May 25, 2022 |
FY 2022 GAA |
WIN2G02853 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Southern Mindoro Engineering District Office |
UACS No. : 320102105013000
Project ID : P00621116LZ
002 : Protect Lives and Properties
Flood Management Program - Construction/Rehabilitation of
Flood Mitigation Facilities within major Basins and Principal Rivers
FROM :
Construction of Bansud River Control,
Sta. 0+000 - Sta. 0+560,
Bansud, Oriental Mindoro
Physical Target - CW1 - Construction of Flood Mitigation
Structure - 415.984 l.m.
Allocation - Php 50.00 Million
TO :
Construction of Bansud River Control,
Sta. 0+000 - Sta. 670,
Bansud, Oriental Mindoro
Physical Target - CW1 - Construction of Flood Mitigation
Structure - 670.00 l.m.
Allocation - Php 50.00 Million
|
May 25, 2022 |
FY 2022 GAA |
WIN2G02852 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Southern Mindoro Engineering District Office |
UACS No. : 320102105008000
Project ID : P00621119LZ
002 : Protect Lives and Properties Against Major Floods
Flood Management Program - Construction/Rehabilitation of
Flood Mitigation Facilities within Major River Basins and
Principal Rivers
FROM :
Construction of Baroc River Control,
Brgy. Sta. Brigida Section, Sta. 0+000 - Sta. 0+680,
Mansalay, Oriental Mindoro
Physical Target - CW1 - Construction of Flood Mitigation Structure
415.98 Lane Km
Allocation - Php 50.00 Million
TO :
Construction of Baroc River Control,
Brgy. Sta. Brigida Section, Sta. 0+000 - Sta. 0+770,
Mansalay, Oriental Mindoro
Physical Target - CW1 - Construction of Flood Mitigation Structure
770.0 Lane Km
Allocation - Php 50.00 Million
|
May 25, 2022 |
2022 |
WIN2C03566 |
SARO-BMB-A-22-0003173 |
March 21, 2022 |
Region VIII |
Eastern Samar District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
AS PER GAA/ORIGINAL:
Wright-Taft-Borongan
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 48.485500 M
Structure: 2,748.610 Square meters
EAO P 0.989500 M
Total P 49.475 M
AS MODIFIED:
Wright-Taft-Borongan Rd - K0872 + 808 - K0872 + 858
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 48.485500 M
Structure: 1,741.05 Square meters
EAO P 0.989500 M
Total P 49.475 M |
May 25, 2022 |
FY 2022 GAA |
WIN2G02845 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Southern Mindoro Engineering District Office |
UACS No. : 320102105013000
Project ID : P00621124LZ
002 ; Protect Lives and Properties
Flood Mitigation Program - Construction/Rehabilitation of Flood
Mitigation Facilities within Major Basins and Principal Rivers
FROM :
Construction of Pula River Control,
Brgy. Sto. Nino Section, Sta. 0+000 - Sta. 0+440,
Pinamalaym.an, Oriental Mindoro
Physical Target - CW1 - Construction of Flood Mitigation Structure
415.984 l.m.
Allocation - Php 50.00 Million
TO :
Construction of Pula River Control,
Brgy. Sto. Nino Section, Sta. 0+000 - Sta. 0+468.8,
Pinamalayan, Oriental Mindoro
Physical Target - CW1 - Construction of Flood Mitigation Structure
468.80 l.m.
Allocation - Php 50.00 Million
|
May 25, 2022 |
2022 |
WIN2C03564 |
SR2022-03-007930 |
March 23, 2022 |
Region VIII |
Eastern Samar District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
AS PER GAA/ORIGINAL:
Wright-Taft-Borongan Rd - K0871 + 400 - K0871 + 700
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 91.134600 M
Structure: 5,246.670 Square meters
EAO P 3.305400 M
Total P 94.440 M
AS MODIFIED:
Wright-Taft-Borongan Rd - K0872 + 558 - K0872 + 658
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 91.134600 M
Structure: 3,383.40 Square meters
EAO P 3.305400 M
Total P 94.440 M |
May 25, 2022 |
FY 2022 GAA |
WIN2G02792 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Southern Mindoro Engineering District Office |
UACS No. : 320102105012000
Project ID : P00621123LZ
002 : Protect Lives and Properties
Flood management Program - Construction/Rehabilitation of
Flood Mitigation Facilities within major basins and Principal Rivers
FROM :
Construction of Pula River Control,
Brgy. Pagalagala Section,
Sta. 0+000 - Sta. 0+480
Physical Target - CW1 - Construction of Flood Mitigation Structure
415.98 l.m.
Allocation - Php 50.00 Million
TO :
Construction of Pula River Control,
Brgy. Pagalagala Section,
Sta. 0+000 - Sta. 0+480,
Sta. 0+000 - Sta. 0+086
Physical Target - CW1 - Construction of Flood Mitigation Structure
566.00 l.m.
Allocation - Php 50.00 Million |
May 25, 2022 |
2022 |
WIN2C03562 |
SR2022-03-007938 |
March 23, 2022 |
Region VIII |
Eastern Samar District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
AS PER GAA/ORIGINAL:
Wright-Taft-Borongan Rd - K0871 + 700 - K0872 + 000
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 93.384015 M
Structure: 5,376.170 Square meters
EAO P 3.386985 M
Total P 96.771 M
AS MODIFIED:
Wright-Taft-Borongan Rd - K0872 + 358 - K0872 + 458
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 93.384015 M
Structure: 3,493 Square meters
EAO P 3.386985 M
Total P 96.771 M
|
May 25, 2022 |
2022 |
WIN2E02386 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Regional Office XIII |
UACS No. : 300217100099000
Project ID: P00630445MN
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Interjurisdictional Roads and/or Bridges (or, roads that traverse multiple LGU jurisdictions)
FROM:
Agusan del Norte / Agusan del Sur North - South Lateral Road, (Las Nieves, Agusan del Norte - Kapalong, Davao del Norte), La Paz - Loreto Section, Package 1, Agusan del Sur
Type of Work:
CW1- Construction of Concrete Road
CW2- Construction of Bridge
Physical Target:
CW1- 6.380 Lane Km
CW2- 286.200 Square meters
Allocation:
TOTAL: P 180,000,000
CW1: P 133,392,713
CW2: P 40,307,287
EAO: P 6,300,000
Unit Cost:
CW1: P 20,907,948.75/ Lane Km
CW2: P 140,836.08/ Square meters
TO:
Agusan del Norte / Agusan del Sur North - South Lateral Road, (Las Nieves, Agusan del Norte - Kapalong, Davao del Norte), La Paz - Loreto Section, Package 1, Agusan del Sur
Type of Work:
CW1- Construction of Concrete Road
CW2- Construction of Gravel Road
Physical Target:
CW1- 0.600 Lane Km
CW2- 14.100 Lane Km
Allocation:
TOTAL: P 180,000,000
CW1: P 14,135,628.62
CW2: P 159,564,371.38
EAO: P 6,300,000
Unit Cost:
CW1: P 23,559,381.03/ Lane Km
CW2: P 11,316,622.08/ Lane Km |
May 25, 2022 |
2022 |
WIN2C03567 |
SR2022-03-007943 |
March 23, 2022 |
Region VIII |
Eastern Samar District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
AS PER GAA/ORIGINAL:
Wright-Taft-Borongan Rd - K0872 + 000 - K0872 + 300
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 96.075400 M
Structure: 5,531.110 Square meters
EAO P 3.484600 M
Total P 99.560 M
AS MODIFIED:
Wright-Taft-Borongan Rd - K0872 + 258 - K0872 + 358
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 96.075400 M
Structure: 3,621 Square meters
EAO P 3.484600 M
Total P 99.560 M
|
May 25, 2022 |
2022 |
WIN2C03555 |
SR2022-03-007957 |
March 23, 2022 |
Region VIII |
Eastern Samar District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
AS PER GAA/ORIGINAL:
Wright-Taft-Borongan Rd - K0872 + 300 - K0872 + 600
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 94.241900 M
Structure: 5,425.560 Square meters
EAO P 3.418100 M
Total P 97.660 M
AS MODIFIED:
Wright-Taft-Borongan Rd - K0872 + 458 - K0872 + 558
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 94.241900 M
Structure: 3,534.50 Square meters
EAO P 3.418100 M
Total P 97.660 M |
May 25, 2022 |
2022 |
WIN2C03563 |
SR2022-03-007960 |
March 23, 2022 |
Region VIII |
Eastern Samar District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
AS PER GAA/ORIGINAL:
Wright-Taft-Borongan Rd - K0872 + 600 - K0872 + 900
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 94.782300 M
Structure: 5,456.670 Square meters
EAO P 3.437700 M
Total P 98.220 M
AS MODIFIED:
Wright-Taft-Borongan Rd - K0872 + 658 - K0872 + 758
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 94.782300 M
Structure: 3,559.80 Square meters
EAO P 3.437700 M
Total P 98.220 M |
May 25, 2022 |
2022 |
WIN2E02317 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. : 300215102369000
Project ID: P00630409MN
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
FROM:
Construction of Road in Sudlon Mountain Farm at Barangay Binocaran, Malimono, Surigao del Norte
Type of Work:
CW1- Construction of Concrete Road
Physical Target:
CW1- 0.983 Lane Km
Allocation:
TOTAL: P 10,000,000
CW1: P 9,800,000
EAO: P 200,000
Unit Cost:
CW1: P 9,969,481.18/ Lane Km
TO:
Construction of Road in Sudlon Mountain Farm at Barangay Binocaran, Malimono, Surigao del Norte
Type of Work:
CW1- Construction of Concrete Road
CW2- Construction of Road Slope Protection Structure
Physical Target:
CW1- 0.469 Lane Km
CW1- 960.225 Square meters
Allocation:
TOTAL: P 10,000,000
CW1: P 4,171,661.5
CW2: P 5,628,338.5
EAO: P 200,000
Unit Cost:
CW1: P 8,894,800.64/ Lane Km
CW2: P 5,861.48/ Square meters |
May 25, 2022 |
2022 |
WIN2E02313 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. : 310202101248000
Project ID: P00602517MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Secondary Roads
FROM:
Surigao-Davao Coastal Rd - K1201 + 000 - K1201 + 567
Type of Work:
CW1- Road Widening
Physical Target:
CW1- 1.134 Lane Km
Allocation:
TOTAL: P 31,369,000
CW1: P 30,741,620
EAO: P 627,380
Unit Cost:
CW1: P 27,109,012.35/ Lane Km
TO:
Surigao-Davao Coastal Rd - K1200 + 454.10 - K1201 + 900
Type of Work:
CW1- Road Widening
CW2- Construction of Drainage Structure along Road
Physical Target:
CW1- 1.7979 Lane Km
CW2- 1,139.680 Lineal meters
Allocation:
TOTAL: P 31,369,000
CW1: P 25,425,058.22
CW2: P 5,316,561.78
EAO: P 627,380
Unit Cost:
CW1: P 14,141,530.8/ Lane Km
CW2: P 4,664.96/ Lineal meters |
May 25, 2022 |
FY 2022 GAA |
WIN2G02726 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Southern Mindoro Engineering District Office |
UACS No. : 300201100085000
Project ID : P00635454LZ
CONVERGENCE AND SPECIAL SUPPORT PROGRAMM
FROM ;
Construction/Improvement of Access Roads leading to Airports
(Kalsada Tungo sa Paliparan, Riles at Daungan Program - KATUPARAN), Pinamalayan, Oriental Mindoro
Physical Target - CW1 - Construction of Concrete Bridge
230.955 sq.m.
Allocation - Php 24.264 Million
TO :
Construction/Improvement of Access Roads leading to Airports -
(Kalsada Tungo sa Paliparan, Riles at Daungan Program -
KATUPARAN0, Pinamalayan, Oriental Mindoro
Physical Target - CW1 - Construction of Concrete Bridge :
73 sq.m.
CW2 - Rehabilitation of Paved Road :
0.7344 lane km
Allocation - Php 24.264 Million
73 sq.m.
|
May 25, 2022 |
2022 |
WIN2C03557 |
SR2022-03-008098 |
March 23, 2022 |
Region VIII |
Eastern Samar District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
AS PER GAA/ORIGINAL:
Arteche-Jipapad-Las Navas-Rawis Rd
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 89.630165 M
Structure: 5,160.060 Square meters
EAO P 3.250835 M
Total P 92.881 M
AS MODIFIED:
Arteche-Jipapad-Las Navas-Rawis Rd- (S00137SM) K0968 + 985 – K0970 + 060, (S00174SM) K0974 + 442 – K0977 + 428, (S00189SM) K0978 + 083 – K0979 + 437
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 89.630165 M
Structure: 11,785.20 Square meters
EAO P 3.250835 M
Total P 92.881 M
|
May 25, 2022 |
2022 |
WIN2C03565 |
GAA FY 2022 |
January 2, 2022 |
Region VIII |
Eastern Samar District Engineering Office |
Convergence and Special Support Program
Convergence and Special Support - Construction/ Improvement of Access Roads leading to Declared Tourism Destinations
AS PER GAA/ORIGINAL:
Access Road leading to Tourist Destination from Borongan Airport to Hilangagan Beach, Borongan City, Eastern Samar
Physical Target: Allocation:
CW1-Construction of Concrete Road P 16.599240 M
: 1.129 Lane Km
EAO P 0.338760 M
Total P 16.938 M
AS MODIFIED:
Access Road leading to Tourist Destination from Borongan Airport to Hilangagan Beach, Borongan City, Eastern Samar
Physical Target: Allocation:
CW1-Construction of Concrete Road P 16.599240 M
: 0.58 Lane Km
EAO P 0.338760 M
Total P 16.938 M
|
May 24, 2022 |
FY 2022 GAA |
WIN2G02906 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Southern Mindoro Engineering District Office |
UACS No. : 310202101135000
Project ID : P00606216LZ
001 : Ensure Safe and Reliable National Road System
Network Development - Road Widening - Secondary Roads
FROM :
Calapan South Road
K0140+000 - K0140+405
Physical Target - CW1 - Road Widening - 0.810 Lane Km
Allocation - Php 12.00 Million
TO :
Calapan South Road
K0140+000 - K0140+283
Physical Target - CW1 - Road Widening - 0.566 Lane Km
Allocation - Php 12.00 Million |
May 24, 2022 |
FY 2022 GAA |
WIN2G02683 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Southern Mindoro Engineering District Office |
UACS No. : 310202101134000
Project ID : P00606227LZ
001 : Ensure Safe and Reliable National Road System
Network Development - Road Widening - Secondary Roads
FROM :
Calapan South Road
K0138+458 - K0138+910
Physical Target - CW1 - Road Widening - 0.904 Lane Km
Allocation - Php 15.00 Million
TO :
Calapan South Road
K0138+458 - K0138+908.70
Physical Target - CW1 - Road Widening - 0.9014 Lane Km
Allocation - Php 15.00 Million |
May 24, 2022 |
FY 2022 GAA |
WIN2G02747 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Southern Mindoro Engineering District Office |
UACS No. : 310202101136000
Project ID : P00606268LZ
001 : Ensure Safe and Reliable national Road System
Network Development - Road Widening - Secondary Roads
FROM :
Calapan South Road
K0145+637 - K0146+750
Physical Target - CW1 - Road Widening : 2.326 Lane Km
Allocation - Php 38.00 Million
TO :
Calapan South Road
K0145+637 - K0146+530
Physical Target - CW1 - Road Widening : 1.855 Lane Km
Allocation - Php 38.00 Million |
May 24, 2022 |
2022 |
WIN2C03566 |
GAA FY 2022 |
January 3, 2022 |
Region VIII |
Leyte 5th District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Primary Roads
AS PER GAA/ORIGINAL:
Tacloban-Baybay South Rd - K0998 + 400 - K0998 + 700
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 19.600 M
Structure: 1,111.10 Square meters
EAO P 0.400 M
Total P 20.00 M
AS MODIFIED:
Tacloban-Baybay South Rd - K0996 + 160 - K0996 + 200, K0998 + 325 - K0998 + 425
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 19.600 M
Structure: 550 Square meters
EAO P 0.400 M
Total P 20.00 M
|
May 24, 2022 |
FY 2022 GAA |
WIN2G02992 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Southern Mindoro Engineering District Office |
UACS No. : 310108100893000
Project ID : P00611271LZ
001 : Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction of Roads with
Slips, Slope Collapse, and Landslide - Secondary Roads
FROM :
Calapan South Road
K0192+100 - K0192+151,
K0192+288 - K0192+334,
K0192+362 - K0192+415
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 966.66 sq. m.
Allocation - Php 17.40 Million
TO :
Calapan South Road
K0192+100.0 - K0192+150,
K0192+280.0 - K0192+332,
K0192+362.2 - K0192+415
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 1030.97 sq.m.
Allocation - Php 17.40 Million
|
May 24, 2022 |
2022 |
WIN2C03570 |
SARO-BMB-A-22-0003170 |
March 23, 2022 |
Region VIII |
Leyte 5th District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Primary Roads
AS PER GAA/ORIGINAL:
Daang Maharlika (LT) - K0996 + 900 - K0997 + 100, K0997 + 200 - K0997 + 400
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 96.500 M
Structure: 5,555.560 Square meters
EAO P 3.500 M
Total P 100.00 M
AS MODIFIED:
Daang Maharlika (LT) - K0979 + 915 - K0979 + 985
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 96.500 M
Structure: 2,534.00 Square meters
EAO P 3.500 M
Total P 100.00 M |
May 24, 2022 |
2022 |
WIN2C03559 |
SARO-BMB-A-22-0003177 |
March 21, 2022 |
Region VIII |
Leyte 5th District Engineering Office |
Convergence and Special Support Program
Construction/ Rehabilitation of Water Supply/ Septage and Sewerage/ Rainwater Collector System - Water Supply
AS PER GAA/ORIGINAL:
Construction of Level III Water Supply System, Abuyog, Leyte
Physical Target: Allocation:
CW1-Construction of Water Supply Systems P 49.00 M
: 1.00 Number of Water Supply Systems
EAO P 1.00 M
Total P 50.00 M
AS MODIFIED:
Construction of Level III Water Supply System, Abuyog, Leyte
Physical Target: Allocation:
CW1-Construction of Water Supply Systems P 49.00 M
: 15.00 Number of Water Supply Systems
EAO P 1.00 M
Total P 50.00 |
May 24, 2022 |
2022 |
WIN2C03558 |
SARO-BMB-A-22-0003177 |
March 21, 2022 |
Region VIII |
Leyte 5th District Engineering Office |
Convergence and Special Support Program
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/Strategic Public Buildings/Facilities
AS PER GAA/ORIGINAL:
Construction (Completion) of Baybay City Boardwalk, Baybay City Reclamation Area, Poblacion, Baybay City, Leyte
Physical Target: Allocation:
CW1-Construction of Concrete Road P 49.00 M
: 4.262 Lane Km
EAO P 1.00 M
Total P 50.00 M
AS MODIFIED:
Construction (Completion) of Baybay City Boardwalk, Baybay City Reclamation Area, Poblacion, Baybay City, Leyte
Physical Target: Allocation:
CW1-Construction of Other Facilities P 49.00 M
: 5.00 Number of Facilities
EAO P 1.00 M
Total P 50.00 M
|
May 24, 2022 |
2022 |
WIN2F06366 |
SARO-BMB-A-22-0002929 |
March 21, 2022 |
Cordillera Administrative Region |
Benguet 1st District Engineering Office |
From: Construction of Cacuduran Flood Control, Nawal, Bokod, Benguet;
Physical Target: 176.929 Lineal Meters;
Allocation: Php 20,000,000.000
To: Construction of Cacuduran Flood Control, Nawal, Bokod, Benguet;
Physical Target: 323.000 Lineal Meters;
Allocation: Php 20,000,000.000
|
May 24, 2022 |
2022 |
WIN2F06367 |
SARO-BMB-A-22-0002929 |
March 21, 2022 |
Cordillera Administrative Region |
Benguet 1st District Engineering Office |
From: Construction of Poblacion Flood Control, Bokod, Benguet;
Physical Target: 88.464 Lineal Meters;
Allocation: Php 10,000,000.000
To: Construction of Poblacion Flood Control, Bokod, Benguet;
Physical Target: 169.000 Lineal Meters;
Allocation: Php 10,000,000.000
|
May 24, 2022 |
2022 |
WIN2C03568 |
SARO-BMB-A-22-0003173 |
March 21, 2022 |
Region VIII |
Eastern Samar District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
AS PER GAA/ORIGINAL:
Wright-Taft-Borongan Rd - K0867 + 150 - K0867 + 450
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 48.486480 M
Structure: 2,748.670 Square meters
EAO P 0.989520 M
Total P 49.476 M
AS MODIFIED:
Wright-Taft-Borongan Rd - K0872 + 758 - K0872 + 808
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 48.486480 M
Structure: 1,738 Square meters
EAO P 0.989520 M
Total P 49.476 M |
May 24, 2022 |
FY 2022 |
WIN2C03556 |
UACS No. 320101107911000 |
March 21, 2022 |
National Capital Region |
Quezon City 2nd Engineering District Office |
As per GAA/Original
UACS No. 320101107911000
Project ID.: P00621436LZ
OO2: Protect Lives and Properties Against Major Floods
Flood Management – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Rehabilitation of Flood Control Structure, Laguna Creek, Barangay Kristong Hari, Quezon City
Physical Target: CW1- Rehabilitation/Major Repair of Flood Control Structure – 412.53 lineal meters
Unit Cost = P 71,267,540/lineal meters
Allocation = P 29,400,000
EAO = P 600,000
Total = P 30,000,000
As Modified
OO2: Protect Lives and Properties Against Major Floods
Flood Management – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Rehabilitation of Flood Control Structure, Lagarian Creek, Barangay Kristong Hari, Quezon City
Physical Target: CW1- Rehabilitation/Major Repair of Flood Control Structure – 370.00 lineal meters
Unit Cost = P 79,459,460/lineal meters
Allocation = P 29,400,000
EAO = P 600,000
Total = P 30,000,000
WIN2C03556
|
May 24, 2022 |
FY 2022 |
WIN2C03569 |
UACS No. 310102100792000 |
March 1, 2022 |
National Capital Region |
Quezon City 1st Engineering District Office |
As per GAA/Original
UACS No. 310102100792000
Project ID.: P00610107LZ
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Secondary Roads
Fairview Ave – K0024+820 – K0023+300
Physical Target: CW1- Preventive Maintenance of Road: Asphalt Overlay - 13.16 lane km
Unit Cost = P 7,332,820/lane km
Allocation = P 96,500,000
EAO = P 3,500,000
Total = P 100,000,000
As Modified
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Secondary Roads
Fairview Ave – K0024+(-550) – K0023+300
Physical Target: CW1- Preventive Maintenance of Road: Asphalt Overlay – 6.94 lane km
Unit Cost = P 13,904,900/lane km
Allocation = P 96,500,000
EAO = P 3,500,000
Total = P 100,000,000
WIN2C03569
|
May 24, 2022 |
FY 2022 |
WIN2C03572 |
UACS No. 310103100854000 |
March 1, 2022 |
National Capital Region |
Quezon City 1st Engineering District Office |
As per GAA/Original
UACS No. 310103100854000
Project ID.: P00603593LZ
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Tertiary Roads
Dapitan St – K0006+(-326) – K0006+225
Physical Target: CW1- Preventive Maintenance of Road: Asphalt Overlay - 1.476 lane km
Unit Cost = P 2,433,400/lane km
Allocation = P 3,591,700
EAO = P 73,300
Total = P 3,665,000
As Modified
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Tertiary Roads
Dapitan St – K0006+(-326) – K0006+225
Physical Target: CW1- Preventive Maintenance of Road: Concrete Reblocking – 0.177 lane km
Unit Cost = P 20,290,430/lane km
Allocation = P 3,591,700
EAO = P 73,300
Total = P 3,665,000
WIN2C03572
|
May 24, 2022 |
FY 2022 |
WIN2C03571 |
UACS No. 310103100778000 |
March 1, 2022 |
National Capital Region |
Quezon City 1st Engineering District Office |
As per GAA/Original
UACS No. 310103100778000
Project ID.: P00610134LZ
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Tertiary Roads
Visayas Ave – K0013+1068 – K0014+(-399), K0013+900 – K0014+000
Physical Target: CW1- Preventive Maintenance of Road: Asphalt Overlay - 13.431 lane km
Unit Cost = P 7,184,870/lane km
Allocation = P 96,500,000
EAO = P 3,500,000
Total = P 100,000,000
As Modified
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Tertiary Roads
Visayas Ave – K0012+(-079) – K0014+328
Physical Target: CW1- Preventive Maintenance of Road: Asphalt Overlay - 6.756 lane km
Unit Cost = P 14,283,490/lane km
Allocation = P 96,500,000
EAO = P 3,500,000
Total = P 100,000,000
WIN2C03571
|
May 24, 2022 |
FY 2022 |
WIN2C03573 |
UACS No. 310101100603000 |
March 1, 2022 |
National Capital Region |
Quezon City 1st Engineering District Office |
As per GAA/Original
UACS No. 310101100603000
Project ID.: P00603595LZ
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Primary Roads
Cloverleaf (S05131LZ) – Chainage 0 – Chainage 234
Physical Target: CW1- Preventive Maintenance of Road: Asphalt Overlay - 0.47 lane km
Unit Cost = P 7,800,380/lane km
Allocation = P 3,666,180
EAO = P 74,820
Total = P 3,741,000
As Modified
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Primary Roads
Cloverleaf (S05131LZ) – Chainage 0 – Chainage 234
Physical Target: CW1- Preventive Maintenance of Road: Concrete Reblocking - 0.184 lane km
Unit Cost = P 19,923,060/lane km
Allocation = P 3,666,180
EAO = P 74,820
Total = P 3,741,000
WIN2C03573
|
May 24, 2022 |
2022 |
WIN2F06258 |
SARO-BMB-A-22-0002937 |
March 21, 2022 |
Cordillera Administrative Region |
Ifugao 1st District Engineering Office |
From: Kiangan-Tinoc-Buguias Rd - K0341+093 - K0341+114, K0341+133 - K0341+163, K0341+427 - K0341+445, K0341+488 - K0341+507, K0342+583 - K0342+621, K0342+736 - K0342+760, K0344+724 - K0344+776, K0348+122 - K0348+163, K0348+313 - K0348+335, K0348+618 - K0348+638, K0350+888 - K0350+919, K0351+860 - K0351+894, K0352+333 - K0352+414, K0355+703 - K0355+733, K0358+460 - K0358+520;
Physical Target: 3,023.000 Square Meters;
Allocation: Php 30,230,000.000
To: Kiangan-Tinoc-Buguias Rd - K0341+093 - K0341+114, K0341+427 - K0341+445, K0341+488 - K0341+507, K0348+122 - K0348+163, K0348+313 - K0348+335, K0348+618 - K0348+638, K0350+888 - K0350+919, K0355+703 - K0355+733, K0358+460 - K0358+520;
Physical Target: 2,098.700 Square Meters;
Allocation: Php 30,230,000.000
|
May 23, 2022 |
FY 2022 GAA |
WIN2G02869 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Southern Mindoro Engineering District Office |
UACS No. : 310106100772000
Project ID : P00603931LZ
001 : Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction/Upgrading
of Damaged Paved Roads - Tertiary Roads
FROM :
Calapan South Road
K0187+398 - K0187+740,
K0187+846 - K0188+000
Physical Target - CW1 - Asset Preservation - Rehabilitation of
Paved Road : 0.992 Lane Km
Allocation - Php 18.00 Million
TO :
Calapan South Road
K0187+380 - K0187+501.60
Physical Target - CW1 - Asset Preservation - Rehabilitation of
Paved Road : 0.243 Lane Km
Allocation - Php 18.00 Million |
May 23, 2022 |
2022 |
WIN2F06347 |
FY 2022 GAA |
December 30, 2021 |
Region III |
Pampanga 1st District Engineering Office |
Asset Preservation Program – Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Primary Roads
Jose Abad Santos Ave (JASA) - K0075+279 - K0075+596
|
May 23, 2022 |
2022 |
WIN2F06344 |
FY 2022 GAA |
December 30, 2021 |
Region III |
Pampanga 1st District Engineering Office |
Network Development Program - Road Widening - Primary Roads
Jose Abad Santos Ave (JASA) - K0072+465 - K0073+346, K0082+916 - K0084+540 |
May 23, 2022 |
FY 2022 GAA |
WIN2G02842 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Southern Mindoro Engineering District Office |
UACS No. : 310111100429000
Project ID : P00604078LZ
001 : Ensure Safe and Reliable National Road System
Asset Preservation - Construction/Upgrading/Rehabilitation of
Drainage along national Roads - Secondary Roads
FROM :
Calapan South Road
K0070+181 - K0071+184,
K0071+236 - K0072+004
Physical Target - CW1 - Construction of Drainage Structure
along Road : 3,572.00 l.m.
Allocation - Php 50.00 Million
TO :
Calapan South Road
K0069+476 - K0071+167.10,
K0071+300 - K071+775
Physical Target - CW1 - Construction of Drainage Structure
along Road : 3,638.70 l.m.
Allocation - Php 50.00 Million
|
May 23, 2022 |
FY 2022 GAA |
WIN2G02716 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Southern Mindoro Engineering District Office |
UACS No. : 310111100428000
Project ID : P00604079LZ
001 : Ensure Safe and Reliable National Road System
Asset Preservation - Construction/Upgrading/Rehabilitation of Drainage along national Roads - Secondary Roads
FROM :
Calapan South Road
K0064+(-249) - K0064+950,
K0064+(-289) - K0064+(-269)
Physical Target - CW1 - Construction of Drainage Structure
along Road - 2,438.00 l.m.
Allocation - Php 35.00 Million
TO :
Calapan South Road
K0064+(-249) - K0064+833
Physical Target - CW1 - Construction of Drainage Structure
along Road - 1,082.00 l.m.
Allocation - Php 35.00 Million |
May 23, 2022 |
2022 |
320101107354000 |
GAA FY 2022 |
January 3, 2022 |
Region II |
Isabela 2nd District Engineering Office |
Organizational Outcome 2: Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems - Construction of Siffu River Flood Control Project (Sinait Section), Quirino, Isabela |
May 23, 2022 |
2022 |
320101107355000 |
GAA FY 2022 |
January 3, 2022 |
Region II |
Isabela 2nd District Engineering Office |
Organizational Outcome 2: Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems - Construction of Siffu River Flood Control Project (Rang-Ayan Section), Roxas, Isabela |
May 23, 2022 |
2022 |
320101107358000 |
GAA FY 2022 |
January 3, 2022 |
Region II |
Isabela 2nd District Engineering Office |
Organizational Outcome 2: Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems - Construction of Mallig River Flood Control Project (Holy Friday Section), Mallig, Isabela |
May 23, 2022 |
2022 |
320101107359000 |
GAA FY 2022 |
January 3, 2022 |
Region II |
Isabela 2nd District Engineering Office |
Organizational Outcome 2: Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems - Construction of Mallig River Flood Control Project (Olango Section), Mallig, Isabela |
May 23, 2022 |
2022 |
310201100972000 |
GAA FY 2022 |
January 3, 2022 |
Region II |
Isabela 4th District Engineering Office |
Organizational Outcome 1: Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Primary Roads - Daang Maharlika (LZ) - K0309+(-496) - K0309+(-413), K0309+(-423) - K0309+(-284), K0323+200 - K0323+505 |
May 23, 2022 |
2022 |
320101107356000 |
GAA FY 2022 |
January 3, 2022 |
Region II |
Isabela 2nd District Engineering Office |
Organizational Outcome 2: Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems - Construction of Siffu River Flood Control Project (San Luis Section), Roxas, Isabela |
May 23, 2022 |
2022 |
320101107357000 |
GAA FY 2022 |
January 3, 2022 |
Region II |
Isabela 2nd District Engineering Office |
Organizational Outcome 2: Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems - Construction of Mallig River Flood Control Project (Luna Section), Quirino, Isabela |
May 23, 2022 |
2022 |
310112100297000 |
GAA FY 2022 |
January 3, 2022 |
Region II |
Batanes District Engineering Office |
OO1: Ensure Safe and Reliable National Road System - Asset Preservation Program - Construction/ Upgrading/ Rehabilitation of Drainage along National Roads - Tertiary Roads - San Vicente-Savidug-Chavayan-Sumnanga-Nakanmuan Rd- (S00003ST) K0020+670 - K0020+782 |
May 23, 2022 |
FY 2022 GAA |
WIN2G02851 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Southern Mindoro Engineering District Office |
UACS No. : 310109100859000
Project ID : p00604404Lz
001 : Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction of Roads
with Slips, Slope Collapse, and Landslide - Tertiary Roads
FROM :
Calapan South Road
K0184+902 - K0184+948
Physical Target - CW1 - Construction of Road Slope Protection
Structure - 366.67 sq.m.
Allocation - Php 5.50 Million
TO :
Calapan South Road
K0184+902 - K0184+966.80
Physical Target - CW1 - Construction of Road Slope Protection
Structure - 339.55 sq.m.
Allocation - Php 5.50 Million
|
May 23, 2022 |
FY 2022 GAA |
WIN2G02871 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Southern Mindoro Engineering District Office |
UACS No. : 310109100860000
Project ID : P00604405LZ
001 : Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction of Roads
with Slips, Slope Collapse, and Landslide - Tertiary Roads
FROM :
Calapan South Road
K0187+348 - K0187+505
Physical Target - CW1 - Construction of Road Slope Protection
Structure - 1886.67 sq. m.
Allocation - Php 28.300 million
TO :
Calapan South Road
K0187+690 - K0187+934.8
Physical Target - CW1 - Construction of Road Slope Protection
Structure - 1282.75 sq.m.
Allocation - Php 28.30 Million |
May 21, 2022 |
FY 2022 |
WIN2E02315 |
310204101795000 |
May 4, 2022 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 310204101795000
Project ID: P00604221MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Bypass and Diversion Roads
Bagalupa-Labangan-Gubang Road, Zamboanga del Sur
CW1- Construction of Concrete Road
Physical Target: 3.8719 Lane km
Unit Cost: ₱ 12,526,149.95/Lane km
ROW- Right-Of-Way Acquisition
Physical Target: 5,807.85 sq.m.
Unit Cost: ₱ 86.09/sq.m.
EAO: ₱ 1,000,000.00
Total Allocation: ₱ 50,000,000.00 |
May 21, 2022 |
FY 2022 |
WIN2E02316 |
310204101799000 |
May 4, 2022 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 310204101799000
Project ID: P00604222MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Bypass and Diversion Roads
NRJ Molave-Tambulig-Don Victoriano Diversion Road, Zamboanga del Sur
CW1- Construction of Concrete Road
Physical Target: 3.575 Lane km
Unit Cost: ₱ 13,706,293.71/Lane km
EAO: ₱ 1,000,000.00
Total Allocation: ₱ 50,000,000.00 |
May 21, 2022 |
FY 2022 |
WIN2E02302 |
300215102015000 |
May 4, 2022 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 300215102015000
Project ID : P00630163MN
Convergence and Special Support Program - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/Facilities
Construction of Alang-Alang-Lower Tiparak-Tungawan By-Pass Road, Zamboanga del Sur
CW1 - Construction of Concrete Road
Physical Target: 1.064 Lane km
Unit Cost : P 18,421,052.63/Lane km
EAO : P 400,000.00
Allocation : P 20,000,000.00 |
May 21, 2022 |
FY 2022 |
WIN2E02180 |
310104100360000 |
March 21, 2022 |
Region IX |
Zamboanga del Norte 1st District Engineering Office |
UACS No. 310104100360000
Project ID: P00601149MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Primary Roads
Dipolog-Sindangan-Liloy Rd (S01057MN) K1861 + 698.00 - K1863 + 556.00, K1863 + 834.84 - K1865 + 911.66, K1865 + 952.00 - K1866 + 867.23
CW1 : Reconstruction to Concrete Pavement
Physical Target: 9.58904 Lane km
Unit Cost : P 8,273.77/Lane km
EAO : P 2,877,525.00
Allocation : P 82,215,000.00 |
May 20, 2022 |
FY 2022 GAA |
WIN2G02827 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Palawan 2nd District Engineering Office |
UACS No. : 3201011081820000
Project ID : P00620660LZ
002 : Protect Lives and Properties
Flood Management - Construction/maintenance of Flood
Mitigation Structures and Drainage Systems
FROM :
Construction of Marangas River Flood Control Structure,
Sta. 0+000 - Sta. 1+080,
Bataraza, Palawan
Physical Target - CW1 - Construction of Flood Mitigation Structure
610 LM
Allocation - Php 30.00 Million
TO :
Construction of Marangas River Flood Control Structure,
Sta. 0+800 - Sta. 1+250, Left Bank
Sta. 1+080 - Sta.1+240
Bataraza, Palawan
Physical Target - CW1 - Construction of Flood Mitigation Structure
610.0 LM
Allocation - Php 30.00 Million |
May 20, 2022 |
FY 2022 GAA |
WIN2G02789 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Palawan 2nd District Engineering Office |
UACS No. : 3201011081830000
Project ID : P00620661LZ
002 : Protect Lives and Properties Against Major Floods
Flood Management - Construction/Maintenance of Flood
Mitigation Structures and Drainage Systems
FROM :
Construction of Narra Poblacion Flood Control,
Sta. 0+000 - Sta. 2+000,
Narra, Palawan
Physical Target - CW1 - Construction of Flood Mitigation Structure
1,790 LM
Allocation - Php 48.00 Million
TO :
Construction of Narra Poblacion Flood Control,
Sta. 0+000 - Sta. 1+790
Narra, Palawan
Physical Target - CW1 - Construction of Flood Mitigation Structure
1,790 LM
Allocation - 48.00 Million |
May 20, 2022 |
2022 |
WIN2E02351 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Agusan del Norte District Engineering Office |
UACS No. : 310107100437000
Project ID: P00601522MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Asset Preservation Program - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads
FROM:
Daang Maharlika (Surigao-Agusan Sect) - K1169 + 793 - K1169 + 875
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 2,310.50 Square meters
Allocation:
TOTAL: P 23,105,000
CW1: P 22,642,900
EAO: P 462,100
Unit Cost:
CW1: P 9,800/ Square meters
TO:
Daang Maharlika (Surigao-Agusan Sect) - K1169 + 793 - K1169 + 858
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 984.500 Square meters
Allocation:
TOTAL: P 23,105,000
CW1: P 22,642,900
EAO: P 462,100
Unit Cost:
CW1: P 22,999.39055/ Square meters
|
May 20, 2022 |
2022 |
WIN2E02349 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. : 300215100607000
Project ID: P00630145MN
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
FROM:
Construction of Road, Barangay Camp Eduard, Alegria, Surigao del Norte
Type of Work:
CW1- Construction of Concrete Road
Physical Target:
CW1- 7.864 Lane Km
Allocation:
TOTAL: P 80,000,000
CW1: P 77,200,000
EAO: P 2,800,000
Unit Cost:
CW1: P 9,816,887.08/ Lane Km
TO:
Construction of Road, Barangay Camp Eduard, Alegria, Surigao del Norte
Type of Work:
CW1- Construction of Concrete Road
CW2- Construction of Drainage Structure along Road
Physical Target:
CW1- 4.2536 Lane Km
CW2- 3,034.38 Lineal meters
Allocation:
TOTAL: P 80,000,000
CW1: P 62,067,108.74
CW2: P 15,132,891.26
EAO: P 2,800,000
Unit Cost:
CW1: P 14,591,665.59/ Lane Km
CW2: P 4,987.14/ Lineal meters |
May 20, 2022 |
2022 |
WIN2E02199 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Surigao del Sur 2nd District Engineering Office |
UACS No. : 300219100392000
Project ID: P00632322MN
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities
FROM:
Rehabilitation and Road Slope Protection Structures along Bislig-Trento Road, K1445+100 -K1445+300
Type of Work:
CW1- Rehabilitation / Major Repair of Slope Protection Structure
Physical Target:
CW1- 4,295.082 Square meters
Allocation:
TOTAL: P 100,000,000
CW1: P 96,500,000
EAO: P 3,500,000
Unit Cost:
CW1: P 22,467.56/ Square meters
TO:
Rehabilitation and Road Slope Protection Structures along Bislig-Trento Road, K1508+510 - K1508+750
Type of Work:
CW1- Rehabilitation / Major Repair of Slope Protection Structure
Physical Target:
CW1- 10,393.78 Square meters
Allocation:
TOTAL: P 100,000,000
CW1: P 96,500,000
EAO: P 3,500,000
Unit Cost:
CW1: P 9,824.39/ Square meters |
May 20, 2022 |
FY 2022 GAA |
WIN2G02910 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Palawan 2nd District Engineering Office |
UACS No. : 320101108185000
Project ID : P00620663LZ
002 : Protect Lives and Properties Against Major Floods
Flood Management - Construction/maintenance of Flood
Mitigation Structures and Drainage Systems
FROM :
Construction of Ransang River Flood Control Structure
Sta. 0+000 - Sta. 0+300,
Rizal, Palawan
Physical Target - CW1 - Construction of Flood Mitigation Structures
233.50 LM
Allocation - Php 20.00 Million
TO :
Construction of Ransang Flood Control Structure
Left Bank Sta. 0+000 - Sta. 0+083 Downstream,
Sta. 0+102.20 - Sta. 0+253 Upstream,
Rizal, Palawan\
Physical Target - CW1 - Construction of Flood Mitigation Structure
233.50 LM
Allocation - Php 20.00 Million
|
May 20, 2022 |
FY 2022 GAA |
WIN2G02824 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Palawan 2nd District Engineering Office |
UACS No. : 320101108186000
Project ID : P00620664LZ
002 : Protect Lives and Properties Against Major Floods
Flood Management - Construction/Maintenance of Flood
Mitigation Structures and Drainage System
FROM :
Construction of Salogon River Flood Control Structure
Sta. 0+000 - Sta. 0+450
Brooke's Point, Palawan
Physical Target - CW1 - Construction of Flood Mitigation Structure
640.00 LM
Allocation - Php 40.00 Million
TO :
Construction of Salogon River Flood Control Structure,
Sta. 0+000 - Sta. 0+520 Right Bank,
Sta. 0+360 - Sta. 0+480 Left Bank,
Brooke's Point, Palawan
Physical Target - CW1 - Construction of Flood Mitigation Structure
640 LM
Allocation - Php 40.00 Million |
May 20, 2022 |
FY 2022 GAA |
WIN2G06274 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Palawan 2nd District Engineering Office |
UACS No. : 320101108188000
Project ID : P00620666LZ
002 : Protect Lives and Properties Against Major Floods
Flood management - Construction/Maintenance of Flood
Mitigation Structures and Drainage Systems
FROM :
Construction of Tagusao River Flood Control Structure,
Sta. 0+100 - Sta. 0+400,
Quezon, Palawan
Physical Target - CW1 - Construction of Flood Mitigation Structure
550.0 LM
Allocation - Php 30.00 Million
TO :
Construction of Tagusao River Flood Control Structure,
Sta. 0+070 - Sta. 0+620 Right Riverbank,
Quezon Palawan
Physical Target - CW1 - Construction of Flood Mitigation Structure
550.0 LM
Allocation - Php 30.00 Million |
May 20, 2022 |
FY 2022 GAA |
WIN2G02932 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Palawan 2nd District Engineering Office |
UACS No. : 320102104996000
Project ID : P00621114LZ
002: Protect Lives and Properties against Major Floods
Flood Management - Construction/Rehabilitation of Flood Mitigation
Facilities along Major River Basins and Principal Rivers
FROM :
Construction of Culasian River Flood Control Structure,
Sta. 0+000 - Sta. 0+152
Rizal, Palawan, Palawan
Physical Target - CW1 - Construction of Flood Mitigation Structure
82.0 LM
Allocation - Php 10.00 Million
TO:
Construction of Culasian River Flood Control Structure,
Sat. 0+000 - Sta. 0+082
Rizal, Palawan
Physical Target - CW1 - Construction of Flood Mitigation Structure
82.0 LM
Allocation - Php 10.00 Million |
May 20, 2022 |
FY 2022 GAA |
WIN2G02933 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Palawan 2nd District Engineering Office |
UACS No. : 320102104997000
Project ID : P00621115LZ
002 : Protect Lives and Properties Against Major Floods
Flood Management - Construction/Rehabilitation of Flood Mitigation
Facilities along Major River Basins and Principal Rivers
FROM :
Construction of Panitian River Flood Control Structure,
Sta. 0+000 - Sta. 0+250
Quezon, Palawan
Physical Target - CW1 - Construction of Flood Mitigation Structure
262.0 LM
Allocation - Php 20.00 Million
TO :
Construction of Panitian River Flood Control Structure
Sta. 0+000 - Sta. 0+131,
Quezon, Palawan
Physical Target - CW1 - Construction of Flood Mitigation Structure
262.0 LM
Allocation - Php 20.00 Million |
May 20, 2022 |
FY 2022 GAA |
WIN2Go2903 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Palawan 2nd District Engineering Office |
UACS No. : 300214100243000
Project ID : P00635991LZ
CONVERGENCE AND SPECIAL SUPPORT PROGRAM
Special Road Fund - Motor Vehicle Users Charge (MVUC)
as per R.A. 11239
FROM :
Preventive Maintenance (Asphalt Overlay) along
Quezon - Aramaywan Rd
K0160+000 - K0160+859,
K0166+000 - K0167+000,
K0172+229 - K0172+548
Physical Target - CW1 - Preventive maintenance of Road :
Asphlat Overlay : 4.478 Lane Km
Allocation - Php 43.687 Million
TO :
Preventive Maintenance (Asphalt Overlay) along
Quezon - Aramaywan Rd\
K0156+504 - K0158+662
Physical Target - CW1 - Preventive Maintenance of Road :
Asphalt Overlay : 4.478Lane Km
Allocation - Php 43.687 Million |
May 19, 2022 |
FY 2022 |
WIN2E02312 |
310204101141000 |
March 23, 2022 |
Region IX |
Regional Office IX |
UACS No. 310204101141000
Project ID: P00604246MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Bypass and Diversion Roads
Airport - Turno - Sinaman Bypass Road, Zamboanga del Norte
CW1- Road Widening
Physical Target: 4.91 Lane Km
Unit Cost: ₱ 20,061,099.80/Lane km
ROW- Right-Of-Way Acquisition
Physical Target: 20,000.00 sq.m.
Unit Cost: ₱ 382.50/sq.m.
EAO: ₱ 3,850,000.00
Allocation: ₱ 110,000,000.00 |
May 19, 2022 |
FY 2022 |
WIN2E02318 |
320101107683000 |
March 22, 2022 |
Region IX |
Regional Office IX |
UACS No. 320101107683000
Project ID: P00620007MN
OO2: Protect Lives and Properties - Flood Management - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control Structure along Panganuran River, Gutalac, Zamboanga del Norte (at Panganuran Br. Section along Liloy - Siocon Road (S01146MN))
CW1- Construction of Flood Mitigation Structure
Physical Target: 567.610 Lineal Meters
Unit Cost: ₱ 171,425.73/Lineal Meters
EAO: ₱ 3,535,000.00
Excess: ₱ 162,042.35
Allocation: ₱ 101,000,000.00 |
May 19, 2022 |
FY 2022 GAA |
WIN2G02660 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Mindoro Occidental District Engineering Office |
UACS No. : 320102104987000
Project ID : P00621103LZ
Construction/Rehabilitation of Flood Mitigation Facilities
within major River basins and principal Rivers
Construction of Flood Control Structure
FROM :
Construction of Flood Control Structure along
Anahawin River, Sta. 0+000 - Sta. 0+473,
Brgy. Poblacion, Calintaan, Occidental Mindoro
Physical Target - CW1 - Construction of Flood Mitigation Structure
315.0 lineal meter
Allocation - Php 45.00 Million
TO :
Construction of Flood Control Structure along
Anahawin River, Sta. 0+000 - Sta. 0+315,
Brgy. Poblacion, Calintaan, Occidental Mindoro
Physical Target - CW1 - Construction of Flood Mitigation Structure
315.00 lineal meter
Allocation - Php 45.00 Million
|
May 19, 2022 |
FY 2022 |
WIN2E02333 |
310103100817000 |
March 23, 2022 |
Region IX |
Regional Office IX |
UACS No. 310103100817000
Project ID: P00601163MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Tertiary Roads
Imelda-Bayog-Kumalarang - Lapuyan-Margosatubig Rd - K1763 + (-656) - K1763 + (-276), K1763 + (-276) - K1763 + 000, K1763 + 000 - K1764 + 316.49, K1765 + 000 - K1767 + 610.51
CW1- Preventive Maintenance of Road: Asphalt Overlay
Physical Target: 9.17 Lane Km
Unit Cost: ₱ 10,687,966.19/Lane Km
EAO: ₱ 3,610,845.00
Excess: ₱ 1,547,505.00
Allocation: ₱ 103,167,000.00 |
May 19, 2022 |
FY 2022 GAA |
WIN2G02753 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Mindoro Occidental District Engineering Office |
UACS No. : 320102104988000
Project ID : P00621104LZ
Construction of Flood Control Structure
FROM :
Construction of Flood Control Structure -
Mompong River, Malisbong Section,
Sta. 0+000 - Sta. 0+474,
Sablayan, Occidental Mindoro
Physical Target - CW1 - Construction of Flood Mitigation Structure
377.00 lineal meter
Allocation - Php 45.00 Million
TO :
Construction of Flood Control Structure -
Mompong River, Malisbong Section,
Sta. 0+000 - Sta. 0+377
Sablayan, Occidental Mindoro
Physical Target - CW1 - Construction of Flood Mitigation Structure
377.00 lineal meter
Allocation - Php 45.00 Million |
May 19, 2022 |
FY 2022 |
WIN2E02327 |
310204101148000 |
March 23, 2022 |
Region IX |
Regional Office IX |
UACS No. 310204101148000
Project ID: P00604243MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Bypass and Diversion Roads
NRJ Lapakan – Lamisahan - Victoria By-Pass Road, Zamboanga City
CW1- Construction of Concrete Road
Physical Target: 1.76 Lane Km
Unit Cost: ₱ 54,882,011.25/Lane km
ROW- Right-Of-Way Acquisition
Physical Target: 33,333.33 sq.m.
Unit Cost: ₱ 286.7298/sq.m.
EAO: ₱ 3,850,000.00
Allocation: ₱ 110,000,000.00 |
May 19, 2022 |
FY 2022 |
WIN2E02328 |
310101100578000 |
March 22, 2022 |
Region IX |
Regional Office IX |
UACS No. 310101100578000
Project ID: P00604683MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads
Pagadian City-Zamboanga City Rd – K1697+400.00 – K1699+000.00, K1719+000.00 – K1719+294.00, K1719+314.00 – K1720+000.00, K1721+200.00 – K1721+420.00, K1704 + 370 - K1704 + 420
CW1- Preventive Maintenance of Road: Concrete Reblocking
Physical Target: 5.60 Lane km
Unit Cost: ₱ 16,820,495.08/Lane km
CW2- Construction of Road Slope Protection Structure
Physical Target: 8,678.50 sq.m.
Unit Cost: ₱ 507.60/sq.m.
EAO: ₱ 3,605,000.00
Excess: ₱ 795,000.00
Allocation: ₱ 103,000,000.00 |
May 19, 2022 |
FY 2022 |
WIN2E02331 |
310305101537000 |
March 22, 2022 |
Region IX |
Regional Office IX |
UACS No. 310305101537000
Project ID: P00602123MN
OO1: Ensure Safe and Reliable National Road System - Bridge - Widening of Permanent Bridges
Opao Br. (B01784MN) along Dipolog-Oroquieta National Rd
CW1- Widening of Bridge
Physical Target: 867.186 sq.m.
Unit Cost: ₱ 115,027.23/Sq.m.
EAO: ₱ 3,675,000.00
Excess: ₱ 1,575,000.00
Allocation: ₱ 105,000,000.00 |
May 19, 2022 |
FY 2022 GAA |
WIN2G02975 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Mindoro Occidental District Engineering Office |
UACS No. : 320102104991000
Project ID : P00621623LZ
002 : Protect Lives and Properties Against Major Flood
Construction/Rehabilitation of Flood Mitigation Facilities
within Major River basins and Principal Rivers
FROM :
Construction of River Protection Structures along
Calawagan River,
Sta. 0+000.00 - Sta. 0+722.89,
Paluan, Occidental Mindoro
Physical Target - CW1 - Construction of Flood Mitigation Structure
662.00 lineal meter
Allocation - Php 50.00 Million
TO :
Construction of River Protection Structure
along Calawagan River
Sta. 0+000 - Sta. 0+322,
Sta. 0+492 - Sta. 0+772,
Paluan, Occidental Mindoro
Physical Target - CW1 - Construction of Flood Mitigation Structure
662.00 lineal meter
Allocation -Php 50.00 |
May 19, 2022 |
FY 2022 |
WIN2E02332 |
310204101585000 |
March 23, 2022 |
Region IX |
Regional Office IX |
UACS No. 310204101585000
Project ID: P00604236MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Bypass and Diversion Roads
NRJ Baluno - La Paz (Sitio Pole) Diversion Road, (Phase II), Zamboanga City
CW1- Construction of Concrete Road
Physical Target: 2.00 Lane Km
Unit Cost: ₱ 48,177,832.77/Lane km
ROW- Right-Of-Way Acquisition
Physical Target: 32,647.78 sq.m.
Unit Cost: ₱ 300.00/sq.m.
EAO: ₱ 3,850,000.00
Allocation: ₱ 110,000,000.00 |
May 19, 2022 |
FY 2022 |
WIN2E02326 |
310204101581000 |
March 23, 2022 |
Region IX |
Regional Office IX |
UACS No. 310204101581000
Project ID: P00604256MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Bypass and Diversion Roads
Ipil Circumferential Road, Veterans-Tiayon-Don Andres Section, Package II, Zamboanga Sibugay
CW1- Road Widening
Physical Target: 6.89 Lane Km
Unit Cost: ₱ 12,612,481.86/Lane km
ROW- Right-Of-Way Acquisition
Physical Target: 38,433.33 sq.m.
Unit Cost: ₱ 300.00/sq.m.
EAO: ₱ 3,570,000.00
Allocation : ₱ 102,000,000.00 |
May 19, 2022 |
FY 2022 |
WIN2E02330 |
310201100904000 |
March 23, 2022 |
Region IX |
Regional Office IX |
UACS No. 310201100904000
Project ID: P00602316MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Liloy-Ipil Rd - K1985 + 081.41 - K1985 + 794.28, K1985 + 981.19 - K1987 + 960.00
CW1- Road Widening
Physical Target: 5.383 Lane Km
Unit Cost: ₱ 15,455,469.15/Lane Km
ROW- Right-Of-Way Acquisition
Physical Target: 27,509.66 sq.m.
Unit Cost: ₱ 500.00/Sq.m.
EAO : ₱ 3,516,380.00
Allocation: ₱ 100,468,000.00 |
May 19, 2022 |
FY 2022 |
WIN2E02329 |
310108100969000 |
March 23, 2022 |
Region IX |
Regional Office IX |
UACS No. 310108100969000
Project ID: P00601386MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Zamboanga West Coastal Rd (Limpapa-Sibuco Sect) - K1991 + 276.00 - K1991 + 385.00, K1993 + 100.39 - K1995 + 413.38
CW1- Construction of Road Slope Protection Structure
Physical Target: 3,978.50 sq.m.
Unit Cost: ₱ 25,493.70/sq.m.
ROW- Right-Of-Way Acquisition
Physical Target: 6,136.22 sq.m.
Unit Cost: ₱ 300.00/sq.m.
EAO: ₱ 3,745,455.00
Allocation: ₱ 107,013,000.00 |
May 19, 2022 |
FY 2022 GAA |
WIN2G02769 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Mindoro Occidental District Engineering Office |
UACS No. : 320102104992000
Project ID : P00621624LZ
002 ; Protect Lives and Properties Against Major Flood
Flood management Program -
Construction/Rehabilitation of Flood Mitigation Facilities
within Major River Basins and principal Rivers
FROM :
Construction of River Protection Structures along
Katanlawan River,
Sta. 0+000 - Sta. 0+679.42
Paluan, Occidental Mindoro
Physical Target - CW1 - Construction of Flood Mitigation Structure
1000.00 Lineal Meter
Allocation - Php 47.00 Million
TO :
Construction of River Protection Structure
along Katanlawan River,
Sta. 0+000 - Sta. 0+840(L/S),
Sta. 0+200 - Sta.0+360(R/S),
Paluan, Occidental Mindoro
Physical Target - CW1 - Construction of Flood Mitigation Structure
1000.00 Lineal Meter
Allocation - 47.00 Million
|
May 19, 2022 |
FY 2022 |
WIN2E02357 |
310211100090000 |
April 5, 2022 |
Region IX |
Zamboanga del Norte 2nd District Engineering Office |
UACS No. 310211100090000
Project ID : P00604483MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Paving of Unpaved Roads - Secondary Roads
Zamboanga West Coastal Road (Sibuco - Sirawai Section) S01166MN
Chainage 12494 - Chainage 14094
CW1 - Paving of Unpaved Roads: 3.200 Lane km
Unit Cost : P 15,312.50/Lane km
EAO : P 1,000,000.00
Allocation : P 50,000,000.00 |
May 19, 2022 |
FY 2022 GAA |
WIN2G02931 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Mindoro Occidental District Engineering Office |
UACS No. : 300105200731000
Project ID : P00655135LZ
LOCAL PROGRAM
National Building Program - Buildings and other Structures
FROM :
Construction(Completion) of Four Storey Hostel Building,
DPWH Mindoro Occidental District Engineering Office
Mamburao, Occidental Mindoro
Physical Target - CW1 - Construction of Multi Purpose Building :
1 number of Building
Allocation - 22.230 Million
TO :
Construction of 2 Storey Hostel Building
DPWH Mindoro Occidental District Engineering Office
Mamburao, Occidental Mindoro
Physical Target - CW1 - Construction of Multi Purpose Building :
1 number of Building
Allocation - Php 22.230 Million |
May 19, 2022 |
2022 |
WIN2E02365 |
FY 2022 GAA R.A. 11639 |
January 1, 2022 |
Region XI |
Davao del Norte District Engineering Office |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System Network Development – Asset Preservation Program – Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide – Secondary Roads
Kapalong-Talaingod-Valencia (Bukidnon) Rd - K1519 + 250 - K1519 + 310
Physical Target:
CW1: 3,333.33 Square Meters (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 50,000,000.00
CW1: P 49,000,000.00 (Construction of Road Slope Protection Structure)
EAO: P 1,000,000.00
TO: OO1: Ensure Safe and Reliable National Road System Network Development – Asset Preservation Program – Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide – Secondary Roads
Kapalong-Talaingod-Valencia (Bukidnon) Rd - K1522 + 340 - K1522 + 403, K1528 + 180 – K1528 + 300
Physical Target:
CW1: 1,916.34 Square Meters (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 50,000,000.00
CW1: P 49,000,000.00 (Construction of Road Slope Protection Structure)
EAO: P 1,000,000.00
|
May 19, 2022 |
2022 |
WIN2E02366 |
FY 2022 GAA R.A. 11639 |
January 1, 2022 |
Region XI |
Davao del Norte District Engineering Office |
MODIFICATION:
FROM: Convergence and Special Support Program – Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) – Access Roads and/or Bridges from the National Road/s leading to Major/Strategic Public Buildings/Facilities
Construction of Jct. Tagum-Panabo Circumferential Road, Brgy. New Bantayan – Brgy. Magatos, Asuncion, Davao del Norte
Physical Target:
CW1: 5.660 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Construction of Concrete Road)
EAO: P 3,500,000.00
TO: Convergence and Special Support Program – Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) – Access Roads and/or Bridges from the National Road/s leading to Major/Strategic Public Buildings/Facilities
Construction of Jct. Tagum-Panabo Circumferential Road, Brgy. New Bantayan – Brgy. Magatos, Asuncion, Davao del Norte
Physical Target:
CW1: 1.360 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Construction of Concrete Road)
EAO: P 3,500,000.00
|
May 19, 2022 |
FY 2022 |
WIN2E02343 |
300204101215000 |
March 23, 2022 |
Region IX |
Zamboanga City 2nd District Engineering Office |
UACS No. 300204101215000
Project ID : P00632755MN
Convergence and Special Support Program - Construction/ Improvement of Access Roads leading to Trades, Industries and Economic Zones
Access Road at Sitio Anuling, Pamucutan to Sta. Rita in Support of High Value Crops (Abaca, Cacao, Rubber and Coffee), Upper La Paz, Zamboanga City
CW1 - Construction of Concrete Road : 1.17 Lane km
Unit Cost : P 41,381,945.56/Lane km
EAO : P 1,000,000.00
Excess: P 583,123.70
Allocation : P 50,000,000.00 |
May 19, 2022 |
FY 2022 GAA |
WIN2G02846 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Palawan 2nd District Engineering Office |
UACS No. : 320101108178000
Project ID : P00620656LZ
002: Protect Lives and Properties against Major Floods
Flood Management - Construction/Maintenance of Flood
Mitigation Structures and Drainage System
FROM :
Construction of Barong-barong Flood Control Structure,
Sta. 0+500 - Sta. 0+700,
Brooke's Point, Palawan
Physical Target - CW1 - Construction of Flood Mitigation Structure
245 LM
Allocation - Php 20.00 Million
TO :
Construction of B0arong-barong Flood Control Structure,
Sta. 0+500 - Sta. 0+745,
Brooke's Point, Palawan
Physical Target - CW1 - Construction of Flood Mitigation Structure
245 LM
Allocation - Php 20.00 Million
|
May 19, 2022 |
FY 2022 |
WIN2E02347 |
310102101054000 |
March 23, 2022 |
Region IX |
Zamboanga City 2nd District Engineering Office |
UACS No. 310102101054000
Project ID : P00604475MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Secondary Roads
Old Rd (Ayala-Talisayan) - K1956 + (-597) - K1956 + 000
CW1 - Preventive Maintenance of Road: Asphalt Overlay
Physical Target: 1.194 Lane km
Unit Cost : P 7,368,347.11/Lane km
EAO : P 180,000.00
Physical Reserved: P 22,193.55
Allocation : P 9,000,000.00 |
May 19, 2022 |
FY 2022 |
WIN2E02342 |
310111100474000 |
March 23, 2022 |
Region IX |
Zamboanga City 2nd District Engineering Office |
UACS No. 310111100474000
Project ID: P00601323MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Construction/ Upgrading/ Rehabilitation of Drainage along National Roads - Secondary Roads
Zamboanga City-Labuan-Limpapa Rd - K1944 + 747 - K1945 + 599.30
CW1 - Rehabilitation /Major Repair of Drainage Structure along Road
Physical Target: 852.30 Ln.m.
Unit Cost: P 16,766.9386/Ln.m.
EAO: P 299,960.00
Excess: P 407,578.23
Allocation: P 14,998,000.00 |
May 19, 2022 |
FY 2022 |
WIN2E02344 |
310101100739000 |
March 23, 2022 |
Region IX |
Zamboanga City 2nd District Engineering Office |
UACS No. 310101100739000
Project ID : P00601144MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads
Pagadian City-Zamboanga City Rd K1900 + 911 - K1901 + 000, K1901 + 829 - K1902 + 318
CW1 - Preventive Maintenance of Road: Asphalt Overlay
Physical Target: 1.228 Lane km
Unit Cost : P 7,955,629.28/Lane km
EAO : P 200,000.00
Excess: P 30,487.25
Allocation : P 10,000,000.00 |
May 19, 2022 |
2022 |
WIN2E02348 |
FY 2022 GAA R.A. 11639 |
January 1, 2022 |
Region XI |
Davao Oriental 1st District Engineering Office |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System – Asset Preservation – Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Benigno S. Aquino Jr. National Highway - K1566+ 935 - K1567 + 035
Physical Target:
CW1: 5,555.56.00 sq. m. (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Construction of Road Slope Protection Structure)
EAO: P 3,500,000.00
TO: OO1: Ensure Safe and Reliable National Road System – Asset Preservation – Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Benigno S. Aquino Jr. National Highway - K1566 + 640 - K1566 + 817
Physical Target:
CW1: 3,540.00 sq. m. (Construction of Road Slope Protection Structure)
ROW: 7,434.00 sq. m. (ROW Acquisition)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 95,000,000.00 (Construction of Road Slope Protection Structure)
ROW: P 1,500,000.00 (ROW Acquisition)
EAO: P 3,500,000.00 |
May 19, 2022 |
2022 |
WIN2E02378 |
FY 2022 GAA R.A. 11639 |
January 1, 2022 |
Region XI |
Davao Oriental 2nd District Engineering Office |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System – Asset Preservation – Preventive Maintenance – Primary Roads
Pres. Diosdado P. Macapagal Natl Hi-way – K1764 + 184 – K1764 + 632
Physical Target:
CW1: 0.896 Lane Km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 10,699,000.00
CW1: P 10,485,020.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 213,980.00
TO: OO1: Ensure Safe and Reliable National Road System – Asset Preservation – Preventive Maintenance – Primary Roads
Pres. Diosdado P. Macapagal Natl Hi-way – K1759 + 889.129 – K1759 + 976.871
Physical Target:
CW1: 0.526 Lane Km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 10,669,000.00
CW1: P 10,485,020.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 213,980.00 |
May 19, 2022 |
2022 |
WIN2E02376 |
FY 2022 GAA R.A. 11639 |
January 1, 2022 |
Region XI |
Davao Oriental 2nd District Engineering Office |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System – Asset Preservation – Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads – Secondary Roads
Mati-Maragusan – K1523 + 953 – K1524 + 228
Physical Target:
CW1: 1.540 Lane Km (Reconstruction to Concrete Pavement)
Allocation:
TOTAL: P 25,000,000.00
CW1: P 24,500,000.00 (Reconstruction to Concrete Pavement)
EAO: P 500,000.00
TO: OO1: Ensure Safe and Reliable National Road System – Asset Preservation – Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads – Secondary Roads
Mati-Maragusan – K1524 + 083 – K1524 + 228
Physical Target:
CW1: 0.045 Lane Km (Reconstruction to Concrete Pavement)
CW2: 540 sq. m. (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 25,000,000.00
CW1: P 14,655,690.00 (Reconstruction to Concrete Pavement)
CW2: P 9,844,310.00 (Construction of Road Slope Protection Structure)
EAO: P 500,000.00 |
May 19, 2022 |
2022 |
WIN2E02380 |
FY 2022 GAA R.A. 11639 |
January 1, 2022 |
Region XI |
Davao Oriental 2nd District Engineering Office |
MODIFICATION:
FROM: OO2: Protect Lives and Properties – Flood Management – Construction/ Rehabilitation of Flood Mitigation Facilities along Major River Basins and Principal Rivers
Construction of Flood Mitigation Structure along Bitanagan River,
Sta. 0+000 - Sta. 0+500, Mati City, Davao Oriental
Physical Target:
CW1: 500.00 Lineal Meters (Construction of Drainage Structure)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 29,400,000.00 (Construction of Drainage Structure)
EAO: P 600,000.00
TO: OO2: Protect Lives and Properties – Flood Management – Construction/ Rehabilitation of Flood Mitigation Facilities along Major River Basins and Principal Rivers
Construction of Flood Mitigation Structure along Bitanagan River, Sta. 0+054 – Sta. 0+136,
Sta. 0+057 – Sta. 0+232, Mati City, Davao Oriental
Physical Target:
CW1: 261.00 Lineal Meters (Construction of Drainage Structure)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 29,400,000.00 (Construction of Drainage Structure)
EAO: P 600,000.00 |
May 19, 2022 |
2022 |
WIN2E02379 |
FY 2022 GAA R.A. 11639 |
January 1, 2022 |
Region XI |
Davao Oriental 2nd District Engineering Office |
MODIFICATION:
FROM: Convergence and Special Support Program – Construction/ Improvement of Access Roads leading to Trades, Industries and Economic Zones (Roads Leveraging Linkages for Industry and Trade Infrastructure Program – ROLL-IT)
Road from Junction Brgy. Sainz connecting to Sitio Licop in support of Cacao, Coffee, Corn,
and Mango Industries, Mati City, Davao Oriental
Physical Target:
CW1: 0.654 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 14,726,000.00
CW1: P 14,431,480.00 (Construction of Concrete Road)
EAO: P 294,520.00
TO: Convergence and Special Support Program – Construction/ Improvement of Access Roads leading to Trades, Industries and Economic Zones (Roads Leveraging Linkages for Industry and Trade Infrastructure Program – ROLL-IT)
Road from Junction Brgy. Sainz connecting to Sitio Licop in support of Cacao, Coffee, Corn,
and Mango Industries, Mati City, Davao Oriental
Physical Target:
CW1: 0.300 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 14,726,000.00
CW1: P 14,431,480.00 (Construction of Concrete Road)
EAO: P 294,520.00 |
May 19, 2022 |
FY 2022 GAA |
WIN2G02864 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Palawan 2nd District Engineering Office |
UACS No. : 320101108179000
Project ID : P00620657LZ
002 : Protect Lives and Properties Against major Floods
Flood Management - Construction/Maintenance of Flood
Mitigation Structures and Drainage System
FROM :
Construction of Lanadio Flood Control Structure,
Sta. 0+000 - Sta. 0+150,
Brooke's Point, Palawan
Physical Target - CW1 - Construction of Flood Mitigation Structure
760 LM
Allocation - Php 30.00 Million
TO :
Construction of Lanadio Flood Control Structure,
Sta. 0+000 - Sta. 0+760
Brooke's Point, Palawan
Physical Target - CW1 - Construction of Flood Mitigation Structure
760 LM
Allocation - Php 30.00 Million |
May 19, 2022 |
FY 2022 GAA |
WIN2G02847 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Palawan 2nd District Engineering Office |
UACS No. : 320101108180000
Project ID : P00620658LZ
002 : Protect Lives and Properties Against Major Floods
Flood Management - Construction/Maintenance of Flood
Mitigation Structures and Drainage System
FROM :
Construction of Malatgao River Flood Control Structure,
Sta. 0+000 - Sta. 0+150,
Quezon, Palawan
Physical Target - CW1 - Construction of Flood Mitigation Structure
168 LM
Allocation - Php 10.00 Million
TO :
Construction of Malatgao River Flood Control Structure,
Sta. 0+000 - Sta. 0+094 Left Riverbank,
Sta. 0+020 - Sta. 0+094 Right Riverbank,
Quezon, Palawan
Physical Target - CW1 - Construction of Flood Mitigation Structure
168 LM
Allocation - Php 10.00 Million
|
May 19, 2022 |
FY 2022 GAA |
WIn2G02809 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Palawan 2nd District Engineering Office |
UACS No. : 320101108181000
Project ID : P00620659LZ
002: Protect Lives and Properties Against Major Floods
Flood Management - Construction/Maintenance of Flood
Mitigation Structures and Drainage System\
FROM :
Construction of Malinao River Flood Control Structure,
Sta. 0+000 - Sta. 0+125,
Narra, Palawan
Physical Target - CW1 - Construction of Flood Mitigation Structure
434 LM
Allocation - Php 30.00 Million
TO :
Construction of Malinao River Flood Control Structure
Sta. 0+000 - Sta. 0+234 Right Bank,
Sta. 0+040 - Sta. 0+240 Left Bank,
Narra, Palawan
Physical Target - CW1 - Construction of Flood Mitigation Structure
434 LM
Allocation - Php 30.00 Million
|
May 19, 2022 |
2022 |
WIN2E02361 |
FY 2022 GAA R.A. 11639 |
January 1, 2022 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation – Preventive Maintenance – Primary Roads
Daang Maharlika (MN) – (S01460MN) Chainage 760 – Chainage 1204
Physical Target:
CW1: 1.332 lane km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 16,048,000.00
CW1: P 15,727,040.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 320,960.00
TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation – Preventive Maintenance – Primary Roads
Daang Maharlika (MN) – K1499 + 015 – K1499 + 325, K1499 + 344 – K1499 + 386, K1499 + 971 – K1500+000
Physical Target:
CW1: 0.782 lane km (Off Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 16,048,000.00
CW1: P 15,727,040.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 320,960.00 |
May 19, 2022 |
2022 |
WIN2E02353 |
FY 2022 GAA R.A. 11639 |
January 1, 2022 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System – Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide – Secondary Roads
Davao City Div Rd - K1511 + 360 - K1511 + 420
Physical Target:
CW1: 3,208.440 square meters (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 57,752,000.00
CW1: P 55,730,680.00 (Construction of Road Slope Protection Structure)
EAO: P 2,021,320.00
TO: OO1: Ensure Safe and Reliable National Road System – Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide – Secondary Roads
Davao City Div Rd – K1511 + 810 – K1511 + 837
Physical Target:
CW1: 1,702.00 square meters (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 57,752,000.00
CW1: P 55,730,680.00 (Construction of Road Slope Protection Structure)
EAO: P 2,021,320.00 |
May 19, 2022 |
2022 |
WIN2E02354 |
FY 2022 GAA R.A. 11639 |
January 1, 2022 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System – Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide – Secondary Roads
Davao City Div Rd – K1511 + 848 – K1511 + 956
Physical Target:
CW1: 5,310.000 square meters (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 79,650,000.00
CW1: P 76,862,250.00 (Construction of Road Slope Protection Structure)
EAO: P 2,787,750.00
TO: OO1: Ensure Safe and Reliable National Road System – Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide – Secondary Roads
Davao City Div Rd – K1511 + 837 – K1511 + 890
Physical Target
CW1: 2,277.000 square meters (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 79,650,000.00
CW1: P 76,862,250.00 (Construction of Road Slope Protection Structure)
EAO: P 2,787,750.00 |
May 19, 2022 |
2022 |
WIN2E02358 |
FY 2022 GAA R.A. 11639 |
January 1, 2022 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System – Network Development – Road Widening – Primary Roads
Davao-Bukidnon Rd - K1698 + 541 - K1698 + 552, K1698 + 624 - K1698 + 649, K1698 + 918 - K1699 + 020, K1701 + 000 - K1701 + 029, K1701 + 093 - K1701 + 104
Physical Target:
CW1: 0.148 Lane Km (Road Widening)
Allocation:
TOTAL: P 4,908,000.00
CW1: P 4,809,840.00 (Road Widening)
EAO: P 98,160.00
TO: OO1: Ensure Safe and Reliable National Road System – Network Development – Road Widening – Primary Roads
Davao–Bukidnon Rd – K1698 + 541 – K1698 + 552, K1698 + 624 – K1698 + 649, K1698 + 918 – K1699 + 020
Physical Target:
CW1: 0.108 Lane Km (Road Widening)
Allocation:
TOTAL: P 4,908,000.00
CW1: P 4,809,840.00 (Road Widening)
EAO: P 98,160.00 |
May 19, 2022 |
2022 |
WIN2E02367 |
FY 2022 GAA R.A. 11639 |
January 1, 2022 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System – Network Development – Road Widening – Secondary Roads
ABS-CBN-Quimpo Blvd Div. Rd - K1512 + 145 - K1512 + 444
Physical Target:
CW1: 0.598 lane km (Road Widening)
ROW Acquisition: 2,098.98 square meters
Allocation:
TOTAL: P 135,729,000.00
CW1: P 75,976,380.00 (Road Widening)
ROW Acquisition: P 55,002,105.00
EAO: P 4,750,515.00
TO: OO1: Ensure Safe and Reliable National Road System – Network Development – Road Widening – Secondary Roads
ABS-CBN-Quimpo Blvd Div. Rd - K1512 + 120 - K1512 + 220, K1512 + 280 - K1512 + 442, K1512 + 600 - K1513 + 630, K1515 + 291- K1515 + 343
Physical Target:
CW1: 1.876 lane km (Road Widening)
ROW Acquisition: 1,067.386 square meters
Allocation:
TOTAL: P 135,729,000.00
CW1: P 73,949,880.00 (Road Widening)
ROW Acquisition: P 57,028,605.00
EAO: P 4,750,515.00 |
May 19, 2022 |
2022 |
WIN2E02359 |
FY 2022 GAA R.A. 11639 |
January 1, 2022 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System – Network Development – Off-Carriageway Improvement – Secondary Roads
Davao City Div Rd – K1509 + 000 - K1509 + 320, K1509 + 575 - K1509 + 940, K1511 + 045 - K1511 + 445, K1511 + 961 - K1511 + 983, K1512 + 172 - K1512 + 294, K1512 + 350 - K1512 + 408, K1514 + 893 - K1514 + 901, K1515 + 015 - K1515 + 030
Physical Target:
CW1: 1,140.00 square meters (Off-Carriageway Improvement: Construction of Traffic Island)
CW2: 432.00 square meters (Off-Carriageway Improvement: Construction of Sidewalk)
ROW Acquisition: 189.60 square meters
Allocation:
TOTAL: P 23,858,000.00
CW1: P 13,918,940.00 (Off-Carriageway Improvement: Construction of Traffic Island)
CW2: P 7,600,880.00 (Off-Carriageway Improvement: Construction of Sidewalk)
ROW Acquisition: P 1,861,020.00
EAO: P 477,160.00
TO: OO1: Ensure Safe and Reliable National Road System – Network Development – Off-Carriageway Improvement – Secondary Roads
Davao City Div Rd – K1507 + 311 – K1507 + 352, K1510 + 470 – K1510 + 850, K1512 + 528 – K1512 + 565, K1512 + 572 – K1512 + 595, K1512 + 820 – K1512 + 860, K1514 + 581 – K1514 + 646, K1514 + 992 – K1515 + 012
Physical Target:
CW1: 384.00 square meters (Construction of Road Slope Protection Structure)
CW2: 1,247.04 square meters (Off-Carriageway Improvement: Construction of Sidewalk)
ROW Acquisition: 395.431 square meters
Allocation:
TOTAL: P 23,858,000.00
CW1: P 4,932,798.91 (Construction of Road Slope Protection Structure)
CW2: P 14,185,531.09 (Off-Carriageway Improvement: Construction of Sidewalk)
ROW Acquisition: P 4,262,510.00
EAO: P 477,160.00 |