July 28, 2022 |
2022 |
310105100675000 |
GAA 2022 |
January 3, 2022 |
Region II |
Quirino District Engineering Office |
ORGANIZATIONAL OUTCOME 1: Ensure Safe and Reliable National Road System - Asset Preservation Program – Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads – Secondary Roads - Cordon – Aurora Bdry Rd (Jct Dumabato – Aurora Bdry) – K0381+927 – K0382+351, K0383+000 – K0383+526, K0383+557 – K0383+700, K0383+700 – K0384+174, K0402+727 – K0403+026 |
July 28, 2022 |
FY 2022 GAA |
WIN2G03089 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 300215101620000
Project ID : P00639239LZ
CONVERGENCE AND SPECIAL SUPPORT PROGRAM
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) -
Access Roads and/or Bridges from the National Road/s leading
to Major/Strategic Public buildings/Facilities
FROM :
Rehabilitation of Road with Slips, Slope Collapse, and Landslide
along Taytay - Bantulan - Sta. Cruz Port Road,
Sta. 2 +749.00 - Sta. 2+827.00,
Taytay, Palawan
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 777.553 square meter
Allocation - Php 34.698 Million
TO :
Rehabilitation of Road with Slips, Slope Collapse, and Landslide
along Taytay - Bantulan - Sta. Cruz Port Road
Sta. 2+749.00 - Sta. 2+847.00,
Taytay, Palawan
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 1,508.450 square meter
Allocation - Php 34.698 Million |
July 28, 2022 |
2022 |
WIN2G02999 |
FY 2022 GAA RA 11639 |
January 3, 2022 |
Region VI |
Capiz 2nd District Engineering Office |
UACS No. 310204101770000
Project ID: P00605352VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Network Development - Construction of By-Pass and Diversion Roads
Sigma Bypass Road, Capiz
CW1 - Road Widening: 2.656 lane km - 29,400.00
CW2 – Construction of Concrete Bridge: 438.84 sq.m. - 19,600.00
EAO - 1,000.00
TO:
OO1: Ensure Safe and Reliable National Road
System
Network Development - Construction of By-Pass and Diversion Roads
Sigma Bypass Road, Capiz
CW1 - Road Widening: 1.272 lane km - 19,600.00
CW2- Construction of Concrete Road: 1.272 lane km - 15,400.00
ROW Acquisition: 26,912.47 sq.m - 14,000.00
EAO - 1,000.00
|
July 28, 2022 |
FY 2022 GAA |
WIN2G03117 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 300215101625000
Project ID : P00639244LZ
CONVERGENCE AND SPECIAL SUPPORT PROGRAM
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) -
Access Roads and/or Bridges from the National Road/s leading
to Major/Strategic Public Buildings/Facilities
FROM :
rehabilitation of Road with Slips, Slope Collapse, and Landslide
along Taytay - Bantulan - Sta. Cruz Port Road,
Sta. 4+359.00 - Sta. 4+441.00,
Taytay, Palawan
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 518.37 square meter
Allocation - Php 23.132 Million
TO :
Rehabilitation of Road with Slips, Slope Collapse, and Landslide
along Taytay - Bantulan - Sta. Cruz Port Road,
Sta. 4+359.00 - Sta. 4+454.00,
Taytay, Palawan
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 1,006.75 square meter
Allocation - Php 23.132 Million
|
July 28, 2022 |
2022 |
WIN2G03152 |
FY 2022 GAA RA 11639 |
January 1, 2022 |
Region VI |
Iloilo 4th District Engineering Office |
UACS No.: 310202101186000
Project ID: P00604972VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Secondary Roads
Iloilo City-Leganes-Dumangas Coastal Rd - K0015 + 907 - K0017 + 517
CW1- Road Widening: 3.220 lane Km - 22,804.60
EAO - 465.40
TO:
OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Secondary Roads
Iloilo City-Leganes-Dumangas Coastal Rd - K0015 + 907 - K0016 + 721
CW1- Road Widening: 0.814 Lane Km - 22,804.60
EAO - 465.40
|
July 28, 2022 |
2022 |
WIN2G03151 |
SARO-BMB-A-22-0002723 |
March 17, 2022 |
Region VI |
Iloilo 4th District Engineering Office |
UACS No.: 310202101185000
Project ID: P00605610VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Secondary Roads
Cabatuan-New Lucena-Banga-Bante Rd - K0045 + 180 - K0046 + 200
CW1 - Road Widening:
2.042 lane km - 24,500.00
EAO - 500.00
TO:
OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Secondary Roads
Cabatuan-New Lucena-Banga-Bante Rd - K0046 + 430 - K0046 + 820
CW1- Road Widening:
0.78 lane km - 24,500.00
EAO - 500.00
|
July 28, 2022 |
FY 2022 GAA |
WIN2G03082 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS NO. ; 300215101626000
Project ID : P00639245LZ
CONVERGENCE AND SPECIAL SUPPORT PROGRAM
Sustainable Infrastructure Projects Alleviating gaps (SIPAG) -
Access Roads and/or Bridges from the National Road/s leading
to Major/Strategic Public Buildings/Facilities
FROM :
Rehabilitation of Road with Slips, Slope Collapse, and Landslide
along Taytay - Bantulan - Sta. Cruz Port Road,
Sta. 8+747.00 - Sta. 8+832.00,
Taytay,Palawan
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 661.34 square meter
Allocation - Php 29.512 Million
TO :
Rehabilitation of Road with Slips, Slope Collapse, and Landslide
along Taytay - Bantulan - Sta. Cruz Port Road,
Sta. 8+747.00 - Sta. 8+845.00,
Taytay, Palawan
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 1,281.18 square meter
Allocation - Php 29.512 Million |
July 28, 2022 |
2022 |
WIN2G03133 |
SR2022-03-006768 |
March 22, 2022 |
Region VI |
Iloilo 4th District Engineering Office |
UACS No.: 310109100877000
Project ID: P00606442VS
FROM:
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
Jct Bancal-Leon-Antique Bdry Rd - K0044 + 670 - K0044 + 770
CW1 - Construction of Road Slope Protection Structure:
5,444.44 sq.m.- 94,570.00
EAO - 3,430.00
TO:
OO1: Ensure Safe and Reliable National Road
System
Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
Jct Bancal-Leon-Antique Bdry Rd - K0043 + 450 - K0043 + 468, K0044 + 516 - K0044 + 600
CW1 - Construction of Road Slope Protection Structure:
2,353.10 sq.m.- 94,570.00
EAO - 3,430.00
|
July 27, 2022 |
FY 2022 |
WIN2E02458 |
310211100091000 |
April 5, 2022 |
Region IX |
Zamboanga del Norte 2nd District Engineering Office |
UACS No. 310211100091000
Project ID: P00604484MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Paving of Unpaved Roads - Secondary Roads
Zamboanga West Coastal Road (Limpapa - Sibuco Section) S01148MN
Chainage 6663 - Chainage 6788.60,
Chainage 11580 - Chainage 12041.66,
Chainage 12840 - Chainage 13067.81
CW1- Paving of Unpaved Roads
Physical Target: 1.630 Lane km
Unit Cost: ₱ 12,625,776.90/Lane km
EAO: ₱ 420,000.00
Total Allocation: ₱ 21,000,000.00 |
July 27, 2022 |
FY 2022 |
WIN2E02409 |
300215102032000 |
May 4, 2022 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 300215102032000
Project ID : P00630180MN
Convergence and Special Support Program - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/Facilities
Construction of Road including Drainage, DPWH Zamboanga del Sur 1st DEO, Dao, Pagadian City
CW1 - Construction of Concrete Road
Physical Target: 0.88912 Lane km
Unit Cost : P 27,555,335.61/Lane km
EAO : P 500,000.00
Allocation : P 25,000,000.00 |
July 27, 2022 |
FY 2022 |
WIN2E02410 |
300215102016000 |
May 4, 2022 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 300215102016000
Project ID : P00630164MN
Convergence and Special Support Program - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/Facilities
Construction of Bagalupa-Langapod-Gubang By-pass Road, Zamboanga del Sur
CW1 - Construction of Concrete Road
Physical Target: 3.256 Lane km
Unit Cost : P 12,039,312.03/Lane km
EAO : P 800,000.00
Allocation : P 40,000,000.00 |
July 27, 2022 |
FY 2022 |
WIN2E02408 |
300215102029000 |
May 4, 2022 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 300215102029000
Project ID : P00630177MN
Convergence and Special Support Program - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/Facilities
Construction of Molave-Tambulig-Don Victoriano By-pass Road, Zamboanga del Sur
CW1 - Construction of Concrete Road
Physical Target: 1.684 Lane km
Unit Cost : P 17,458,432.30/Lane km
EAO : P 600,000.00
Allocation : P 30,000,000.00 |
July 27, 2022 |
FY 2022 |
WIN2E02404 |
310204101386000 |
May 4, 2022 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 310204101386000
Project ID: P00604220MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Bypass and Diversion Roads
NRJ Poblacion Tambulig-Tungawan-Pasingkalan Road, Zamboanga del Sur
CW1- Construction of Concrete Road
Physical Target: 2.177 Lane km
Unit Cost: ₱ 15,335,871.84/Lane km
CW2- Construction of Slope Protection Structure
Physical Target: 3,592.05 sq.m.
Unit Cost: ₱ 10,749.80/sq.m
ROW Acquisition: 6,780.00 Square meters
EAO: ₱ 2,625,000.00
Total Allocation: ₱ 75,000,000.00 |
July 27, 2022 |
FY 2022 |
WIN2E02444 |
310203100610000 |
May 4, 2022 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 310203100610000
Project ID: P00602299MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Tertiary Roads
Jct Aurora-Monte Alegre-Jct Labangan Rd - K1630 + 802.5 - K1631 + 141.80
CW1- Road Widening
Physical Target: 0.6806 Lane km
Unit Cost: ₱ 14,105,201.29/Lane km
ROW Acquisition: 2,041.80 Square meters
EAO: ₱ 200,000.00
Total Allocation: ₱ 10,000,000.00 |
July 27, 2022 |
FY 2022 |
WIN2E02445 |
310201101018000 |
May 4, 2022 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 310201101018000
Project ID: P00602296MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Tucuran Jct-Karomatan Jct Rd - K1654 + 070 - K1654 + 352
CW1- Road Widening
Physical Target: 0.564 Lane km
Unit Cost: ₱ 16,843,971.63/Lane km
ROW Acquisition: 1,692.00 Square meters
EAO: ₱ 200,000.00
Total Allocation: ₱ 10,000,000.00 |
July 27, 2022 |
FY 2022 |
WIN2E02406 |
300215102035000 |
May 6, 2022 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 300215102035000
Project ID : P00630183MN
Convergence and Special Support Program - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/Facilities
Construction of San Vicente - Dalaguete - Balanan - Tuboran Road, Mahayag, Zamboanga del Sur
CW1 - Construction of Concrete Road
Physical Target: 3.822 Lane km
Unit Cost : P 12,820,512.82/Lane km
EAO : P 1,000,000.00
Allocation : P 50,000,000.00 |
July 27, 2022 |
FY 2022 |
WIN2E02405 |
310201101016000 |
May 6, 2022 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 310201101016000
Project ID: P00602297MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Jct Aurora-Ozamis City Rd - K1642+057.00 - K1642+383.50
CW1- Road Widening
Physical Target: 0.653 Lane km
Unit Cost: ₱ 14,548,238.90/Lane km
ROW Acquisition: 1,959.00 Square meters
EAO: ₱ 200,000.00
Total Allocation: ₱ 10,000,000.00 |
July 27, 2022 |
FY 2022 |
WIN2E02407 |
310201101017000 |
May 6, 2022 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 310201101017000
Project ID: P00602298MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Jct Blancia-Molave-Josefina Rd - K1672 + 341 - K1672 + 657.50
CW1- Road Widening
Physical Target: 0.633 Lane km
Unit Cost: ₱ 15,165,876.78/Lane km
ROW Acquisition: 3,315.00 Square meters
EAO: ₱ 200,000.00
Total Allocation: ₱ 10,000,000.00 |
July 27, 2022 |
FY 2022 |
WIN2E02411 |
300215102033000 |
May 6, 2022 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 300215102033000
Project ID : P00630181MN
Convergence and Special Support Program - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/Facilities
Construction of Road, Dao, Pagadian City, Zamboanga del Sur
CW1 - Construction of Concrete Road
Physical Target: 1.616 Lane km
Unit Cost : P 12,315,853.96/Lane km
EAO : P 800,000.00
Allocation : P 40,000,000.00 |
July 27, 2022 |
FY 2021 |
WIN1B00771 |
300107201302000 |
October 23, 2021 |
Region IX |
Regional Office IX |
UACS No. 300107201302000
Project ID: P00550562MN
Flood Control and Drainage - Flood Control Structures / Facilities - Local Infrastructure Program
Construction/Improvement of Seawall from Barangay Tandu-Bagua to Barangay Umangay, Patikul, Sulu
CW1 - Construction of Flood Mitigation Structure : 364.0 ln.m.
Unit Cost: P 21,758.24176
EAO: P 80,000
Allocation: P 8,000,000.00 |
July 27, 2022 |
FY 2022 |
WIN2E02436 |
300204101057000 |
May 6, 2022 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 300204101057000
Project ID : P00632813MN
Convergence and Special Support Program (CSSP) - Construction/ Improvement of Access Roads leading to Trades, Industries and Economic Zones (Roads Leveraging Linkages for Industry and Trade Infrastructure Program - ROLL-IT)
NRJ to Brgy. Upper Timonan-Marangan-Kahayagan-Palili-Timbaboy in support of Abaca Handicraft Processing, Zamboanga del Sur
CW1 - Construction of Concrete Road : 0.286 lane-km
Unit Cost : P 17,132,867.13/lane-km
EAO : P 100,000.00
Allocation : P 5,000,000.00 |
July 27, 2022 |
FY 2021 |
WIN1B00772 |
300107201303000 |
October 23, 2021 |
Region IX |
Regional Office IX |
UACS No. 300107201303000
Project ID: P00550563MN
Flood Control and Drainage - Flood Control Structures / Facilities - Local Infrastructure Program
Construction/Improvement of Seawall in Barangay Bangas, Hadji Panglima Tahil, Sulu
CW1 - Construction of Flood Mitigation Structure : 180.0 ln.m.
Unit Cost: P 22,000.00
EAO: P 40,000
Allocation: P 4,000,000.00 |
July 27, 2022 |
FY 2022 |
WIN2E02468 |
320101107698000 |
June 7, 2022 |
Region IX |
Regional Office IX |
UACS No. 320101107698000
Project ID: P00620023MN
OO2: Protect Lives and Properties - Flood Management - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Isabela Urban Drainage, Isabela City, Basilan
CW1- Construction of Drainage Structure
Physical Target: 1,682.56 Lineal Meters
Unit Cost: ₱ 65,956.04
EAO: ₱ 4,025,000.00
Allocation: ₱ 115,000,000.00 |
July 27, 2022 |
FY 2022 |
WIN2E02400 |
310205100733000 |
March 23, 2022 |
Region IX |
Regional Office IX |
UACS No. 310205100733000
Project ID: P00603743MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Missing Links/ New Roads
Sindangan - Bayog - Lakewood Road, Package 2, Zamboanga del Norte
CW1- Construction of Concrete Road
Physical Target: 1.90 Lane km
Unit Cost: ₱ 25,868,421.05/Lane km
ROW- Right of Way Acquisition
Physical Target: 19,516.67 sq.m.
Unit Cost: ₱ 300.00/sq.m.
EAO: ₱ 1,995,000.00
Allocation: ₱ 57,000,000.00
|
July 27, 2022 |
FY 2022 |
WIN2E02481 |
310205100695000 |
June 7, 2022 |
Region IX |
Regional Office IX |
UACS No. 310205100695000
Project ID: P00603750MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Missing Links/ New Roads
Midsalip-Buboan Road, Zamboanga Del Sur
CW1- Construction of Concrete Road
Physical Target: 3.840 Lane km
Unit Cost: ₱ 23,028,645.83/Lane km
ROW- Right of Way Acquisition
Physical Target: 33,333.333 sq.m.
Unit Cost: ₱ 300.00/sq.m.
EAO: ₱ 3,570,000.00
Allocation: ₱ 102,000,000.00
|
July 27, 2022 |
FY 2022 |
WIN2E02470 |
310205100732000 |
June 7, 2022 |
Region IX |
Regional Office IX |
UACS No. 310205100732000
Project ID: P00603806MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Missing Links/ New Roads
Sindangan - Bayog - Lakewood Road, Package 1, Zamboanga Del Sur
CW1- Construction of Concrete Road
Physical Target: 3.23 Lane Km
Unit Cost: ₱ 19,792,852.94/Lane Km
ROW- Right-Of-Way Acquisition
Physical Target: 16,666.67 sq.m.
Unit Cost: ₱ 300.00/sq.m.
EAO: ₱ 2,500,085.00
Allocation: ₱ 71,431,000.00 |
July 27, 2022 |
FY 2022 |
WIN2E02476 |
310204101584000 |
June 7, 2022 |
Region IX |
Regional Office IX |
UACS No. 310204101584000
Project ID: P00604251MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Bypass and Diversion Roads
NRJ Balucot-Lower Usugan-Tungawan Road, Tambulig, Zamboanga del Sur
CW1- Construction of Concrete Road
Physical Target: 1.74 Lane Km
Unit Cost: ₱ 38,721,264.37/Lane km
ROW- Right-Of-Way Acquisition
Physical Target: 16,666.666 sq.m
Unit Cost: ₱ 300.00/sq.m.
EAO: ₱ 2,625,000.00
Allocation: ₱ 75,000,000.00 |
July 27, 2022 |
FY 2022 |
WIN2E02492 |
320101107696000 |
June 7, 2022 |
Region IX |
Regional Office IX |
UACS No. 320101107696000
Project ID: P00620020MN
OO2: Protect Lives and Properties - Flood Management - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control Structure, Salug Diut River, Molave, Zamboanga del Sur
CW1- Construction of Flood Mitigation Structure
Physical Target: 359.00 Lineal Meters
Unit Cost: ₱ 187,047.35/Lineal Meters
ROW- Right-Of-Way Acquisition
Physical Target: 1,333.333 sq.m.
Unit Cost: ₱ 300.00/sq.m.
EAO: ₱ 2,450,000.00
Allocation: ₱ 70,000,000.00 |
July 27, 2022 |
FY 2022 |
WIN2E02484 |
310205100734000 |
June 7, 2022 |
Region IX |
Regional Office IX |
UACS No. 310205100734000
Project ID: P00603807MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Missing Links/ New Roads
Sindangan - Bayog - Lakewood Road, Package 2, Zamboanga Del Sur
CW1- Construction of Concrete Road
Physical Target: 1.73 Lane Km
Unit Cost: ₱ 30,020,231.21/Lane Km
ROW- Right-Of-Way Acquisition
Physical Target: 16,666.67 sq.m.
Unit Cost: ₱ 300.00/sq.m.
EAO: ₱ 2,065,000.00
Allocation :₱ 59,000,000.00 |
July 27, 2022 |
FY 2022 |
WIN2E02449 |
320101107688000 |
March 23, 2022 |
Region IX |
Regional Office IX |
UACS No. 320101107688000
Project ID: P00620012MN
OO2: Protect Lives and Properties - Flood Management - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control Structure at Limpapa River, Zamboanga City-Labuan-LimpapaRoad (Limpapa Br. Section) Phase II, Zamboanga City
CW1- Construction of Flood Mitigation Structure
Physical Target: 330.000 Lineal Meters
Unit Cost: ₱ 293,636.36/Lineal Meters
EAO: ₱ 3,570,000.00
Excess: ₱ 1,530,000.000
Allocation: ₱ 102,000,000.00 |
July 27, 2022 |
FY 2022 |
WIN2E02443 |
310205100936000 |
March 23, 2022 |
Region IX |
Regional Office IX |
UACS No. 310205100936000
Project ID: P00603744MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Missing Links/ New Roads
Sindangan - Bayog - Lakewood Road, Biwa Bridge, Zamboanga Del Norte
CW1- Construction of Concrete Bridge
Physical Target: 580.986 sq.m.
Unit Cost: ₱ 111,190.29/sq.m.
EAO: ₱ 2,380,000.00
Excess: ₱ 1,020,000.00
Allocation: ₱ 68,000,000.00 |
July 27, 2022 |
FY 2022 |
WIN2E02441 |
310204101589000 |
March 23, 2022 |
Region IX |
Regional Office IX |
UACS No. 310204101589000
Project ID: P00604235MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Bypass and Diversion Roads
NRJ Sinunuc-Malagutay-San Roque Section, Phase II, Zamboanga City
CW1- Construction of Concrete Road
Physical Target: 3.360 Lane Km
Unit Cost: ₱ 18,937,440.98/Lane km
ROW- Right-Of-Way Acquisition
Physical Target: 141,733.99 sq.m.
Unit Cost: ₱ 300.00/sq.m.
EAO: ₱ 3,850,000.00
Allocation: ₱ 110,000,000.00 |
July 26, 2022 |
FY 2022 GAA |
WIN2G03147 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 300215101633000
Project ID : P00636965LZ
CONVERGENCE AND SPECIAL SUPPORT PROGRAM
Sustainable Infrastructure Projects Alleviating gaps (SIPAG) -
Access Roads and/or Bridges from the National Road/s leading
to Major/Strategic Public Buildings/Facilities
FROM :
Rehabilitation of Road with Slips, Slope Collapse, and Landslide
Sta. 9+741.00 to Sta. 9+793.00,
Kemdeng, San Vicente, Palawan
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 556.307 square meter
Allocation - Php 24.825 Million
TO :
Rehabilitation of Road with Slips, Slope Collapse, and Landslide
Sta. 9+741.00 to Sta. 9+800.00,
Kemdeng, San Vicente, Palawan
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 1,079.12 square meter
Allocation - Php 24.825 Million
|
July 26, 2022 |
FY 2022 GAA |
Win2G03085 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 300215101640000
Project ID : P00636972LZ
CONVERGENCE AND SPECIAL SUPPORT PROGRAM
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) -
Access Roads and/or Bridges from the National Road/s leading
to Major/Strategic Public Buildings/Facilities
FROM :
Rehabilitation/Reconstruction of roads with Slips, Slope Collapse, and Landslide : Port Barton - Kemdeng Road, San Vicente,
Palawan, Sta. 1+394 - Sta. 1+454
Physical Target - CW1 - Rehabilitation/Major Repair of Road Slope
Protection Structure :
978.635 square meter
Allocation - Php 22.785 Million
TO :
Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse,
and Landslide : Port Barton - Kemdeng Road, San Vicente,
Palawan, Sta. 0+812 - Sta. 0+848
Physical Target - CW1 - Rehabilitation/Major Repair of Road Slope
Protection Structure :
952.520 square meter
Allocation - Php 22.785 Million
|
July 26, 2022 |
FY 2021 |
WIN1B00805 |
310109100566000 |
May 24, 2021 |
Region IX |
Regional Office IX |
UACS No. 310109100566000
Project ID: P00501935MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope
Collapse, and Landslide - Tertiary Roads
Umus Mataha-Lupa-Pula Rd - Sta. 0 + 000 - Sta. 1 + 065
CW1 - Construction of Road Slope Protection Structure : 5,987.0 sq.m.
Unit Cost: P 16,884.597 /sq.m.
CW2 - Construction of Concrete Road : 2.13 lane km
Unit Cost: P 20,610,985.1 /lane km
EAO: P 5,250,000
Allocation: P 150,000,000.00 |
July 26, 2022 |
FY 2021 |
WIN1B00806 |
310109100565000 |
April 23, 2021 |
Region IX |
Regional Office IX |
UACS No. 310109100565000
Project ID: P00501936MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope
Collapse, and Landslide - Tertiary Roads
Tawi-Tawi Mainland Circumferential Road - Sta. 5 + 488 - Sta. 6 + 500
CW1 - Construction of Road Slope Protection Structure : 6,340.0 sq.m.
Unit Cost: P 16,159.3924 /sq.m.
CW2 - Construction of Concrete Road : 2.204 lane km
Unit Cost: P 20,790,499.63 /lane km
EAO: P 5,250,000
EXCESS: P 219,480.68
Allocation: P 15,000,000.00 |
July 26, 2022 |
FY 2021 |
WIN1B00782 |
300107201300000 |
October 23, 2021 |
Region IX |
Regional Office IX |
UACS No. 300107201300000
Project ID: P00550560MN
Flood Control and Drainage - Flood Control Structures / Facilities - Local Infrastructure
Program
Construction of Rockcauseway along River at Barangay Poblacion, Maimbung, Sulu
CW1 - Construction of Flood Mitigation Structure : 60.50 ln.m.
Unit Cost: P 81,818.18182
EAO: P 50,000
Allocation: P 5,000,000.00 |
July 25, 2022 |
FY 2022 GAA |
WIN2G03054 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 310109100866000
Project ID : P00611432LZ
OO1 : Ensure Safe and Reliable National Road System
Asset Preservation Program - Rehabilitation/Reconstruction of
Roads with Slips, Slope Collapse, and Landslide -
Secondary Roads
FROM :
Odiongan - East - West Rd
K0008+645.00 - K0008+840.00
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 10,833.33 square meter
Allocation - Php 195.00 Million
TO :
Odiongan - East - West Rd
Sta. 8+601 - Sta. 8+840
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 8,585.55 square meter
Allocation - Php 195.00 Million
|
July 25, 2022 |
FY 2022 GAA |
WIN2G03068 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 310109100990000
Project ID : P00611440LZ
OO1 : Ensure Safe and Reliable National Road System
Asset Preservation program - Rehabilitation/Reconstruction of
Roads with Slips, Slope Collapse, and Landslide -
Secondary Roads
FROM :
tagbac - Lubang - Looc Rd
K0035+170 - K0035+210
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 1,111.11 square meter
Allocation - Php 20.00 Million
TO :
Tagbac - Lubang - Looc Rd
K0035+170 - K0035+197.51
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 874 square meter
Allocation - Php 20.00 Million |
July 25, 2022 |
FY 2021 GAA |
WIN2G03051 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 320102104627000
Project ID : P00621108LZ
OO2 ; Protect Lives and Properties Against Major Floods
Construction/Rehabilitation of Flood mitigation Facilities within
Major River Basins and Principal Rivers
FROM :
Construction of Flood Control Structure,
Amnay River, Sta. 0+000 - Sta. 0+456
Ilvita Section, Sablayan, Occidental Mindoro
Physical Target - CW1 - Construction of Flood Mitigation
Structure : 456 lineal meter
Allocation - Php 45.00 Million
TO :
Construction of Flood Control Structure,
Amnay River, Sta. 0+000 - Sta. 0+307
Ilvita Section, Sablayan, Occidental Mindoro
Physical Target - CW1 - Construction of Flood Mitigation
Structure : 307 lineal meter
Allocation - Php 45.00 Million
|
July 25, 2022 |
FY 2022 GAA |
WIN2G03083 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 300203101642000
Project ID : P00635475LZ
CONVERGENCE AND SPECIAL SUPPORT PROGRAM
Construction/Improvement of Access Roads leading to Declared Tourism Destinations
(Tourism Road Infrastructure Program - TRIP)
FROM :
Balabac Circumferential Road, Balabac, Palawan
Physical Target - CW1 - Construction of Concrete Road :
3.330 Lane km
Allocation - Php 50.00 Million
TO :
Balabac Circumferential Road, Balabac, Palawan
Physical Target - CW1 - Construction of Concrete Road :
3.090 Lane km
Allocation - Php 50.00 Million |
July 25, 2022 |
FY 2022 GAA |
WIN2G03107 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 300215100238000
Project ID : P00636840LZ
CONVERGENCE AND SPECIAL SUPPORT PROGRAM
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG)
Access Roads and/or Bridges from the National Road/s leading
to Major/Strategic Public Buildings/Facilities
FROM :
Rehabilitation of Roads with Slips, Slope Collapse, and Landslide
along TDC - Pagdanan Road, San Vicente, Palawan
Sta. 9+318.00 - Sta. 9+495.00
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 4,841.521 square meter
Allocation - Php 216.051 Million
TO :
Rehabilitation of Roads with Slips, Slope Collapse, and landslide
along TDC - Pagdanan Road, San Vicente, Palawan
Sta. 9+318.00 - Sta. 9+945.00,
Sta. 9+864.00 - Sta. 10+055.00
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 9,490.750 square meter
Allocation - Php 216.051 Million
|
July 25, 2022 |
FY 2022 GAA |
WIN2G03110 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 300215100239000
Project ID : P00636841LZ
CONVERGENCE AND SPECIAL SUPPORT PROGRAM
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG)
Access Roads and/or bridges from the National Road/s leading
to Major/Strategic Public Buildings/Facilities
FROM:
Rehabilitation of Road with Slips, Slope Collapse, and Landslide
along TDC - Pagdanan Road, San Vicente, Palawan
Sta. 9+617.00 - Sta. 9+813.00
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 3,550.328 square meter
Allocation - Php 158.432 Million
TO :
Rehabilitation of Road with Slips, Slope Collapse, and Landslide
along TDC - Pagdanan Road, San Vicente, Palawan
Sta. 8+266.00 - Sta. 8+400
physical Target - CW1 - Construction of Road Slope protection
Structure : 6,821.760 square meter
Allocation - Php 158.432 Million |
July 25, 2022 |
FY 2022 GAA |
WIn2G03093 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 300215100246000
Project ID : P00636848LZ
CONVERGENCE AND SPECIAL SUPPORT PROGRAM
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG)
Access Roads and/or Bridges from the national Road/s leading
to Major/Strategic Public Buildings/Facilities
FROM :
Rehabilitation of Road with Slips, Slope Collapse, and Landslide
Port Barton - Kemdeng Road, San Vicente, Palawan
Sta. 0+485.00 - Sta. 0+643.00
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 2,100.59 square meter
Allocation - Php 93.738 Million
TO :
Rehabilitation of Road with Slips, Slope Collapse, and Landslide
Port Barton - Kemdeng Road, San Vicente, Palawan
Sta. 0+250.00 - Sta. 0+458.00
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 3,609.55 square meter
Allocation - Php 93.738 Million
|
July 25, 2022 |
FY 2022 GAA |
WIN2G03080 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 300215100249000
Project ID : P00636851LZ
CONVERGENCE AND SPECIAL SUPPORT PROGRAM
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) -
Access Roads and/or Bridges from the national Road/s leading
to major/Strategic Public buildings/Facilities
FROM :
Construction of Road, barangay Maniwaya, Santa Cruz, Marinduque (Phase II)
Physical Target - CW1 - Construction of Concrete Road :
12.429 Lane Km
Allocation - Php 150.00 Million
TO :
Construction of Road, barangay Maniwaya, Santa Cruz,
Marinduque (Phase II)
Physical Target - CW1- Construction of Concrete Road :
6.84 Lane Km
CW2 - Construction of Road Slope Protection
Structure : 2,982 square meter
CW3 - Road Safety : Pavement Markings :
6.84 Lane Km
Allocation - Php 150.00 Million
|
July 25, 2022 |
FY 2020 |
WIN1G02890 |
320101104218000 |
July 25, 2020 |
Region IX |
Regional Office IX |
UACS No. 320101104218000
Project ID: P00420376MN
OO2: Protect Lives and Properties Against Major Floods - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control Structure along Salug Daku (Miligan), Molave, Zamboanga del Sur
CW1 - Construction of Flood Mitigation Structure: 524.00 lm
Unit Cost: P 186,221.00/lm
ROW: 3,347.9833 sq. m.
Unit Cost: P 300/ sq.m.
EAO: P 3,415,310.31
Allocation: P 102,000,000.00 |
July 25, 2022 |
FY 2022 GAA |
WIN2G03116 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 300215100251000
Project ID : P00636853LZ
CONVERGENCE AND SPECIAL SUPPORT PROGRAM
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) -
Access Roads and/or Bridges from the national Road/s leading
to Major/Strategic Public buildings/Facilities
FROM :
Construction of Burirao - Isugod Cross Country Road,
Brgy. Burirao Narra and Brgy Isugod, Quezon (vis Brgy. Kalatagbak
and Brgy. Maasin, Quezon), Palawan
Physical Target - CW1- Construction of Concrete Road :
17.40 Lane Km
Allocation - Php 210.00 Million
TO :
Construction of Burirao - Isugod Cross Country Road,
Brgy. Burirao narra and brgy. Isugod, Quezon (vis Brgy. Kalatagbak
and Brgy. Maasin, Quezon), Palawan
Physical Target - CW1 - Construction of Gravel Road :
16.95 Lane Km
Allocation - Php 210.00 Million
|
July 25, 2022 |
FY 2022 GAA |
WIN2G03061 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 300215100261000
Project ID : P00636856LZ
CONVERGENCE AND SPECIAL SUPPORT PROGRAM
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG)
Access Roads and/or Bridges from the National Road/s leading
to Major/Strategic Public Buildings/Facilities
FROM :
Construction of Magbabadil - Magsaysay Road, Aborlan, Palawan
Physical Target - CW1 - Construction of Concrete Road :
8.286 lane Km
Allocation - Php 100.00 Million
TO :
Construction of Magbabadil - Magsaysay Road, Aborlan, Palawan
Physical Target - CW1- Construction of Concrete Road :
6.784 Lane Km
Allocation - Php 100.00 Million |
July 20, 2022 |
FY 2022 GAA |
WIN2G03105 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 310108100890000
Project ID : P00609312LZ
OO1 : Ensure Safe and Reliable National Road System
Asset Preservation program - Rehabilitation/Reconstruction of
Roads with Slips, Slope Collapse, and Landslide -
Secondary Roads
FROM ;
Puerto Princesa North Rd
K0017+121 - K0017+300
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 6,365.940 square meter
Allocation - Php 114.587 Million
TO :
Puerto Princesa North Rd
K0017+121 - K0017+300
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 4,925.000 square meter
Allocation - Php 114.587 Million |
July 20, 2022 |
FY 2022 GAA |
WIN2G03108 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 310108101144000
Project ID : P00609314LZ
OO1 : Ensure Safe and Reliable National Road System
Asset Preservation Program - Rehabilitation/Reconstruction of
Roads with Slips, Slope Collapse, and Landslide -
Secondary Roads
FROM :
PPSR Jct - Napsan - Apurawan Rd
K0036+734 - K0036+802
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 1,557.56 square meter
Allocation - Php 28.036 Million
TO :
PPSR Jct - Napsan - Apurawan Rd
K0036+734 - K0036+805
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 1,268.43 square meter
Allocation - Php 28.036 Million |
July 20, 2022 |
FY 2022 GAA |
WIN2G03050 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 310108101145000
Project ID : P00609315LZ
OO1: Ensure Safe and Reliable National Road System
Asset Preservation Program - Rehabilitation/Reconstruction of
Roads with Slips, Slope Collapse, and Landslide -
Secondary Roads
FROM :
PPSR Jct - Napsan - Apurawan Rd
K0037+409 - K0037+520
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 1,873.44 square meter
Allocation - Php 33.722 Million
TO :
PPSR Jct - Napsan - Apurawan Rd
K0037+409 - K0037+469
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 1,526.60 square meter
Allocation - Php 33.722 Million
|
July 20, 2022 |
2022 |
WIN2C03595 |
SR2022-03-007298 |
March 23, 2022 |
Region VIII |
Regional Office VIII |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Primary Roads
AS PER GAA/ORIGINAL:
Palo-Carigara-Ormoc Rd - K0931 + 000 - K0934 + 000
Physical Target: Allocation:
CW1-Preventive Maintenance of Road: P 53.2487 M
Asphalt Overlay: 9.526 Lane Km
EAO P 1.9313 M
Total P 55.180 M
AS MODIFIED:
Palo-Carigara-Ormoc Rd - K0931 + 000 - K0934 + 000
Physical Target: Allocation:
CW1-Preventive Maintenance of Road: P 53.2487 M
Asphalt Overlay: 5.690 Lane Km
EAO P 1.9313 M
Total P 55.180 M |
July 20, 2022 |
2022 |
WIN2C03594 |
SR2022-03-008894 |
March 23, 2022 |
Region VIII |
Regional Office VIII |
Convergence and Special Support Program
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/Facilities
AS PER GAA/ORIGINAL:
Concreting of Dolores-Maslog Road, Eastern Samar
Physical Target: Allocation:
CW1-Construction of Concrete Road: P 96.500 M
4.022 Lane Km
EAO P 3.500 M
Total P 100.00 M
AS MODIFIED:
Concreting of Dolores-Maslog Road, Eastern Samar
Physical Target: Allocation:
CW1-Construction of Concrete Road: P 96.500 M
2.60 Lane Km
EAO P 3.500 M
Total P 100.00 M
|
July 20, 2022 |
FY 2022 GAA |
WIN2G03052 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 310108101146000
Project ID : P00609316LZ
OO1 : Ensure Safe and Reliable National Road System
Asset Preservation Program - Rehabilitation/Reconstruction of
Roads with Slips, Slope Collapse, and Landslide -
Secondary Roads
FROM :
PPSR Jct - Napsan - Apurawan Rd
K0041+808 - K0041+881
Physical Target - CW1 - Construction of Roads Slope Protection
Structure : 1,789.170 square meter
Allocation - Php 32.205 Million
TO :
PPSR Jct - Napsan - Apurawan Rd
K0041+808 - K0041+863
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 1,456.95 square meter
Allocation - Php 32.205 Million |
July 20, 2022 |
FY 2022 GAA |
WIN2G03086 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 310108100879000
Project ID : P00611355LZ
OO1 : Ensure Safe and Reliable National Road System
Asset Preservation Program - Rehabilitation/Reconstruction of
Roads with Slips, Slope Collapse, and Landslide -
Secondary Roads
FROM :
Mindoro West Coastal Rd
K0446+(-089) - K0446+(-061)
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 5,000.00 square meter
Allocation - Php 90.00 Million
TO :
Mindoro west Coastal Rd
K044++(-089) - K0446+(-040),
K0446+180 - K0446+255.10
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 2,799.65 square meter
Allocation - Php 90.00 million |
July 20, 2022 |
2022 |
P00620102MN |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Regional Office XIII |
UACS No. : 320101107785000
Project ID: P00620102MN
ORGANIZATIONAL OUTCOME 2 : Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
FROM:
Construction of Flood Control Structure Along Lake Mainit- Tubay River (Kalinawan-Karak-an Section), Sta. 0+000.00 - Sta. 0+570.00, Package 2, Tubay, Agusan del Norte
Type of Work:
CW1- Construction of Flood Mitigation Structure
Physical Target:
CW1- 418.000 Lineal meters
Allocation:
TOTAL: P 110,000,000
CW1: P 106,150,000
EAO: P 3,850,000
Unit Cost:
CW1: P 253,947.37/ Lineal meters
TO:
Construction of Flood Control Structure Along Lake Mainit- Tubay River (Kalinawan-Karak-an Section), Sta. 2+422.75 - Sta. 2+788.00, Package 2, Tubay, Agusan del Norte
Type of Work:
CW1- Construction of Flood Mitigation Structure
Physical Target:
CW1- 365.250 Lineal meters
Allocation:
TOTAL: P 110,000,000
CW1: P 106,150,000
EAO: P 3,850,000
Unit Cost:
CW1: P 290,622.86/ Lineal meters |
July 20, 2022 |
2022 |
WIN2XY00009 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Regional Office XIII |
UACS No. : 320101107785000
Project ID: P00620102MN
ORGANIZATIONAL OUTCOME 2 : Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
FROM:
Construction of Flood Control Structure Along Lake Mainit- Tubay River (Kalinawan-Karak-an Section), Sta. 0+000.00 - Sta. 0+570.00, Package 2, Tubay, Agusan del Norte
Type of Work:
CW1- Construction of Flood Mitigation Structure
Physical Target:
CW1- 418.000 Lineal meters
Allocation:
TOTAL: P 110,000,000
CW1: P 106,150,000
EAO: P 3,850,000
Unit Cost:
CW1: P 253,947.37/ Lineal meters
TO:
Construction of Flood Control Structure Along Lake Mainit- Tubay River (Kalinawan-Karak-an Section), Sta. 2+422.75 - Sta. 2+788.00, Package 2, Tubay, Agusan del Norte
Type of Work:
CW1- Construction of Flood Mitigation Structure
Physical Target:
CW1- 365.250 Lineal meters
Allocation:
TOTAL: P 110,000,000
CW1: P 106,150,000
EAO: P 3,850,000
Unit Cost:
CW1: P 290,622.86/ Lineal meters |
July 20, 2022 |
2022 |
WIN2XY00010 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Regional Office XIII |
UACS No. : 320101107786000
Project ID: P00620103MN
ORGANIZATIONAL OUTCOME 2 : Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
FROM:
Construction of Flood Mitigation Structure along NRJ Tagcatong-Vinapor Road, Sta. 0+000.00 - Sta. 0+340.00, Carmen, Agusan del Norte
Type of Work:
CW1- Construction of Flood Mitigation Structure
Physical Target:
CW1- 416.667 Lineal meters
Allocation:
TOTAL: P 125,000,000
CW1: P 120,625,000
EAO: P 4,375,000
Unit Cost:
CW1: P 289,499.77/ Lineal meters
TO:
Construction of Flood Mitigation Structure along NRJ Tagcatong-Vinapor Road, Sta. 0+000 - Sta. 0+424.15, Carmen, Agusan del Norte
Type of Work:
CW1- Construction of Flood Mitigation Structure
Physical Target:
CW1- 424.150 Lineal meters
Allocation:
TOTAL: P 125,000,000
CW1: P 120,625,000
EAO: P 4,375,000
Unit Cost:
CW1: P 284,392.31/ Lineal meters |
July 20, 2022 |
2022 |
WIN2XY00014 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Regional Office XIII |
UACS No. : 300215100624000
Project ID: P00630161MN
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
FROM:
Replacement of Agusan Pequeño Bridge into 4 lanes, Butuan City, Agusan del Norte
Type of Work:
CW1- Replacement of Bridge
CW2- Construction of Concrete Road
Physical Target:
CW1- 1,068.000 Square meters
CW2- 3.48 Lane Km
Allocation:
TOTAL: P 300,000,000
CW1: P 145,432,742
CW2: P 144,067,258
EAO: P 10,500,000
Unit Cost:
CW1: P 136,173.00/ Square meters
CW2: P 41,398,637.36/ Lane Km
TO:
Replacement of Agusan Pequeño Bridge into 4 lanes, Butuan City, Agusan del Norte
Type of Work:
CW1- Replacement of Bridge
CW2- Construction of Concrete Road
CW3- Construction of Slope Protection Structure
Physical Target:
CW1- 1,068.000 Square meters
CW2- 0.400 Lane Km
CW3- 2,632.35 Square meters
Allocation:
TOTAL: P 300,000,000
CW1: P 186,210,010
CW2: P 21,706,070
CW3: P 81,583,920
EAO: P 10,500,000
Unit Cost:
CW1: P 174,353.94/ Square meters
CW2: P 54,265,175/ Lane Km
CW3: P 30,992.81/ Square meters |
July 20, 2022 |
2022 |
WIN2XY00006 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Regional Office XIII |
UACS No. : 310204101718000
Project ID: P00604279MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Construction of By-Pass and Diversion Roads
FROM:
Butuan City West Diversion Road, Package 5, Butuan City
Type of Work:
CW1- Construction of Concrete Road
Physical Target:
CW1- 9.560 Lane Km
Allocation:
TOTAL: P 105,000,000
CW1: P 101,325,000
EAO: P 3,675,000
Unit Cost:
CW1: P 10,598,849.37/ Lane Km
TO:
Butuan City West Diversion Road, Package 5, Butuan City
Type of Work:
CW1- Construction of Concrete Road
Physical Target:
CW1- 7.940 Lane Km
Allocation:
TOTAL: P 105,000,000
CW1: P 101,325,000
EAO: P 3,675,000
Unit Cost:
CW1: P 12,761,335.01/ Lane Km |
July 20, 2022 |
2022 |
WIN2XY00013 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Regional Office XIII |
UACS No. : 310204101721000
Project ID: P00604290MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Construction of By-Pass and Diversion Roads
FROM:
Butuan City-Agusan Del Norte Logistical Highway, Package 25, Butuan City
Type of Work:
CW1- Construction of Gravel Road
ROW- ROW Acquisition
Physical Target:
CW1- 2.640 Lane Km
ROW- 13,983.390 Square meters
Allocation:
TOTAL: P 105,000,000
CW1: P 93,605,000
ROW: P 7,720,000
EAO: P 3,675,000
Unit Cost:
CW1: P 35,456,439.39/ Lane Km
ROW: P 552.08/ Square meters
TO:
Butuan City-Agusan Del Norte Logistical Highway, Package 25, Butuan City
Type of Work:
CW1- Construction of Gravel Road
ROW- ROW Acquisition
Physical Target:
CW1- 3.153 Lane Km
ROW- 13,983.390 Square meters
Allocation:
TOTAL: P 105,000,000
CW1: P 93,605,000
ROW: P 7,720,000
EAO: P 3,675,000
Unit Cost:
CW1: P 29,687,599.11/ Lane Km
ROW: P 552.08/ Square meters |
July 20, 2022 |
2022 |
WIN2XY00007 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Regional Office XIII |
UACS No. : 310204101906000
Project ID: P00604282MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Construction of By-Pass and Diversion Roads
FROM:
Butuan City-Agusan Del Norte Logistical Highway, Package 17 Butuan City
Type of Work:
CW1- Construction of Gravel Road
ROW- ROW Acquisition
Physical Target:
CW1- 2.052 Lane Km
ROW- 8,739.620 Square meters
Allocation:
TOTAL: P 68,000,000
CW1: P 60,795,000
ROW: P 4,825,000
EAO: P 2,380,000
Unit Cost:
CW1: P 29,627,192.98/ Lane Km
ROW: P 552.08/ Square meters
TO:
Butuan City-Agusan Del Norte Logistical Highway, Package 17 Butuan City
Type of Work:
CW1- Construction of Gravel Road
ROW- ROW Acquisition
Physical Target:
CW1- 1.620 Lane Km
ROW- 8,739.620 Square meters
Allocation:
TOTAL: P 68,000,000
CW1: P 60,795,000
ROW: P 4,825,000
EAO: P 2,380,000
Unit Cost:
CW1: P 37,527,777.78/ Lane Km
ROW: P 552.08/ Square meters |
July 20, 2022 |
2022 |
WIN2XY00016 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Regional Office XIII |
UACS No. : 310204101907000
Project ID: P00604283MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Construction of By-Pass and Diversion Roads
FROM:
Butuan City-Agusan Del Norte Logistical Highway, Package 18, Butuan City
Type of Work:
CW1- Construction of Gravel Road
ROW- ROW Acquisition
Physical Target:
CW1- 1.332 Lane Km
ROW- 8,739.620 Square meters
Allocation:
TOTAL: P 68,000,000
CW1: P 60,795,000
ROW: P 4,825,000
EAO: P 2,380,000
Unit Cost:
CW1: P 45,641,891.89/ Lane Km
ROW: P 552.08/ Square meters
TO:
Butuan City-Agusan Del Norte Logistical Highway, Package 18, Butuan City
Type of Work:
CW1- Construction of Gravel Road
ROW- ROW Acquisition
Physical Target:
CW1- 1.284 Lane Km
ROW- 8,739.620 Square meters
Allocation:
TOTAL: P 68,000,000
CW1: P 60,795,000
ROW: P 4,825,000
EAO: P 2,380,000
Unit Cost:
CW1: P 47,348,130.84/ Lane Km
ROW: P 552.08/ Square meters |
July 20, 2022 |
2022 |
WIN2XY00012 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Regional Office XIII |
UACS No. : 310305101553000
Project ID: P00602220MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Bridge Program - Widening of Permanent Bridges
FROM:
Construction of Bislig Bridge, Surigao del Sur
Type of Work:
CW1- Widening of Bridge
Physical Target:
CW1- 2,488.320 Square meters
Allocation:
TOTAL: P 105,000,000
CW1: P 101,325,000
EAO: P 3,675,000
Unit Cost:
CW1: P 40,720.24/ Square meters
TO:
Construction of Bislig Bridge, Surigao del Sur
Type of Work:
CW1- Widening of Bridge
Physical Target:
CW1- 3,090.960 Square meters
Allocation:
TOTAL: P 105,000,000
CW1: P 101,325,000
EAO: P 3,675,000
Unit Cost:
CW1: P 32,781.08/ Square meters |
July 20, 2022 |
2022 |
WIN2C03598 |
SR2022-05-010181 |
May 11, 2022 |
Region VIII |
Leyte 1st District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Tertiary Roads
AS PER GAA/ORIGINAL:
Bagahupi-Babatngon-Sta Cruz-Barugo-Carigara Rd - K0911 + 540 - K0913 + 036
Physical Target: Allocation:
CW1-Road Widening: 3.00 Lane Km P 86.850 M
EAO P 3.150 M
Total P 90.00 M
AS MODIFIED:
Bagahupi-Babatngon-Sta Cruz-Barugo-Carigara Rd - K0911 + 540 - K0913 + 786
Physical Target: Allocation:
CW1-Road Widening: 4.50 Lane Km P 86.850 M
EAO P 3.150 M
Total P 90.00 M |
July 20, 2022 |
FY 2022 GAA |
WIN2G03126 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 310108100881000
Project ID : P00611357LZ
OO1 : Ensure Safe and Reliable National Road System
Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide -
Secondary Roads
FROM :
Mindoro West Coastal Road
K00447+150 - K0447+330
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 5,000.00 square meter
Allocation - Php 90.00 Million
TO :
Mindoro West Coastal Road
K0447+300 - K0447+360,
K0447+400 - K0447+450.82
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 3,854.15 square meter
Allocation - Php 90.00 Million |
July 20, 2022 |
FY 2022 GAA |
WIN2G03056 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 310109100864000
Project ID : P00611430LZ
OO1 : Ensure Safe and Reliable National Road System
Asset Preservation Program - Rehabilitation/Reconstruction of
Roads with Slips, Slope Collapse, and Landslide
FROM :
Tagbac - Lubang - Looc Rd (S00004LB)
K0035+380 - K0035+530
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 5,000 square meter
Allocation - Php 90.00 Million
TO :
Tagbac - Lubang - Looc Rd
K0035+380 - K0035+478,
K0035+507 - K0035+523.55
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 3,949 square meter
Allocation - Php 90.00 Million
|
July 19, 2022 |
FY 2022 GAA |
WIN2G03122 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 310108100894000
Project ID : P00604380LZ
OO1 : Ensure Safe and Reliable National Road System
Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide -
Secondary Roads
FROM :
Mindoro West Coastal Rd
K0346+150 - K0346+250
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 1,000.00 square meter
Allocation - Php 10.00 Million
TO :
Mindoro West Coastal Rd
K346+150 - K0346+241
Physical Target - CW1 - Construction of Road Slope Protection
Structure ; 1,223.60 square meter
Allocation - Php 10.00 Million |
July 19, 2022 |
FY 2022 GAA |
WIN2G03103 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 310108100895000
Project ID : P00604381LZ
OO1 : Ensure Safe and Reliable National Road System
Asset Preservation Program - Rehabilitation/Reconstruction of
Roads with Slips, Slope Collapse, and Landslide -
Secondary Roads
FROM ;
Mindoro West Coastal Rd
K0346+940 - K0347+050
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 1,000.00 square meter
Allocation - Php 12.50 Million
TO :
Mindoro West Coastal Rd
K0346+950 - K0347+027
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 603.00 square meter
Allocation - Php 12.50 million
|
July 19, 2022 |
FY 2022 GAA |
WIN2G03067 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 310108100896000
Project ID : P00604382LZ
OO1 : Ensure Safe and Reliable National Road System
Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and landslide -
Secondary Roads
FROM :
Mindoro West Coastal Rd
K0348+250.00 - K0348+410.00
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 2,480.00 square meter
Allocation - Php 49.60 Million
TO :
Mindoro West Coastal Rd
K0348+250.00 - K0348+327.90
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 2,073.00 square meter
Allocation - Php 49.60 Million |
July 19, 2022 |
FY 2022 GAA |
WIN2G03053 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 310305101498000
Project ID : P00605542LZ
OO1 : Ensure Safe and Reliable National Road System
Bridge : Widening of Permanent Bridge
FROM:
Tagbolante Bridge (B00324PW) along
Aramaywan - Berong - Pto. Princesa Rd
Physical Target - CW1 - Widening of Bridge : 298.90 square meter
Allocation - Php 62.769 Million
TO :
Tagbolante Bridge (B00324PW) along
Aramaywan - Berong - Pto. Princesa Rd
Physical Target - CW1 - Widening of Bridge : 242.40 square meter
Allocation - Php 62.769 Million
|
July 19, 2022 |
FY 2022 GAA |
WIN2G03119 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 310305101497000
Project ID : P00605563LZ
OO1 : Ensure Safe and Reliable National Road System
Bridge Program - Widening of Permanent Bridge
FROM :
Sijeron Bridge (B00031TL) along Tablas Circumferential Rd
Physical Target - CW1 - Widening of Bridge :
1,192.500 square meter
Allocation - Php 250.00 Million
TO :
Sijeron Bridge (B0031TL) along Tablas Circumferential Rd
Physical Target - CW1 - Widening of Bridge :
1,028.412 square meter
Allocation - Php 250.00 Million |
July 19, 2022 |
FY 2022 GAA |
WIN2G03087 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 310204101538000
Project ID : P00609271LZ
OO1 : Ensure Safe and Reliable National Road System
Network Development - Construction of By-Pass and
Diversion Roads
FROM :
Puerto Princesa South Diversion Road II
K0047+409 - K0050+710,
Puerto Princesa South Road
Physical Target - CW1 - Construction of Concrete Road :
5.480 Lane Km
Allocation - Php 137.00 Million
TO :
Puerto Princesa South Diversion Road II
Sta. 047+635 - Sta. 049+460,
Puerto Princesa South Road
Physical Target - CW1 - Construction of Concrete Road :
3.650 Lane Km
CW2 - Road Safety : Pavement Markings -
3.650 Lane Km
Allocation - Php 137.00 Million
|
July 19, 2022 |
FY 2022 GAA |
WIN2G03070 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 310108101130000
Project ID : P00609308LZ
OO1 : Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide -
Secondary Roads
FROM :
Aramaywan - Berong - Pto. Princesa Rd (S00064PW)
K0183+442 - K0183+485
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 1,803.70 square meter
Allocation - Php 18.037 Million
TO :
Aramaywan - Berong - Pto. Princesa Rd
K0183+442 - K0183+492
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 816.56 square meter
Allocation - Php 18.037 Million |
July 14, 2022 |
2022 |
WIN2C03596 |
SR2022-03-008157 |
March 23, 2022 |
Region VIII |
Regional Office VIII |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Tertiary Roads
AS PER GAA/ORIGINAL:
Tigbao - Sta. Fe - San Miguel Road, K0907+900 - K0907+980
Physical Target: Allocation:
CW1-Reconstruction to Concrete Pavement P 144.750 M
: 8.00 Lane Km
EAO P 5.250 M
Total P 150.00 M
AS MODIFIED:
Tigbao - Sta. Fe - San Miguel Road, K0907+900 - K0907+996
Physical Target: Allocation:
CW1-Reconstruction to Concrete Pavement P 139.750 M
: 0.384 Lane Km
ROW- ROW Acquisition: 5,000 Square meters P 5.00 M
EAO P 5.250 M
Total P 150.00 M
|
July 14, 2022 |
2022 |
WIN2C03599 |
SR2022-03-008148 |
March 23, 2022 |
Region VIII |
Regional Office VIII |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Tertiary Roads
AS PER GAA/ORIGINAL:
Tigbao - Sta. Fe - San Miguel Road
Physical Target: Allocation:
CW1-Reconstruction to Concrete Pavement P 86.850 M
: 4.968 Lane Km
EAO P 3.150 M
Total P 90.00 M
AS MODIFIED:
Tigbao - Sta. Fe - San Miguel Road, K0907+996 - K0908+060
Physical Target: Allocation:
CW1-Reconstruction to Concrete Pavement P 81.850 M
: 0.256 Lane Km
ROW-ROW Acquisition: 5,000 Square meters P 5.00 M
EAO P 3.150 M
Total P 90.00 M |
July 14, 2022 |
2022 |
WIN2C03597 |
SR2022-03-007293 |
March 23, 2022 |
Region VIII |
Regional Office VIII |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Primary Roads
AS PER GAA/ORIGINAL:
Palo-Carigara-Ormoc Rd - K0923 + 000 - K0926 + 000
Physical Target: Allocation:
CW1-Preventive Maintenance of Road: P 53.301775 M
Asphalt Overlay : 9.858 Lane Km
EAO P 1.933225 M
Total P 55.235 M
AS MODIFIED:
Palo-Carigara-Ormoc Rd - K0923 + 000 - K0926 + 000
Physical Target: Allocation:
CW1-Preventive Maintenance of Road: P 53.301775 M
Asphalt Overlay : 5.830 Lane Km
EAO P 1.933225 M
Total P 55.235 M
|
July 9, 2022 |
2022 |
WIN2F06532 |
SARO-BMB-A-22-0002930 |
March 21, 2022 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
From: Improvement of Road along Proper Paoay to Bosleng, Brgy. Paoay, Atok, Benguet;
Physical Target: 1.053 Lane Km;
Allocation: Php 10,000,000.000
To: Improvement of Road along Proper Paoay to Bosleng, Brgy. Paoay, Atok, Benguet;
Physical Target: 0.500 Lane Km;
Allocation: Php 10,000,000.000
|
July 9, 2022 |
2022 |
WIN2F06534 |
SARO-BMB-A-22-0002930 |
March 21, 2022 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
From: Construction (Completion) of Bodehow Road, Daclan, Tublay, Benguet;
Type of Work: Construction of Concrete Road;
Physical Target: 0.302 Lane Km;
Allocation: Php 3,000,000.000
To: Construction (Completion) of Bodehow Road, Daclan, Tublay, Benguet;
Type of Work: Construction of Road Slope Protection Structure;
Physical Target: 354.000 Square meters;
Allocation: Php 3,000,000.000
|
July 9, 2022 |
2022 |
WIN2F06533 |
SARO-BMB-A-22-0002930 |
March 21, 2022 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
From: Cong. Andres Acop Cosalan Rd - K0350+000 - K0356+000;
Physical Target: 5,700.000 Square meters;
Allocation: Php 40,000,000.000
To: Cong. Andres Acop Cosalan Rd - K0351+353 - K0351+760, K0352+249 - K0352+509, K0355+197 - K0355+239, K0355+395 - K0356+000;
Physical Target: 3,218.500 Square meters;
Allocation: Php 40,000,000.000
|
July 9, 2022 |
2022 |
WIN2F06541 |
SARO-BMB-A-22-0002938 |
March 21, 2022 |
Cordillera Administrative Region |
Ifugao 2nd District Engineering Office |
From: Construction of Sitio Rosenda Access Road in Brgy. Sta. Maria, Alfonso Lista, Ifugao;
Physical Target: 0.702 Lane Km.;
Allocation: Php 5,000,000.000
To: Construction of Sitio Rosenda Access Road in Brgy. Sta. Maria, Alfonso Lista, Ifugao;
Physical Target: 0.600 Lane Km.;
Allocation: Php 5,000,000.000
|
July 9, 2022 |
2022 |
WIN2F06567 |
GAA 2022 |
January 2, 2022 |
Cordillera Administrative Region |
Ifugao 1st District Engineering Office |
From: Nueva Vizcaya-Ifugao-Mt Province Rd - K0305 + 000 - K0307 + 000;
Physical Target: 4.106 Lane Km;
Allocation: Php 20,000,000.000
To: Nueva Vizcaya-Ifugao-Mt Province Rd - K0305 + 000 - K0307 + 000;
Physical Target: 2.174 Lane Km;
Allocation: Php 20,000,000.000
|
July 9, 2022 |
2022 |
WIN2F06568 |
SARO-BMB-A-22-0002937 |
March 22, 2022 |
Cordillera Administrative Region |
Ifugao 1st District Engineering Office |
From: Banaue-Hungduan-Benguet Bdry Rd - K0387 + 650 - K0387 + 680, K0389 + 170 - K0389 + 182, K0369 + 790 - K0369 + 819, K0377 + 081 - K0377 + 150;
Physical Target: 4,073.000 Square Meters;
Allocation: Php 40,730,000.000
To: Banaue-Hungduan-Benguet Bdry Rd - K0387 + 650 - K0387 + 680, K0389 + 170 - K0389 + 182, K0369 + 790 - K0369 + 819, K0377 + 081 - K0377 + 150;
Physical Target: 1,913.000 Square Meters;
Allocation: Php 40,730,000.000
|
July 9, 2022 |
2022 |
WIN2F06542 |
GAA 2022 |
January 2, 2022 |
Cordillera Administrative Region |
Ifugao 1st District Engineering Office |
From: Construction of Sitio Humalophop Access Road in Brgy. Mompolia, Hingyon, Ifugao;
Type of Work: Construction of Concrete Road;
Physical Target: 0.504 Lane Km;
Allocation: Php 5,000,000.000
To: Construction of Sitio Humalophop Access Road in Brgy. Mompolia, Hingyon, Ifugao;
Type of Work: Construction of Gravel Road;
Physical Target: 1.200 Lane Km;
Allocation: Php 5,000,000.000
|
July 9, 2022 |
2022 |
WIN2F06535 |
SR2022-03-007809 |
March 23, 2022 |
Cordillera Administrative Region |
Benguet 1st District Engineering Office |
From: Construction of Road, Bua-Gumatdang-Pacalso Road, Itogon, Benguet;
Type of Work: Construction of Concrete Road;
Physical Target: 8.056 Lane Km;
Allocation: Php 80,000,000.000
To: Construction of Road, Bua-Gumatdang-Pacalso Road, Itogon, Benguet;
Type of Work: Construction of Gravel Road;
Physical Target: 3.577 Lane Km;
Allocation: Php 80,000,000.000
|
July 6, 2022 |
2022 |
WIN2F06575 |
FY 2022 GAA |
December 30, 2021 |
Region III |
Pampanga 1st District Engineering Office |
Asset Preservation Program - Preventive Maintenance - Tertiary Roads
Tulauc - Sto. Domingo Rd - K0060+000 - K0061+510 |
July 6, 2022 |
2022 |
WIN2F06520 |
FY 2022 GAA |
December 30, 2021 |
Region III |
Pampanga 1st District Engineering Office |
Asset Preservation Program – Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Tertiary Roads
Bahay Pare - Sn Luis - Sto. Domingo Rd - K0064+432 - K0064+640, K0064+954 - K0065+040, K0065+183 - K0065+120 |
July 5, 2022 |
FY 2022 |
WIN2C03600 |
UACS No. 300221100002000 |
February 24, 2022 |
National Capital Region |
Metro Manila 3rd District Engineering Office |
As per GAA/Original
UACS No. 300221100002000
Project ID.: P00631911LZ
Convergence and Special Support Program
Basic Infrastructure Program (BIP) – Access Roads and/or Bridges from the National Road/s
Leading to Major/ Strategic Public Buildings/Facilities
Improvement of Road with Drainage, Kawayan Creek Orient St., Barangay San Agustin,
Quezon City
Physical Target: CW1- Rehabilitation of Concrete Road 0.200 Lane Km
Unit Cost = P 49,500,000/lane km
Allocation = P 9,900,000
EAO = P 100,000
Total = P 10,000,000
As Modified
Convergence and Special Support Program
Basic Infrastructure Program (BIP) – Access Roads and/or Bridges from the National Road/s
Leading to Major/ Strategic Public Buildings/Facilities
Improvement of Road with Drainage, Kawayan Creek Orient St., Barangay 170, Caloocan City
Physical Target: CW1- Rehabilitation of Concrete Road 0.450 Lane Km
Unit Cost = P 22,000,000/lane km
Allocation = P 9,900,000
EAO = P 100,000
Total = P 10,000,000
WIN2C03600
|
July 5, 2022 |
2022 |
WIN2E02490 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Regional Office XIII |
UACS No. : 310205100956000
Project ID: P00603813MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Construction of Missing Links/ New Roads
FROM:
East-West lateral road connecting Agusan del Sur/Bukidnon Agusan-Malaybalay Road, Package 4, Agusan Del Sur
Type of Work:
CW1- Construction of Concrete Bridge
CW2- Construction of Concrete Road
Physical Target:
CW1- 333.900 Square meters
CW2- 1.770 Lane Km
Allocation:
TOTAL: P 68,000,000
CW1: P 43,054,440
CW2: P 22,565,560
EAO: P 2,380,000
Unit Cost:
CW1: P 128,944.12/ Square meters
CW2: P 12,748,903.95/ Lane Km
TO:
East-West lateral road connecting Agusan del Sur/Bukidnon Agusan-Malaybalay Road, Package 4, Agusan Del Sur
Type of Work:
CW1- Construction of Concrete Bridge
CW2- Construction of Concrete Road
Physical Target:
CW1- 333.900 Square meters
CW2- 1.160 Lane Km
Allocation:
TOTAL: P 68,000,000
CW1: P 47,362,586
CW2: P 18,257,414
EAO: P 2,380,000
Unit Cost:
CW1: P 141,846.62/ Square meters
CW2: P 15,739,150/ Lane Km |
July 5, 2022 |
2022 |
WIN2E02475 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Regional Office XIII |
UACS No. : 300215100586000
Project ID: P00630123MN
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
FROM:
Construction of Kawayan Bridge, Barangay Langasian, La Paz, Agusan del Sur
Type of Work:
CW1- Construction of Bridge
CW2- Construction of Concrete Road
CW3- Construction of Road Slope Protection Structure
Physical Target:
CW1- 1,001.700 Square meters
CW2- 2.220 Lane Km
CW3- 8,783.380 Square meters
Allocation:
TOTAL: P 200,000,000
CW1: P 129,597,854
CW2: P 56,345,845
CW3: P 7,056,301
EAO: P 7,000,000
Unit Cost:
CW1: P 129,377.91/ Square meters
CW2: P 25,381,011.26/ Lane Km
CW3: P 803.37/ Square meters
TO:
Construction of Kawayan Bridge, Barangay Langasian, La Paz, Agusan del Sur
Type of Work:
CW1- Construction of Bridge
CW2- Construction of Concrete Road
CW3- Construction of Road Slope Protection Structure
Physical Target:
CW1- 1,001.700 Square meters
CW2- 1.080 Lane Km
CW3- 4,960.800 Square meters
Allocation:
TOTAL: P 200,000,000
CW1: P 146,448,789.13
CW2: P 39,382,658.96
CW3: P 7,168,551.91
EAO: P 7,000,000
Unit Cost:
CW1: P 146,200.25/ Square meters
CW2: P 36,465,424.96/ Lane Km
CW3: P 1,445.04/ Square meters
|
July 5, 2022 |
2022 |
WIN2E02465 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Regional Office XIII |
UACS No. : 300203102084000
Project ID: P00633283MN
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/ Improvement of Access Roads leading to Declared Tourism Destinations (Tourism Road Infrastructure Program - TRIP)
FROM:
Panaytayon-Taod-oy Provincial Road leading to Taod-oy View Deck and Magellan's Cross (Faith Tourism), Magallanes, Agusan del Norte
Type of Work:
CW1- Construction of Concrete Road
CW2- Construction of Concrete Bridge
CW3- Construction of Road Slope Protection Structure
Physical Target:
CW1- 0.560 Lane Km
CW2- 343.440 Square meters
CW3- 3103.740 Square meters
Allocation:
TOTAL: P 105,000,000
CW1: P 23,895,390
CW2: P 43,460,000
CW3: P 33,969,610
EAO: P 3,675,000
Unit Cost:
CW1: P 42,670,339.29/ Lane Km
CW2: P 126,543.21/ Square meters
CW3: P 10,944.73/ Square meters
TO:
Panaytayon-Taod-oy Provincial Road leading to Taod-oy View Deck and Magellan's Cross (Faith Tourism), Magallanes, Agusan del Norte
Type of Work:
CW1- Construction of Concrete Road
CW2- Construction of Concrete Bridge
CW3- Construction of Road Slope Protection Structure
Physical Target:
CW1- 0.560 Lane Km
CW2- 343.440 Square meters
CW3- 2,366.12 Square meters
Allocation:
TOTAL: P 105,000,000
CW1: P 25,220,955.78
CW2: P 45,558,452.95
CW3: P 30,545,591.27
EAO: P 3,675,000
Unit Cost:
CW1: P 45,037,421.04/ Lane Km
CW2: P 132,653.31/ Square meters
CW3: P 12,909.57/ Square meters |
July 5, 2022 |
2022 |
WIN2E02474 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Regional Office XIII |
UACS No. : 300217100105000
Project ID: P00630451MN
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Interjurisdictional Roads and/or Bridges (or, roads that traverse multiple LGU jurisdictions)
FROM:
Construction of San Roque, Bislig to Bunawan By-pass Road, Bunawan, Agusan del Sur
Type of Work:
CW1- Construction of Concrete Road
Physical Target:
CW- 6.000 Lane Km
Allocation:
TOTAL: P 105,000,000
CW1: P 101,325,000
EAO: P 3,675,000
Unit Cost:
CW1: P 16,887,500/ Lane Km
TO:
Construction of San Roque, Bislig to Bunawan By-pass Road, Bunawan, Agusan del Sur
Type of Work:
CW1- Construction of Concrete Road
Physical Target:
CW- 5.400 Lane Km
Allocation:
TOTAL: P 105,000,000
CW1: P 101,325,000
EAO: P 3,675,000
Unit Cost:
CW1: P 18,763,888.89/ Lane Km
|
July 4, 2022 |
2022 |
WIN2E02439 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Regional Office XIII |
UACS No. : 300217100114000
Project ID: P00630460MN
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Interjurisdictional Roads and/or Bridges (or, roads that traverse multiple LGU jurisdictions) - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG)
FROM:
NRJ Maug - La Purisima - San Juan - New Tubigon Road, Package 3, Agusan Del Sur
Type of Work:
CW1- Construction of Concrete Road
CW2- Construction of Concrete Bridge
Physical Target:
CW1- 1.78 Lane Km
CW2- 572.400 Square meters
Allocation:
TOTAL: P 135,000,000
CW1: P 49,127,183
CW2: P 81,147,817
EAO: P 4,725,000
Unit Cost:
CW1: P 27,599,541.01/ Lane Km
CW2: P 141,767.67/ Square meters
TO:
NRJ Maug - La Purisima - San Juan - New Tubigon Road, Package 3, Agusan Del Sur
Type of Work:
CW1- Construction of Concrete Bridge
Physical Target:
CW1- 858.600 Square meters
Allocation:
TOTAL: P 135,000,000
CW1: P 130,275,000
EAO: P 4,725,000
Unit Cost:
CW1: P 151,729.56/Square meters |
July 4, 2022 |
2022 |
WIN2F06539 |
FY 2022 GAA |
December 30, 2021 |
Region III |
Bulacan 2nd District Engineering Office |
Convergence and Special Support Program - Basic Infrastructure Program (BIP) - Multi-Purpose Buildings / Facilities to Support Social Services
Construction of Multi-Purpose Building, Poblacion, Marilao, Bulacan |
July 4, 2022 |
2022 |
WIN2F06538 |
FY 2022 GAA |
December 30, 2021 |
Region III |
Nueva Ecija 1st District Engineering Office |
Network Development Program - Construction of By-Pass and Diversion Roads
San Roque - Maturanoc Road, Guimba By-pass, Nueva Ecija |
July 4, 2022 |
2022 |
WIN2F06523 |
FY 2022 GAA |
December 30, 2021 |
Region III |
Pampanga 1st District Engineering Office |
Asset Preservation Program – Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Tertiary Roads
Sto. Tomas - Minalin Rd (Minalin - Macabebe Sect) - K0064+236 - K0064+410 |
July 4, 2022 |
2022 |
WIN2F06521 |
FY 2022 GAA |
December 30, 2021 |
Region III |
Pampanga 1st District Engineering Office |
Asset Preservation Program – Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Tertiary Roads
Arayat - Magalang Rd - K0092+168 - K0092+350 |
July 4, 2022 |
2022 |
WIN2F06528 |
FY 2022 GAA |
December 30, 2021 |
Region III |
Pampanga 1st District Engineering Office |
Asset Preservation Program – Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Primary Roads
Manila North Rd - K0067+676 - K0068+098 |
July 4, 2022 |
2022 |
WIN2F06525 |
FY 2022 GAA |
December 30, 2021 |
Region III |
Pampanga 1st District Engineering Office |
Asset Preservation Program – Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Tertiary Roads
Candaba - Sn Miguel Rd - K0074+000 - K0074+151 |
July 4, 2022 |
2022 |
WIN2F06522 |
FY 2022 GAA |
December 30, 2021 |
Region III |
Pampanga 1st District Engineering Office |
Asset Preservation Program - Construction / Upgrading / Rehabilitation of Drainage along National Roads - Tertiary Roads
Sto. Tomas - Minalin Rd (Minalin - Macabebe Sect) - K0064+236 - K0064+410, K0067+425 - K0068+075, K0068+155 - K0069+730, K0069+781- K0070+330 |