March 30, 2023 |
2023 |
|
FY 2023 GAA |
February 17, 2023 |
Region III |
Bulacan 1st District Engineering Office |
Convergence and Special Support Program - Basic Infrastructure Program (BIP) - Multi-Purpose Buildings / Facilities to Support Social Services
Construction of Multi-Purpose Building, Barangay Antipona, Bocaue, Bulacan |
March 30, 2023 |
2023 |
310101100970000 |
GAA FY 2023 |
December 26, 2022 |
Region II |
Cagayan 3rd District Engineering Office |
Organizational Outcome 1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads - Santiago - Tuguegarao Rd (Jct Kalinga - Tuguegarao Section) - K0439 + 000 - K0439 + 310 |
March 30, 2023 |
2023 |
310109101139000 |
GAA FY 2023 |
December 26, 2022 |
Region II |
Cagayan 3rd District Engineering Office |
Organizational Outcome 1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse and Landslide - Tertiary Roads - Peñablanca - Callao Cave Rd Phase III Package 3 - K0479 + 798.33 - K0479 + 898 |
March 30, 2023 |
2023 |
310109101140000 |
GAA FY 2023 |
December 26, 2022 |
Region II |
Cagayan 3rd District Engineering Office |
Organizational Outcome 1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads - Peñablanca - Callao Cave Rd - Phase III Package 4 K0483 + 000 - K0483 + 128.50 |
March 30, 2023 |
2023 |
310109101138000 |
GAA FY 2023 |
December 26, 2022 |
Region II |
Cagayan 3rd District Engineering Office |
Organizational Outcome 1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse and Landslide - Tertiary Roads - Peñablanca - Callao Cave Rd Phase III Package 2 - K0479 + 565 - K0479 + 670 |
March 30, 2023 |
2023 |
|
FY 2023 GAA |
February 17, 2023 |
Region III |
Bulacan 1st District Engineering Office |
Convergence and Special Support Program - Basic Infrastructure Program (BIP) - Multi-Purpose Buildings / Facilities to Support Social Services
Construction of Multi-Purpose Building, B-Tech, Pagala, Baliuag, Bulacan |
March 30, 2023 |
2023 |
310109101141000 |
GAA FY 2023 |
December 26, 2022 |
Region II |
Cagayan 3rd District Engineering Office |
Organizational Outcome 1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse and Landslide - Tertiary Roads - Peñablanca - Callao Cave Rd Phase III Package 5 K0483 + 128.50 - K0483 + 257 |
March 30, 2023 |
2023 |
|
FY 2023 GAA |
February 17, 2023 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Convergence and Special Support Program - Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road /s leading to Major/Strategic Public Buildings / Facilities
Construction of Multi-Purpose Building (Covered Court), Valle Cruz Elementary School, Barangay Valle Cruz, Cabanatuan City, Nueva Ecija |
March 30, 2023 |
2023 |
|
FY 2023 GAA |
February 17, 2023 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Asset Preservation Program – Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Tertiary Roads
Sta. Rosa - Fort Magsaysay Rd - K0108+(-421.00) - K0108+(-240.00), K0108+(-203.00) - K0108+(-187.50), K0108+(-147) - K0108+(-142.50), K0121+135.00 - K0121+543.90 |
March 30, 2023 |
2023 |
WIN3F07058 |
FY 2023 GAA |
February 17, 2023 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Asset Preservation Program – Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Secondary Roads
Bongabon - Rizal - Aurora Rd - K0145+(-872) - K0145+147,K0145+153 - K0145+313, K0145+356.00 - K0145+364.00, K0145+556.50 - K0145+566.50, K0145+964.00 - K0145+1094.00, K0146+260.00 - K0146+320.00, K0146+580.00 - K0146+680.00, K0146+753.00 - K0146+810.00
|
March 30, 2023 |
2023 |
WIN3F07056 |
FY 2023 GAA |
February 17, 2023 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Asset Preservation Program – Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Secondary Roads
Jct Tablang - Gabaldon Rd - K0136+000.00 - K0136+960.00, K0140+029.00 - K0140+140.00, K0141+000.00 - K0141+471.40, K0141+478.30 - K0141+835.00, K0144+795.00 - K0144+988.50, K0146+945.00 - K0147+307.50, K0147+314.50 - K0147+542.00, K0147+740.00 - K0147+955.00, K0147+1210.00 - K0147+1284.40, K0147+000.00 - K0149+305.00
|
March 30, 2023 |
2023 |
|
FY 2023 GAA |
February 17, 2023 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Asset Preservation Program - Preventive Maintenance - Secondary Roads
Nueva Ecija - Aurora Rd - K0119+460.00 - K0120+020.00, K0124+225.70 - K0124+600.00, K0126+247.00 - K0126+297.70, K0126+769.70 - K0126+827.70, K0127+067.70 - K0127+134.40, K0127+210.40 - K0127+338.70, K0127+478.00 - K0127+567.50, K0127+722.90 - K0127+865.40, K0127+940.00 - K0128+141.60, K0128+354.60 - K0128+412.00 |
March 30, 2023 |
2023 |
|
FY 2023 GAA |
February 17, 2023 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Network Development Program - Off-Carriageway Improvement - Tertiary Roads
Gapan - Fort Magsaysay Rd - K0094+(-215) - K0094+387, K0095+020 - K0095+240, K0095+320 - K0095+358, K0096+000 - K0096+600 |
March 30, 2023 |
2023 |
310109101128000 |
GAA FY 2023 |
December 26, 2022 |
Region II |
Nueva Vizcaya 2nd District Engineering Office |
Organizational Outcome 1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads - Papaya - Malabing - Wangal - Binugawan - Tadji - Runruno Rd - K0307 + 850 - K0307 + 970 |
March 30, 2023 |
2023 |
310109101126000 |
GAA FY 2023 |
December 26, 2022 |
Region II |
Nueva Vizcaya 2nd District Engineering Office |
Organizational Outcome 1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads - Papaya - Malabing - Wangal - Binugawan - Tadji - Runruno Rd - K0306 + 1040 - K0307 + 285 |
March 30, 2023 |
2023 |
|
FY 2023 GAA |
February 17, 2023 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Network Development Program - Road Widening - Primary Roads
Jose Abad Santos Ave (JASA) , K0109+872.30 - K0109+1010, K0110+000.00 - K0110+051.15
|
March 30, 2023 |
2023 |
WIN3F07063 |
FY 2023 GAA |
February 17, 2023 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Network Development Program - Road Widening - Secondary Roads
Nueva Ecija - Aurora Road , K0148+168.20 - K0150+238.00 |
March 30, 2023 |
2023 |
310109101125000 |
GAA FY 2023 |
December 26, 2022 |
Region II |
Nueva Vizcaya 2nd District Engineering Office |
Organizational Outcome 1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads - Papaya - Malabing - Wangal - Binugawan - Tadji - Runruno Rd - K0306 + 490 - K0306 +651, K0306 + 794 - K0306 + 980 |
March 30, 2023 |
2023 |
WIN3F06993 |
FY 2023 GAA |
February 17, 2023 |
Region III |
Tarlac 2nd District Engineering Office |
Asset Preservation Program - Preventive Maintenance - Tertiary Roads
Tarlac - Zambales Rd - K0115+000 - K0116+168 |
March 30, 2023 |
2023 |
WIN3F06968 |
FY 2023 GAA |
February 17, 2022 |
Region III |
Tarlac 2nd District Engineering Office |
Flood Management Program - Construction / Maintenance of Flood Mitigation Structures and Drainage Systems
Rehabilitation of Dike along O'Donnell River, Sta. 8+564 - Sta. 8+888, Downstream of Bueno Bridge 1, Left Bank, Capas, Tarlac |
March 30, 2023 |
2023 |
|
FY 2023 GAA |
February 17, 2023 |
Region III |
Tarlac 2nd District Engineering Office |
Asset Preservation Program - Preventive Maintenance - Tertiary Roads
Concepcion - La Paz Road - K0122+100 - K0124+000, K0126+000 - K0127+700 |
March 30, 2023 |
2023 |
310109101129000 |
GAA FY 2023 |
December 26, 2022 |
Region II |
Nueva Vizcaya 2nd District Engineering Office |
Organizational Outcome 1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads - Papaya - Malabing - Wangal - Binugawan - Tadji - Runruno Rd - K0307 + 970 - K308 + 165 |
March 30, 2023 |
2023 |
|
FY 2023 GAA |
February 17, 2023 |
Region III |
Tarlac 2nd District Engineering Office |
Asset Preservation Program - Preventive Maintenance - Tertiary Roads
Concepcion - La Paz Rd - K0117+110.50 - K0117+346, K0117+346 - K0117+675, K0117+675 - K0118+000, K0118+000 - K0118+266, K0118+266 - K0118+589 |
March 30, 2023 |
2023 |
|
FY 2023 GAA |
February 17, 2023 |
Region III |
Tarlac 2nd District Engineering Office |
Asset Preservation Program - Preventive Maintenance - Primary Roads
Manila North Road - K0108+000 - K0110+120 |
March 30, 2023 |
2023 |
|
FY 2023 GAA |
February 17, 2023 |
Region III |
Tarlac 2nd District Engineering Office |
Asset Preservation Program - Preventive Maintenance - Primary Roads
Manila North Road - K0098+(-532) - K0098+(-439), K0098+(-439) - K0098+(-071) , K0104+742 - K0104+966, K0104+966 - K0105+050, K0105+583 - K0105+838, K0110+120 - K0110+613, K0110+613 - K0110+643, K0110+643 - K0110+956 |
March 29, 2023 |
CY 2023 |
WIN3F07052 |
UACS No. 310103101058000 |
February 2, 2023 |
National Capital Region |
Las Piñas - Muntinlupa District Engineering Office |
As per GAA/Original
UACS No. 310103101058000
Project ID.: P00712438LZ
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Tertiary Roads
South Super H-way East Service Rd – K0020+(-1064) – K0022+000
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay 6.655 Lane Km
Unit Cost (P’000) = P 7,989.13/lane km
Allocation = P 53,167,640.00
EAO = P 1,928,360.00
Total = P 55,096,000.00
As Modified
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Tertiary Roads
South Super H-way East Service Rd – K0020+(-1064) – K0020+(-299), K0020+(-274) – K0020+352
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay 3.227 Lane Km
Unit Cost (P’000) = P 16,475.87/lane km P 32.8 m/km
Allocation = P 53,167,640.00
EAO = P 1,928,360.00
Total = P 55,096,000.00
WIN3F07052
|
March 29, 2023 |
CY 2023 |
WIN3F07030 |
UACS No. 310102101084000 |
March 7, 2023 |
National Capital Region |
North Manila District Engineering Office |
As per GAA/Original
UACS No. 310102101084000
Project ID.: P00714637LZ
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Secondary Roads
Preventive Maintenance Preventive Maintenance – Secondary Roads – Jose Abad Santos Avenue, Tondo, Manila
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay 11.756 lane Km
Unit Cost (P’000) = P 9,255.250/lane km
Allocation = P 108,804,715.00
EAO = P 3,946,285.00
Total = P 112,751,000.00
As Modified
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Secondary Roads
Preventive Maintenance Preventive Maintenance – Secondary Roads – Jose Abad Santos Avenue, Tondo, Manila (S02299LZ) K0004 + 974.8 - K0004 + 1144.40, K0005 + 000.00 - K0005 + 407.3, K0005+418.1 – K0005 + 898.4, K0006+000.0 – K0006+301.1, (S02287LZ) K0005+515.1 – K0005 + 1061.
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay 7.62 lane Km
Unit Cost (P’000) = P 14,278.834/lane km P 28.4 m/km
Allocation = P 108,804,715.00
EAO = P 3,946,285.00
Total = P 112,751,000.00
WIN3F07030
|
March 29, 2023 |
CY 2023 |
|
UACS No. 300226104876000 |
January 27, 2023 |
National Capital Region |
Metro Manila 1st District Engineering Office |
As per GAA/Original
UACS No. 300226104876000
Project ID.: P00742694LZ
Convergence and Special Support Program
Basic Infrastructure Program (BIP) – Multi-Purpose Buildings/Facilities to Support Social Services
Rehabilitation of Multipurpose Building in Highway Hills Elementary School Phase I, Calbayog Street,
Barangay Highway Hills, Mandaluyong City
Physical Target: CW1 = Rehabilitation/Major Repair of Multi-Purpose Building 1 bldg.
Unit Cost (P’000) = P 21,070.00 no. of bldg.
Allocation = P 21,070,000.00
EAO = P 430,000.00
Total = P 21,500,000.00
As Modified
Convergence and Special Support Program
Basic Infrastructure Program (BIP) – Multi-Purpose Buildings/Facilities to Support Social Services
Rehabilitation of Multipurpose Building in Highway Hills Integrated School Phase I, Calbayog Street,
Barangay Highway Hills, Mandaluyong City
Physical Target: CW1 = Rehabilitation/Major Repair of Multi-Purpose Building 1 bldg.
Unit Cost (P’000) = P 21,070.00 no. of bldg.
Allocation = P 21,070,000.00
EAO = P 430,000.00
Total = P 21,500,000.00
|
March 28, 2023 |
CY 2023 |
|
UACS No. 310102101239000 |
February 21, 2023 |
National Capital Region |
North Manila District Engineering Office |
As per GAA/Original
UACS No. 310102101239000
Project ID.: P00714142LZ
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Secondary Roads
Preventive Maintenance (Asphalt Overlay) along CM Recto Ave. (S02229LZ), Sta. Cruz, Manila City
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay 1.90 Lane Km
Unit Cost (P’000) = P 13,926.31/Lane km
Allocation = P 26,460,000.00
EAO = P 540,000.00
Total = P 27,000,000.00
As Modified
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Secondary Roads
Preventive Maintenance (Asphalt Overlay) along CM Recto Ave. (S02229LZ), Sta. Cruz, Manila City -
K0004+(-1584.70) – K0004(-1199.00), K0004+(099.40) – K0004+225.80
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay 2.133 Lane Km
Unit Cost (P’000) = P 12,405.06/Lane km P 24.8 M/Km
Allocation = P 26,460,000.00
EAO = P 540,000.00
Total = P 27,000,000.00
|
March 28, 2023 |
CY 2023 |
|
UACS No. 310102101241000 |
February 21, 2023 |
National Capital Region |
North Manila District Engineering Office |
As per GAA/Original
UACS No. 310102101241000
Project ID.: P00714144LZ
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Secondary Roads
Preventive Maintenance (Asphalt Overlay) along Blumentritt St., Manila City
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay 1.672 lane km
Unit Cost (P’000) = P 16,710.99/lane km
Allocation = P 27,940,780.00
EAO = P 570,220.00
Total = P 278,511,000.00
As Modified
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Secondary Roads
Preventive Maintenance (Asphalt Overlay) along Blumentritt St. C 400 – C 734 Manila City
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay 2.004 lane km
Unit Cost (P’000) = P 13,942.50/lane km P 27.8 m/km
Allocation = P 27,940,780.00
EAO = P 570,220.00
Total = P 278,511,000.00
|
March 27, 2023 |
2023 |
WIN3F07009 |
FY 2023 GAA |
February 17, 2023 |
Region III |
Regional Office III |
Asset Preservation Program - Preventive Maintenance - Secondary Roads
Roman Expressway - K0143+(-252) - K0143+100, K0143+300 - K0143+910 |
March 27, 2023 |
2023 |
none |
FY 2023 GAA |
February 17, 2023 |
Region III |
Regional Office III |
Asset Preservation Program – Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Primary Roads
Manila North Road - K0018+(-583) - K0018+(-218), K0018+(-218) - K0018+457, K0019+287 - K0020+104 |
March 27, 2023 |
2023 |
|
FY 2023 GAA |
February 17, 2022 |
Region III |
Regional Office III |
Asset Preservation Program – Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Primary Roads
Manila North Road - K0055+350 - K0055+750, K0056+300 - K0056+420, K0056+525 - K0056+602, K0056+690 - K0056+825, K0057+550 - K0057+747, K0061+396 - K0061+446, K0062+388 - K0062+450 |
March 27, 2023 |
CY 2023 |
|
UACS No. 310103101123000 |
February 2, 2023 |
National Capital Region |
Las Piñas - Muntinlupa District Engineering Office |
As per GAA/Original
UACS No. 310103101123000
Project ID.: P00712437LZ
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Tertiary Roads
Muntinlupa-Insular Prison Rd – K0031+109 -K0032+178
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay 2.124 Lane Km
Unit Cost (P’000) = P 10,420.57/Lane km
Allocation = P 22,133,300.00
EAO = P 451,700.00
Total = P 22,585,000.00
As Modified
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Tertiary Roads
Muntinlupa-Insular Prison Rd – K0031+109 -K0032+274
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay 2.316 Lane Km
Unit Cost (P’000) = P 9,556.69/lane km
Allocation = P 22,133,300.00
EAO = P 451,700.00
Total = P 22,585,000.00
|
March 27, 2023 |
2023 |
|
FY 2023 GAA |
February 17, 2023 |
Region III |
Regional Office III |
Asset Preservation Program – Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Primary Roads
Jose Abad Santos Ave (JASA) - K0075+602 - K0075+958, K0093+672.50 - K0094+000 |
March 27, 2023 |
2023 |
|
FY 2023 GAA |
February 17, 2023 |
Region III |
Regional Office III |
Asset Preservation Program – Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Primary Roads
Jose Abad Santos Ave (JASA) - K0078+097 - K0079+285, K0091+242 - K0093+672 |
March 24, 2023 |
CY 2023 |
WIN3F06953 |
UACS No. 300105200878000 |
February 17, 2023 |
National Capital Region |
NCR - Regional Office |
As per GAA/Original
UACS No. 300105200878000
Project ID.: P00755159LZ
Local Program
National Building Program – Buildings And Other Structures – Multipurpose / Facilities
Construction of University of the Philippines (UP) Diliman College of Arts and Letters (CAL) Building,
Phase 3, Diliman, Quezon City
Physical Target: CW1 = Construction of Multi-Purpose Building 1 bldg.
Unit Cost (P’000) = P 289,500.00/no. of bldg.
Allocation = P 289,500,000.00
EAO = P 10,500,000.00
Total = P 300,000,000.00
As Modified
Local Program
National Building Program – Buildings And Other Structures – Multipurpose / Facilities
Construction of University of the Philippines (UP) Diliman College of Arts and Letters (CAL) Building,
Phase 2, Diliman, Quezon City
Physical Target: CW1 = Construction of Multi-Purpose Building 1 bldg.
Unit Cost (P’000) = P 289,500.00/no. of bldg.
Allocation = P 289,500,000.00
EAO = P 10,500,000.00
Total = P 300,000,000.00
WIN3F06953
|
March 23, 2023 |
2023 |
WIN3F06921 |
FY 2023 GAA |
February 17, 2023 |
Region III |
Regional Office III |
Asset Preservation Program – Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Primary Roads
Manila North Road - K0020+104 - K0020+601 |
March 23, 2023 |
2023 |
WIN3F06887 |
FY 2023 GAA |
February 17, 2023 |
Region III |
Regional Office III |
Asset Preservation Program - Rehabilitation / Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Nueva Ecija - Aurora Rd - K0160+740 - K0160+930 |
March 23, 2023 |
2023 |
WIN3F06886 |
FY 2023 GAA |
February 17, 2023 |
Region III |
Regional Office III |
Asset Preservation Program - Rehabilitation / Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Nueva Ecija - Aurora Rd - K0156+240 - K0156+335 |
March 23, 2023 |
2023 |
WIN3F06866 |
FY 2023 GAA |
February 17, 2023 |
Region III |
Regional Office III |
Asset Preservation Program - Rehabilitation / Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Madella - Dinadiawan Rd - K0411+258 - K0411+330, K0412+(-091) - K0412+025 |
March 23, 2023 |
2023 |
WIN3F06854 |
FY 2023 GAA |
February 17, 2023 |
Region III |
Regional Office III |
Asset Preservation Program – Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Primary Roads
Manila North Rd - K0020+601 - K0021+587, K0022+464 - K0022+1209 |
March 23, 2023 |
2023 |
WIN3F06852 |
FY 2023 GAA |
February 17, 2023 |
Region III |
Regional Office III |
Asset Preservation Program - Preventive Maintenance - Tertiary Roads
A Castañeda - Ma. Aurora - Sn Luis Rd - K0220+000 - K0220+903 |
March 23, 2023 |
2023 |
WIN3F06848 |
FY 2023 GAA |
February 17, 2023 |
Region III |
Regional Office III |
Asset Preservation Program – Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Primary Roads
Jose Abad Santos Ave (JASA) - K0097+ 000 - K0097+180, K0104+000 - K0105+000, K0110+000 - K0110+695, K0112+934 - K0114+000, K0114+138 - K0114+675 |
March 23, 2023 |
2023 |
WIN3F06849 |
FY 2023 GAA |
February 17, 2023 |
Region III |
Regional Office III |
Asset Preservation Program - Rehabilitation / Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Madella- Dinadiawan Rd - K0410+012 - K0410+100, K0410+580 - K0410+615 |
March 23, 2023 |
2023 |
WIN3F06847 |
FY 2023 GAA |
February 17, 2023 |
Region III |
Regional Office III |
Asset Preservation Program - Rehabilitation / Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Madella - Dinadiawan Rd - K0416+111 - K0416+185, K0416+265 - K0416+340, K0416+407 - K0416+475 |
March 23, 2023 |
2023 |
WIN3F06857 |
FY 2023 GAA |
February 17, 2022 |
Region III |
Regional Office III |
Asset Preservation Program – Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Primary Roads
Daang Maharlika (LZ) -K0085+(-916) - K0085+(-385), K0085+(-375) - K0085+758, K0085+768 - K0086+116 |
March 23, 2023 |
CY 2023 |
WIN3F06911 |
UACS No. 300105200587000 |
February 7, 2023 |
National Capital Region |
NCR - Regional Office |
As per GAA/Original
UACS No. 300105200587000
Project ID.: P00755199LZ
Local Program
Local – Building and Other Structures – Multipurpose/Facilities – National Building Program
Construction of Public Attorney’s Office (PAO) Building Phase II, Commonwealth, Batasan Hills, Quezon City
Physical Target: CW1 = Construction of Multi-Purpose Building 1 bldg.
Unit Cost (P’000) = P 289,500.00/no. of bldg.
Allocation = P 289,500,000.00
EAO = P 10,500,000.00
Total = P 300,000,000.00
As Modified
Local Program
Local – Building and Other Structures – Multipurpose/Facilities – National Building Program
Construction of Public Attorney’s Office (PAO) Building Phase III, Commonwealth Avenue, Batasan Hills,
Quezon City
Physical Target: CW1 = Construction of Multi-Purpose Building 1 bldg.
Unit Cost (P’000) = P 289,500.00/no. of bldg.
Allocation = P 289,500,000.00
EAO = P 10,500,000.00
Total = P 300,000,000.00
WIN3F06911
|
March 23, 2023 |
CY 2023 |
WIN3F06915 |
UACS No. 300105200585000 |
February 7, 2023 |
National Capital Region |
NCR - Regional Office |
As per GAA/Original
UACS No. 300105200585000
Project ID.: P00755201LZ
Local Program
Local – Building and Other Structures – Multipurpose/Facilities – National Building Program
Construction of Professional Regulation Commission Building (Phase II), Central Business Part 1,
Island A, Macapagal Boulevard, Pasay City
Physical Target: CW1 = Construction of Multi-Purpose Building 1 bldg.
Unit Cost (P’000) = P 289,500.00/no. of bldg.
Allocation = P 289,500,000.00
EAO = P 10,500,000.00
Total = P 300,000,000.00
As Modified
Local Program
Local – Building and Other Structures – Multipurpose/Facilities – National Building Program
Construction of Professional Regulation Commission Building (Phase III), Central Business Part 1,
Island A, Macapagal Boulevard, Pasay City
Physical Target: CW1 = Construction of Multi-Purpose Building 1 bldg.
Unit Cost (P’000) = P 289,500.00/no. of bldg.
Allocation = P 289,500,000.00
EAO = P 10,500,000.00
Total = P 300,000,000.00
WIN3F06915
|
March 23, 2023 |
2023 |
WIN3F06846 |
FY 2023 GAA |
February 17, 2022 |
Region III |
Regional Office III |
Asset Preservation Program – Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Primary Roads
Manila North Rd - K0065+585 - K0065+958, K0066+093 - K0066+754, K0066+850 - K0067+120, K0068+101 - K0068+460, K0068+481 - K0068+650, K0068+650 - K0069+310 |
March 23, 2023 |
CY 2023 |
WIN3F06917 |
UACS No. 300105200897000 |
February 7, 2023 |
National Capital Region |
NCR - Regional Office |
As per GAA/Original
UACS No. 300105200897000
Project ID.: P00755171LZ
Local Program
Local – Building and Other Structures – Multipurpose/Facilities – National Building Program
Construction of 9-Storey with Roof Deck-Main Academic Building, Polytechnic University of the
Philippines (PUP), A. Mabini Campus, Anonas St., Sta. Mesa, Manila
Physical Target: CW1 = Construction of Multi-Purpose Building 1 bldg.
Unit Cost (P’000) = P 38,600.00/no. of bldg.
Allocation = P 38,600,000.00
EAO = P 1,400,000.00
Total = P 40,000,000.00
As Modified
Local Program
Local – Building and Other Structures – Multipurpose/Facilities – National Building Program
Construction of 9-Storey with Roof Deck-Main Academic Building, Polytechnic University of the
Philippines (PUP), A. Mabini Campus, Anonas St., Sta. Mesa, Manila (Phase II)
Physical Target: CW1 = Construction of Multi-Purpose Building 1 bldg.
Unit Cost (P’000) = P 38,600.00/no. of bldg.
Allocation = P 38,600,000.00
EAO = P 1,400,000.00
Total = P 40,000,000.00
WIN3F06917
|
March 23, 2023 |
2023 |
WIN3F06864 |
FY 2023 GAA |
February 17, 2023 |
Region III |
Tarlac District Engineering Office |
Asset Preservation Program - Construction / Upgrading / Rehabilitation of Drainage along National Roads - Primary Roads
Romulo H-way - K0126+500 - K0127+050 |
March 23, 2023 |
2023 |
WIN3F06835 |
FY 2023 GAA |
February 17, 2023 |
Region III |
Tarlac District Engineering Office |
Asset Preservation Program - Construction / Upgrading / Rehabilitation of Drainage along National Roads - Primary Roads
Romulo H-way - K0148+395 - K0148+968 |
March 23, 2023 |
2023 |
WIN3F06833 |
FY 2023 GAA |
February 17, 2023 |
Region III |
Tarlac District Engineering Office |
Asset Preservation Program - Preventive Maintenance - Primary Roads
Manila North Rd - K0161+609 - K0161+963 |
March 23, 2023 |
2023 |
WIN3F06836 |
FY 2023 GAA |
February 17, 2023 |
Region III |
Tarlac District Engineering Office |
Asset Preservation Program - Preventive Maintenance - Primary Roads
Manila North Rd - K0149+565 - K0150+522 |
March 23, 2023 |
2023 |
WIN3F06838 |
FY 2023 GAA |
February 17, 2023 |
Region III |
Tarlac District Engineering Office |
Asset Preservation Program - Preventive Maintenance - Primary Roads
Manila North Rd - K0154+790 - K0155+876 |
March 23, 2023 |
2023 |
WIN3F06834 |
FY 2023 GAA |
February 17, 2023 |
Region III |
Tarlac District Engineering Office |
Asset Preservation Program - Preventive Maintenance - Primary Roads
Romulo H-way - K0145+843 - K0146+865 |
March 23, 2023 |
2023 |
WIN3F06827 |
FY 2023 GAA |
February 17, 2023 |
Region III |
Tarlac District Engineering Office |
Asset Preservation Program - Preventive Maintenance - Primary Roads
Manila North Rd - K0132+073 - K0132+933 |
March 23, 2023 |
2023 |
WIN3F06828 |
FY 2023 GAA |
February 17, 2023 |
Region III |
Tarlac District Engineering Office |
Asset Preservation Program - Construction / Upgrading / Rehabilitation of Drainage along National Roads - Tertiary Roads
Tarlac - Sn Miguel via Macabulos Rd - K0119+(-530) - K0119+(-340) |
March 21, 2023 |
CY 2023 |
WIN3F06867 |
SR2023-01-0002495 |
January 30, 2023 |
National Capital Region |
Las Piñas - Muntinlupa District Engineering Office |
As per GAA/Original
UACS No. 310101100773000
Project ID.: P00712434LZ
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Primary Roads
Daang Maharlika (LZ) – K0026+(-120) – K0028+240
Physical Target: CW1 = Maintenance of Road: Asphalt Overlay = 9.416 Lane Km
Unit Cost (P’000) = P 10,249.51/lane km
Allocation = P 96,500,000.00
EAO = P 3,500,000.00
Total = P 100,000,000.00
As Modified
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Primary Roads
Daang Maharlika (LZ) – K0026+(-120) – K0027+285.28
Physical Target: CW1 = Maintenance of Road: Asphalt Overlay = 5.605 Lane Km
Unit Cost (P’000) = P 17,216.77/lane km = P34.4 m/km
Allocation = P 96,500,000.00
EAO = P 3,500,000.00
Total = P 100,000,000.00
WIN3F06867
|
March 21, 2023 |
CY 2023 |
WIN3F06882 |
UACS No. 310101100923000 |
February 2, 2023 |
National Capital Region |
Las Piñas - Muntinlupa District Engineering Office |
As per GAA/Original
UACS No. 310101100923000
Project ID.: P00712435LZ
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Primary Roads
Daang Maharlika (LZ) – K0030+000 – K0030+783
Physical Target: CW1 = Maintenance of Road: Asphalt Overlay =3.132 Lane Km
Unit Cost (P’000) = P 13,767.56/lane km
Allocation = P 43,120,000.00
EAO = P 880,000.00
Total = P 44,000,000.00
As Modified
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Primary Roads
Daang Maharlika (LZ) – K0030+180 – K0030+783
Physical Target: CW1 = Maintenance of Road: Asphalt Overlay =2.412 Lane Km
Unit Cost (P’000) = P 17,877.28/lane km = P35.6 m/Km
Allocation = P 43,120,000.00
EAO = P 880,000.00
Total = P 44,000,000.00
WIN3F06882
|
March 10, 2023 |
2023 |
WIN3F06826 |
FY 2023 GAA |
February 17, 2023 |
Region III |
Regional Office III |
Asset Preservation Program - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Primary Roads
Manila North Road - K0025+(-1138) - K0025+(-236), K0025+618 - K0026+010, K0027+098 - K0028+000, K0028+000 - K0028+310 |
February 1, 2023 |
2022 |
WIN2E02548 |
GAA 2022 |
January 2, 2022 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Abra-Kalinga Rd - K0457 + 000 - K0457 + 100;
Physical Target: 5555.56 Square meters;
Allocation: Php 100,000,000.000
To: Abra-Kalinga Rd - K0457 + 427 - K0457 + 527;
Physical Target: 3404.88 Square meters;
Allocation: Php 99,834,000.000
Excess: Php 166,000.000
|
February 1, 2023 |
2022 |
WIN2E02560 |
GAA 2022 |
January 2, 2022 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Construction of Malabbaga Flood Control Structure (Phase III), Sta. 6 + 820 - Sta. 7 + 820, La Paz, Abra;
Physical Target: 884.642 Lineal meters;
Allocation: Php 100,000,000.000
To: Construction of Malabbaga Flood Control Structure (Phase III), Sta. 6 + 820 - Sta. 7 + 820, La Paz, Abra;
Physical Target: 368 Lineal meters;
Allocation: Php 94,860,000.000
Excess: Php 5,140,000.000
|
February 1, 2023 |
2022 |
WIN2E02554 |
GAA 2022 |
January 2, 2022 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Construction of Patagui Flood Control Structure, La Paz, Abra;
Physical Target: 884.642 Lineal meters;
Allocation: Php 100,000,000.000
To: Construction of Patagui Flood Control Structure, La Paz, Abra;
Physical Target: 372.4 Lineal meters;
Allocation: Php 97,746,000.000
Excess: Php 2,254,000.000
|
February 1, 2023 |
2022 |
WIN2E02561 |
GAA 2022 |
January 2, 2022 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Construction of Soot Flood Control Structure, La Paz, Abra;
Physical Target: 884.642 Lineal meters;
Allocation: Php 100,000,000.000
To: Construction of Soot Flood Control Structure, La Paz, Abra;
Physical Target: 177 Lineal meters;
Allocation: Php 95,450,000.000
Excess: Php 4,550,000.000
|
February 1, 2023 |
2022 |
WIN2E02555 |
GAA 2022 |
January 2, 2022 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Construction of Cardona Flood Control Structure, Barangay Cardona, Dolores, Abra;
Physical Target: 884.642 Lineal meters;
Allocation: Php 100,000,000.000
To: Construction of Cardona Flood Control Structure, Barangay Cardona, Dolores, Abra;
Physical Target: 351.8 Lineal meters;
Allocation: Php 99,408,000.000
Excess: Php 592,000.000
|
February 1, 2023 |
2022 |
WIN2E02550 |
GAA 2022 |
January 2, 2022 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Construction of Poblacion East Flood Control, Pidigan, Abra;
Physical Target: 442.321 Lineal meters;
Allocation: Php 50,000,000.000
To: Construction of Poblacion East Flood Control, Pidigan, Abra;
Physical Target: 127.2 Lineal meters;
Allocation: Php 99,521,000.000
Excess: Php 479,000.000
|
February 1, 2023 |
2022 |
WIN2E02552 |
GAA 2022 |
January 2, 2022 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Construction of Bañacao Flood Control, Bangued, Abra;
Physical Target: 442.321 Lineal meters;
Allocation: Php 50,000,000.000
To: Construction of Bañacao Flood Control, Bangued, Abra;
Physical Target: 284 Lineal meters;
Allocation: Php 99,807,000.000
Excess: Php 193,000.000
|
February 1, 2023 |
2022 |
WIN2E02551 |
GAA 2022 |
January 2, 2022 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Construction of Coribot Flood Control Phase 2, Mudeng, La Paz, Abra;
Physical Target: 443.321 Lineal meters;
Allocation: Php 50,000,000.000
To: Construction of Coribot Flood Control Phase 2, Mudeng, La Paz, Abra;
Physical Target: 115 Lineal meters;
Allocation: Php 50,000,000.000
|
February 1, 2023 |
2022 |
WIN2E02547 |
GAA 2022 |
January 2, 2022 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Construction of Caribot Flood Control Structure, Barangay Mudeng, La Paz, Abra;
Physical Target: 444.321 Lineal meters;
Allocation: Php 50,000,000.000
To: Construction of Caribot Flood Control Structure, Barangay Mudeng, La Paz, Abra;
Physical Target: 111.8 Lineal meters;
Allocation: Php 50,000,000.000
|
February 1, 2023 |
2022 |
WIN2E02558 |
GAA 2022 |
January 2, 2022 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Construction of Flood Control Structure, Barangay Isit, Dolores, Abra;
Physical Target: 884.642 Lineal meters;
Allocation: Php 100,000,000.000
To: Construction of Flood Control Structure, Barangay Isit, Dolores, Abra;
Physical Target: 339.2 Lineal meters;
Allocation: Php 97,550,000.000
Excess: Php 2,450,000.000
|
February 1, 2023 |
2022 |
WIN2E02549 |
GAA 2022 |
January 2, 2022 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Construction of Flood Control Structure, Barangay Mudeng, La Paz, Abra;
Physical Target: 884.642 Lineal meters;
Allocation: Php 100,000,000.000
To: Construction of Flood Control Structure, Barangay Mudeng, La Paz, Abra;
Physical Target: 232.4 Lineal meters;
Allocation: Php 98,693,000.000
Excess: Php 1,307,000.000
|
February 1, 2023 |
2022 |
WIN2E02557 |
GAA 2022 |
January 2, 2022 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Construction of Flood Control Structure, Coribot, Barangay Mudeng, La Paz, Abra;
Physical Target: 884.642 Lineal meters;
Allocation: Php 100,000,000.000
To: Construction of Flood Control Structure, Coribot, Barangay Mudeng, La Paz, Abra;
Physical Target: 224.8 Lineal meters;
Allocation: Php 97,516,000.000
Excess: Php 2,484,000.000
|
February 1, 2023 |
2022 |
WIN2E02553 |
GAA 2022 |
January 2, 2022 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Construction of Flood Control Structure, Malabbaga, La Paz, Abra;
Physical Target: 884.642 Lineal meters;
Allocation: Php 100,000,000.000
To: Construction of Flood Control Structure, Malabbaga, La Paz, Abra;
Physical Target: 355.6 Lineal meters;
Allocation: Php 94,723,000.000
Excess: Php 5,277,000.000
|
February 1, 2023 |
2022 |
WIN2E02559 |
GAA 2022 |
January 2, 2022 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Construction of Flood Control Structure, Barangay Banbancag, Bucay, Abra;
Physical Target: 265.393 Lineal meters;
Allocation: Php 30,000,000.000
To: Construction of Flood Control Structure, Barangay Banbancag, Bucay, Abra;
Physical Target: 98 Lineal meters;
Allocation: Php 29,592,000.000
Excess: Php 408,000.000
|
January 27, 2023 |
FY 2022 |
WIN3F06768 |
DPWH Infra Projects FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 300215100199000
Project ID : P00638865LZ
CONVERGENCE AND SPECIAL SUPPORT PROGRAM
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) -
Access Roads and/or Bridges from the National Road/s leading to Major/Strategic Public Buildings/Facilities
FROM:
Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide along Port Barton to Barangay Kemdeng Road,
Sta. 2 + 926 - Sta. 3 + 230
Physical Target : CW1- Construction of Concrete Road :
10.556 lane km (l-km)
Allocation : Php 127.400Million
TO:
Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide along Port Barton to Barangay Kemdeng Road,
Sta. 014 +050.00 - Sta. 014 + 360.00
Physical Target : CW1- Construction of Road Slope Protection
Structure : 4,580.00 square meter
Allocation : Php 127.400 Million
|
January 26, 2023 |
FY 2021 |
WIN2F06733 |
UACS No. 320101106342000 |
March 14, 2022 |
National Capital Region |
Malabon-Navotas District Engineering Office |
As per GAA/Original
UACS No. 320101106342000
Project ID.: P00525708LZ
OO2: Protect Lives and Properties
Flood Management – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Riverwall and Road Dike along Batasan River (Phase 6), Brgy. Dampalit, Malabon City
Physical Target: CW1- Construction of Dike 0.00 lm
Unit Cost (P’000) = P 0.00/ l.m.
Allocation (P’000) = P 34,790.00
EAO (P’000) = P 710.00
Total (P’000) = P 35,500.00
As Modified
OO2: Protect Lives and Properties
Flood Management – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Riverwall and Road Dike along Batasan River (Phase 6), Brgy. Dampalit, Malabon City
Physical Target: CW1- Construction of Dike 74.50 lm
Unit Cost (P’000) = P 466.98/ l.m.
Allocation (P’000) = P 34,790.00/l.m.
EAO (P’000) = P 710.00
Total (P’000) = P 35,500.00
WIN2F06733
|
January 26, 2023 |
CY 2021 |
WIN3F06735 |
UACS No. 320101106344000 |
March 14, 2022 |
National Capital Region |
Malabon-Navotas District Engineering Office |
As per GAA/Original
UACS No. 320101106344000
Project ID.: P00525710LZ
OO2: Protect Lives and Properties
Flood Management – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Riverwall and Road Dike along Batasan River (Phase 8), Brgy. Dampalit, Malabon City
Physical Target: CW1- Construction of Dike 0.00 lm
Unit Cost (P’000) = P 0.00/ l.m.
Allocation (P’000) = P 34,790.00
EAO (P’000) = P 710.00
Total (P’000) = P 35,500.00
As Modified
OO2: Protect Lives and Properties
Flood Management – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Riverwall and Road Dike along Batasan River (Phase 8), Brgy. Dampalit, Malabon City
Physical Target: CW1- Construction of Dike 74.50 lm
Unit Cost (P’000) = P 460.7947/ l.m.
Allocation (P’000) = P 34,790.00/l.m.
EAO (P’000) = P 710.00
Total (P’000) = P 35,500.00
WIN3F06735
|
January 26, 2023 |
CY 2021 |
WIN3F06734 |
UACS No. 320101106345000 |
March 14, 2022 |
National Capital Region |
Malabon-Navotas District Engineering Office |
As per GAA/Original
UACS No. 320101106345000
Project ID.: P00525711LZ
OO2: Protect Lives and Properties
Flood Management – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Riverwall and Road Dike along Batasan River (Phase 9), Brgy. Dampalit, Malabon City
Physical Target: CW1- Construction of Dike 0.00 lm
Unit Cost (P’000) = P 0.00/ l.m.
Allocation (P’000) = P 34,790.00
EAO (P’000) = P 710.00
Total (P’000) = P 35,500.00
As Modified
OO2: Protect Lives and Properties
Flood Management – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Riverwall and Road Dike along Batasan River (Phase 9), Brgy. Dampalit, Malabon City
Physical Target: CW1- Construction of Dike 74.50 lm
Unit Cost (P’000) = P 466.98/ l.m.
Allocation (P’000) = P 34,790.00/l.m.
EAO (P’000) = P 710.00
Total (P’000) = P 35,500.00
WIN3F06734
|
January 26, 2023 |
CY 2021 |
WIN3F06736 |
UACS No. 320101106346000 |
March 14, 2022 |
National Capital Region |
Malabon-Navotas District Engineering Office |
As per GAA/Original
UACS No. 320101106346000
Project ID.: P00525712LZ
OO2: Protect Lives and Properties
Flood Management – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Riverwall and Road Dike along Batasan River (Phase 10), Brgy. Dampalit, Malabon City
Physical Target: CW1- Construction of Dike 0.00 lm
Unit Cost (P’000) = P 0.00/ l.m.
Allocation (P’000) = P 34,790.00
EAO (P’000) = P 710.00
Total (P’000) = P 35,500.00
As Modified
OO2: Protect Lives and Properties
Flood Management – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Riverwall and Road Dike along Batasan River (Phase 10), Brgy. Dampalit, Malabon City Physical Target: CW1- Construction of Dike 74.50 lm
Unit Cost (P’000) = P 466.98/ l.m.
Allocation (P’000) = P 34,790.00/l.m.
EAO (P’000) = P 710.00
Total (P’000) = P 35,500.00
WIN3F06736
|
January 16, 2023 |
2022 |
WIN2F06531 |
SARO-BMB-A-22-0002929 |
March 21, 2022 |
Cordillera Administrative Region |
Benguet 1st District Engineering Office |
From: Construction of Road, Mongol - Bolok Road, Batan, Kabayan, Benguet;
Type of Work: Construction of Concrete Road;
Physical Target: 3.021 Lane Km;
Allocation: Php 30,000,000.00
To: Construction of Road, Mongol - Bolok Road, Batan, Kabayan, Benguet;
Type of Work: Construction of Gravel Road;
Physical Target: 4.980 Lane Km;
Allocation: Php 30,000,000.00
|
January 16, 2023 |
2022 |
WIN2F06530 |
SARO-BMB-A-22-0002929 |
March 21, 2022 |
Cordillera Administrative Region |
Benguet 1st District Engineering Office |
From: Construction of Road, Disay Shelpi, Wangal, La Trinidad, Benguet;
Type of Work: Construction of Concrete Road;
Physical Target: 0.504 Lane Km;
Allocation: Php 50,000,000.000
To: Construction of Road, Disay Shelpi, Wangal, La Trinidad, Benguet;
Type of Work: Construction of Concrete Road;
Physical Target: 0.400 Lane Km;
Allocation: Php 50,000,000.000
|
January 16, 2023 |
2022 |
WIN2F06536 |
SR2022-03-007807 |
March 23, 2022 |
Cordillera Administrative Region |
Benguet 1st District Engineering Office |
From: Construction of Road, Ambacuan - Orign - La Trinidad Road, Sablan, Benguet;
Type of Work: Construction of Concrete Road;
Physical Target: 7.049 Lane Km;
Allocation: Php 70,000,000.000
To: Construction of Road, Ambacuag - Oring - La Trinidad Road, Sablan, Benguet;
Type of Work: Construction of Gravel Road;
Physical Target: 9.600 Lane Km;
Allocation: Php 70,000,000.000
|
January 16, 2023 |
2022 |
WIN2F06537 |
SARO-BMB-A-22-0002929 |
March 21, 2022 |
Cordillera Administrative Region |
Benguet 1st District Engineering Office |
From: Construction of Road, Baay to Crossing Apanberang, Pacso, Kabayan, Benguet;
Type of Work: Construction of Concrete Road;
Physical Target: 5.035 Lane Km;
Allocation: Php 50,000,000.000
To: Construction of Road, Baay to Crossing Apanberang, Pacso, Kabayan, Benguet;
Type of Work: Construction of Gravel Road;
Physical Target: 8.220 Lane Km;
Allocation: Php 50,000,000.000
|
January 16, 2023 |
2022 |
WIN2F06529 |
SARO-BMB-A-22-0002929 |
March 21, 2022 |
Cordillera Administrative Region |
Benguet 1st District Engineering Office |
From: Construction of Pines Park to Lubas-Ambiong Road, La Trinidad, Benguet;
Type of Work: Construction of Concrete Road;
Physical Target: 1.41 Lane Km;
Allocation: Php 14,000,000.000
To: Construction of Pines Park to Lubas-Ambiong Road, La Trinidad, Benguet;
Type of Work: Rehabilitation of Paved Road;
Physical Target: 1.124 Lane Km;
Allocation: Php 14,000,000.000
|
January 13, 2023 |
2022 |
WIN2E02556 |
SR2022-02-000130 |
February 3, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Kennon Rd - K0228 + 886 - K0228 + 970, K0237 + 529 - K0237 + 777, K0239 + 000 - K0239 + 100;
Physical Target: 26,507.780 Square meters;
Allocation: Php 477,140,000.000
To: Kennon Rd - K0228 + 810 - K0228 + 874, K0237 + 529 - K0237 + 680, K0239 + 395 - K0239 + 480;
Physical Target: 9861.800 Square meters;
Allocation: Php 476,866,000.000
Excess: Php 137,000.000
|
December 21, 2022 |
2022 |
WIN2F06703 |
FY 2022 GAA |
December 28, 2021 |
Region III |
Pampanga 1st District Engineering Office |
Network Development Program - Road Widening - Tertiary Roads
Candaba - Sn Miguel Rd - K0074+000 - K0074+120 |
November 21, 2022 |
2022 |
WIN2F06696 |
FY 2022 GAA |
November 28, 2021 |
Region III |
Regional Office III |
Network Development Program - Construction of Flyovers / Interchanges / Underpasses / Long Span Bridges
Hermosa - SCTEX Interchange, Hermosa, Bataan
|
November 9, 2022 |
2022 |
WIN2E02524 |
FY 2022 GAA R.A. 11639 |
January 1, 2022 |
Region XI |
Davao del Norte District Engineering Office |
MODIFICATION:
FROM: Convergence and Special Support Program – Basic Infrastructure Program (BIP) – Flood Mitigation Structures protecting Public Infrastructures/Facilities
Construction of Concrete Revetment including Pump Station, Sadpudon Creek, Carmen, Davao del Sur
Physical Target:
CW1: 60 lineal meters (Construction of Revetment)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 99,000,000.00 (Construction of Revetment)
EAO: P 1,000,000.00
TO: Convergence and Special Support Program – Basic Infrastructure Program (BIP) – Flood Mitigation Structures protecting Public Infrastructures/Facilities
Construction of Concrete Revetment including Pump Station, Sadpudon Creek, Carmen, Davao del Norte
Physical Target:
CW1: 60 lineal meters (Construction of Revetment)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 99,000,000.00 (Construction of Revetment)
EAO: P 1,000,000.00 |
October 17, 2022 |
FY 2022 |
WIN2XY00069 |
310204101150000 |
August 2, 2022 |
Region IX |
Regional Office IX |
UACS No. 310204101150000
Project ID: P00604249MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Bypass and Diversion Roads
Sominot-Dumingag Road, Zamboanga del Sur
CW1- Construction of Concrete Road
Physical Target: 0.956 Lane Km
Unit Cost: ₱ 36,465,670.09/Lane km
CW2- Construction of Concrete Bridge
Physical Target: 294.786 square meters
Unit Cost: ₱ 110,296.3485/square meters
ROW- Right-Of-Way Acquisition
Physical Target: 16,666.67 sq.m.
Unit Cost: ₱ 300.00/sq.m.
EAO: ₱ 2,625,000.00
Allocation: ₱ 75,000,000.00
|
October 17, 2022 |
FY 2022 |
WIN2XY00068 |
310204101596000 |
July 20, 2022 |
Region IX |
Regional Office IX |
UACS No. 310204101596000
Project ID: P00604238MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Bypass and Diversion Roads
Zamboanga City By-pass Road, Widening of Tulungatung Bridge including approaches), Zamboanga City
CW1- Widening of Bridge
Physical Target: 390.186 sq.m.
Unit Cost: ₱ 196,089.92/sq.m.
CW2- Road Widening
Physical Target: 1.16 Lane km
Unit Cost: ₱ 19,352,120.17/Lane km
ROW- Right-Of-Way Acquisition
Physical Target: 2,800.00 sq.m.
Unit Cost: ₱ 500.00/sq.m.
EAO: ₱ 3,640,000.00
Total Allocation: ₱ 104,000,000.00 |
October 17, 2022 |
FY 2022 |
WIN2XY00064 |
310206100068000 |
July 20, 2022 |
Region IX |
Regional Office IX |
UACS No. 310206100068000
Project ID: P00603881MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Flyovers/ Interchanges/ Underpasses/ Long Span Bridges
Gov. Camins/MCLL Highway and Veterans Ave. Flyover
CW1- Construction of Flyover
Physical Target: 7,659.75 Square Meters
Unit cost: ₱ 16,685.99/Square Meters
ROW- Right of Way Acquisition
Physical Target: 564.65 sq.m.
Unit cost: ₱ 30,000.00/sq.m.
EAO: ₱ 5,250,000.00
Allocation: ₱ 150,000,000.00 |
October 17, 2022 |
FY 2022 |
WIN2XY00081 |
310205100833000 |
July 13, 2022 |
Region IX |
Regional Office IX |
UACS No. 310205100833000
Project ID: P00603790MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Missing Links/ New Roads
Zamboanga del Sur Coastal Road, Brgy. Biu os-Brgy. Talanusa, Phase 2, Zamboanga del Sur
CW1- Construction of Concrete Road
Physical Target: 1.88 Lane Km
Unit Cost: ₱ 46,728,723.40/Lane km
ROW- Right-Of-Way Acquisition
Physical Target: 33,333.333 sq.m.
Unit Cost: ₱ 346.35/sq.m.
EAO: ₱ 3,605,000.00
Total Allocation: ₱ 103,000,000.00 |
October 17, 2022 |
FY 2022 |
WIN2XY00067 |
300217100046000 |
July 20, 2022 |
Region IX |
Regional Office IX |
UACS No. 300217100046000
Project ID: P00633888MN
Convergence and Special Support Program - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Interjurisdictional Roads and/or Bridges (or, roads that traverse multiple LGU jurisdictions)
Preventive Maintenance along Lanao-Pagadian-Zamboanga City Road
CW1- Preventive Maintenance of Road: Asphalt Overlay
Physical Target: 2.982 Lane km
Unit Cost: ₱ 16,501,470.56/Lane km
CW1- Preventive Maintenance of Road: Concrete Reblocking
Physical Target: 0.852 Lane km
Unit Cost: ₱ 10,202,599.51/Lane km
EAO: ₱ 2,100,000.00
Allocation: ₱ 60,000,000.00 |
October 10, 2022 |
2022 |
WIN2XY00102 |
SR2022-02-000855 |
February 3, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Banaue-Mayoyao-A Lista-Isabela Bdry Rd - K0362 + 040 - K0362 + 240, K0386 + 536 - K0387 + 000, K0409 + 600 - K0409 + 765;
Physical Target: 3,333.300 Square meters;
Allocation: Php 60,000,000.000
To: Banaue-Mayoyao-A Lista-Isabela Bdry Rd - K0362 + 080 - K0362 + 140;
Physical Target: 2,190.000 Square meters;
Allocation: Php 60,000,000.000
|
October 3, 2022 |
2022 |
WIN2F06615 |
FY 2022 GAA |
December 28, 2021 |
Region III |
Regional Office III |
Convergence and Special Support Program - Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road /s leading to Major/Strategic Public Buildings / Facilities
Construction of Road, Ciudad de Victoria (Phase II), Bocaue, Bulacan |
September 29, 2022 |
FY 2022 |
WIN2B00921 |
300215100441000 |
July 1, 2022 |
Region IX |
Regional Office IX |
UACS No. 300215100441000
Project ID: P00633756MN
Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Construction of Road, Camp Andres Tandu Bato Romandier National, Km. 40 + 200 - Km. 41 + 520, Luuk, Sulu
CW1 - Construction of Concrete Road : 2.64 lane km
Unit Cost: P 21,931,818.18 /lane km
EAO: P 2,100,000.00
Allocation: P 60,000,000.00 |
September 29, 2022 |
FY 2022 |
WIN2B00892 |
300221100054000 |
April 22, 2022 |
Region IX |
Regional Office IX |
UACS No. 300221100054000
Project ID: P00630775MN
Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Construction of Tabu Bato Access Road from Maimbung - Indanan Road, Barangay Tabo Bato, Maimbung, Sulu
CW1 - Construction of Concrete Road : 0.78 lane km
Unit Cost: P 10,153,846.00 /lane km
EAO: P 800,000.00
Allocation: P 8,000,000.00 |
September 29, 2022 |
FY 2022 |
WIN2B00896 |
300221100051000 |
April 22, 2022 |
Region IX |
Regional Office IX |
UACS No. 300221100051000
Project ID: P00630772MN
Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Construction of Access Road leading to Bud Agad, Barangay Anuling, Patikul, Sulu
CW1 - Construction of Concrete Road : 0.99 lane km
Unit Cost: P 10,000,000.00 /lane km
EAO: P 100,000.00
Allocation: P 10,000,000.00 |