September 29, 2022 |
FY 2022 |
WIN2B00894 |
310203100522000 |
March 23, 2022 |
Region IX |
Regional Office IX |
UACS No. 310203100522000
Project ID: P00602306MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Tertiary Roads
Sanga - Sanga - Bato - Bato Road (Package I) - Sta. 9+891.72 - Sta. 12+040.00
CW1 - Road Widening : 4.297 lane km
Unit Cost: P 15,896,361.00 /lane km
ROW - Right of Way Acquisition : 3,319.448 sq.m.
Unit Cost: P 300.00 /sq. m
EAO: P 2,553,250.00
EXCESS : P 1,094,250.00
Allocation: P 72,950,000.00 |
September 29, 2022 |
FY 2022 |
WIN2B00899 |
300222100009000 |
April 22, 2022 |
Region IX |
Regional Office IX |
UACS No. 300222100009000
Project ID: P00631050MN
Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Roads connecting to Indigenous People (IP) Communities
Rehabilitation of Kulasi - Lihdung Access Road connecting to Badjao Indigenous People(IP) Community, Barangay Kulasi, Maimbung, Sulu
CW1 - Rehabilitation of Concrete Road : 0.72 lane km
Unit Cost: P 11,000,000.00 /lane km
EAO: P 80,000.00
Allocation: P 8,000,000.00 |
September 29, 2022 |
FY 2022 |
WIN2B00925 |
300215100435000 |
July 1, 2022 |
Region IX |
Regional Office IX |
UACS No. 300215100435000
Project ID: P00633753MN
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/Facilities
Construction of Tandu - Bato Camp Andres - Gaguil Road, Sulu
CW1 - Construction of Concrete Road : 5.29 lane km
Unit Cost: P 18,241,965.97 /lane km
EAO: P 3,500,000.00
Allocation: P 100,000,000.00 |
September 29, 2022 |
FY 2022 |
WIN2B00927 |
300217100044000 |
July 1, 2022 |
Region IX |
Regional Office IX |
UACS No. 300217100044000
Project ID: P00633886MN
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Interjurisdictional Roads and/or Bridges (or, roads that traverse multiple LGU jurisdictions)
Rehabilitation of Road, Maimbung - Ipil - Bilaan Road (Sta. 0008+000 - Sta. 0011+675), Maimbung and Talipao, Sulu
CW1 - Rehabilitation of Concrete Road : 7.35 lane km
Unit Cost: P 19,693,877.55 /lane km
EAO: P 5,250,000.00
Allocation: P 150,000,000.00 |
September 29, 2022 |
FY 2022 |
WIN2B00931 |
300217100043000 |
July 1, 2022 |
Region IX |
Regional Office IX |
UACS No. 300217100043000
Project ID: P00633885MN
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Interjurisdictional Roads and/or Bridges (or, roads that traverse multiple LGU jurisdictions)
Rehabilitation of Road, Jolo - Batobato - Silangkan Road (Sta. 0010+750 - Sta. 0015+700), Jolo - Indanan, Sulu
CW1 - Rehabilitation of Concrete Road : 9.90 lane km
Unit Cost: P 14,621,212.12 /lane km
EAO: P 5,250,000.00
Allocation: P 150,000,000.00 |
September 29, 2022 |
FY 2022 |
WIN2B00924 |
300221100064000 |
July 1, 2022 |
Region IX |
Regional Office IX |
UACS No. 300221100064000
Project ID: P00630785MN
Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Rehabilitation of Kandang - Ratag Limbun Access Road from Parang - Maimbung - Talipao Road, Barangay Ratag Limbun, Maimbung, Sulu
CW1 - Rehabilitation of Concrete Road : 0.93 lane km
Unit Cost: P 10,734,940.00 /lane km
EAO: P 90,000.00
Allocation: P 9,000,000.00 |
September 29, 2022 |
2022 |
WIN2E02511 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Regional Office XIII |
UACS No. : 310204101905000
Project ID: P00604281MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Construction of By-Pass and Diversion Roads
FROM:
Butuan City-Agusan Del Norte Logistical Highway, Package 16, Butuan City
Type of Work:
CW1- Construction of Gravel Road
ROW- ROW Acquisition
Physical Target:
CW1- 3.270 Lane Km
ROW- 8,739.620 Square meters
Allocation:
TOTAL: P 98,000,000
CW1: P 89,745,000
ROW: P 4,825,000
EAO: P 3,430,000
Unit Cost:
CW1: P 27,444,954.13/Lane Km
ROW: P 552.08/Square meters
TO:
Butuan City-Agusan Del Norte Logistical Highway, Package 16, Butuan City
Type of Work:
CW1- Construction of Gravel Road
ROW- ROW Acquisition
Physical Target:
CW1- 2.070 Lane Km
ROW- 8,739.620 Square meters
Allocation:
TOTAL: P 98,000,000
CW1: P 89,745,000
ROW: P 4,825,000
EAO: P 3,430,000
Unit Cost:
CW1: P 43,355,072.46/Lane Km
ROW: P 552.08/Square meters |
September 27, 2022 |
2022 |
WIN2F06597 |
FY 2022 GAA |
December 28, 2021 |
Region III |
Pampanga 1st District Engineering Office |
Asset Preservation Program - Construction / Upgrading / Rehabilitation of Drainage along National Roads - Tertiary Roads
Candaba - Sn Miguel Rd - K0081+863 - K0082+713 |
September 26, 2022 |
2022 |
WIN2XY00055 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. : 300221102184000
Project ID: P00634111MN
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
FROM:
Construction of Road at Candava, Barangay Washington, Surigao City, Surigao del Norte
Type of Work:
CW1- Construction of Concrete Road
Physical Target:
CW1- 0.466 Lane Km
Allocation:
TOTAL: P 5,000,000
CW1: P 4,950,000
EAO: P 50,000
Unit Cost:
CW1: P 10,622,317.60/Lane Km
TO:
Construction of Road at Candava, Barangay Washington, Surigao City, Surigao del Norte
Type of Work:
CW1- Construction of Concrete Road
Physical Target:
CW1- 0.682 Lane Km
Allocation:
TOTAL: P 5,000,000
CW1: P 4,950,000
EAO: P 50,000
Unit Cost:
CW1: P 7,258,064.52/Lane Km
|
September 26, 2022 |
2022 |
WIN2E02300 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Regional Office XIII |
UACS No. : 320102104749000
Project ID: P00620256MN
ORGANIZATIONAL OUTCOME 2 : Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers
FROM:
Construction of Flood Mitigation Structure along Agusan River (Tungao Section) Package 2, Sta. 0+000.00 - Sta. 0+175.80, Butuan City, Agusan del Norte
Type of Work:
CW1- Construction of Flood Mitigation Structure
Physical Target:
CW1- 283.058 Lineal meters
Allocation:
TOTAL: P 100,852,000
CW1: P 97,322,180
EAO: P 3,529,820
Unit Cost:
CW1: P 343,824.16/Lineal meters
TO:
Construction of Flood Mitigation Structure along Agusan River (Tungao Section) Package 2, Sta. 0+228 - Sta. 0+355, Butuan City, Agusan del Norte
Type of Work:
CW1- Construction of Flood Mitigation Structure
Physical Target:
CW1- 127.000 Lineal meters
Allocation:
TOTAL: P 100,852,000
CW1: P 97,322,180
EAO: P 3,529,820
Unit Cost:
CW1: P 766,316.38/Lineal meters |
September 26, 2022 |
2022 |
WIN2E02082 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Regional Office XIII |
UACS No. : 320101107789000
Project ID: P00620105MN
ORGANIZATIONAL OUTCOME 2 : Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
FROM:
Construction of Revetment along Telaje River, Brgy. Dagocdoc, Sta. 0+000.00 - Sta. 0+138.40, Tandag City, Surigao Del Sur
Type of Work:
CW1- Construction of Flood Mitigation Structure
Physical Target:
CW1- 827.804 Lineal meters
Allocation:
TOTAL: P 105,000,000
CW1: P 101,325,000
EAO: P 3,675,000
Unit Cost:
CW1: P 122,402.216/Lineal meters
TO:
Construction of Revetment along Telaje River, Brgy. Dagocdoc, Sta. 0+000.00 - Sta. 0+058.7, Sta. 0+071.6 - Sta. 0+460.20, Sta. 0+460.2 - Sta. 0+496.00, Tandag City, Surigao Del Sur
Type of Work:
CW1- Construction of Flood Mitigation Structure
Physical Target:
CW1- 518.900 Lineal meters
Allocation:
TOTAL: P 105,000,000
CW1: P 101,325,000
EAO: P 3,675,000
Unit Cost:
CW1: P 195,268.830/Lineal meters
|
September 26, 2022 |
2022 |
WIN2F06446 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 310218100028000
Project ID: P00639307LZ
AS PER GAA:
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Coastal Roads/Causeway for environmental protection/conservation - Construction of Poblacion Coastal Road/Back Up Area, Brgy. Poblacion, Rapu - Rapu, Albay
Physical Target: CW1 - Construction of Road Slope Protection Structure – 3854.488 Square meters
Allocation (Php): Php 200,000,000
AS MODIFIED:
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Coastal Roads/Causeway for environmental protection/conservation - Construction of Poblacion Coastal Road/Back Up Area, Brgy. Poblacion, Rapu - Rapu, Albay
Physical Target: CW1 - Construction of Road Slope Protection Structure – 2380.62 Square meters
|
September 26, 2022 |
2022 |
WIN2F06507 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 310219100153000
Project ID: P00639389LZ
AS PER GAA:
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Drainage Structures in Barangay Bigaa, Buyuan, Bonga, Pawa, Bogtong, Rawis, Gogon, Cruzada, San Roque, Bonot, Padang, Bagong Abre, Matanag, Mabinit, Legazpi City, Albay
Physical Target: CW1 - Construction of Drainage Structure – 8432.00 Lineal meters
Allocation (Php): Php 149,000,000
AS MODIFIED:
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Drainage Structures in Barangay Bigaa, Buyuan, Bonga, Pawa, Bogtong, Rawis, Gogon, Cruzada, San Roque, Bonot, Padang, Bagong Abre, Matanag, Mabinit, Legazpi City, Albay
Physical Target: CW1 - Construction of Drainage Structure – 4211.32 Lineal meters
|
September 26, 2022 |
2022 |
WIN2E02512 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Regional Office XIII |
UACS No. : 300217100101000
Project ID: P00630447MN
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Interjurisdictional Roads and/or Bridges (or, roads that traverse multiple LGU jurisdictions)
FROM:
Agusan del Norte / Agusan del Sur North - South Lateral Road, (Las Nieves, Agusan del Norte - Kapalong, Davao del Norte), Package 1, Agusan del Sur
Type of Work:
CW1- Construction of Concrete Road
Physical Target:
CW1- 8.600 Lane Km
Allocation:
TOTAL: P 180,000,000
CW1: P 173,700,000
EAO: P 6,300,000
Unit Cost:
CW1: P 20,197,674.42/Lane Km
TO:
Agusan del Norte / Agusan del Sur North - South Lateral Road, (Las Nieves, Agusan del Norte - Kapalong, Davao del Norte), Package 1, Agusan del Sur
Type of Work:
CW1- Construction of Gravel Road
Physical Target:
CW1- 6.120 Lane Km
Allocation:
TOTAL: P 180,000,000
CW1: P 173,700,000
EAO: P 6,300,000
Unit Cost:
CW1: P 28,382,352.94/Lane Km
|
September 26, 2022 |
2022 |
WIN2F06416 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 310219100154000
Project ID: P00639390LZ
AS PER GAA:
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Obi River Control Structures, Brgy. Obi, Caramoran, Catanduanes
Physical Target: CW1 - Construction of Flood Mitgation Structure – 1080 Lineal meters
Allocation (Php): Php 115,000,000
AS MODIFIED:
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Obi River Control Structures, Brgy. Obi, Caramoran, Catanduanes
Physical Target: CW1 - Construction of Flood Mitigation Structure – 462 Lineal meters
Allocation (Php): Php 115,000,000
|
September 26, 2022 |
2022 |
WIN2E02514 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Regional Office XIII |
UACS No. : 310204101720000
Project ID: P00604289MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Construction of By-Pass and Diversion Roads
FROM:
Butuan City-Agusan Del Norte Logistical Highway, Package 24, Butuan City
Type of Work:
CW1- Construction of Gravel Road
ROW- ROW Acquisition
Physical Target:
CW1- 4.225 Lane Km
ROW- 13,983.39 Square meters
Allocation:
TOTAL: P 105,000,000
CW1: P 93,605,000
ROW: P 7,720,000
EAO: P 3,675,000
Unit Cost:
CW1: P 22,155,029.59/Lane Km
ROW: P 552.08/Square meters
TO:
Butuan City-Agusan Del Norte Logistical Highway, Package 24, Butuan City
Type of Work:
CW1- Construction of Gravel Road
ROW- ROW Acquisition
Physical Target:
CW1- 1.662 Lane Km
ROW- 13,983.39 Square meters
Allocation:
TOTAL: P 105,000,000
CW1: P 93,605,000
ROW: P 7,720,000
EAO: P 3,675,000
Unit Cost:
CW1: P 56,320,697.95/Lane Km
ROW: P 552.08/Square meters
|
September 26, 2022 |
2022 |
WIN2F06413 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 310219100161000
Project ID: P00639397LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Shore Protection, Bahi Seawall (Phase 2), Bacacay, Albay
Physical Target: CW1 – Construction of Road Slope Protection Structure – 5293.46 Square meters
Allocation (Php): 170,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Shore Protection, Bahi Seawall (Phase 2), Bacacay, Albay
Physical Target: CW1 – Construction of Road Slope Protection Structure – 4313.45 Square meters
Allocation (Php): 170,000,000
|
September 26, 2022 |
2022 |
WIN2F06447 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Rehabilitation of Flood Control Structure at Binagasbasan, Brgy. Paraiso, San Miguel, Catanduanes
Physical Target: CW1 – Rehabilitation / Major Repair of Flood Control Structure – 1093.00 Square meters
Allocation (Php): 115,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Rehabilitation of Flood Control Structure at Binagasbasan, Brgy. Paraiso, San Miguel, Catanduanes
Physical Target: CW1 – Rehabilitation / Major Repair of Flood Control Structure – 376.10 Square meters
|
September 26, 2022 |
2022 |
WIN2E02513 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Regional Office XIII |
UACS No. : 310204101912000
Project ID: P00604288MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Construction of By-Pass and Diversion Roads
FROM:
Butuan City-Agusan Del Norte Logistical Highway, Package 23, Butuan City
Type of Work:
CW1- Construction of Gravel Road
ROW- ROW Acquisition
Physical Target:
CW1- 1.918 Lane Km
ROW- 8,739.62 Square meters
Allocation:
TOTAL: P 68,000,000
CW1: P 60,795,000
ROW: P 4,825,000
EAO: P 2,380,000
Unit Cost:
CW1: P 31,697,080.29/Lane Km
ROW: P 552.08/Square meters
TO:
Butuan City-Agusan Del Norte Logistical Highway, Package 23, Butuan City
Type of Work:
CW1- Construction of Gravel Road
ROW- ROW Acquisition
Physical Target:
CW1- 1.010 Lane Km
ROW- 8,739.62 Square meters
Allocation:
TOTAL: P 68,000,000
CW1: P 60,795,000
ROW: P 4,825,000
EAO: P 2,380,000
Unit Cost:
CW1: P 60,193,069.31/Lane Km
ROW: P 552.08/Square meters |
September 26, 2022 |
2022 |
WIN2F06457 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300219100225000
Project ID: P00639400LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Road Dike Along Hitoma River, Sta. 0+000 - Sta. 0+300 (With Exception), Brgy. Obi, Caramoran, Catanduanes
Physical Target: CW1 – Construction of Dike – 300.00 Lineal meters
Allocation (Php): 180,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Road Dike Along Hitoma River, Sta. 4+023.50 - Sta. 5+547.38; (With Exception), Brgy. Obi, Caramoran, Catanduanes
Physical Target: CW1 – Construction of Dike – 601.88 Lineal meters
|
September 26, 2022 |
2022 |
WIN2F06509 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 30022510032000
Project ID: P00640474LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Pantao Seawall, Barokoda-Maligaya, Libon, Alba
Physical Target: CW1 – Construction of Road Slope Protection Structure – 2963.81 Square meters
Allocation (Php): 110,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Pantao Seawall, Baracuda-Maligaya, Libon, Albay
Physical Target: CW1 – Construction of Road Slope Protection Structure – 2963.81 Square meters
Allocation (Php): 110,000,000
|
September 26, 2022 |
2022 |
WIN2F06500 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300225100036000
Project ID: P00640478LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Rehabilitation of Flood Mitigation Structure along Bito River, Brgy. Buena Suerte, San Fernando, Masbate
Physical Target: CW1 – Rehabilitation / Major Repair of Flood Control Structure – 613.93 Lineal meters
Allocation (Php): 100,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Rehabilitation of Flood Mitigation Structure along Bito River, Barangay Buenos Aires, San Fernando, Masbate
Physical Target: CW1 – Rehabilitation / Major Repair of Flood Control Structure – 473.83 Lineal meters
Allocation (Php): 100,000,000
|
September 26, 2022 |
2022 |
WIN2F06411 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 30022510038000
Project ID: P00640480LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Rehabilitation of Flood Mitigation Structure along Tutuban River, Brgy. Sta. Rosa, San Jacinto, Masbate
Physical Target: CW1 – Rehabilitation / Major Repair of Flood Control Structure – 618.18 Lineal meters
Allocation (Php): 100,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Rehabilitation of Flood Mitigation Structure along Tutuban River, Brgy. Sta. Rosa, San Jacinto, Masbate
Physical Target: CW1 – Rehabilitation / Major Repair of Flood Control Structure – 800.62 Lineal meters
Allocation (Php): 100,000,000
|
September 26, 2022 |
2022 |
WIN2F06456 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 30022510039000
Project ID: P00640481LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Rehabilitation of Shore Protection Structure, Brgy. Guinhadap, Monreal, Masbate
Physical Target: CW1 – Rehabilitation / Major Repair of Slope Protection Structure – 1297.35 Square meters
Allocation (Php): 100,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Rehabilitation of Shore Protection Structure, Brgy. Guinhadap, Monreal, Masbate
Physical Target: CW1 – Rehabilitation / Major Repair of Slope Protection Structure – 2439.49 Square meters
Allocation (Php): 100,000,000
|
September 26, 2022 |
2022 |
WIN2F06501 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 30022510040000
Project ID: P00640482LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Rehabilitation of Shore Protection Structure, Sitio Busdak, Brgy. Bartolabac, San Jacinto, Masbate
Physical Target: CW1 – Rehabilitation / Major Repair of Slope Protection Structure – 3963.35 Square meters
Allocation (Php): 100,000,000
AS MODIFIED: ONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Rehabilitation of Shore Protection Structure, Sitio Busdak, Brgy. Bartolabac, San Jacinto, Masbate
Physical Target: CW1 – Rehabilitation / Major Repair of Slope Protection Structure – 1842.00 Square meters
|
September 26, 2022 |
2022 |
WIN2F06463 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300215100347000
Project ID: P00641235LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Provincial Road (Pantao to Camarines Sur), Pantao Section, Libon, Albay
Physical Target: CW1 – Construction of Concrete Road – 1.56 Lane Km
CW2 – Construction of Road Slope Protection Structure – 10484.65 Square meters
Allocation (Php): 249,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Provincial Road (Pantao to Camarines Sur), Pantao Section, Libon, Albay
Physical Target: CW1 – Construction of Concrete Road – 0.816 Lane Km
CW2 – Construction of Road Slope Protection Structure – 4273.05 Square meters
CW3 – Construction of Gravel Road – 4.33 Lane Km
Allocation (Php): 249,000,000
|
September 26, 2022 |
2022 |
WIN2F06452 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300215100350000
Project ID: P00641238LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Road, Batbat - Marcial O. Rañola - Palanas, Guinobatan, Albay
Physical Target: CW1 – Construction of Concrete Road – 8.48 Lane Km
CW2 – Construction of Road Slope Protection Structure – 7198.32 Square meters
Allocation (Php): 149,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Road, Batbat - Marcial O. Rañola - Palanas, Guinobatan, Albay
Physical Target: CW1 – Construction of Concrete Road – 3.16 Lane Km
CW2 – Construction of Road Slope Protection Structure – 2999.46 Square meters
Allocation (Php): 149,000,000
|
September 26, 2022 |
2022 |
WIN2F06510 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300215100321000
Project ID: P00641852LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Road, Dugui San Vicente to National Road, Virac, Catanduanes
Physical Target: CW1 – Construction of Concrete Road – 1.152 Lane Km
CW2 – Construction of Road Slope Protection Structure – 2335.24 Square meters
CW3 – Construction of Drainage Structure along Road – 379.58 Lineal meter
Allocation (Php): 30,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Road, Dugui San Vicente to National Road, Virac, Catanduanes
Physical Target: CW1 – Construction of Concrete Road – 0.722 Lane Km
CW2 – Construction of Road Slope Protection Structure – 655.5 Square meters
CW3 – Construction of Drainage Structure along Road – 439Lineal meter
|
September 26, 2022 |
2022 |
WIN2F06472 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300205100082000
Project ID: P00642361LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/ Rehabilitation of Water Supply/ Septage and Sewerage/ Rainwater Collector System - Water Supply System - Construction of Water System (Level II) Project in the Province of Sorsogon
Physical Target: CW1 – Construction of Water Supply Systems – 1.0 Number of Water Supply Systems
Allocation (Php): 50,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/ Rehabilitation of Water Supply/ Septage and Sewerage/ Rainwater Collector System - Water Supply System - Construction of Water System (Level II) Project in the Province of Sorsogon
Physical Target: CW1 – Construction of Water Supply Systems – 10.0 Number of Water Supply Systems
|
September 26, 2022 |
2022 |
WIN2F06469 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300205100083000
Project ID: P00642362LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/ Rehabilitation of Water Supply/ Septage and Sewerage/ Rainwater Collector System - Water Supply System - Construction of Water System Level II Project, Albay
Physical Target: CW1 – Construction of Water Supply Systems – 1.0 Number of Water Supply Systems
Allocation (Php): 100,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/ Rehabilitation of Water Supply/ Septage and Sewerage/ Rainwater Collector System - Water Supply System - Construction of Water System Level II Project, Albay
Physical Target: CW1 – Construction of Water Supply Systems – 20.0 Number of Water Supply Systems
Allocation (Php): 100,000,000
|
September 26, 2022 |
2022 |
WIN2F06513 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300205100084000
Project ID: P00642363LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/ Rehabilitation of Water Supply/ Septage and Sewerage/ Rainwater Collector System - Water Supply System - Construction of Water System Level II Project, Camarines Sur
Physical Target: CW1 – Construction of Water Supply Systems – 1.0 Number of Water Supply Systems
Allocation (Php): 100,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/ Rehabilitation of Water Supply/ Septage and Sewerage/ Rainwater Collector System - Water Supply System - Construction of Water System Level II Project, Camarines Sur
Physical Target: CW1 – Construction of Water Supply Systems – 20.0 Number of Water Supply Systems
Allocation (Php): 100,000,000
|
September 26, 2022 |
2022 |
WIN2F06475 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 30022510037000
Project ID: P00640479LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Rehabilitation of Flood Mitigation Structure along Dorong-an River, Brgy. Dorong-an, San Jacinto, Masbate
Physical Target: CW1 – Rehabilitation / Major Repair of Flood Control Structure – 615.54 Lineal meters
Allocation (Php): 100,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Rehabilitation of Flood Mitigation Structure along Dorong-an River, Brgy. Bagahanglad, San Jacinto, Masbate
Physical Target: CW1 – Rehabilitation / Major Repair of Flood Control Structure – 564.29 Lineal meters
Allocation (Php): 100,000,000
|
September 20, 2022 |
2022 |
WIN2E02510 |
FY 2022 GAA R.A. 11639 |
January 1, 2022 |
Region XI |
Regional Office XI |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System – Network Development – Construction of Missing Links/ New Roads
Bukidnon – Compostela Valley Road, Brgy. Namnam, San Fernando, Bukidnon – Laak Compostela Valley (Package 13), Davao del Norte
Physical Target:
CW1: 2.675 Lane Km (Construction of Gravel Road)
CW2: 858.600 sq. m. (Construction of Bridge)
ROW Acquisition: 20,070.000 sq. m. (ROW Acquisition)
Allocation:
TOTAL: P 250,000,000.00
CW1: P 144,277,150.00 (Construction of Gravel Road)
CW2: P 91,761,850.00 (Construction of Bridge)
ROW Acquisition: P 5,211,000.00
EAO: P 8,750,000.00
TO: OO1: Ensure Safe and Reliable National Road System – Network Development – Construction of Missing Links/ New Roads
Bukidnon – Compostela Valley Road, Brgy. Namnam, San Fernando, Bukidnon – Laak Compostela Valley (Package 13), Davao del Norte
Physical Target:
CW1: 2.16252 Lane Km (Construction of Gravel Road)
CW2: 858.600 sq. m. (Construction of Bridge)
ROW Acquisition: 16,350.000 sq. m. (ROW Acquisition)
Allocation:
TOTAL: P 250,000,000.00
CW1: P 123,479,800.00 (Construction of Gravel Road)
CW2: P 113,215,400.00 (Construction of Bridge)
ROW Acquisition: P 4,554,800.00
EAO: P 8,750,000.00 |
September 20, 2022 |
2022 |
WIN2XY00042 |
SR2022-03-007815 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Construction of Road, Camp 1 - Tabaan Sur - Tabaan Norte - Taloy Sur Road to Marcos Highway, Tuba Benguet;
Physical Target: 22.155 Lane Km;
Allocation: Php 220,000,000.000
To: Construction of Road, Camp 1 - Tabaan Sur - Tabaan Norte - Taloy Sur Road to Marcos Highway, Tuba Benguet;
Physical Target: 17.120 Lane Km;
Allocation: Php 220,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00043 |
SR2022-03-007821 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Construction of Road, Lab-Ang - Ampucao to Bitnong-Ansagan Road, Itogon & Tuba, Benguet;
Physical Target: 10.070 Lane Km;
Allocation: Php 100,000,000.000
To: Construction of Road, Lab-Ang - Ampucao to Bitnong-Ansagan Road, Itogon & Tuba, Benguet;
Physical Target: 8.000 Lane Km;
Allocation: Php 100,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00047 |
SR2022-03-007830 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Construction of Road, Solnob/Belao - Cemento Road, Bokod, Benguet;
Physical Target: 10.070 Lane Km;
Allocation: Php 100,000,000.000
To: Construction of Road, Solnob/Belao - Cemento Road, Bokod, Benguet;
Physical Target: 7.600 Lane Km;
Allocation: Php 100,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00049 |
SR2022-03-007834 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Construction of Road, Tinongdan Proper - Cayuco - Cawayan Road, Itogon, Benguet;
Physical Target: 10.070 Lane Km;
Allocation: Php 100,000,000.000
To: Construction of Road, Tinongdan Proper - Cayuco - Cawayan Road, Itogon, Benguet;
Physical Target: CW1: 4.000
CW2: 0.320 Lane Km;
Allocation: Php 100,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00046 |
SR2022-03-007817 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Construction of Road, Gadang - Lanas - Amponget - Bagulin, Gadang & Sagubo, Kapangan, Benguet;
Physical Target: 15.110 Lane Km; Allocation:
Php 150,000,000.000
To: Construction of Road, Gadang - Lanas - Amponget - Bagulin, Gadang & Sagubo, Kapangan, Benguet;
Physical Target: 7.840 Lane Km;
Allocation: Php 150,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00045 |
SR2022-03-007823 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Construction of Road, Liwang - Akmet - Dek-dek, Mankayan, Benguet;
Physical Target: 10.070 Lane Km;
Allocation: Php 100,000,000.000
To: Construction of Road, Liwang - Akmet - Dek-dek, Mankayan, Benguet;
Physical Target: 7.280 Lane Km;
Allocation: Php 100,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00044 |
SR2022-03-007827 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Construction of Road, Poblacion - Sagpat - Lubo - Madaymen, Kibungan, Benguet;
Physical Target: 10.070 Lane Km;
Allocation: Php 100,000,000.000
To: Construction of Road, Poblacion - Sagpat - Lubo - Madaymen, Kibungan, Benguet;
Physical Target: 5.928 Lane Km;
Allocation: Php 100,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00057 |
SARO-BMB-A-22-0002937 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Construction of Flood Control Structure along Nayon River, Sta. 13+916- Sta. 14+140, (Bimpal side) Lamut, Ifugao;
Physical Target: 115.004 Lineal meters;
Allocation: Php 13,000,000.000
To: Construction of Flood Control Structure along Nayon River, Sta. 13+904- Sta. 13+960 and Sta. 13+970- Sta. 14+114, (Bimpal side) Lamut, Ifugao;
Physical Target: 192.000 Lineal meters;
Allocation: Php 13,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00070 |
SR2022-02-000850 |
February 3, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Banaue-Mayoyao-A Lista-Isabela Bdry Rd - K0353 + 740 - K0353 + 848;
Physical Target: 5,246.890 Square meters;
Allocation: Php 94,444,000.000
To: Banaue-Mayoyao-A Lista-Isabela Bdry Rd - K0353 + 710 - K0353 + 804;
Physical Target: 3,566.000 Square meters;
Allocation: Php 94,444,000.000
|
September 20, 2022 |
2022 |
WIN2XY00058 |
SR2022-02-000852 |
February 3, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Banaue-Mayoyao-A Lista-Isabela Bdry Rd - K0358 + 880 - K0359 + 047;
Physical Target: 3,833.330 Square meters;
Allocation: Php 69,000,000.000
To: Banaue-Mayoyao-A Lista-Isabela Bdry Rd - K0358 + 842 - K0359 + 047;
Physical Target: 2,683.000 Square meters;
Allocation: Php 69,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00061 |
SR2022-03-007695 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Baguio-Bontoc Rd - K0369 + 640 - K0369 + 930;
Physical Target: 10,000.000 Square meters;
Allocation: Php 180,000,000.000
To: Baguio-Bontoc Rd - K0369 + 640 - K0369 + 910;
Physical Target: 6,655.000 Square meters;
Allocation: Php 180,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00077 |
SR2022-03-007595 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: along Claveria - Calanasan Kabugao Rd K0630 + 516 - K0630 + 662;
Physical Target: 5,110.000 Square meters;
Allocation: Php 91,980,000.000
To: along Claveria - Calanasan Kabugao Rd - K0646 + 472 - K0646 + 507;
Physical Target: 3,516.000 Square meters;
Allocation: Php 91,980,000.000
|
September 20, 2022 |
2022 |
WIN2XY00096 |
SR2022-02-000203 |
February 3, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Baguio-La Trinidad-Itogon-Sablan-Tuba and Tublay, Kamog Jct.-Calot-Pappa-Bagong-Balluay-Tuel Jct. (Section 2 of BLISTT Outer Ring Circumferential Road), Package 2, Benguet;
Physical Target: CW1: 11.667 Lane Km
ROW: 2000.000 Square meters;
Allocation: Php 177,000,000.000
To: Baguio-La Trinidad-Itogon-Sablan-Tuba and Tublay, Kamog Jct.-Calot-Pappa-Bagong-Balluay-Tuel Jct. (Section 2 of BLISTT Outer Ring Circumferential Road), Package 2, Benguet;
Physical Target: 633.912 Square meters;
Allocation: Php 177,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00094 |
SR2022-03-007732 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Gov. Bado Dangwa National Rd - K0318 + (-280) - K0318 + (-430);
Physical Target: 6,666.670 Square meters;
Allocation: Php 120,000,000.000
To: Gov. Bado Dangwa National Rd - K0319 + 310 - K0319 + 460;
Physical Target: 4,472.000 Square meters;
Allocation: Php 120,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00056 |
SR2022-03-007734 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Gov. Bado Dangwa National Rd - K0338 + 320 - K0338 + 480;
Physical Target: 8,333.330 Square meters;
Allocation: Php 150,000,000.000
To: Gov. Bado Dangwa National Rd - K0338 + 320 - K0338 + 473;
Physical Target: 5,791.500 Square meters;
Allocation: Php 150,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00063 |
SR2022-03-007735 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Gov. Bado Dangwa National Rd - K0339 + 500 - K0339 + 660;
Physical Target: 9,444.440 Square meters;
Allocation: Php 170,000,000.000
To: Gov. Bado Dangwa National Rd - K0339 + 548 - K0339 + 706;
Physical Target: 6,400.000 Square meters;
Allocation: Php 170,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00089 |
SR2022-03-007808 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Construction of Road, Bayating - Makidot - Dacaan Saddle, Atok, Benguet;
Physical Target: 10.070 Lane Km;
Allocation: Php 100,000,000.000
To: Construction of Road, Bayating - Makidot - Dacaan Saddle, Atok, Benguet;
Physical Target: 6.120 Lane Km;
Allocation: Php 100,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00065 |
SR2022-03-007730 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Kiangan-Tinoc-Buguias Rd - K0355 + 550 - K0355 + 650;
Physical Target: 11,111.110 Square meters;
Allocation: Php 200,000,000.000
To: Kiangan-Tinoc-Buguias Rd - K0355 + 520 - K0355 + 668;
Physical Target: 7,586.000 Square meters;
Allocation: Php 200,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00066 |
SR2022-03-007692 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Baguio - Bontoc Rd - K0375 + 100 - K0375 + 190, K0375 + 935 - K0376 + 065;
Physical Target: 7,777.780 Square meters;
Allocation: Php 140,000,000.000
To: Baguio - Bontoc Rd - K0375 + 100 - K0375 + 130, K0375 + 935 - K0376 + 042;
Physical Target: 5,368.000 Square meters;
Allocation: Php 140,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00095 |
SR2022-03-007693 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Baguio - Bontoc Rd - K0379 + 880 - K0380 + 020, K0380 + 917 - K0381 + 000;
Physical Target: 8,888.880 Square meters;
Allocation: Php 160,000,000.000
To: Baguio - Bontoc Rd - K0379 + 880 - K0380 + 020, K0380 + 917 - K0380 + 986;
Physical Target: 5,859.000 Square meters;
Allocation: Php 160,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00074 |
SR2022-03-007696 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Baguio-Bontoc Rd - K0374+100 - K0374+300, Sabangan, Mt. Province;
Physical Target: 8,363.890 Square meters;
Allocation: Php 150,550,000.000
To: Baguio-Bontoc Rd - K0374+120 - K0374+285, Sabangan, Mt. Province;
Physical Target: 5,853.040 Square meters;
Allocation: Php 150,550,000.000
|
September 20, 2022 |
2022 |
WIN2XY00073 |
SR2022-03-007698 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Mt Prov-Cagayan via Tabuk-Enrile Rd - K0415 + 481 - K0415 + 616;
Physical Target: 6,111.110 Square meters;
Allocation: Php 110,000,000.000
To: Mt Prov-Cagayan via Tabuk-Enrile Rd - K0415 + 481 - K0415 + 608;
Physical Target: 4,109.000 Square meters;
Allocation: Php 110,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00076 |
SR2022-03-007699 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Mt Prov-Cagayan via Tabuk-Enrile Rd - K0416 + 110 - K0416 + 190;
Physical Target: 6,111.110 Square meters;
Allocation: Php 110,000,000.000
To: Mt Prov-Cagayan via Tabuk-Enrile Rd - K0405 + 150 - K0405 + 345;
Physical Target: 4,007.000 Square meters;
Allocation: Php 110,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00084 |
SR2022-03-007710 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Mt Prov-Cagayan via Tabuk-Enrile Rd - K0404 + 800 - K0404 + 935;
Physical Target: 8,333.330 Square meters;
Allocation: Php 150,000,000.000
To: Mt Prov-Cagayan via Tabuk-Enrile Rd - K0404 + 660 - K0404 + 770;
Physical Target: 5,655.000 Square meters;
Allocation: Php 150,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00090 |
SR2022-03-007712 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Mt Prov-Cagayan via Tabuk-Enrile Rd - K0404 + 955 - K0405 + 060;
Physical Target: 8,333.330 Square meters;
Allocation: Php 150,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00093 |
SR2022-03-007716 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Mt Prov-Cagayan via Tabuk-Enrile Rd - K0418 + 460 - K0418 + 630;
Physical Target: 13,888.890 Square meters;
Allocation: Php 250,000,000.000
To: Mt Prov-Cagayan via Tabuk-Enrile Rd - K0406 + 746 - K0406 + 941;
Physical Target: 9,473.000 Square meters;
Allocation: Php 250,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00091 |
SR2022-03-007720 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Baguio-Bontoc Rd - K0347 + 710 - K0348 + 050;
Physical Target: 13,888.890 Square meters;
Allocation: Php 250,000,000.000
To: Baguio-Bontoc Rd - K0347 + 710 - K0347 + 1014;
Physical Target: 9,448.500 Square meters;
Allocation: Php 250,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00075 |
SR2022-03-007723 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Jct Talubin-Barlig-Natonin-Paracelis-Calaccad Rd - K0380 + 173 - K0380 + 330;
Physical Target: 11,111.110 Square meters;
Allocation: Php 200,000,000.000
To: Jct Talubin-Barlig-Natonin-Paracelis-Calaccad Rd - K0380 + 173 - K0380 + 320;
Physical Target: 7,559.500 Square meters;
Allocation: Php 200,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00092 |
SR2022-03-007726 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Jct Talubin-Barlig-Natonin-Paracelis-Calaccad Rd - K0381 + 968 - K0382 + 133;
Physical Target: 10,666.670 Square meters;
Allocation: Php 192,000,000.000
To: Jct Talubin-Barlig-Natonin-Paracelis-Calaccad Rd - K0380 + 1912 - K0380 + 2104;
Physical Target: 7,344.000 Square meters;
Allocation: Php 192,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00083 |
SR2022-03-007724 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Jct Talubin-Barlig-Natonin-Paracelis-Calaccad Rd - K0380 + 330 - K0380 + 503;
Physical Target: 13,055.560 Square meters;
Allocation: Php 235,000,000.000
To: Jct Talubin-Barlig-Natonin-Paracelis-Calaccad Rd - K0380 + 320 - K0380 + 486;
Physical Target: 9,192.200 Square meters;
Allocation: Php 235,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00072 |
SR2022-02-000848 |
February 3, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Banaue-Mayoyao-A Lista-Isabela Bdry Rd - K0350 + 660 - K0350 + 775;
Physical Target: 4,772.500 Square meters;
Allocation: Php 85,905,000.000
To: Banaue-Mayoyao-A Lista-Isabela Bdry Rd - K0350 + 650 - K0350 + 760;
Physical Target: 3,140.000 Square meters;
Allocation: Php 85,905,000.000
|
September 20, 2022 |
2022 |
WIN2XY00071 |
SR2022-03-007592 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: along Claveria - Calanasan Kabugao Rd K0625 + 720 - K0625 + 869;
Physical Target: 5,364.000 Square meters;
Allocation: Php 96,552,000.000
To: along Claveria - Calanasan Kabugao Rd - K0646 + 450 - K0646 + 472;
Physical Target: 3,660.000 Square meters;
Allocation: Php 96,552,000.000
|
September 20, 2022 |
2022 |
WIN2XY00086 |
SR2022-03-007733 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Gov. Bado Dangwa National Rd - K0319 + 560 - K0319 + 736;
Physical Target: 6,666.670 Square meters;
Allocation: Php 120,000,000.000
To: Gov. Bado Dangwa National Rd - K0319 + 572 - K0319 + 736;
Physical Target: 4,561.000 Square meters;
Allocation: Php 120,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00078 |
SR2022-03-007713 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Mt Prov-Cagayan via Tabuk-Enrile Rd - K0406 + 453 - K0406 + 708;
Physical Target: 16,666.670 Square meters;
Allocation: Php 300,000,000.000
To: Mt Prov-Cagayan via Tabuk-Enrile Rd - K0406 + 453 - K0406 + 692;
Physical Target: 11,394.000 Square meters;
Allocation: Php 300,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00088 |
SR2022-03-007715 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Mt Prov-Cagayan via Tabuk-Enrile Rd - K0418 + 230 - K0418 + 380;
Physical Target: 8,333.330 Square meters;
Allocation: Php 150,000,000.000
To: Mt Prov-Cagayan via Tabuk-Enrile Rd - K0418 + 580 - K0418 + 623, K0418 + 780 - K0418 + 898;
Physical Target: 5,524.000 Square meters;
Allocation: Php 150,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00087 |
SR2022-03-007718 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Baguio-Bontoc Rd - K0347 + 370 - K0347 + 710;
Physical Target: 13,888.890 Square meters;
Allocation: Php 250,000,000.000
To: Baguio-Bontoc Rd - K0347 + 520 - K0347 + 577;
Physical Target: 9,600.500 Square meters;
Allocation: Php 250,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00085 |
SR2022-03-007725 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Jct Talubin-Barlig-Natonin-Paracelis-Calaccad Rd - K0381 + 162 - K0381 + 362;
Physical Target: 9,722.220 Square meters;
Allocation: Php 175,000,000.000
To: Jct Talubin-Barlig-Natonin-Paracelis-Calaccad Rd - K0380 + 1112 - K0380 + 1295;
Physical Target: 6,495.500 Square meters;
Allocation: Php 175,000,000.000
|
September 20, 2022 |
2022 |
WIN2XY00080 |
SR2022-03-007727 |
March 23, 2022 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Jct Talubin-Barlig-Natonin-Paracelis-Calaccad Rd - K0406 + 226 - K0406 + 401, K0406 + 431 - K0406 + 516;
Physical Target: 11,000.000 Square meters;
Allocation: Php 198,000,000.000
To: Jct Talubin-Barlig-Natonin-Paracelis-Calaccad Rd - K0406 + 226 - K0406 + 401, K0406 + 431 - K0406 + 490;
Physical Target: 7,525.000 Square meters;
Allocation: Php 198,000,000.000
|
September 14, 2022 |
2022 |
WIN2F06453 |
FY 2022 GAA |
December 29, 2022 |
Region V |
Regional Office V |
UACS No.: 310305101502000
Project ID: P00605720LZ
AS PER GAA:
ORGANIZATIONAL OUTCOME 1: Ensure Safe and Reliable National Road System - Bridge Program - Widening of Permanent Bridges - Baldoza Br. (B00058MT) along Buenavista-Kawayan Rd
Physical Target: CW1 - Widening of Bridge - 699.36 Square meters
Allocation (Php): Php 111,000,000
AS MODIFIED:
ORGANIZATIONAL OUTCOME 1: Ensure Safe and Reliable National Road System - Bridge Program - Widening of Permanent Bridges - Baldoza Br. (B00058MT) along Buenavista-Kawayan Rd
Physical Target: CW1 - Widening of Bridge - 699.36 Square meters
CW2 – Construction of Concrete Road – 2.169 Lane Km
CW3 – Construction of Drainage Structure along road – 1,087.900 Lineal meters
CW4 – Construction of Road Slope Protection Structure - 1,430.880 Square meters
|
September 14, 2022 |
2022 |
WIN2F06518 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 310204101088000
Project ID: P00608745LZ
AS PER GAA:
ORGANIZATIONAL OUTCOME 1: Ensure Safe and Reliable National Road System - Network Development Program - Construction of By-Pass and Diversion Roads - Labo Bypass Road, Camarines Norte
Physical Target: CW1 - Construction of Concrete Road - 3.71 Lane Km
CW2 – Construction of Road Slope Protection Structure – 5070.36 Square meters
Allocation (Php): Php 100,000,000
AS MODIFIED:
ORGANIZATIONAL OUTCOME 1: Ensure Safe and Reliable National Road System - Network Development Program - Construction of By-Pass and Diversion Roads - Labo Bypass Road, Camarines Norte
Physical Target: CW1 – Construction of Concrete Road – 0.634 Lane Km
CW2 – Construction of Road Slope Protection Structure – 4477.29 Square meters
CW3 – Construction of Gravel Road – 1.682 Lane Km
ROW – ROW Acquisition – 62500 Square meters
|
September 14, 2022 |
2022 |
WIN2F06412 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 310204101546000
Project ID: P00608750LZ
AS PER GAA:
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Construction of By-Pass and Diversion Roads - Milaor-Pili Bypass Road, Package 3, Camarines Sur
Physical Target: CW1 - Construction of Concrete Bridge - 1106.16 Square meters
CW2 – Construction of Concrete Road – 0.96 Lane Km
ROW – ROW Acquisition – 60400 Square meters
Allocation (Php): 120,000,000
AS MODIFIED:
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Construction of By-Pass and Diversion Roads - Milaor-Pili Bypass Road, Package 3, Camarines Sur
Physical Target: CW1 – Construction of Concrete Bridge – 1957.46 Square meters
|
September 14, 2022 |
2022 |
WIN2F06414 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 310204101857000
Project ID: P00608759LZ
AS PER GAA: ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Construction of By-Pass and Diversion Roads - Legazpi City Coastal Road, Albay
Physical Target: CW1 – Construction of Concrete Road – 0.33 Lane Km
CW2 – Construction of Road Slope Protection Structure – 1407.08 Square meters
Allocation (Php): 100,000,000
AS MODIFIED: ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Construction of By-Pass and Diversion Roads - Legazpi City Coastal Road, Albay
Physical Target: CW1 – Construction of Concrete Road - 0.373 Lane Km
CW2 – Construction of Road Slope Protection Structure – 1083.86 Square meters
|
September 14, 2022 |
2022 |
WIN2F06454 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 310109100873000
Project ID: P00611266LZ
AS PER GAA: ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Asset Preservation Program - Baras-Gigmoto-Viga Rd - K0031 + 603 - K0031 + 627, K0046 + 676 - K0046 + 700, K0049 + 491 - K0049 + 514, K0054 + 500 - K0054 + 538, K0063 + 218 - K0063 + 235, K0068 + 323 - K0068 + 343, K0076 + 190 - K0076 + 210
Physical Target: CW1 – Construction of Road Slope Protection Structure – 5833.31 Square meters
Allocation (Php): 105,000,000
AS MODIFIED: ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Asset Preservation Program - Baras-Gigmoto-Viga Rd - K0031 + 603 - K0031 + 627, K0046 + 676 - K0046 + 700, K0049 + 491 - K0049 + 514, K0054 + 500 - K0054 + 538, K0063 + 218 - K0063 + 235, K0068 + 323 - K0068 + 343, K0076 + 190 - K0076 + 210
Physical Target: CW1 – Construction of Road Slope Protection Structure – 6087 Square meters
|
September 14, 2022 |
2022 |
WIN2F06371 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 320101107525000
Project ID: P00621518LZ
AS PER GAA: ORGANIZATIONAL OUTCOME 2: Protect Lives and Properties against Major Floods - Flood Management Program - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems - Construction/Improvement of Sipocot River Flood Mitigation Structures, Sipocot Camarines Sur
Physical Target: CW1 – Construction of Flood Mitigation Structure – 388.5 Lineal meters
Allocation (Php): 92, 627,000
AS MODIFIED: ORGANIZATIONAL OUTCOME 2: Protect Lives and Properties against Major Floods - Flood Management Program - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems - Construction/Improvement of Sipocot River Flood Mitigation Structures, Sipocot Camarines Sur
Physical Target: CW1 – Construction of Flood Mitigation Structure – 338.7 Lineal meters
|
September 14, 2022 |
2022 |
WIN2F06465 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300215100343000
Project ID: P00630829LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Baras - Gigmoto - Viga Road, Junction National Road to Minaabat Point, Catanduanes
Physical Target: CW1 – Construction of Gravel Road – 1.692 Lane Km
Allocation (Php): 30,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Baras - Gigmoto - Viga Road, Junction National Road to Minaabat Point, Catanduanes
Physical Target: CW1 – Construction of Gravel Road – 1.232 Lane Km
|
September 14, 2022 |
2022 |
WIN2F06506 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300215100344000
Project ID: P00630830LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Baras - Gigmoto - Viga Road, Junction National Road to Minaabat Point, Sicmil, Gigmoto, Catanduanes
Physical Target: CW1 – Construction of Gravel Road – 0.52 Lane Km
CW2 – Construction of Road Slope Protection Structure – 1928.4 Square meters
Allocation (Php): 30,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Baras - Gigmoto - Viga Road, Junction National Road to Minaabat Point, Sicmil, Gigmoto, Catanduanes
Physical Target: CW1 – Construction of Gravel Road – 0.608 Lane Km
CW2 – Construction of Road Slope Protection Structure – 1928.4 Square meters
|
September 14, 2022 |
2022 |
WIN2F06451 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300219100216000
Project ID: P00631458LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Flood Control Structure along Sitio Guiwanon River, San Jacinto, Masbate
Physical Target: CW1 – Construction of Flood Mitigation Structure – 242.21 Lineal meters
Allocation (Php): 50,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Flood Control Structure along Sitio Guiwanon River, San Jacinto, Masbate
Physical Target: CW1 – Construction of Flood Mitigation Structure – 185.21 Lineal meters
|
September 14, 2022 |
2022 |
WIN2F06453 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300219100217000
Project ID: P00631459LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Flood Control Structure at Sitio Dalakit, Monreal, Masbate
Physical Target: CW1 – Construction of Flood Mitigation Structure – 298.38 Lineal meters
Allocation (Php): 50,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Flood Control Structure at Sitio Dalakit, Monreal, Masbate
Physical Target: CW1 – Construction of Flood Mitigation Structure – 217.58 Lineal meters
|
September 14, 2022 |
2022 |
WIN2F06458 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300219100218000
Project ID: P00631460LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Flood Control Structure, Sitio Busdak, Barangay Bartolabac, San Jacinto, Masbate
Physical Target: CW1 – Construction of Flood Control Mitigation Structure – 290.16 Lineal meters
Allocation (Php): 50,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Flood Control Structure, Sitio Busdak, Barangay Bartolabac, San Jacinto, Masbate
Physical Target: CW1 – Construction of Flood Control Mitigation Structure – 209.01 Lineal meters
|
September 14, 2022 |
2022 |
WIN2F06455 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300219100209000
Project ID: P00631466LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Flood Mitigation Structures along Bito River, Sitio Bacolod, San Fernando, Masbate
Physical Target: CW1 – Construction of Flood Mitigation Structure – 200.6 Lineal meters
Allocation (Php): 30,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Flood Mitigation Structures along Bito River, Sitio Bacolod, San Fernando, Masbate
Physical Target: CW1 – Construction of Flood Mitigation Structure – 141.5 Lineal meters
|
September 14, 2022 |
2022 |
WIN2F06449 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300219100210000
Project ID: P00631467LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Flood Mitigation Structures along Bito River, Sitio Puring Giti, San Fernando, Masbate
Physical Target: CW1 – Construction of Flood Mitigation Structure – 196.2 Lineal meters
Allocation (Php): 30,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Flood Mitigation Structures along Bito River, Sitio Puring Giti, San Fernando, Masbate
Physical Target: CW1 – Construction of Flood Mitigation Structure – 141.3 Lineal meters
|
September 14, 2022 |
2022 |
WIN2F06396 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300219100211000
Project ID: P00631468LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Mababoy Shore Protection Structures, Barangay Guinhadap, Monreal, Masbate
Physical Target: CW1 – Construction of Flood Mitigation Structure – 106.26 Lineal meters
Allocation (Php): 50,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Mababoy Shore Protection Structures, Barangay Guinhadap, Monreal, Masbate
Physical Target: CW1 – Construction of Flood Mitigation Structure – 92.15 Lineal meters
|
September 14, 2022 |
2022 |
WIN2F06448 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300219100212000
Project ID: P00631469LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Sitio Dalakit Shore Protection Structures, Sitio Dalakit, Barangay Macarthur, Monreal, Masbate
Physical Target: CW1 – Construction of Flood Mitigation Structure – 96.75 Lineal
Allocation (Php): 35,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Sitio Dalakit Shore Protection Structures, Sitio Dalakit, Barangay Macarthur, Monreal, Masbate
Physical Target: CW1 – Construction of Flood Mitigation Structure – 77.5 Lineal
|
September 14, 2022 |
2022 |
WIN2F06453 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300219100213000
Project ID: P00631470LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Sitio Guiwanon Shore Protection Structures, Barangay Danao, San Jacinto, Masbate
Physical Target: CW1 – Construction of Slope Protection Structure – 1877.47 Square meters
Allocation (Php): 50,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Sitio Guiwanon Shore Protection Structures, Barangay Danao, San Jacinto, Masbate
Physical Target: CW1 – Construction of Slope Protection Structure – 1516.73 Square meters
|
September 14, 2022 |
2022 |
WIN2F06579 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300220100065000
Project ID: P00631517LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Multi-Purpose Buildings/ Facilities to support Social Services - Construction of Cruise Port and Facilities (Phase 2), Legazpi City, Albay
Physical Target: CW1 – Construction of Other Facilities – 1 Number of Facilities
Allocation (Php): 150,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Multi-Purpose Buildings/ Facilities to support Social Services - Construction of Cruise Port and Facilities (Phase 2), Legazpi City, Albay
Physical Target: CW1 – Construction of Other Facilities – 1 Number of Facilities
CWD – Design Component of a Design and Build Project – 1 Number of Facilities
|
September 14, 2022 |
2022 |
WIN2F06415 |
FY 2022 GAA |
December 29, 2020 |
Region V |
Regional Office V |
UACS No.: 300209100015000
Project ID: P00634975LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/ Improvement of Access Roads leading to Railway Stations (Kalsada Tungo sa Paliparan, Riles at Daungan Program - KATUPARAN) - Access Road leading to Naga City PNR Station, Naga City, Camarines Sur
Physical Target: CW1 – Construction of Concrete Road – 0.5 Lane Km
Allocation (Php): 10,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/ Improvement of Access Roads leading to Railway Stations (Kalsada Tungo sa Paliparan, Riles at Daungan Program - KATUPARAN) - Access Road leading to Naga City PNR Station, Naga City, Camarines Sur
Physical Target: CW1 – Construction of Concrete Road – 0.118 Lane Km
CW2 – Construction of Dike – 24.27 Lineal meters
|
September 14, 2022 |
2022 |
WIN2F06514 |
FY 2022 GAA |
December 29, 2020 |
Region V |
Regional Office V |
UACS No.: 300209100014000
Project ID: P00634976LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/ Improvement of Access Roads leading to Railway Stations (Kalsada Tungo sa Paliparan, Riles at Daungan Program - KATUPARAN) - Access Road leading to Iriga Railway Station, Iriga, Camarines Sur
Physical Target: CW1 – Construction of Concrete Road – 0.5 Lane Km
Allocation (Php): 10,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/ Improvement of Access Roads leading to Railway Stations (Kalsada Tungo sa Paliparan, Riles at Daungan Program - KATUPARAN) - Access Road leading to Iriga Railway Station, Iriga, Camarines Sur
Physical Target: CW1 – Construction of Concrete Road – 0.225 Lane Km
CW2 – Construction of Road Slope Protection Structure – 220.51 Square meters
|
September 14, 2022 |
2022 |
WIN2F06375 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
WIN2F06375
UACS No.: 300215100264000
Project ID: P00638901LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Magallang - Moroponros Road, Libon/Oas, Albay
Physical Target: CW1 – Construction of Concrete Road – 4 Lane Km
Allocation (Php): 250,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Magallang - Moroponros Road, Libon/Oas, Albay
Physical Target: CW1 – Construction of Concrete Road – 0.56 Lane Km
CW2 – Construction of Gravel Road – 7.537 Lane Km
|
September 14, 2022 |
2022 |
WIN2F06471 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300215100274000
Project ID: P00638911LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Pantao to Moroponros Road, Libon, Albay
Physical Target: CW1 – Construction of Drainage Structure along Road – 3236.84 Lineal meters
CW2 – Construction of Road Slope Protection Structure – 16924.43 Square meters
Allocation (Php): 200,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Pantao to Moroponros Road, Libon, Albay
Physical Target: CW1 – Construction of Gravel Road – 6 Lane Km
CW2 – Construction of Road Slope Protection Structure – 1571.49 Square meters
|
September 14, 2022 |
2022 |
WIN2F06476 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300215100281000
Project ID: P00638918LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Road with Slip, Slope Collapse and Landslide Protection of Cagbulacao - Cagraray Section, Bacacay, Albay
Physical Target: CW1 – Construction of Road Slope Protection Structure – 9754.94 Square meters
Allocation (Php): 250,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Road with Slip, Slope Collapse and Landslide Protection of Cagbulacao - Cagraray Section, Bacacay, Albay
Physical Target: CW1 – Construction of Road Slope Protection Structure – 8755.13 Square meters
|
September 14, 2022 |
2022 |
WIN2F06464 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300215100282000
Project ID: P00638919LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Road with Slip, Slope Collapse and Landslide Protection of Cagbulacao Section, Bacacay, Albay
Physical Target: CW1 – Construction of Road Slope Protection Structure – 9819.52 Square meters
Allocation (Php): 250,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Road with Slip, Slope Collapse and Landslide Protection of Cagbulacao Section, Bacacay, Albay
Physical Target: Construction of Road Slope Protection Structure – 8834.24 Square meters
|
September 14, 2022 |
2022 |
WIN2F06470 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300215100287000
Project ID: P00638924LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Road, Macabugos via Caratagan - Tagbac, Sta. 0 + 000 - Sta. 2 + 100, Libon, Albay
Physical Target: CW1 – Construction of Concrete Road - 4.2 Lane Km
Allocation (Php): 150,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Road, Macabugos via Caratagan - Tagbac, Sta. 0 + 000 - Sta. 2 + 100, Libon, Albay
Physical Target: CW1 – Construction of Concrete Road – 0.4 Lane Km
CW2 – Construction of Gravel Road – 3.8 Lane Km
CW3 – Construction of Road Slope Protection Structure – 4612.51 Square meters
|
September 14, 2022 |
2022 |
WIN2F06450 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300215100290000
Project ID: P00638927LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Road, Pantao - Jovellar (Pantao Section), Libon, Albay
Physical Target: CW1 – Construction of Concrete Road – 3.283 Lane Km
CW2 – Construction of Road Slope Protection Structure – 8502.71
CW3 – Construction of Drainage Structure along Road – 3282.9 Lineal meters
Allocation (Php): 146,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Road, Pantao - Jovellar (Pantao Section), Libon, Albay
Physical Target: CW1 – Construction of Concrete Road – 6.967 Lane Km
CW2 – Construction of Road Slope Protection Structure – 4731.76 Square meters
CW3 – Construction of Drainage Structure along Road – 3212.620 Lineal meters
|
September 14, 2022 |
2022 |
WIN2F06405 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300215100291000
Project ID: P00638928LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Road, Tablon - West Coast (Tablon Section), Oas, Albay
Physical Target: CW1 – Construction of Concrete Road – 6 Lane Km
Allocation (Php): 170,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Road, Tablon - West Coast (Tablon Section), Oas, Albay
Physical Target: CW1 – Construction of Concrete Road – 0.6 Lane Km
CW2 – Construction of Gravel Road – 1.715 Lane Km
|
September 14, 2022 |
2022 |
WIN2F06582 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300215100298000
Project ID: P00638935LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Tablon - Maonon Road, Oas/Ligao City, Albay
Physical Target: CW1 – Construction of Concrete Road – 2422 Lane Km
Allocation (Php): 250,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Tablon - Maonon Road, Oas/Ligao City, Albay
Physical Target: CW1 – Construction of Gravel Road – 2.424 Lane Km
|
September 14, 2022 |
2022 |
WIN2F06459 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300215100308000
Project ID: P00638945LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Rehabilitation of Solong - Boctot Road, Brgy. Solong, San Miguel, Catanduanes
Physical Target: CW1 - Rehabilitation of Concrete Road – 4.190 Lane Km
CW2 - Construction of Road Slope Protection Structure - 15314.4 Square meters
CW3 - Construction of Drainage Structure along Road – 4190 Lineal meters
Allocation (Php):
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Rehabilitation of Solong - Boctot Road, Brgy. Solong, San Miguel, Catanduanes
Physical Target: CW1 - Rehabilitation of Concrete Road – 2.540 Lane Km
CW2 - Construction of Road Slope Protection Structure – 7683.13 Square meters
CW3 - Construction of Drainage Structure along Road – 2514.4 Lineal meters
|
September 14, 2022 |
2022 |
WIN2F06519 |
FY 2022 GAA |
December 29, 2021 |
Region V |
Regional Office V |
UACS No.: 300215100310000
Project ID: P00638947LZ
AS PER GAA: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Topaz - Oma - Oma Road, Ligao City, Albay
Physical Target: CW1 - Construction of Concrete Road - 12.08 Lane Km
CW2 - Construction of Road Slope Protection Structure - 8302.17 Square meters
Allocation (Php): 250,000,000
AS MODIFIED: CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Topaz - Oma - Oma Road, Ligao City, Albay
Physical Target: CW1 - Construction of Gravel Road - 5.2627 Lane Km
CW2 - Construction of Road Slope Protection Structure - 20822.05 Square meters
|