Construction of Mondragon-Silvino Lobos Road (Phase 5), 27.51% completed
The construction of the Mondragon-Silvino Lobos Road (Phase 5) which started last August 31, 2018 has 27.51% work accomplishment as of April 30, 2019.
It is expected to be completed after 420 calendar days under the Monolithic Construction and Concrete Products Inc. and Solid M Construction (Joint Venture).
This P235M road project with a contract ID number 18II0053 is funded under the Office of the Presidential Adviser on Peace Process/Payapa at Masaganang Pamayanan (OPPAP/PAMANA) thru the General Appropriation Act (GAA) of CY 2018.