sur in Region 13 and Bukidnon Province in Region 10 has reached 33 percent accomplishment.

The road project which is expected to cater to the tribes of Manobo and Mamanwa in the area of Caraga has already received an allocation of P2.81 billion out of the P7.14 billion needed to construct the entire 73.06-kilometer road.

New road to benefit indigenous communities in Caraga, underway

Progress of works for the Department of Public Works and Highways’ (DPWH) 2-lane Sampaguita – Makilos Road project connecting Agusan del Sur in Region 13 and Bukidnon Province in Region 10 has reached 33 percent accomplishment.

The road project which is expected to cater to the tribes of Manobo and Mamanwa in the area of Caraga has already received an allocation of P2.81 billion out of the P7.14 billion needed to construct the entire 73.06-kilometer road.

Davao de Oro revetment structure now 90% completed

The Department of Public Works and Highways (DPWH) is currently implementing the construction of P72.17 million revetment project in Davao de Oro, formerly known as Compostela Valley.

According to DPWH Region XI Director Allan S. Borromeo, the on-going construction of flood mitigation project along Manat River leading to Agusan River in Barangay Bankerohan, Montevista, Davao de Oro is now 90 percent completed.

Davao de Oro revetment structure now 90% completed

The Department of Public Works and Highways (DPWH) is currently implementing the construction of P72.17 million revetment project in Davao de Oro, formerly known as Compostela Valley.

According to DPWH Region XI Director Allan S. Borromeo, the on-going construction of flood mitigation project along Manat River leading to Agusan River in Barangay Bankerohan, Montevista, Davao de Oro is now 90 percent completed.

Cavite resettlement site construction set to start by July 2020

The Department of Public Works and Highways (DPWH) plans to start by July 2020 the construction of 8-hectare San Rafael North Resettlement Site in Noveleta City, Cavite which is a component of the Cavite Industrial Area Flood Risk Management Project (CIA-FRIMP).

The resettlement site construction which will be implemented under CIA-FRIMP Package 5 will include residential land development, road and drainage works, embarkment and slope protection works, laying down of water supply pipelines and electric posts wiring, and other community facilities when deemed necessary.

Cavite resettlement site construction set to start by July 2020

The Department of Public Works and Highways (DPWH) plans to start by July 2020 the construction of 8-hectare San Rafael North Resettlement Site in Noveleta City, Cavite which is a component of the Cavite Industrial Area Flood Risk Management Project (CIA-FRIMP).

The resettlement site construction which will be implemented under CIA-FRIMP Package 5 will include residential land development, road and drainage works, embarkment and slope protection works, laying down of water supply pipelines and electric posts wiring, and other community facilities when deemed necessary.