Modification and Realignment



Date Posted GAA Year Reference No SARO Number SARO Date Region Implementing Office Description
June 20, 2018 FY - 2018 WIN8F05562 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Romblon District Engineering Office
Local Programs: Local Infrastructure Program

Local - National Roads and Bridges - Local Roads
- Local Infrastructure Program

FROM:
Construction of Road at Sitio Timbaon, Brgy. Tulay,
Odiongan, Romblon

CW1: 0.704 lane km ( Construction of Concrete Road )
Allocation: 4,000,000 Php

TO:
Construction of Road at Sitio Timbaon, Brgy. Tulay,
Odiongan, Romblon

CW1: 0.446 lane km ( Construction of Concrete Road )
Allocation: 4,000,000 Php
June 20, 2018 FY 2018 GAA WIN8C03212 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao City District Engineering Office

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System
Network Development Program - Construction of By-Pass and Diversion Roads
Alternate Road from Region XI to Region X (Jct Davao City Diversion Road-Catalunan Grande-Talandag-Sumimao-Panalum-Tapak-Cabanglasan-Aglayan, Malaybalay), Davao City
Physical Target:
CW1: 0.800 lane km (Construction of Concrete Road)
Allocation:
TOTAL: P 16,000,000.00
CW1: P 15,680,000.00 (Construction of Concrete Road)
EAO: P 320,000.00

TO: OO1: Ensure Safe and Reliable National Road System
Network Development Program - Construction of By-Pass and Diversion Roads
Alternate Road from Region XI to Region X (Jct Davao City Diversion Road-Catalunan Grande-Talandag-Sumimao-Panalum-Tapak-Cabanglasan-Aglayan, Malaybalay), Davao City
Physical Target:
CW1: 0.776 lane km (Construction of Concrete Road)
CW2: 114.48 square meters (Construction of Concrete Bridge)
CW3: 3,880 square meters (ROW Acquisition)
Allocation:
TOTAL: P 16,000,000.00
CW1: P 6,490,320.00 (Construction of Concrete Road)
CW2: P 6, 069,680.00 (Construction of Concrete Bridge)
CW3: P 3,120,000.00 (ROW Acquisition)
EAO: P 320,000.00
June 20, 2018 FY 2018 GAA WIN8C03220 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao City District Engineering Office

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
Fatima-Malabog Rd - K1501 + 229 - K1501 + 267,
K1510 + 018 - K1510 + 041, K1510 + 081 - K1510 + 115, K1510 + 669 - K1510 + 704
Physical Target:
CW1: 4,950.00 Square meters (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Construction of Road Slope Protection Structure)
EAO: P 3,500,000.00

TO: OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
Fatima-Malabog Rd - K1510 + 018 - K1510 + 041,
K1510 + 081 - K1510 + 115, K1510 + 669 - K1510 + 704,
K1510 + 920 - K1510 + 960
Physical Target:
CW1: 6,739.30 Square meters (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Construction of Road Slope Protection Structure)
EAO: P 3,500,000.00
June 20, 2018 FY 2018 GAA WIN8C03225 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao City District Engineering Office
MODIFICATION:

FROM: OO2 : Protect Lives and Properties Against Major Floods
Flood Management Program
Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Slope Protection along Lasang River, Pañalum Section, Protecting Pañalum Bridge (Sta. 38+798 - Sta. 39+293), Right Bank, Davao City
Physical Target:
CW1: 496 Lineal meters (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 50,000,000.00
CW1: P 49,000,000.00 (Construction of Flood Mitigation Structure)
EAO: P 1,000,000.00

TO: OO2 : Protect Lives and Properties Against Major Floods
Flood Management Program
Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Slope Protection along Lasang River, Pañalum Section, Protecting Pañalum Bridge,(Sta. 40+231 – Sta. 40+785, Sta. 40+924 – Sta. 41+078), Right Bank, Davao City
Physical Target:
CW1: 708 Lineal meters (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 50,000,000.00
CW1: P 49,000,000.00 (Construction of Flood Mitigation Structure)
EAO: P 1,000,000.00
June 20, 2018 FY 2018 GAA WIN8C03227 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao City District Engineering Office
MODIFICATION:

FROM: OO2 : Protect Lives and Properties Against Major Floods
Flood Management Program
Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Slope Protection along Lasang River, Pañalum Section, Protecting Pañalum Bridge (Sta. 38+798 - Sta. 39+290), Left Bank, Davao City
Physical Target:
CW1: 496 Lineal meters (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 50,000,000.00
CW1: P 49,000,000.00 (Construction of Flood Mitigation Structure)
EAO: P 1,000,000.00

TO: OO2 : Protect Lives and Properties Against Major Floods
Flood Management Program
Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Slope Protection along Lasang River, Pañalum Section, Protecting Pañalum Bridge, Sta. 38+999 – Sta. 39+464, Sta. 39+992 – Sta. 40+231), Left Bank, Davao City
Physical Target:
CW1: 704 Lineal meters (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 50,000,000.00
CW1: P 49,000,000.00 (Construction of Flood Mitigation Structure)
EAO: P 1,000,000.00
June 20, 2018 FY 2018 GAA WIN8C03238 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao City District Engineering Office

MODIFICATION:

FROM: OO1 : Ensure Safe and Reliable National Road System
Network Development Program - Road Widening -
Secondary Roads
Construction of Jct. Davao-Cotabato Old Road (Bago Gallera Section), leading to Philippine Coconut Authority (PCA), Davao City
Physical Target:
CW1: 1.800 lane km (Road Widening)
Allocation:
TOTAL: P 89,100,000.00
CW1: P 85,981,500.00 (Road Widening)
EAO: P 3,118,500.00

TO: OO1 : Ensure Safe and Reliable National Road System
Network Development Program - Road Widening -
Secondary Roads
Construction of Jct. Davao-Cotabato Old Road (Bago Gallera Section), leading to Philippine Coconut Authority (PCA), Davao City
Physical Target:
CW1: 2.426 lane km (Road Widening)
ROW: 7,278 Square Meters (ROW Acquisition)
Allocation:
TOTAL: P 89,100,000.00
CW1: P 49,591,500.00 (Road Widening)
ROW: P 36,390,000.00 (ROW Acquisition)
EAO: P 3,118,500.00
June 20, 2018 FY 2018 GAA WIN8C03214 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao City District Engineering Office

MODIFICATION:

FROM: Local Program
Flood Control and Drainage
Drainage/Protection Works - Construction/Repair/ Rehabilitation/Improvement of Various Infrastructure including Local Projects
Improvement/Rehabilitation of Drainage along
ABS-CBN Quimpo Blvd. Diversion Road (Jct. Tulip Drive-Jct. Ecoland Terminal), Davao City
Physical Target:
CW1: 2,040 lineal meters (Construction of Drainage Structure)
Allocation:
TOTAL: P 61,200,000.00
CW1: P 59,058,000.00 (Construction of Drainage Structure)
EAO: P 2,142,000.00

TO: Local Program
Flood Control and Drainage
Drainage/Protection Works - Construction/Repair/ Rehabilitation/Improvement of Various Infrastructure including Local Projects
Improvement/Rehabilitation of Drainage along
ABS-CBN Quimpo Blvd. Diversion Road (Jct. Tulip Drive-Jct. Ecoland Terminal), Davao City
Physical Target:
CW1: 2,609 lineal meters (Construction of Drainage Structure)
Allocation:
TOTAL: P 61,200,000.00
CW1: P 59,058,000.00 (Construction of Drainage Structure)
EAO: P 2,142,000.00
June 20, 2018 FY 2018 GAA WIN8C03226 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao City District Engineering Office

MODIFICATION:

FROM: Local Program
Local Roads and Bridges - Local Roads – Local Infrastructure Program
Construction of Road, Brgy. Dumoy, Davao City
Physical Target:
CW1: 1.000 lane km (Construction of Concrete Road)
Allocation:
TOTAL: P 15,000,000.00
CW1: P 14,850,000.00 (Construction of Concrete Road)
EAO: P 150,000.00

TO: Local Program
Local Roads and Bridges - Local Roads – Local Infrastructure Program
Construction of Road, Brgy. Dumoy, Davao City
Physical Target:
CW1: 3.840 lane km (Construction of Concrete Road)
Allocation:
TOTAL: P 15,000,000.00
CW1: P 14,850,000.00 (Construction of Concrete Road)
EAO: P 150,000.00
June 20, 2018 FY 2018 GAA WIN8C03218 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao City District Engineering Office

MODIFICATION:

FROM: Local Program
Local Roads and Bridges - Local Roads – Local Infrastructure Program
Construction of Road, Brgy. Bago Gallera, Davao City
Physical Target:
CW1: 1.000 lane km (Construction of Concrete Road)
Allocation:
TOTAL: P 11,000,000.00
CW1: P 10,890,000.00 (Construction of Concrete Road)
EAO: P 110,000.00

TO: Local Program
Local Roads and Bridges - Local Roads – Local Infrastructure Program
Construction of Road, Brgy. Bago Gallera, Davao City
Physical Target:
CW1: 2.986 lane km (Construction of Concrete Road)
Allocation:
TOTAL: P 11,000,000.00
CW1: P 10,890,000.00 (Construction of Concrete Road)
EAO: P 110,000.00
June 19, 2018 FY - 2018 WIN8F05571 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Romblon District Engineering Office
Local Programs: Local Infrastructure Program

Local - National Roads and Bridges - Local Roads
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM:
Construction of Gravel Road -
Construction of barangay Punta - Barangay Limon Sur
Jct Looc - Odionga Road, Romblon

CW1: 4.072 lane km ( Construction of Gravel Road )
Allocation: 80,000,000 Php

TO:
Construction of Gravel Road -
Construction of Barangay Punta - Barangay Limon Sur
Jct Looc - Odiongan Road, Romblon

CW1: 5.71 lane km ( Construction of Gravel Road )
Allocation: 80,000,000 Php
June 19, 2018 FY - 2018 WIN8F05563 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Romblon District Engineering Office
Local Programs: Local Infrastructure Program

Local - National Roads and Bridges - Local Roads
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM:
Construction of Roads -
Brgy. Tanagan and Brgy. Victoria,
San Andres, Romblon

CW1; 1.759 lane km ( Construction of Concrete Road )
Allocation; 10,000,000php

TO:
Construction of Roads -
Brgy. Tanagan and Brgy. Victoria,
San Andres, Romblon

CW1: 1.320 lane km ( Construction of Concrete Road )
Allocation; 10,000,000 Php
June 19, 2018 FY - 2018 WIN8F05570 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Romblon District Engineering Office
Local Programs: Local Infrastructure Program

Local - National Roads and Bridges - Local Roads
Construction/Repair/rehabilitation/Improvement of
Various Infrastructure including local Projects

FROM:
Construction of Gravel Road - Construction of Road,
Sitio Bariri, Hinag-oman, Ferrol, Romblon

CW1: 5.040 lane km ( Construction of Gravel Road )
Allocation: 85,500,000 Php

TO:
Construction of Gravel Road - Construction of Road,
Sitio Bariri, Hinag-oman, Ferrol, Romblon

CW1: 6.12 lane km ( Construction of Gravel Road )
Allocation: 85,500,000 Php
June 19, 2018 FY 2018 GAA WIN8C03241 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Alternate Road from Region XI to Region X (Jct. Davao City Diversion Road – Catalunan Grande – Talandag – Sumimao – Panalum – Tapak – Cabangsalan – Aglayan, Malaybalay), Package B, incl. ROW and Bridge, Davao City
Physical Target:
CW1: 14.704 Lane Km (Construction of Gravel Road)
CW2: 763.2 sq. m. (Construction of Concrete Bridge)
ROW: 28,046.512 sq.m.
Allocation:
TOTAL: P 300,000,000.00
CW1: P 157,179,200.00 (Construction of Gravel Road)
CW2: P 109,045,000.00 (Construction of Concrete Bridge)
ROW: P 23,275,800.00
EAO: P 10,500,000.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Alternate Road from Region XI to Region X (Jct. Davao City Diversion Road – Catalunan Grande – Talandag – Sumimao – Panalum – Tapak – Cabangsalan – Aglayan, Malaybalay), Package B, incl. ROW and Bridge, Davao City
Physical Target:
Physical Target:
CW1: 6.251 Lane Km (Construction of Gravel Road)
CW2: 429.3 sq. m. (Construction of Concrete Bridge)
ROW: 28,046.512 sq.m.
Allocation:
TOTAL: P 300,000,000.00
CW1: P 157,179,200.00 (Construction of Gravel Road)
CW2: P 109,045,000.00 (Construction of Concrete Bridge)
ROW: P 23,275,800.00
EAO: P 10,500,000.00
June 19, 2018 FY 2018 WIN8C03208 UACS No. 300204100068000 June 6, 2018 Region IX Regional Office IX
UACS No. 300204100068000
Project ID: P00230035MN
Convergence and Special Support Program
Construction/ Improvement of Access Roads leading to Trades, Industries and Economic Zones
Road Network of the Philippine Halal Hub-The Asian Halal Center (Zamboanga Economic Zone), Talisayan, Zamboanga City
Physical Target:
CW-1- Construction of Concrete Road: 8.23 lane km
Unit Cost: P 14,656,743.61/lane km
EAO: P 4,375,000.00
Allocation: P 125,000,000.00
June 19, 2018 FY 2018 WIN8C03201 UACS No. 310204100147000 June 6, 2018 Region IX Regional Office IX
UACS No. 310204100147000
Project ID: P00200300MN
OO1: Ensure Safe and Reliable National Road System
Network Development - Construction of Bypass and Diversion Roads
Jct. Nat'l Highway R.T. Lim - Jct. Nat'l Highway Siocon Road, (Surabay - San Fernandino), Zamboanga Sibugay
Physical Target:
CW-1- Construction of Gravel Road: 17.15 lane km
Unit Cost: P 16,588,921.28/lane km
ROW: 16,666.67 sq.m.
Unit Cost: P 300/sq.m.
EAO: P 10,500,000.00
Allocation: P 300,000,000.00
June 19, 2018 FY 2018 GAA WIN8C03244 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Davao City Coastal Bypass Road at Jct. Davao-Cotabato Road-Bago Aplaya-Talomo-Matina Aplaya-Roxas Avenue-Sta. Ana Wharf-R. Castillo (Bago Aplaya-Times Beach), Package 2, Davao City
Physical Target:
CW1: 1.884 Lane Km (Construction of Asphalt Road)
CW2: 2,926 sq. m. (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 250,470,000.00
CW1: P 145,444,800.00 (Construction of Asphalt Road)
CW2: P 96,258,750.00 (Construction of Road Slope Protection Structure)
EAO: P 8,766,450.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Davao City Coastal Bypass Road at Jct. Davao-Cotabato Road-Bago Aplaya-Talomo-Matina Aplaya-Roxas Avenue-Sta. Ana Wharf-R. Castillo (Bago Aplaya-Times Beach), Package 2, Davao City
Physical Target:
CW1: 1.140 Lane Km (Construction of Asphalt Road)
CW2: 3,867.36 sq. m. (Construction of Road Slope Protection Structure)
CW3: 0.443 Lane Km (Construction of Gravel Road)
Allocation:
TOTAL: P 250,470,000.00
CW1: P 147,033,933.69 (Construction of Asphalt Road)
CW2: P 89,578,561.93 (Construction of Road Slope Protection Structure)
CW3: P 5,091,054.38 (Construction of Gravel Road)
EAO: P 8,766,450.00
June 19, 2018 FY 2018 WIN8C03200 UACS No. 310204100045000 June 6, 2018 Region IX Regional Office IX
UACS No. 310204100045000
Project ID: P00200295MN
OO1: Ensure Safe and Reliable National Road System
Network Development - Construction of Bypass and Diversion Roads
Buenavista - Bolong Coastal Bypass Road, (Mala - Bolong Section) including Bridge, Zamboanga City
Physical Target:
CW-1- Construction of Concrete Road:4.52 lane km
Unit Cost: P 25,012,754.78/ lane km
ROW: 9,141.16 sq.m.
Unit Cost: P 300/sq.m
EAO: P 4,200,000.00
Allocation: P 120,000,000.00
June 19, 2018 FY 2018 WIN8C03180 UACS No. 310203100125000 June 5, 2018 Region IX Zamboanga del Sur 1st District Engineering Office
UACS No. 310203100125000
Project ID: P00200780MN
OO1: Ensure Safe and Reliable National Road
Network Development - Road Widening - Tertiary Roads
Jct. Aurora- Monte Alegre - Jct. Labangan Rd
K1649+400 - K1650+281
Physical Target:
CW-1- Road Widening: 1.762 lane km
Unit Cost: P 22.247 M
EAO: 0.800 M
Allocation: P 40.0 M
June 19, 2018 FY 2018 WIN8C03203 UACS No. 300104204148000 June 5, 2018 Region IX Zamboanga del Sur 1st District Engineering Office
UACS No. 300104204148000
Project ID: P00257128MN
Local Program
Local - Buildings and Other Structures
Multipurpose/ Facilities - Local Infrastructure Program
Construction of a Multi-purpose Building (Livelihood Center), Barangay Upper Salug Daku, Mahayag, Zamboanga del Sur
Physical Target:
CW-1- Construction of Multi Purpose Building: 1.0 Building
Unit Cost: P 1.980 M/ Building
EAO: P 0.020 M
Allocation: P 2.0 M
June 19, 2018 FY - 2018 WIN8F05573 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Romblon District Engineering Office
Local Programs: Local Infrastructure Program

Local - National Roads and Bridges - Local Roads
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM:
Construction of Guinhayaan, Looc - Danao Norte -
Sta. Fe National Road leading to Malbog Port, Looc,
Romblon ( Phase 2 )

CW1: 7.590 lane km ( Construction of Gravel Road )
Allocation: 100,000,000 Php

TO:
Construction of Guinhayaan, Looc - Danao Norte -
Sta. Fe National Road leading to Malbog Port, Looc,
Romblon ( Phase 2 )

CW1: 4.25536 lane km ( Construction of Gravel Road )
Allocation: 100,000,000 Php
June 19, 2018 FY 2018 WIN8C03202 UACS No. 310203100126000 June 5, 2018 Region IX Zamboanga del Sur 1st District Engineering Office
UACS No. 310203100126000
Project ID: P00201351MN
OO1: Ensure Safe and Reliable National Road
Network Development - Road Widening - Tertiary Roads
Jct. Aurora - Monte Alegre - Labangan Jct Rd
K1640+400 - K1641+320
Physical Target:
CW-1- Road Widening: 1.84 lane km
Unit Cost: P 13.848M/Lane km
EAO: P 0.520 M
Allocation: P 26.0 M
June 19, 2018 FY 2018 GAA WIN8C03239 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Davao City Coastal Bypass Road at Jct. Davao-Cotabato Road-Bago Aplaya-Talomo-Matina Aplaya-Roxas Avenue-Sta. Ana Wharf-R. Castillo (Bago Aplaya-Times Beach), Package 6, incl. ROW, Davao City
Physical Target:
CW1: 2.216 Lane Km (Construction of Asphalt Road)
CW2: 4,367 sq. m. (Construction of Road Slope Protection Structure)
ROW: 20,000 sq.m.
Allocation:
TOTAL: P 526,155,000.00
CW1: P 171,075,200.00 (Construction of Asphalt Road)
CW2: P 143,664,375.00 (Construction of Road Slope Protection Structure)
ROW: 193,000,000.00
EAO: P 18,415,425.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Davao City Coastal Bypass Road at Jct. Davao-Cotabato Road-Bago Aplaya-Talomo-Matina Aplaya-Roxas Avenue-Sta. Ana Wharf-R. Castillo (Bago Aplaya-Times Beach), Package 6, incl. ROW, Davao City
Physical Target:
CW1: 1.516 Lane Km (Construction of Asphalt Road)
CW2: 7,332.134 sq. m. (Construction of Road Slope Protection Structure)
CW3: 0.400 Lane Km (Construction of Gravel Road)
ROW: ROW: 20,000 sq.m.
Allocation:
TOTAL: P 526,155,000.00
CW1: P 173,410,201.12 (Construction of Asphalt Road)
CW2: P 138,012,372.97 (Construction of Road Slope Protection Structure)
CW3: P 3,317,000.91 (Construction of Gravel Road)
ROW: 193,000,000.00
EAO: P 18,415,425.00
June 19, 2018 FY 2018 GAA WIN8C03211 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI
MODIFICATION:

FROM: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Brgy. Mahayahay, Maragusan – Brgy. Singapore – Brgy. Anitapan – Brgy. Mascareg – Brgy. Cabuyuan, incl. ROW, Mabini Compostela Valley

Physical Target:
CW1: 3.381 Lane Km (Construction of Gravel Road)
CW2: 286 sq.m. (Construction of Concrete Bridge)
ROW: 20,408 sq.m.
Allocation:
TOTAL: P 110,000,000.00
CW1: P 83,955,000.00 (Construction of Concrete Road)
CW2: P 20,265,000.00 (Construction of Concrete Bridge)
ROW: P 1,930,000.00
EAO: P 3,850,000.00

TO: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Brgy. Mahayahay, Maragusan – Brgy. Singapore – Brgy. Anitapan – Brgy. Mascareg – Brgy. Cabuyuan, incl. ROW, Mabini Compostela Valley

Physical Target:
CW1: 4.20 Lane Km (Construction of Gravel Road)
Allocation:
TOTAL: P 110,000,000.00
CW1: P 104,220,000.00 (Construction of Concrete Road)
ROW: P 1,930,000.00
EAO: P 3,850,000.00
June 19, 2018 FY 2018 WIN8C03123 UACS No. 310110100040000 June 4, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 310110100040000
Project ID: P00201582MN
OO1: Ensure Safe and Reliable National Road System
Asset Preservation: Construction/ Upgrading/ Rehabilitation of Drainage along National Roads - Primary Roads
Pagadian City - Zamboanga City Road
K1866+000 - K1866+079
K1866+307 - K1866+366
K1866+497 - K1866+621
K1866+788 - K1867+336
K1867+561 - K1867+727
K1867+851 - K1868+000
K1869+800 - K1870+675
Physical Target:
CW-1- Construction of Drainage Structure along Road: 2,000.00 l.m
Unit Cost: P 6,571.80/l.m.
ROW: 395 sq.m
Unit Cost: P 1,012.66/sq.m.
EAO: P 276,400.00
Allocation: P 13,820,000.00
June 19, 2018 FY 2018 GAA WIN8C03179 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao City District Engineering Office
MODIFICATION:

FROM: Local Program
Local - National Local Roads and Bridges - Local Roads – Local Infrastructure Program
Construction of Road, Brgy. 9-A, Davao City
Physical Target:
CW1: 0.400 lane km (Construction of Concrete Road)
Allocation:
TOTAL: P 7,000,000.00
CW1: P 6,930,000.00 (Construction of Concrete Road)
EAO: P 70,000.00

TO: Local Program
Local - National Local Roads and Bridges - Local Roads – Local Infrastructure Program
Construction of Road, Brgy. 9-A, Davao City
Physical Target:
CW1: 1.860 lane km (Construction of Concrete Road)
Allocation:
TOTAL: P 7,000,000.00
CW1: P 6,930,000.00 (Construction of Concrete Road)
EAO: P 70,000.00
June 19, 2018 FY 2018 WIN8C03120 UACS No. 300109200206000 June 4, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300109200206000
Project ID: P00250069MN
Local Program
Local - Flood Control and Drainage
Drainage/ Protection Works - Local Infrastructure Program
Construction of Drainage System, Kasanyangan, Zamboanga City
Physical Target:
CW-1- Construction of Drainage Structure: 300.00 l.m.
Unit Cost: P 6,600.00/ l.m.
EAO: P 20,000.00
Allocation: P 2,000,000.00
June 19, 2018 FY 2018 GAA WIN8C03191 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao City District Engineering Office
MODIFICATION:

FROM: Local Program
Local - Flood Control and Drainage - Drainage / Protection Works – Local Infrastructure Program
Construction of Drainage System, Brgy. 8-A, Davao City
Physical Target:
CW1: 160 Lineal meters (Construction of Drainage Structure)
Allocation:
TOTAL: P 3,000,000.00
CW1: P 2,970,000.00 (Construction of Drainage Structure)
EAO: P 30,000.00

TO: Local Program
Local - Flood Control and Drainage - Drainage / Protection Works – Local Infrastructure Program
Construction of Drainage System, Brgy. 8-A, Davao City
Physical Target:
CW1: 489 Lineal meters (Construction of Drainage Structure)
Allocation:
TOTAL: P 3,000,000.00
CW1: P 2,970,000.00 (Construction of Drainage Structure)
EAO: P 30,000.00
June 19, 2018 FY 2018 WIN8C03215 UACS No. 300109200204000 June 6, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300109200204000
Project ID: P00250055MN
Local Program
Flood Control and Drainage - Drainage/Protection Works - Local Infrastructure Program
Construction of Drainage System, Brgy. Boalan, Zamboanga City
Physical Target:
CW-1- Construction of Drainage Structure: 170.00 l.m.
Unit Cost: P 5,882.35/ l.m.
Allocation: P 1,000,000.00
June 19, 2018 FY 2018 GAA WIN8C03181 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao City District Engineering Office
MODIFICATION:

FROM: Local Program
Local - Flood Control and Drainage - Drainage / Protection Works – Local Infrastructure Program
Construction of Drainage System, Brgy. Baliok, Davao City
Physical Target:
CW1: 300 Lineal meters (Construction of Drainage Structure)
Allocation:
TOTAL: P 6,000,000.00
CW1: P 5,994,000.00 (Construction of Drainage Structure)
EAO: P 60,000.00

TO: Local Program
Local - Flood Control and Drainage - Drainage / Protection Works – Local Infrastructure Program
Construction of Drainage System, Brgy. Baliok, Davao City
Physical Target:
CW1: 1,061 Lineal meters (Construction of Drainage Structure)
Allocation:
TOTAL: P 6,000,000.00
CW1: P 5,994,000.00 (Construction of Drainage Structure)
EAO: P 60,000.00
June 19, 2018 FY 2018 WIN8C03209 UACS No. 300107200219000 June 6, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300107200219000
Project ID: P00250064MN
Local Program
Flood Control and Drainage - Flood Control Structures/ Facilities - Local Infrastructure Program
Construction of Flood Control, Brgy. Boalan, Zamboanga City
Physical Target:
CW-1- Construction of Drainage Structure: 44.00 l.m.
Unit Cost: P 22,727.27/ l.m
Allocation: P 1,000,000.00
June 19, 2018 FY 2018 GAA WIN8C03184 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao City District Engineering Office
MODIFICATION:

FROM: : Local Program
Local - Flood Control and Drainage - Drainage/Protection Works - Local Infrastructure Program
Construction of Drainage System, Brgy. Bucana 76-A, Davao City
Physical Target:
CW1: 400 Lineal meters (Construction of Drainage Structure)
Allocation:
TOTAL: P 8,000,000.00
CW1: P 7,920,000.00 (Construction of Drainage Structure)
EAO: P 80,000.00

TO: Local Program
Local - Flood Control and Drainage - Drainage/Protection Works - Local Infrastructure Program
Construction of Drainage System, Brgy. Bucana 76-A, Davao City
Physical Target:
CW1: 1,150 Lineal meters (Construction of Drainage Structure)
Allocation:
TOTAL: P 8,000,000.00
CW1: P 7,920,000.00 (Construction of Drainage Structure)
EAO: P 80,000.00
June 19, 2018 FY 2018 GAA WIN8C03195 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao City District Engineering Office
MODIFICATION:

FROM: Local Program
Local - Flood Control and Drainage - Drainage/Protection Works - Local Infrastructure Program
Construction of Drainage System, Brgy. Maa, Davao City
Physical Target:
CW1: 130 Lineal meters (Construction of Drainage Structure)
Allocation:
TOTAL: P 2,000,000.00
CW1: P 1,980,000.00 (Construction of Drainage Structure)
EAO: P 20,000.00

TO: Local Program
Local - Flood Control and Drainage - Drainage/Protection Works - Local Infrastructure Program
Construction of Drainage System, Brgy. Maa, Davao City
Physical Target:
CW1: 236 Lineal meters (Construction of Drainage Structure)
Allocation:
TOTAL: P 2,000,000.00
CW1: P 1,980,000.00 (Construction of Drainage Structure)
EAO: P 20,000.00
June 19, 2018 FY 2018 WIN8C03124 UACS No. 300109200207000 June 4, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300109200207000
Project ID: P00250070MN
Local Program
Local - Flood Control and Drainage
Drainage/Slope Protection Works - Local Infrastructure Program
Construction of Drainage System, Sangali, Zamboanga City
Physical Target:
CW-1- Construction of Drainage Structure: 110.00 l.m.
Unit Cost: P 18,000.00/ l.m.
EAO: P 20,000.00
Allocation: P 2,000,000.00
June 19, 2018 FY 2018 GAA WIN8C03030 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao City District Engineering Office
MODIFICATION:

FROM: OO1 : Ensure Safe and Reliable National Road System
Network Development - Construction of By-Pass and Diversion Roads
Slaughter House Road until F. Torres Bridge, Package 4, Davao City
Physical Target:
CW1: 0.860 lane km (Construction of Concrete Road)
Allocation:
TOTAL: P 17,194,000.00
CW1: P 16,850,120.00 (Construction of Concrete Road)
EAO: P 343,880.00

TO: OO1 : Ensure Safe and Reliable National Road System
Network Development - Construction of By-Pass and Diversion Roads
Slaughter House Road until F. Torres Bridge, Package 4, Davao City
Physical Target:
CW1: 0.664 lane km (Reconstruction to Concrete Pavement)
CW2: 1,640.84 sq.m. (Additional Lane Width)
Allocation:
TOTAL: P 17,194,000.00
CW1: P 9,782,360.00 ((Reconstruction to Concrete Pavement)
CW2: P 7,067,760.00 (Additional Lane Width)
EAO: P 343,880.00
June 19, 2018 FY 2018 WIN8C03217 UACS No. 300108200063000 June 6, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300108200063000
Projecct ID: P00257487MN
Local Program
Flood Control and Drainage
Drainage/ Protection Works - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Drainage Facilities at Villahermosa Housing, Luyahan, Pasonanca, Zamboanga City
Physical Target:
CW-1- Construction of Drainage Structure: 631.55 l.m.
Unit Cost: P 7,758.68894/ l.m.
EAO: P 100,000.00
Allocation: P 5,000,000.00
June 19, 2018 FY 2018 GAA WIN8C03046 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao City District Engineering Office
MODIFICATION:

FROM: Convergence and Special Support Program
Construction/ Improvement of Access Roads leading to Declared Tourism Destinations
Jct. Davao City Diversion Road-Matina Pangi Road leading to Jaca (Mountain) Resort and DECA Wakeboard Park, Brgy. Matina Pangi, Davao City
Physical Targets:
CW1: 0.510 lane kilometers (Construction of Concrete Road)
CW2: 3.164 lane kilometers (Reconstruction from Paved to Concrete)
Allocation:
TOTAL: P 28,090,000.00
CW1: P 4,272,800.00 (Construction of Concrete Road)
CW2: P 23,255,400.00 (Reconstruction from Paved to Concrete)
EAO: P 561,800.00

TO: Convergence and Special Support Program
Construction/ Improvement of Access Roads leading to Declared Tourism Destinations
Jct. Davao City Diversion Road-Matina Pangi Road leading to Jaca (Mountain) Resort and DECA Wakeboard Park, Brgy. Matina Pangi, Davao City
Physical Targets:
CW1: 3.392 lane kilometers (Reconstruction to Concrete Pavement)
Allocation:
TOTAL: P 28,090,000.00
CW1: P 27,528,200.00 (Reconstruction from Paved to Concrete)
EAO: P 561,800.00
June 19, 2018 FY 2018 GAA WIN8C03243 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Bukidnon – Compostela Valley Road (Brgy. Namnam, San Fernando, Bukidnon – Laak COmpostela Valley), Package 3, incl. ROW, Davao del Norte
Physical Target:
CW1: 12.912 Lane Km (Construction of Concrete Road)
ROW: 96,840 sq.m.
Allocation:
TOTAL: P 300,000,000.00
CW1: P 280,351,800.00 (Construction of Concrete Road)
ROW: 9,148,000.00
EAO: P 10,500,000.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Bukidnon – Compostela Valley Road (Brgy. Namnam, San Fernando, Bukidnon – Laak COmpostela Valley), Package 3, incl. ROW, Davao del Norte
Physical Target:
CW1: 6.8063 Lane Km (Construction of Concrete Road)
ROW: 96,840 sq.m.
Allocation:
TOTAL: P 300,000,000.00
CW1: P 280,351,800.00 (Construction of Concrete Road)
ROW: 9,148,000.00
EAO: P 10,500,000.00

June 19, 2018 FY 2018 WIN8C03122 UACS No. 310105100166000 June 4, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 310105100166000
Project ID: P00200117MN
OO1: Ensure Safe and Reliable National Road System
Asset Preservation: Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Secondary Roads
Zamboanga City - Labuan - Limpapa Rd
K1959+598.5 - K1959+639
K1962+185.5 - K1962+799
K1963+841 - K1963+935.5
K1964+266.5 - K1964+738.5
K1966+018 - K 1966+945
K1972+928 - K1973+206
Physical Target:
CW-1- Reconstruction from Paved to Concrete: 0.810 lane km
Unit Cost: P 9,254,345.68/ lane km
EAO: P 152,980.00
Allocation: P 7,649,000.00
June 19, 2018 FY 2018 GAA WIN8C03052 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao City District Engineering Office

MODIFICATION:

FROM: Convergence and Special Support Program
Construction/ Improvement of Access Roads leading to Declared Tourism Destinations
Roxas Avenue - Padre Gomez St. - Palma Gil St. - Camus St. - Legaspi St. leading to People's Park, Davao City
Physical Targets:
CW1: 2.52 Lane Km (Reconstruction from Paved to Concrete)
Allocation:
TOTAL: P 23,080,000.00
CW1: P 22,618,400.00 (Reconstruction from Paved to Concrete)
EAO: P 461,600.00

TO: Convergence and Special Support Program
Construction/ Improvement of Access Roads leading to Declared Tourism Destinations
Roxas Avenue - Padre Gomez St. - Palma Gil St. - Camus St. - Legaspi St. leading to People's Park, Davao City
Physical Targets:
CW1: 1.09 Lane Km (Reconstruction from Paved to Concrete)
CW2: 664 Lineal meters (Construction of Drainage Structure)
Allocation:
TOTAL: P 23,080,000.00
CW1: P 7,759,430.00 (Reconstruction from Paved to Concrete)
CW2: P 14,858,970.00 (Construction of Drainage Structure)
EAO: P 461,600.00
June 19, 2018 FY 2018 GAA WIN8C03240 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Bukidnon – Compostela Valley Road (Brgy. Namnam, San Fernando, Bukidnon – Laak COmpostela Valley), Package 2, incl. ROW, Davao del Norte
Physical Target:
CW1: 12.912 Lane Km (Construction of Concrete Road)
ROW: 96,840 sq.m.
Allocation:
TOTAL: P 300,000,000.00
CW1: P 280,351,800.00 (Construction of Concrete Road)
ROW: 9,148,000.00
EAO: P 10,500,000.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Bukidnon – Compostela Valley Road (Brgy. Namnam, San Fernando, Bukidnon – Laak COmpostela Valley), Package 2, incl. ROW, Davao del Norte
Physical Target:
CW1: 7.17934 Lane Km (Construction of Concrete Road)
ROW: 96,840 sq.m.
Allocation:
TOTAL: P 300,000,000.00
CW1: P 280,351,800.00 (Construction of Concrete Road)
ROW: 9,148,000.00
EAO: P 10,500,000.00
June 19, 2018 FY 2018 WIN8C03216 UACS No. 310202100001000 June 6, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 310202100001000
Project ID: P00200706MN
OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Secondary Roads
Airport Road incl. ROW - (S01208MN)
Chainage 000 - Chainage 493
Physical Target:
CW-1- Road Widening: 0.5352 lane km
Unit Cost: P 31,310,756.93/ lane km
ROW: 72,300.00 sq.m.
Unit Cost: P 1,012.04471/sq.m.
EAO: P 3,261,650.00
Allocation: P 93,190,000.00
June 19, 2018 FY 2018 WIN8G02407 FY 2018 GAA January 4, 2018 Region III Pampanga 3rd District Engineering Office
Local Roads and Bridges – Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects – Construction of New Road including Drainage leading to Pampanga Economic Zone (PEZ), Angeles City, Pampanga
June 19, 2018 FY 2018 GAA WIN8C03242 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Bukidnon – Compostela Valley Road (Brgy. Namnam, San Fernando, Bukidnon – Laak COmpostela Valley), Package 4, incl. ROW, Davao del Norte
Physical Target:
CW1: 12.912 Lane Km (Construction of Concrete Road)
ROW: 96,840 sq.m.
Allocation:
TOTAL: P 300,000,000.00
CW1: P 280,351,800.00 (Construction of Concrete Road)
ROW: 9,148,000.00
EAO: P 10,500,000.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Bukidnon – Compostela Valley Road (Brgy. Namnam, San Fernando, Bukidnon – Laak COmpostela Valley), Package 4, incl. ROW, Davao del Norte
Physical Target:
CW1: 6.5443 Lane Km (Construction of Concrete Road)
ROW: 96,840 sq.m.
Allocation:
TOTAL: P 300,000,000.00
CW1: P 280,351,800.00 (Construction of Concrete Road)
ROW: 9,148,000.00
EAO: P 10,500,000.00
June 19, 2018 FY 2018 GAA WIN8C03199 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao City District Engineering Office
MODIFICATION:

FROM: OO1 : Ensure Safe and Reliable National Road System
Network Development - Road Widening - Primary Roads
Daang Maharlika (MN) incl. ROW -
K1484 + (-979) - K1484 + (-844),
K1485 + 573 - K1485 + 870,
K1486 + 863 - K1487 + 109,
K1487 + 708 - K1488 + 500
Physical Target:
CW1: 2.391 Lane Km (Road Widening)
CW2: 523.338 Square meters (ROW Acquisition)
Allocation:
TOTAL: P 56,400,000.00
CW1: P 44,652,480.00 (Road Widening)
CW2: P 9,773,520.00 (ROW Acquisition)
EAO: P 1,974,000.00

TO: OO1 : Ensure Safe and Reliable National Road System
Network Development - Road Widening - Primary Roads
Daang Maharlika (MN) incl. ROW -
K1484 + (-979) - K1484 + (-844),
K1485 + 573 - K1485 + 870,
K1486 + 863 - K1487 + 109,
K1487 + 708 - K1488 + 500
Physical Target:
CW1: 2.094 Lane Km (Road Widening)
CW2: 523.338 Square meters (ROW Acquisition)
Allocation:
TOTAL: P 56,400,000.00
CW1: P 44,652,480.00 (Road Widening)
CW2: P 9,773,520.00 (ROW Acquisition)
EAO: P 1,974,000.00
June 19, 2018 FY 2018 WIN8C03213 UACS No. 300109200205000 June 6, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300109200205000
Project ID: P00250068MN
Local Program
Local - Flood Control and Drainage
Drainage/ Protection Works - Local Infrastructure Program
Construction of Drainage System, Bungiao, Zamboanga City
Physical Target:
CW-1- Construction of Drainage Structure: 520.00 l.m.
Unit Cost: P 3,807.69/ l.m.
EAO: P 20,000.00
Allocation: P 2,000,000.00
June 19, 2018 FY 2018 GAA WIN8C03194 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao City District Engineering Office
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System
Asset Preservation
Construction / Upgrading / Rehabilitation of Drainage along National Roads - Secondary Roads
Davao City Div Rd - K1507 + 815 - K1510 + 905
Physical Target:
CW1: 6,020 Lineal meters (Construction of Drainage Structure along Road)
Allocation:
TOTAL: P 60,000,000.00
CW1: P 57,900,000.00 (Construction of Drainage Structure along Road)
Allocation:
EAO: P 2,100,000.00

TO: OO1: Ensure Safe and Reliable National Road System
Asset Preservation
Construction / Upgrading / Rehabilitation of Drainage along National Roads - Secondary Roads
Davao City Div Rd – K1508 + 280 – K1510 + 905
Physical Target:
CW1: 5,206 Lineal meters (Construction of Drainage Structure along Road)
Allocation:
TOTAL: P 60,000,000.00
CW1: P 57,900,000.00 (Construction of Drainage Structure along Road)
Allocation:
EAO: P 2,100,000.00
June 19, 2018 FY 2018 WIN8C03210 UACS No. 300106200141000 June 6, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300106200141000
Project ID: P00257639MN
Local Program
Flood Control and Drainage - Flood Control Structures/ Facilities
Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Flood Control at Sta. Maria Creek, Sta. Maria, Zamboanga City
Physical Target:
CW-1- Construction of Drainage Structure: 187.32 l.m.
Unit Cost: P 15,695.07/l.m.
EAO: P 60,000.00
Allocation: P 3,000,000.00
June 19, 2018 FY 2018 GAA WIN8C03134 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao City District Engineering Office

MODIFICATION:

FROM: OO2: Protect Lives and Properties Against Major Floods
Flood Management Program
Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Concrete Revetment along Lasang River, Lasang Section, Davao City
Physical Target:
CW1: 185 lineal meters (Construction of Revetment)
Allocation:
TOTAL: P 50,000,000.00
CW1: P 49,000,000.00 (Construction of Revetment)
EAO: P 1,000,000.00

TO: OO2: Protect Lives and Properties Against Major Floods
Flood Management Program
Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Concrete Revetment along Lasang River, Lasang Section, Davao City
Physical Target:
CW1: 350 lineal meters (Construction of Revetment)
Allocation:
TOTAL: P 50,000,000.00
CW1: P 49,000,000.00 (Construction of Revetment)
EAO: P 1,000,000.00
June 19, 2018 FY 2018 GAA WIN8C03174 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao City District Engineering Office

MODIFICATION:

FROM: Convergence and Special Support Program
Construction/ Improvement of Access Roads leading to Declared Tourism Destinations
Mabini Extension Road leading to Davao Crocodile Park, Davao City
Physical Targets:
CW1: 1.130 lane kilometers (Construction of Concrete Road)
CW2: 1,340 lineal meters (Construction of Drainage Structure)
Allocation:
TOTAL: P 25,870,000.00
CW1: P 15,503,600.00 (Construction of Concrete Road)
CW2: P 9,849,000.00 lane kilometers (Construction of Drainage Structure)
EAO: P 517,400.00

TO: Convergence and Special Support Program
Construction/ Improvement of Access Roads leading to Declared Tourism Destinations
Mabini Extension Road leading to Davao Crocodile Park, Davao City
Physical Targets:
CW1: 0.278 lane kilometers (Construction of Concrete Road)
CW2: 406 lineal meters(Construction of Drainage Structure)
CW3: 1.722 lane kilometers (Reconstruction to Concrete Pavement)
Allocation:
TOTAL: P 25,870,000.00
CW1: P 1,625,580.00 (Construction of Concrete Road)
CW2: P 2,322,600.00 lane kilometers (Construction of Drainage Structure)
CW3: P 21,404,420.00 (Reconstruction to Concrete Pavement)
EAO: P 517,400.00
June 18, 2018 FY - 2018 WIN8F05578 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
Local Program

Buildings and Other Structures - Multipurpose/Facilities
- Local Infrastructure Program

FROM:
Construction of Multi-Purpose Building,
Brgy. Binuga, Boac, Marinduque

CW1: 1 Bldg. ( Construction of Multi-Purpose Building )
Allocation: 5,000,000 Php

TO:
Construction/Completion of Multi-Purpose Building,
Brgy. Binunga, Boac, Marinduque

CW1: 1 Bldg. ( Construction of Multi-Purpose Building )
Allocation: 5,000,000 Php
June 18, 2018 FY - 2018 WIN8F05565 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Romblon District Engineering Office
Local Programs: Local Infrastructure Program

Local - National Roads and Bridges - Local Roads
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM:
Construction of Tumingad - Canlumay - Patoo Road
leading to Romblon Airport, Phase 2, Odiongan, Romblon

CW1: 7.15 lane km ( Construction of Gravel Road )
Allocation: 100,000,000 Php

TO:
Construction of Tumingad - Canlumay - Patoo Road
leading to Romblon Airport, Phase 2, Odiongan, Romblon

CW1: 3.80 lane km ( Construction of Gravel Road )
Allocation : 100,000,000 Php
June 18, 2018 FY - 2018 WIN8F05568 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Romblon District Engineering Office
Local Programs: Local Infrastructure Program

Local - National Roads and Bridges - Local Roads
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM:
Construction of Roads, Brgy. Bangon,
Odiongan, Romblon

CW1: 0.352 lane km ( Construction of Concrete Road )
Allocation: 2,000,000 Php

TO:
Construction of Roads, Brgy. Bangon,
Odiongan, Romblon

CW1: 0.456 lane km ( Construction of Concrete Road )
Allocation: 2,000,000 Php
June 18, 2018 FY - 2018 WIN8F05567 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Romblon District Engineering Office
Local Programs: Local Infrastructure Program

Local - National Roads and Bridges - Local Roads
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM:
Construction of Gravel Road -
Construction of Claro M. Recto Road and
Odiongan - Tugdan Road leading to Romblon Airport,
Recto, Ferrol, Romblon

CW1: 5.303 lane km ( Construction of Gravel Road )
Allocation: 87,000,000 Php

TO:
Construction of Gravel Road -
Construction of Claro M. Recto Road and
Odiongan - Tugdan Road leading to Romblon Airport,
Recto, Ferrol, Romblom

CW1: 6021 lane km ( Construction of Gravel Road )
Allocation: 87,000,000 Php
June 18, 2018 FY - 2018 WIN8F05566 FY - 2018 GAA DPWH Infra PRogram December 19, 2017 Region IV-B Romblon District Engineering Office
Local Programs : Local Infrastructure Program

Local - national Roads and Bridges - Local Roads
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM:
Rehabilitation of Concrete Road -
Improvement/Rehabilitation of Road, Barangay Mabini,
Corcuera, Romblon

CW1: 0.190 lane km ( Rehabilitation of Concrete Road )
Allocation: 2,500,000 Php

TO:
Rehabilitation of Concrete Road -
Improvement/Rehabilitation of Road, Barangay Mabini,
Corcuera, Romblon

CW1: 0.296 lane km ( Rehabilitation of Concrete Road )
Allocation: 2,500,000 Php

June 18, 2018 FY 2018 GAA WIN8C03171 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Sur District Engineering Office
MODIFICATION:

FROM: OO1: Ensure Safe Reliable National Road System – Asset Preservation
Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide – Primary Roads
Digos-Makar Rd-
K1589 + 994 – K1589 + 1077,
K1589 + 454 – K1591 + 160

Physical Target:
CW1: 16,780 sq.m. (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 80,870,000.00
CW1: P 78,039,550.00 (Construction of Road Slope Protection Structure)
EAO: P 2,830,450.00

TO: OO1: Ensure Safe Reliable National Road System – Asset Preservation
Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide – Primary Roads
Digos-Makar Rd-
K1589 + 935 – K1589 + 987,
K1589 + 997 – K1589 + 1065,
K1589 + 1071 – K1589 + 1225,
K1590 + 454 – K1590 + 560,
K1590 + 658 – K1590 + 798,
K1590 + 800 – K1591 + 040,
K1591 + 062 – K1591 + 164
Physical Target:
CW1: 5,093 sq.m. (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 80,870,000.00
CW1: P 78,039,550.00 (Construction of Road Slope Protection Structure)
EAO: P 2,830,450.00
June 18, 2018 FY - 2018 WIN8F05569 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Romblon District Engineering Office
Local Programs : Local Infrastructure Program

Local - National Roads and bridges - Local Roads
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM:
Construction of Roads,
Brgy. Poblacion, Calatrava, Romblon

CW1: 0.704 llane km ( Construction of Concrete Road )
Allocation: 4,000,000 Php

TO:
Construction of Roads,
Brgy. Poblacion, Calatrava, Romblon

CW1: 0.35028 lane km ( Construction of Concrete Road )
Allocation: 4,000,000 Php
June 18, 2018 FY 2018 GAA WIN8C03150 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Norte District Engineering Office
MODIFICATION:

FROM: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction/Rehabilitation of Road Brgy. Concepcion, Asuncion – Brgy. Kipalili, San Isidro, Davao del Norte

Physical Target:
CW1: 0.800 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 10,000,000.00
CW1: P 9,800,000.00 (Construction of Concrete Road)
EAO: P 200,000.00

TO: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction/Rehabilitation of Road Brgy. Concepcion, Asuncion – Brgy. Kipalili, San Isidro, Davao del Norte

Physical Target:
CW1: 1.000 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 10,000,000.00
CW1: P 9,800,000.00 (Construction of Concrete Road)
EAO: P 200,000.00
June 18, 2018 FY 2018 GAA WIN8C03117 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Norte District Engineering Office
MODIFICATION:

FROM: Local Program
Local – Local Roads and Bridges – Local Bridges – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Bunawan Bridge, Brgy. Concepcion, Asuncion, Davao de Norte

Physical Target:
CW1: 191 Sq.m. (Construction of Concrete Bridge)
Allocation:
TOTAL: P 20,000,000.00
CW1: P 19,600,000.00 (Construction of Concrete Bridge)
EAO: P 400,000.00

TO: Local Program
Local – Local Roads and Bridges – Local Bridges – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Bunawan Bridge, Brgy. Concepcion, Asuncion, Davao del Norte

Physical Target:
CW1: 286.20 Sq.m. (Construction of Concrete Bridge)
Allocation:
TOTAL: P 20,000,000.00
CW1: P 19,600,000.00 (Construction of Concrete Bridge)
EAO: P 400,000.00
June 18, 2018 FY 2018 GAA WIN8C03141 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Norte District Engineering Office
MODIFICATION:

FROM: 001: Ensure Safe and Reliable National Road System
Asset Preservation – Rehabilitation/Reconstruction of National Roads with Slips, Collapse, and Landslide – Secondary Roads
Kapalong – Talaingod – Valencia (Bukidnon) Rd –
K1485 + 927 – K1485 + 943,
K1493 + 329 – K1493 + 360,
K1494 + 507 – K1494 + 520,
K1495 + 380 – K1495 + 465

Physical Target:
CW1: 4,385 Sq.m. (Construction of Slope Protection Structure)
Allocation:
TOTAL: P 38,000,000.00
CW1: P 37,240,000.00 (Construction of Slope Protection Structure)
EAO: P 760,000.00

TO: 001: Ensure Safe and Reliable National Road System
Asset Preservation – Rehabilitation/Reconstruction of National Roads with Slips, Collapse, and Landslide – Secondary Roads
Kapalong – Talaingod – Valencia (Bukidnon) Rd –
K1494 + 507.2 – K1494 + 520.2,
K1495 + 380 – K1495 + 460,
K1504 + 570 – K1504 + 600

Physical Target:
CW1: 618.91 Sq.m. (Construction of Slope Protection Structure)
Allocation:
TOTAL: P 38,000,000.00
CW1: P 37,240,000.00 (Construction of Slope Protection Structure)
EAO: P 760,000.00
June 18, 2018 FY 2018 GAA WIN8C03182 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao City District Engineering Office
MODIFICATION

FROM: Local Program
Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Improvement/ Construction of Drainage along Acacia St., - Jct. Patnubay St., Davao City
Physical Target:
CW1: 405 Lineal Meters (Construction of Drainage Structure)
Allocation:
TOTAL: P 16,200,000.00
CW1: P 15,633,000.00 (Construction of Drainage Structure)
EAO: P 567,000.00

TO: Local Program
Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Improvement/ Construction of Drainage along Acacia St., - Jct. Patnubay St., Davao City
Physical Target:
CW1: 810 Lineal Meters (Construction of Drainage Structure)
Allocation:
TOTAL: P 16,200,000.00
CW1: P 15,633,000.00 (Construction of Drainage Structure)
EAO: P 567,000.00
June 18, 2018 FY 2018 GAA WIN8C03188 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Norte District Engineering Office
MODIFICATION:

FROM: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction/Improvement of Road, Lake Village with Bridge Component, Brgy. Sawata, San Isidro, Davao del Norte

Physical Target:
CW1: 1.090 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 20,000,000.00
CW1: P 19,600,000.00 (Construction of Concrete Road)
EAO: P 400,000.00

TO: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction/Improvement of Road, Lake Village, Brgy. Sawata, San Isidro, Davao del Norte

Physical Target:
CW1: 1.360 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 10,000,000.00
CW1: P 19,600,000.00 (Construction of Concrete Road)
EAO: P 400,000.00
June 18, 2018 FY 2018 GAA WIN8C03159 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Norte District Engineering Office
MODIFICATION:

FROM: Local Program
Local – Local Roads and Bridges – Local Roads – Local Infrastructure Program
Construction of Lawig Subdivision Road connecting Barangay San Agustin Road, Bakbak District, Island Garden City of Samal, Davao del Norte

Physical Target:
CW1: 0.650 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 5,000,000.00
CW1: P 4,950,000.00 (Construction of Concrete Road)
EAO: P 50,000.00

TO: Local Program
Local – Local Roads and Bridges – Local Roads – Local Infrastructure Program
Construction of Lawig Subdivision Road connecting Barangay San Agustin Road, Babak District, Island Garden City of Samal, Davao del Norte

Physical Target:
CW1: 0.776 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 5,000,000.00
CW1: P 4,950,000.00 (Construction of Concrete Road)
EAO: P 50,000.00
June 18, 2018 FY 2018 GAA WIN8C03183 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Norte District Engineering Office
MODIFICATION:

FROM: Local Program
Local – Local Roads and Bridges – Local Bridges – Local Infrastructure Program
Construction of Mama Bridge, Brgy. San Miguel, San Isidro, Davao del Norte

Physical Target:
CW1: 143 Sq.m. (Construction of Concrete Bridge)
Allocation:
TOTAL: P 15,000,000.00
CW1: P 14,700,000.00 (Construction of Concrete Bridge)
EAO: P 300,000.00

TO: Local Program
Local – Local Roads and Bridges – Local Bridges – Local Infrastructure Program
Construction of Mama Bridge, Brgy. San Miguel, San Isidro, Davao del Norte

Physical Target:
CW1: 248.80 Sq.m. (Construction of Concrete Bridge)
Allocation:
TOTAL: P 15,000,000.00
CW1: P 14,700,000.00 (Construction of Concrete Bridge)
EAO: P 300,000.00
June 18, 2018 FY 2018 GAA WIN8C03197 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Norte District Engineering Office
MODIFICATION:

FROM: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction/Rehabilitation of Road Purok 1 Brgy. Linao – Purok 4, Brgy. San Miguel, San Isidro with Bridge Component, Brgy. San Miguel, San Isidro, Davao del Norte

Physical Target:
CW1: 2.600 Lane Km (Rehabilitation of Concrete Road)
Allocation:
TOTAL: P 40,000,000.00
CW1: P 39,200,000.00 (Construction of Concrete Road)
EAO: P 800,000.00

TO: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction/Rehabilitation of Road Purok 1 Brgy. Linao – Purok 4, Brgy. San Miguel, San Isidro, Davao del Norte

Physical Target:
CW1: 2.520 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 40,000,000.00
CW1: P 39,200,000.00 (Construction of Concrete Road)
EAO: P 800,000.00
June 18, 2018 FY 2018 GAA WIN8C03187 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Norte District Engineering Office
MODIFICATION:

FROM: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Road Prk. 13 – Pro. 4 with Bridge Component at Sabangan, San Isidro, Davao del Norte

Physical Target:
CW1: 0.600 Lane Km (Rehabilitation of Concrete Road)
Allocation:
TOTAL: P 15,000,000.00
CW1: P 14,700,000.00 (Rehabilitation of Concrete Road)
EAO: P 300,000.00

TO: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Road Purok 13 – Purok 4 at Sabangan, San Isidro, Davao del Norte

Physical Target:
CW1: 1.380 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 15,000,000.00
CW1: P 14,700,000.00 (Construction of Concrete Road)
EAO: P 300,000.00
June 18, 2018 FY 2018 GAA WIN8C03204 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Norte District Engineering Office
MODIFICATION:

FROM: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction/Rehabilitation of Sabangan – Purok Falcata – Brgy. Sawata with Bridge component, Sabangan, San Isidro, Davao del Norte

Physical Target:
CW1: 1.700 Lane Km (Rehabilitation of Concrete Road)
Allocation:
TOTAL: P 20,000,000.00
CW1: P 19,600,000.00 (Rehabilitation of Concrete Road)
EAO: P 400,000.00

TO: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction/Rehabilitation of Sabangan – Purok Falcata – Brgy. Sawata, Sabangan, San Isidro, Davao del Norte

Physical Target:
CW1: 1.930 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 20,000,000.00
CW1: P 19,600,000.00 (Construction of Concrete Road)
EAO: P 400,000.00
June 18, 2018 FY 2018 GAA WIN8C03193 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Norte District Engineering Office
MODIFICATION:

FROM: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Drainage Canal Upper La Filipina, Tagum City, Davao del Norte

Physical Target:
CW1: 6 Lineal Meters (Construction of Drainage Structure)
Allocation:
TOTAL: P 50,000,000.00
CW1: P 48,250,000.00 (Rehabilitation of Concrete Road)
EAO: P 1,750,000.00

TO: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Drainage Canal Upper La Filipina, Tagum City, Davao del Norte

Physical Target:
CW1: 2,038.98 Lineal Meters (Construction of Drainage Structure)
Allocation:
TOTAL: P 50,000,000.00
CW1: P 48,250,000.00 (Rehabilitation of Concrete Road)
EAO: P 1,750,000.00
June 14, 2018 FY 2018 WIN8G01858 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Camarines Sur 4th District Engineering Office
UACS No.: 310102100144000
Project ID: P00200189LZ
OO1: Ensure Safe and Reliable National Road System –
Asset Preservation Program - Preventive Maintenance – Secondary Roads – Baao-Iriga City Nabua Rd - K0470+014 - K0470+1075, K0472+000 - K0473+280
Physical Target - CW1-Preventive Maintenance of Road: Aspha;t Overlay / 4.39 Lane-Km
Unit Cost: CW1 – Php 8.603 M /lane-km
Estimated Cost: Php 38.538 M
(As Modified)
June 14, 2018 FY 2018 WIN8G01893 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Camarines Sur 4th District Engineering Office
UACS No.: 310109100087000
Project ID: P00200935LZ
OO1: Ensure Safe and Reliable National Road System –
Asset Preservation Program - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide – Tertiary Roads – Nabua-Balatan Rd – K0486+334 – K0486+360, K0486+393 – K0486+480, k0490+(-020) – K0490+130, K0490+187 – K0490+225
Physical Target - CW1 - Construction of Road Slope Protection Structure/ 7,826.00 sq.m.
Unit Cost: CW1 – Php 4,361.54/sq.m.
Estimated Cost: Php 34.83 M
(As Modified)
June 14, 2018 FY 2018 WIN8G01895 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Camarines Sur 4th District Engineering Office
UACS No.: 310208100093000
Project ID: P00201554LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program – Off-Carriageway Improvement – Secondary Road – Iriga City-San isidro-Sagrada-Sn Ramon-Hanawan Rd – K0473+009 – K0473+442.20, K0473+452 – K0473+955, K0479+760 – K0480+503, K0480+600 – K0481+000
Physical Target - CW1 - Off-Carriageway improvement: Shoulder Paving/Construction/ 2,956.00 sq.m.
Unit Cost: CW1 – Php 6,630.58/sq.m.
Estimated Cost: Php 20.0 M
(As Modified)
June 14, 2018 FY 2018 WIN8G02150 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Albay 2nd Engineering Office
UACS No.: 300104202418000
Project ID: P00249128LZ
Local Program – Buildings and Other Structures - Multipurpose/Facilities - Local Infrastructure Program – Construction of Multi-Purpose Building, Anislag Elementary School, Anislag, Daraga, Albay
Physical Target - CW1 - Construction of Mulri-Purpose building/ 1 building
Unit Cost: CW1- Php 4.950 M/building
Estimated Cost: Php 5.0 M
(As Modified)


June 14, 2018 FY 2018 WIN8G02145 FY 2018 GAA R.A. 10964 December 28, 2017 Region V Albay 2nd Engineering Office
UACS No.: 310209100066000
Project ID: P00201619LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program – Off-Carriageway Improvement – Tertiary Roads – Comun-Inarado-Peñafrancia Rd - K0529+229 - K0529+610
Physical Target - CW1 - Off-Carriageway improvement: Shoulder Paving/Construction/ 1,511.00 sq.m.
Unit Cost: CW1 – Php 10.86T/sq.m.
Estimated Cost: Php 16.741 M
(As Modified)
June 14, 2018 FY 2018 WIN8G02137 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Albay 2nd Engineering Office
UACS No.: 310102100139000
Project ID: P00200184LZ
OO1: Ensure Safe and Reliable National Road System –
Asset Preservation Program - Preventive Maintenance – Secondary Roads – Legazpi Airport Rd – K0530+-972 – K0530+-242
Physical Target: CW1 - Preventive maintenance of Road: Asphalt Overlay/ 1.46 lane-km
Unit Cost: CW1 - Php 8.26355 M/lane-km
Estimated Cost: Php 16.741 M
(As Modified)
June 14, 2018 FY 2018 WIN8G02134 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Albay 2nd Engineering Office
UACS No.: 310208100006000
Project ID: P00201546LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program – Off-Carriageway Improvement – Secondary Roads – Banquerohan-Bariis-Sogoy-Sorsogon Bdry Rd - K0551+000 - K0551+592, K0552+000 - K0552+795, k0552+844 - k0555+107
Physical Target: CW1 - Off-Carriageway improvement: Shoulder Paving/Construction/ 15,433.00 sq.m.
Unit Cost: CW1 – Php 4.6896T/sq.m.
Estimated Cost: Php 75.00 M
(As Modified)
June 14, 2018 FY 2018 WIN8G02135 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Albay 2nd Engineering Office
UACS No.: 310208100032000
Project ID: P00201550LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program – Off-Carriageway Improvement – Secondary Roads – Legazpi City-Punta de Jesus Rd – K0538+563 – K0539+242, K0552+000 – K0554+844
Physical Target: CW1 - Off-Carriageway improvement: Shoulder Paving/Construction/ 19,640.00 sq.m.
Unit Cost: CW1 – Php 4.6531 T/sq.m.
Estimated Cost: Php 94.702 M
(As Modified)
June 14, 2018 FY 2018 WIN8G02176 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Albay 2nd Engineering Office
UACS No.: 320102100425000
Project ID: P00221297LZ
OO2: Protect Lives and Properties Against Major Floods – Flood Management Program – Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers – Construction/Improvement of Quirangay River Course (Tagaytay Section), Sta 1+141 – Sta. 1+252 (BS), Albay
Physical Target: CW1 – Construction of Flood Mitigation Structure/ 222.00 lm
Unit Cost: CW1 – Php 88.29 T/lm.
Estimated Cost: Php 20.0 M
(As Modified)
June 14, 2018 FY 2018 WIN8G02140 FY 2018 GAA R.A. 10964 December 28, 2017 Region V Albay 2nd Engineering Office
UACS No.: 320101101617000
Project ID: P00221304LZ
OO2: Protect Lives and Properties Against Major Floods – Flood Management Program – Construction/Maintenance of Flood Mitigation Structures and Drainage System – Construction of Cagsawa Ruins Protection Dike, Sta. 0+446 – Sta. 0+595 (B/S, Tributary “B”), Brgy. Cullat, Daraga, Albay
Physical Target: CW1 – Construction of Dike/ 298.00 lm
Unit Cost: CW1 – Php 131.54 T/lm.
Estimated Cost: Php 40.0 M
(As Modified)
June 14, 2018 FY 2018 WIN8G02136 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Albay 2nd Engineering Office
UACS No.: 320102100427000
Project ID: P00222704LZ
OO2: Protect Lives and Properties Against Major Floods – Flood Management Program – Construction/Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers – Construction/Rehabilitation of Yawa Flood Control Structure, La Playa Section, Sta. 0+268 - Sta. 0+446, Bonot, Legazpi City, Albay
Physical Target: CW1 – Construction of Flood Mitigation Structure/ 178.00 lm
Unit Cost: CW1 – Php 115.62 T/lm.
Estimated Cost: Php 21.0 M
(As Modified)
June 14, 2018 FY 2018 WIN8G02337 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Sorsogon District Engineering Office
UACS No.: 310102100030000
Project ID: P00202700LZ
OO1: Ensure Safe and Reliable National Road System –
Asset Preservation Program - Preventive Maintenance – Secondary Roads – Jct Putiao-Pilar-Donsol Rd - K0556+700 - K0559+028
Physical Target: CW1 – Preventive Maintenance of Road: Asphalt Overlay/ 4.54 lane-km
CW2 - Off-Carriageway Improvement: Shoulder Paving/Construction/ 5,061 sq.m.
Unit Cost: CW1 – Php 15.84 M/ lane-km.
CW2 – Php 4,853.59 / sq.m.
Estimated Cost: Php 100.0 M
(As Modified)
June 14, 2018 FY 2018 WIN8G02334 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Sorsogon District Engineering Office
UACS No.: 310102100029000
Project ID: P00202699LZ
OO1: Ensure Safe and Reliable National Road System –
Asset Preservation Program - Preventive Maintenance – Secondary Roads – Jct Putiao-Pilar-Donsol Rd - K0554+480 - K0556+700
Physical Target: CW1 -Preventive Maintenance of Road: Asphalt Overlay/ 4.22 lane-km
CW2 - Off-Carriageway improvement: Shoulder Paving/Construction/ 5,133 sq.m.
Unit Cost: CW1 – Php 16.53 M /lane-km
CW2 – Php 5,208.26/sq.m.
Estimated Cost: Php 100.0 M
(As Modified)
June 14, 2018 FY 2018 WIN8G02347 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Sorsogon District Engineering Office
UACS No.: 310207100026000
Project ID: P00201492LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program – Off-Carriageway Improvement – Primary Roads – Daang Maharlika (LZ) – K0543+556, K0544+697, K0548+174, K0548+773, K0552+510, K0553+044, K0553+686, K0553+910, K0554+960, K0559+490, K0562+519, K0566+668, K0574+335, K0574+769, K0575+612, K0577+145, K0582+362, K0582+981, K0585+192, K0588+200, K0596+390, K0598+473
Physical Target: CW1 – Off-Carriageway Improvement: Flaring of Intersections/ 22 intersections
Unit Cost: CW1 – Php 1.54 M/intersection
Estimated Cost: Php 34.60 M
(As Modified)
June 14, 2018 FY 2018 WIN8G02098 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Sorsogon 2nd District Engineering Office
UACS No.: 300116200980000
Project ID: P00240933LZ
LOCAL PROGRAM – Local Roads and Bridges – Local Roads – Construction / Repair / Rehabilitation /Improvement of Various Infrastructure including Local Projects - Construction of Mapaso-Cabarbuhan Road, Sta. 0+000 – Sta. 0+905, Irosin, Sorsogon
Physical Target: CW1 – Construction of Concrete Road/ 1.81 lane-km
Unit Cost: CW1 – Php 4.06 M/lm.
Estimated Cost: Php 7.50 M
(As Modified)
June 14, 2018 FY 2018 WIN8G02067 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Sorsogon 2nd District Engineering Office
UACS No.: 310209100073000
Project ID: P00201626LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program – Off-Carriageway Improvement – Tertiary Roads – Bacon-Sawanga-Prieto Diaz Rd – K0612+(-249) – K0612+660, K0612+701 – K0613+924, K0613+931 – K0614+249, K0614+269 – K0615+103, K0615+467 – K0615+518, K0615+857 – K0615+952
Physical Target: CW1 - Off-Carriageway improvement: Shoulder Paving/Construction/ 12,660 sq.m.
Unit Cost: CW1 – Php 3,087.15/sq.m.
Estimated Cost: Php 39.881 M
(As Modified)
June 14, 2018 FY 2018 WIN8G02082 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Sorsogon District Engineering Office
UACS No.: 310209100071000
Project ID: P00201624LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program – Off-Carriageway Improvement – Tertiary Roads – Ariman-Casiguran Rd – K0602+(-864) – K0604+677, K0606+315 – K0607+500, K0611+093 – K0611+678
Physical Target: CW1 - Off-Carriageway improvement: Shoulder Paving/Construction/ 19,734 sq.m.
Unit Cost: CW1 – Php 2,483.02/sq.m.
Estimated Cost: Php 50.0 M
(As Modified)
June 14, 2018 F WIN8G02391 FY 2018 GAA January 4, 2018 Region III Pampanga 2nd District Engineering Office
Local Roads and Bridges - Local Roads – Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects – Concreting of Road, Sitio Remedios, Brgy. San Nicolas, Sasmuan, Pampanga
June 14, 2018 FY 2018 WIN8G02394 FY 2018 GAA January 4, 2018 Region III Pampanga 2nd District Engineering Office
Flood Management Program – Construction / Maintenance of Flood Mitigation Structures and Drainage Systems – Construction of Slope Protection along Sta. Ursula Creek, Guagua, Pampanga
June 14, 2018 FY 2018 WIN8G02359 FY 2018 GAA January 4, 2018 Region III Pampanga 2nd District Engineering Office
Network Development Project - Off-Carriageway Improvement – Tertiary Rd – San Fernando – Lubao Rd, K0083+153 – K0083+526, K0083+538.20 – K0084+160, K0084+188.60 – K0084+703.90 – K0084+713.60 – K0084+875
June 14, 2018 FY 2018 WIN8G02392 FY 2018 GAA January 4, 2018 Region III Pampanga 2nd District Engineering Office
Local Roads and Bridges - Local Roads – Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects - Concreting of Road, Purok 6 to Purok 7, Brgy. Santiago, Lubao, Pampanga
June 14, 2018 FY 2018 WIN8G02399 FY 2018 GAA January 4, 2018 Region III Pampanga 2nd District Engineering Office
Flood Control and Drainage – Drainage / Protection Works – Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects - Construction of Line Canal , Barangay Sinura, Porac, Pampanga
June 14, 2018 FY 2018 WIN8G02390 FY 2018 GAA January 4, 2018 Region III Pampanga 2nd District Engineering Office
Local Roads and Bridges - Local Roads – Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects - Concreting of Road, Purok 6, Brgy. San Pablo, Lubao, Pampanga
June 13, 2018 FY - 2018 WIN8F05534 FY - 2018 GAA DPWH Infra Proram December 19, 2017 Region IV-B Palawan 1st District Engineering Office
Convergence Special Support Program

Convergence and Special Support -
Construction/Improvement of Access Roads leading to Declared Tourism Destinations

FROM:
Busuanga Airport - Kiwit Road leading to Various Beaches, Island Destinations, and World War II
Ship Wreck Dive Sites, incl. Bridge, Busuanga, Palawan

CW1: 2.800 lane km ( Construction of Concrete Road )
CW2: 267.12 sq.m. ( Construction of Concrete Bridge )
Allocation: 70,000,000 Php

TO:
Busuanga Airport - Kiwit Road leading to Various
Beaches, Island Destinations, and World War II
Ship Wreck Dive Sites, incl. Bridge, Busuanga , Palawan

CW1: 1.12 lane km ( Construction of Concrete Road )
CW2: 267.12 sq.m. ( Construction of Concrete Bridge )
Allocation: 70,000,000 Php
June 13, 2018 FY - 2018 WIN8F05530 FY - 2018 GAA DOWH Infra Program December 19, 2017 Region IV-B Regional Office IV-B
Local Program

Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects -
Local Roads

FROM:
Road Opening of the Missing Gap,
Dr. Damian Reyes Road ( Boac Side ),
Boac, Marinduque

CW1: 35.18 lane km ( Construction of Concrete Road )
Allocation: 200,000,000 Php

TO:
Road Opening of the Missing Gap,
Dr. Damian Reyes Road ( Boac Side ),
Boac, Marinduque

CW1: 4.007 lane km ( Construction of Concrete Road )
Allocation: 200,000,000 Php
June 13, 2018 2018 310201100199000 GAA FY 2018 January 1, 2018 Region II Isabela 2nd District Engineering Office
OO1: Ensure Safe and Reliable National Road System Network Development Program - Road Widening - Primary Roads
Santiago-Tuguegarao Rd K0411+000 - K0412+105
June 13, 2018 FY - 2018 WIN8F05544 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Regional Office IV-B
Local Program

Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects -
Local Roads and Bridges - Local Roads

FROM:
Rehabilitation/Concreting of Pinagsabangan Beach Road
including Drainage, Oriental Mindoro

CW1: 24.626 lane km ( Construction of Concrete Road )
Allocation: 140,000,000 Php

TO:
Rehabilitation/Concreting of Pinagsabangan Beache Road
including Drainage, Naujan, Oriental Mindoro

CW1: 9.53476 lane km ( Rehabilitation of Paved Road )
Allocation: 140,000,000 Php
June 13, 2018 FY - 2018 WIN8F05098 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Regional Office IV-B
001 - Ensure Safe and Reliable National Road System

Network Development - Road Widening - Secondary Roads

FROM:
Calapan South Rd
K0064+456 - K0064+635,
K0064+824 - K0066+680,
K0066+850 - K0069+060,
K0069+356 - K0071+105,
K0064+(-780) - K0064+(-319),
K0064+(-199) - K0064+325

CW1: 14.13 lane km ( Road Widening )
Allocation: 211,950,000 Php

TO:
Calapan South Rd
K0064+(-780) - K0064+(-320),
K0064+(-200) - K0064+328,
K0064+456 - K0064+638,
K0064+822 - K0066+680,
K0066+868 - KJ0069+053,
K0069+356 - K0071+160,
K0071+273 - K0072+128,
K0072+241 - K0072+445,
K0072+628 - K0073+687,
K0073+794 - K0074+640

CW1: 20.072 lane km ( Road Widening )
Allocation: 211,950,000 Php
K

June 13, 2018 2018 WIN8F05477 R.A. 10964 December 19, 2017 Region VII Regional Office VII
Organizational Outcome 1: Ensure safe and Reliable National Road System, Network Development-Road Widening of Primary Roads, N. Bacalso Ave (Cebu South Rd) incl. ROW-K057+(-815)-K0057+793, K0057+799-K0060+000
June 13, 2018 2018 WIN8F05478 R.A. 10964 December 19, 2017 Region VII Regional Office VII
Organizational Outcome 1: Ensure Safe and Reliable National Road System, Network Development Program -Road Widening -Primary Roads- Cebu North Hagnaya Wharf Rd incl. ROW- K0024+795 - K0025+374, K0025+413 - K0025+298, K0028+090 - K0029+080, K0031+963 - K0032+192.65
June 13, 2018 2018 WIN8F05553 R.A. 10964 December 19, 2017 Region VII Cebu 5th District Engineering Office
ORGANIZATIONAL OUTCOME 1: Ensure Safe and Reliable National Road System, Network Development - Road Widening - Cebu North Hagnaya Wharf Rd - K0050 + 630 - K0051 + 602, K0073+847 - K0074+562, K0076+640 - K0077+044
June 13, 2018 2018 WIN8C02876 R.A. 10964 December 19, 2017 Region VII Cebu 6th District Engineering Office
ORGANIZATIONAL OUTCOME 1: Ensure Safe and Reliable National Road System, Network Development - Road Widening - Tertiary Roads, M Logarta Rd - (S00192CB) Chainage 056.4 - Chainage 1328,
(S00194CB) Chainage 000 - Chainage 411
June 13, 2018 2018 WIN8C02849 R.A. 10964 December 19, 2017 Region VII Cebu 6th District Engineering Office
ORGANIZATIONAL OUTCOME 1: Ensure Safe and Reliable National Road System, Network Development - Road Widening - Tertiary Roads, Canduman-Cebu North Rd - K0011 + (-639) - K0011 + 400